CN107269028A - The supporting construction that a kind of engineering construction is used - Google Patents

The supporting construction that a kind of engineering construction is used Download PDF

Info

Publication number
CN107269028A
CN107269028A CN201710624095.8A CN201710624095A CN107269028A CN 107269028 A CN107269028 A CN 107269028A CN 201710624095 A CN201710624095 A CN 201710624095A CN 107269028 A CN107269028 A CN 107269028A
Authority
CN
China
Prior art keywords
support
supporting construction
engineering construction
support unit
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710624095.8A
Other languages
Chinese (zh)
Inventor
范雄杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710624095.8A priority Critical patent/CN107269028A/en
Publication of CN107269028A publication Critical patent/CN107269028A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G25/00Shores or struts; Chocks
    • E04G25/02Shores or struts; Chocks non-telescopic
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G25/00Shores or struts; Chocks
    • E04G2025/003Supports therefor, e.g. tripods

Abstract

The present invention relates to the supporting construction that a kind of engineering construction is used, including:Support platform, the space support body in support platform;The space support body is included in multiple support units of vertical or/and horizontal direction superposition, multiple connectors for connecting adjacent supports unit;The support unit is provided with current breach;The current breach of the adjacent supports unit is connected, to form transit passage;The space support body and the removable connection of support platform.Multiple space support bodies are built in support platform according to the profile of building structure, and adjacent space support body is fixed up by connector, a stable support overall structure are formed, to ensure load-bearing requirements during construction.The present invention can adjust gravity vertical, adjustable stress point, can move, and may be reused, also with the assembly and disassembly time is reduced, the features such as reducing construction cost, reduction technical difficulty, raising operating efficiency.

Description

The supporting construction that a kind of engineering construction is used
Technical field
The present invention relates to a kind of building implement, more particularly to the supporting construction that a kind of engineering construction is used.
Background technology
The species of architectural support structure at this stage is more, and most of supported using common steel tube column built, Support function is played in building construction process though can realize, mainly there is following deficiency:1. installing/dismounting process is cumbersome, flexible Property poor, low production efficiency, service life is short, transport and storage inconvenience, and usage quantity is more, and space-consuming directly causes greatly engineering cost Increase;2. opening up screw thread on the support bar having, screw thread lines is longer, it is long-term it is exposed be easy to get rusty beyond nut or by Hurt and can not be continuing with, and the regulated quantity of adjusting nut is big, and inconvenient operation, difficulty of processing is also big;3. workman's operation is endangered Dangerous height.
In the market also has a kind of adjustable tubular steel post, i.e., adjusting nut is set between lower branch line or support bar, or The cotter way for symmetrically opening up lock-joint in lower branch line or support bar and being communicated with lock-joint, and connected by latch.By latch come Pillar is adjusted, though governing speed is very fast, because lock-joint and cotter way are excessive, so as to reduce the rigidity intensity of pillar, is being used In be easily deformed and can not be continuing with, will unbalance stress if occurring deformation in work progress, it is difficult to bear above Weight and there is engineering accident.And the pillar positioned with latch can not realize fine setting, therefore machining precision requires high, difficulty Greatly.
Also part construction site uses steel tubular support with couplers, provided with span one outside support body increase support frame loading zone One corresponding critical load requirement, does not increase the outer span of support frame loading zone and improves frame structure bearing capacity method, scene with Experience is set up, on the one hand, is caused the increase of waste of material cost, on the other hand, is caused potential safety hazard, and what is had even occurs great peace Full accident.
The content of the invention
In place of in order to overcome the above-mentioned deficiencies of the prior art, it is an object of the invention to provide the branch that a kind of engineering construction is used Support structure.
The technical scheme is that:
The supporting construction that a kind of engineering construction is used, including:Support platform, the space support body in support platform; The space support body is included in multiple support units of vertical or/and horizontal direction superposition, for connecting adjacent supports unit Multiple connectors;The support unit is provided with current breach;The current breach of the adjacent supports unit is connected, to be formed Transit passage;The space support body and the removable connection of support platform.
Its further technical scheme is:The support unit includes the right prism or cylinder being made up of multiple side plates.
Its further technical scheme is:The side of the support unit or many side openings, support unit also include being used for Support side plate and the support component for being bordering on the opening.
Its further technical scheme is:The support unit includes being made up of panel assembly and side or many side openings Cuboid or square;The panel assembly is that one piece of connecting plate or two orthogonal connecting plates or three are orthogonal Connecting plate.
Its further technical scheme is:The support unit includes right prism or cylindrical space skeleton, and located at space Fixed plate on the outside of skeleton.
Its further technical scheme is:The support unit includes an at least root post, upper cover plate and lower cover;It is described vertical The two ends of post are fixedly connected with upper cover plate and lower cover respectively.
Its further technical scheme is:The support unit is additionally provided with air vent, loophole, lightening hole or connected for installation The connecting hole of fitting.
Its further technical scheme is:The transit passage includes horizontal channel and Vertical Channel;The engineering construction makes Supporting construction also includes in support unit and is communicated in the cat ladder of Vertical Channel.
Its further technical scheme is:Sealing waterproof layer is additionally provided between the adjacent supports unit;The engineering construction The supporting construction used also includes the part that keeps off the rain located at the external side of space support.
Its further technical scheme is:The supporting construction that the engineering construction is used also includes being used to adjust support platform height The adjusting part of degree;The adjusting part is located at the lower section of support platform;The adjusting part include adjusting screw rod, base, with And locking member;The support platform is provided with the regulation screwed hole being engaged with adjusting screw rod;The locking member locks adjusting screw rod In support platform.
Its further technical scheme is:The supporting construction that the engineering construction is used also include be used for detect adjusting part by The pressure sensor of power, the processor being connected with pressure sensor, the display screen and alarm being connected respectively with processor.
Its further technical scheme is:The support platform include some crossbeams, and be fixedly connected with crossbeam it is some Longeron;The adjusting part is connected with crossbeam or longitudinal beam-adjustable.
The present invention having the technical effect that compared with prior art:The supporting construction that a kind of engineering construction is used, according to building The profile of structure builds multiple space support bodies in support platform, and adjacent space support body is fixed by connector Come, a stable support overall structure is formed, to ensure load-bearing requirements during construction.A kind of engineering construction of the present invention makes Supporting construction, it is the support of face body to improve present point face support, and it is an entirety to make support section, and the weight of support is uniform It is distributed on each stress surface, so considerably increases the security of system, and gravity vertical, adjustable stress can also be adjusted It point, can move, may be reused, and with the assembly and disassembly time is reduced, reduce construction cost, reduction technical difficulty, improve work The features such as making efficiency.
Further, support unit includes the right prism or cylinder that are made up of multiple side plates, and being assembled into using side plate can be by The stable body structure of power.Quick-assembling can be achieved, speed is built also very soon, also, stress object in support platform For the panel of support unit.The stress equalization of supporting construction, the load that can be carried is big, and stability is high, and workmen is single in support Security in first during current operation is also high.
Further, the one side or the multi-lateral opening of support unit, and be provided with support component to ensure support unit in opening Stress stability, while overall weight can also be mitigated, lower manufacturing cost.
Further, support unit be made up of panel assembly and side or many side openings cuboid or square.Face After plate dismounting, transport can be overlapped mutually, to reduce transport space.
Further, support unit includes right prism or cylinder, the spatial skeleton that column is constituted and combines fixed panel, shape Into stable supporting construction, can either load-bearing can mitigate weight again.
Further, transit passage is provided with support unit, can as operating personnel aisle, can also make as transport Industry passage.
Further, position or the height of support platform are adjusted by adjusting part, to reach the whole supporting construction weight of balance The purpose of the heart, it is to avoid security incident occur because local pressure is uneven.
Further, the stressing conditions of adjusting part, the pressure detected when pressure sensor are detected by pressure sensor During more than setting value, processor can control alarm carry out early warning so that potential safety hazard can in time early warning, and occur accident it It is preceding to be just resolved.
Further, support platform lower end is additionally provided with universal wheel group, during the building such as repairing overpass, it is only necessary to split part Then structure moves to next place and can just reuse, and has saved the substantial amounts of assembly and disassembly time.
The invention will be further described with specific embodiment below in conjunction with the accompanying drawings.
Brief description of the drawings
Fig. 1 is the structural representation for the supporting construction that a kind of engineering construction of the invention is used;
Fig. 2 is the structural representation of support platform of the present invention;
Fig. 3 is the circuit block diagram that the supporting construction that a kind of engineering construction of the invention is used is used to point out pressure data size;
Fig. 4 is the side view of locking member of the present invention;
Fig. 5 is the connection diagram of space support body of the present invention;
Fig. 6 is the side view panel figure of support unit of the present invention;
Fig. 7 is the side view of support unit second embodiment case shape space structure of the present invention;
Fig. 8 is the side view of support unit 3rd embodiment of the present invention;
Fig. 9 is the schematic diagram of first embodiment of the invention column travel position;
Figure 10 is the schematic diagram of the nested travel position of first embodiment of the invention column;
Figure 11 is the schematic diagram of panel assembly first embodiment travel position of the present invention;
Figure 12 is the schematic diagram of panel assembly second embodiment travel position of the present invention;
Figure 13 is the schematic diagram of panel assembly 3rd embodiment travel position of the present invention.
Reference
The support platform of 10 supporting construction 1
The screwed hole of 11 crossbeam 111
The support unit of 12 longeron 2
The 21 current columns of breach 22
The upper cover plate of 221 connecting pole 23
The side plate of 24 lower cover 25
The connecting plate of 26 panel assembly 261
The batter post of 27 pillar 28
The connector of 29 support column 3
The adjusting part of 4 cat ladder 5
The plug-in opening of 51 adjusting screw rod 511
The locking member of 52 base 53
The locking hole of 531 extension 532
6 universal wheel groups 7 are kept off the rain part
The processor of 81 pressure sensor 82
The 83 display alarms of (screen) device 84
85 buttons
Embodiment
It is further to technical scheme with reference to schematic diagram in order to more fully understand the technology contents of the present invention Introduce and illustrate, but be not limited to this.
The supporting construction that a kind of engineering construction is used, is used, it is necessary to carry certain in architectural engineering as supporting construction Load.The supporting construction that a kind of engineering construction is used, including:Support platform, the space support body in support platform.Space Supporter is included in multiple support units of vertical or/and horizontal direction superposition, multiple companies for connecting adjacent supports unit Fitting.Support unit is provided with current breach, and the current breach of adjacent supports unit is connected, with the inner space with support unit It is collectively forming transit passage, space support body and the removable connection of support platform.When actual use, building for space support body is Depending on the profile of building body and construction.Therefore, the stacked system of support unit can be vertical or/and horizontal direction is folded Plus.When it is implemented, support unit is a kind of space fixed structure, physical deformation will not be occurred by bearing certain external force, i.e., grand Seeing volume will not change.Therefore, support unit can be container body, cylinder, column assembly, cuboid, square etc. Rule and the composite unit structure of easy processing shaping.The material of support unit can be metal, timber, plastics, fiberglass, rubber Deng.The specific size of support unit can be made according to Specific construction situation.Under same execution conditions, manufactured size differs The support unit of sample size, can also make different spatial group whole body structures, combined using a variety of spatial group zoariums and be assembled into Meet the space support body of construction requirement.Connector can be the block for connecting two support units closer to the distance, It can be the rod-like element for connecting two distant support units.
As shown in figure 1, the supporting construction 10 that a kind of engineering construction is used, including:Support platform 1, in support platform 1 Space support body.Space support body is included in multiple support units 2 of vertical and horizontal direction superposition, for connecting adjacent branch Multiple connectors of unit 2 are supportted, support unit 2 is provided with current breach 21.The current breach 21 of adjacent supports unit 2 is connected, To form transit passage.Space support body and the removable connection of support platform 1.
In the present embodiment, support unit 2 includes the cuboid being made up of multiple side plates 25, according to specific construction need Ask, in the side of support unit 2 or many side openings.Rust resistance and corrosion resistance processing is done in the outside of side plate 25, to improve support unit 2 Service life.Support unit 2 also includes for support side plate 25 and is bordering on the support component of opening, the effect master of support component It is easy for ensureing that at opening external force can be born, so as to ensure the force stability of whole support unit 2.If when it is implemented, The cuboid that side plate 25 is constituted itself can bear to meet the external force of construction requirement, and support unit 2 can also be not provided with support Component.In other embodiments, support unit 2 can be that container body, cylinder, the column being made up of multiple side plates 25 are combined The stable space structure such as body, square.It is preferred that, support unit 2 uses right prism or cylindrical structure.
Transit passage includes horizontal channel and Vertical Channel, and the supporting construction 10 that engineering construction is used also is included located at support Unit 2 is interior and is communicated in the cat ladder 4 of Vertical Channel.Workmen can be walked about in transit passage and article transport.And And, due to there is the protection of side plate 25, it can also avoid falling the dangerous objects such as stone on building body.Due to the bottom plate of transit passage Steadily, the security that operating personnel advance is also very high, therefore the splicing structure of support unit is effectively guaranteed operating personnel's Life safety.
The supporting construction 10 that engineering construction is used also includes the adjusting part 5 for being used to adjust the height of support platform 1, regulation group Part 5 is located at the lower section of support platform 1.Adjusting part 5 includes adjusting screw rod 51, base 52, and locking member 53.Support platform 1 Provided with the regulation screwed hole being engaged with adjusting screw rod 51.Locking member can lock adjusting screw rod 51 in support platform 1, to prevent non- Under normal operating state, it have adjusted adjusting screw rod 51 and cause stress balance to be broken.Wherein, adjusting screw rod 51 is perpendicular to ground Face, before use, the position of each adjusting screw rod 51 and support platform 1 has been pre-adjusted, to cause support platform 1 to be in level, So as to avoid the discontinuity equalization of supporting construction 10 that engineering construction is used.
The supporting construction 10 that engineering construction is used also includes the universal wheel group 6 located at the lower end of support platform 1, if support platform 1 also needs to be moved to other places and is continuing with.When such as building overpass, the progress of supporting construction 10 office that engineering construction can be used Portion is split, at the A-A in such as figure, and being then moved to another position by support platform 1 carries out assembly, can save substantial amounts of Assembling duration.
It is preferred that, the supporting construction 10 that engineering construction is used also includes the part 7 that keeps off the rain located at the external side of space support.
As shown in Fig. 2 support platform 1 includes many crossbeams 11, and many longerons 12 being fixedly connected with crossbeam 11, branch The global shape of support platform 1 specifically requires to be built when being according to construction.Adjusting part 5 and the adjustable connection of crossbeam 11, One end of crossbeam 11 extends laterally, and provided with the screwed hole being engaged with adjusting screw rod 51.When it is implemented, according to specific Condition of construction, support platform 1 can also assemble by many beams longitudinal and transverse, that oblique is wrong.When it is implemented, adjusting part 5 Also can be according to actual conditions and the adjustable connection of longeron 12.
After support platform 1 is put up, a support unit 2 is lifted and is placed on specified location, then layer by layer Put, pile after one layer, carried out all being connected with dormant bolt, so that each layer is all more smooth.Next again with hanging One layer above Che Fanggeng, a space support body is finally spliced into.
As shown in figure 3, the pressure that the supporting construction 10 that engineering construction is used also includes being used to detect the stress of adjusting part 5 is passed Sensor 81, the processor 82 being connected with pressure sensor 81, the display screen 83 and alarm 84 being connected respectively with processor 82, with And for operation or the button 85 of arrange parameter.When the load ratio that the somewhere for the supporting construction 10 that engineering construction is used is subject to relatively collects When middle, the pressure data that the pressure sensor 81 of support platform 1 is detected can be significantly increased, and processor 82 will can also be detected Data display, will when processor 82, which detects the data that pressure sensor 81 passes back, is more than setting value on display screen 83 Control alarm 84 to carry out early warning, to cause the attention of workmen, so as to anticipate, it is to avoid accident occurs, play effectively Anti- pre- suggesting effect.
As shown in figure 4, locking member 53 is a tube-like piece for being sheathed on the upper end of adjusting screw rod 51, the lower end of locking member 53 is provided with Two extensions 531 extended downwardly, its upper end is provided with some locking holes 532, and the upper end of adjusting screw rod 51 also is provided with plug-in opening 511 (with reference to Fig. 1).After the position adjustments of support platform 1 and adjusting screw rod 51 are good, locking member 53 is set in adjusting screw rod 51 Upper end, and anti-skidding latch or locking bar are inserted into locking hole 532 and plug-in opening 511, because crossbeam 11 is located at two extensions Between portion 531, therefore, locking member 53 can not be rotated relative to crossbeam 11, be inserted between locking member 53 and adjusting screw rod 51 due to anti-skidding The effect of pin or locking bar will not also rotate, and support platform 1 will not produce change in location with adjusting screw rod 51, so as to ensure branch Support the stability and security of platform 1.
As shown in figure 5, being connected between adjacent support unit 2 using connector 3, so that space support body is one Can overall uniform stressed structure.The connecting hole corresponding with connector 3 is also equipped with support unit 2, in order to pass through spiral shell Bolt is connected.When it is implemented, connector 3 can be bolt, latch, lock etc..
It is preferred that, sealing waterproof layer is additionally provided between adjacent supports unit 2, antirust, anti-corrosive is also made in the outside of support unit 2 Erosion is handled, to improve the service life and reliability of support unit 2.
As shown in fig. 6, support unit 2 is additionally provided with air vent, loophole, lightening hole or the connection for installation connecting element 3 Hole.Air vent, loophole, lightening hole are all in the case where not influenceing support unit 2 to bear load, according to specific construction feelings What condition was configured.
As shown in fig. 7, support unit 2 includes four columns 22 being parallel to each other, upper cover plate 23 and lower cover 24, column 22 Two ends be fixedly connected respectively with upper cover plate 23 and lower cover 24.When it is implemented, column can be interfixed by one or more Connecting pole composition.
In other embodiments, support unit is included by a root post, and upper cover plate and lower cover, the two ends of column It is fixedly connected respectively with upper cover plate and lower cover.
In other embodiments, support unit is included by many columns being parallel to each other, and upper cover plate and lower cover, The two ends of column are fixedly connected with upper cover plate and lower cover respectively.Also, in order to ensure the load-carrying properties of support unit, Ke Yi Oblique bracing piece or reinforcing prop is set between column.
As shown in figure 8, support unit 2 includes the five or many pillars 27 being parallel to each other, many batter posts 28, and fix In the support column 29 of pillar upper and lower ends.
As shown in figure 9, the two ends of connecting pole 221 are respectively equipped with two ring flanges, ring flange, which is provided with, is used for bolt locking Fixing hole.It is preferred that, connecting pole is in the case where ensure that and do not influence support unit 2 to bear load, according to specifically applying Work situation is configured.During transport, connecting pole can be with transport close to each other, to save cost of transportation, improve conevying efficiency.
As shown in Figure 10, one end of connecting pole 221 is provided with ring flange, and ring flange, which is provided with, is used for the fixation that bolt is locked Hole.It is preferred that, in the specific implementation, because the load suffered by each load bearing unit is different, therefore, at all levels, region Load bearing unit connecting pole can also ensure do not influence support unit 2 to bear load in the case of, it is big using different-diameter Small connecting pole.During transport, the connecting pole of different-diameter size can nest together transport, to save cost of transportation, raising Conevying efficiency.
As shown in figure 11, support unit 2 includes the cuboid being made up of multiple side plates 25, wherein, the side of support unit 2 Opening.In the specific implementation, because the load suffered by each load bearing unit is different, therefore, at all levels, region carrying Unit can also be in the case where ensureing not influenceing support unit 2 to bear load, using different lengths.During transport, no Support unit 2 with size can nest together transport, five face superpositions, to save cost of transportation, improve conevying efficiency.
As shown in figure 12, support unit 2 include being made up of panel assembly 26 and the cuboid of side or many side openings or Square, panel assembly 26 is two orthogonal connecting plates 261.During transport, support unit 2 can be superimposed with two faces, with Save cost of transportation, improve conevying efficiency.
As shown in figure 13, support unit 2 include being made up of panel assembly 26 and the cuboid of side or many side openings or Square, panel assembly 26 is three orthogonal connecting plates 261.During transport, support unit 2 can be superimposed with three faces, with Save cost of transportation, improve conevying efficiency.
When it is implemented, support unit 2 can also be by one piece one piece panel or support component, according to specific requirement group Into.During transport, transport can be directly stacked, to save cost of transportation, improve conevying efficiency.
One support unit 2 can also be by two orthogonal connecting plates 261 and three orthogonal connecting plates 261 It is assembled.
The surface of panel assembly 26 can also set air vent, loophole, lightening hole or for installation connecting element 3 according to demand Connecting hole, rust resistance and corrosion resistance processing is made on surface, to improve the service life and reliability of support unit 2.
In other embodiments, support unit includes right prism or cylindrical space skeleton, and support unit also includes being located at Fixed plate on the outside of spatial skeleton.Fixed plate may also set up air vent, loophole, lightening hole or the connection for installation connecting element Rust resistance and corrosion resistance processing is made on hole, surface, to improve the service life and reliability of support unit.
The above-mentioned technology contents that the present invention is only further illustrated with embodiment, in order to which reader is easier to understand, but not Represent embodiments of the present invention and be only limitted to this, any technology done according to the present invention extends or recreated, by the present invention's Protection, protection scope of the present invention is defined by claims.

Claims (12)

1. the supporting construction that a kind of engineering construction is used, it is characterised in that including:Support platform, the sky in support platform Between supporter;The space support body is included in multiple support units of vertical or/and horizontal direction superposition, adjacent for connecting Multiple connectors of support unit;The support unit is provided with current breach;The current breach of the adjacent supports unit is connected It is logical, to form transit passage;The space support body and the removable connection of support platform.
2. the supporting construction that engineering construction according to claim 1 is used, it is characterised in that the support unit include by Right prism or cylinder that multiple side plates are constituted.
3. the supporting construction that engineering construction according to claim 2 is used, it is characterised in that the side of the support unit Or many side openings, support unit also includes for support side plate and is bordering on the support component of the opening.
4. the supporting construction that engineering construction according to claim 1 is used, it is characterised in that the support unit include by The cuboid or square of panel assembly composition and side or many side openings;The panel assembly is one piece of connecting plate or two Orthogonal connecting plate or three orthogonal connecting plates.
5. the supporting construction that engineering construction according to claim 1 is used, it is characterised in that the support unit includes straight Prism or cylindrical space skeleton, and the fixed plate on the outside of spatial skeleton.
6. the supporting construction that engineering construction according to claim 1 is used, it is characterised in that the support unit is included extremely A few root post, upper cover plate and lower cover;The two ends of the column are fixedly connected with upper cover plate and lower cover respectively.
7. the supporting construction that engineering construction according to claim 1 is used, it is characterised in that the support unit is additionally provided with Air vent, loophole, lightening hole or the connecting hole for installation connecting element.
8. the supporting construction that engineering construction according to claim 1 is used, it is characterised in that the transit passage includes water Flat passage and Vertical Channel;The supporting construction that the engineering construction is used also includes in support unit and is communicated in vertical logical The cat ladder in road.
9. the supporting construction that engineering construction according to claim 1 is used, it is characterised in that the adjacent supports unit it Between be additionally provided with sealing waterproof layer;The supporting construction that the engineering construction is used also includes keeping off the rain located at the external side of space support Part.
10. the supporting construction that engineering construction according to claim 1 is used, it is characterised in that the engineering construction is used Supporting construction also include being used to adjust the adjusting part of support platform height;The adjusting part is located under support platform Side;The adjusting part includes adjusting screw rod, base, and locking member;The support platform is provided with and is engaged with adjusting screw rod Regulation screwed hole;The locking member locks adjusting screw rod in support platform.
11. the supporting construction that engineering construction according to claim 10 is used, it is characterised in that the engineering construction is used Supporting construction also include being used to detect the pressure sensor of adjusting part stress, processor be connected with pressure sensor divides The display and alarm not being connected with processor.
12. the supporting construction that engineering construction according to claim 10 is used, it is characterised in that the support platform includes Some crossbeams, and some longerons being fixedly connected with crossbeam;The adjusting part is connected with crossbeam or longitudinal beam-adjustable.
CN201710624095.8A 2017-07-27 2017-07-27 The supporting construction that a kind of engineering construction is used Pending CN107269028A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710624095.8A CN107269028A (en) 2017-07-27 2017-07-27 The supporting construction that a kind of engineering construction is used

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710624095.8A CN107269028A (en) 2017-07-27 2017-07-27 The supporting construction that a kind of engineering construction is used

Publications (1)

Publication Number Publication Date
CN107269028A true CN107269028A (en) 2017-10-20

Family

ID=60079248

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710624095.8A Pending CN107269028A (en) 2017-07-27 2017-07-27 The supporting construction that a kind of engineering construction is used

Country Status (1)

Country Link
CN (1) CN107269028A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111335483A (en) * 2018-12-18 2020-06-26 王琛 Self-locking structure for building

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3881571A (en) * 1973-10-19 1975-05-06 Michael Maldwyn Moulton Building unit for scaffolding or a trestle
CN101538929A (en) * 2009-04-20 2009-09-23 许树根 Vertical tower device of mast climb type aerial working platform
US20110162293A1 (en) * 2010-01-06 2011-07-07 Jared Levy Modular Housing
CN102191852A (en) * 2010-02-25 2011-09-21 约翰·克莱门特·普雷斯顿 Scaffolding
CN103628700A (en) * 2013-11-08 2014-03-12 中天建设集团有限公司 Detachable stairway for construction
CN205088929U (en) * 2015-09-29 2016-03-16 中国建筑第八工程局有限公司 Portable operation platform base of keyway formula
CN205935746U (en) * 2016-07-05 2017-02-08 广州市第二市政工程有限公司 Simple and easy terraced barreled is put
CN206928695U (en) * 2017-07-27 2018-01-26 范雄杰 The supporting construction that a kind of engineering construction uses

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3881571A (en) * 1973-10-19 1975-05-06 Michael Maldwyn Moulton Building unit for scaffolding or a trestle
CN101538929A (en) * 2009-04-20 2009-09-23 许树根 Vertical tower device of mast climb type aerial working platform
US20110162293A1 (en) * 2010-01-06 2011-07-07 Jared Levy Modular Housing
CN102191852A (en) * 2010-02-25 2011-09-21 约翰·克莱门特·普雷斯顿 Scaffolding
CN103628700A (en) * 2013-11-08 2014-03-12 中天建设集团有限公司 Detachable stairway for construction
CN205088929U (en) * 2015-09-29 2016-03-16 中国建筑第八工程局有限公司 Portable operation platform base of keyway formula
CN205935746U (en) * 2016-07-05 2017-02-08 广州市第二市政工程有限公司 Simple and easy terraced barreled is put
CN206928695U (en) * 2017-07-27 2018-01-26 范雄杰 The supporting construction that a kind of engineering construction uses

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111335483A (en) * 2018-12-18 2020-06-26 王琛 Self-locking structure for building
CN111335483B (en) * 2018-12-18 2021-08-17 王琛 Self-locking structure for building

Similar Documents

Publication Publication Date Title
CN104141383B (en) A kind of Bailey beam pendent form support system and construction thereof
CN101725255A (en) Segmental slipping and assembling process of overhead large-span steel structure
CN103195256B (en) Hanging column type steel structure jig frame construction method
CN105003090B (en) Temporary support frame for mounting assembly type steel structure
CN101435276A (en) Cabin top steel beam hydraulic hoisting and positioning apparatus of cylinder cabin structure building and construction method thereof
CN204781881U (en) Elevartor shaft structure construction handling frame
CN104372961A (en) Anti-seismic integrated lightweight steel construction house
CN105040986A (en) Modular mounting technology for steel-structure door type frame roof system
CN102337782B (en) Lift system for constructing truss platform on top of tall and large space
CN108868096A (en) It is fixed on the outer protection tripod of pin-connected panel safety and its application method of precast facade
CN206928695U (en) The supporting construction that a kind of engineering construction uses
CN101868701A (en) Modular weighbridge
CN111456422A (en) Belt supporting device and method for conical steel truss on top of sliding-form silo of squat silo wall
CN102322134B (en) Method for determining difference in bearing capacities of fastener-type full space support frame and full space scaffold
CN107269028A (en) The supporting construction that a kind of engineering construction is used
CN204876631U (en) Assembled steel structure installation uses interim support frame
CN103523665A (en) Transport device and method for gantry crane
CN103628692A (en) Floor beam mounting bracket and use and construction method thereof
CN205777531U (en) Floor slab construction beam string shuttering supporting equipment
CN104594631B (en) The construction technology of sliding form apparatus traction operation platform construction granulation tower spraying layer
CN103225411A (en) Existing line protective shed
CN107806264B (en) Engineering method of assembled parking frame and parking frame
CN201610974U (en) Installing structure of large-span cable bridge frame
CN201649618U (en) Wall-attaching device for building safe operating platform
CN205840384U (en) Concrete column beam connecting node underpinning device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination