CN107268458A - A kind of double width continuous rigid frame bridge tied arch ruggedized construction and its construction method - Google Patents

A kind of double width continuous rigid frame bridge tied arch ruggedized construction and its construction method Download PDF

Info

Publication number
CN107268458A
CN107268458A CN201710445588.5A CN201710445588A CN107268458A CN 107268458 A CN107268458 A CN 107268458A CN 201710445588 A CN201710445588 A CN 201710445588A CN 107268458 A CN107268458 A CN 107268458A
Authority
CN
China
Prior art keywords
mrow
skewback
crossbeam
msub
suspension rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710445588.5A
Other languages
Chinese (zh)
Other versions
CN107268458B (en
Inventor
薛兴伟
华旭东
李宏男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenyang Jianzhu University
Original Assignee
Shenyang Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang Jianzhu University filed Critical Shenyang Jianzhu University
Priority to CN201710445588.5A priority Critical patent/CN107268458B/en
Publication of CN107268458A publication Critical patent/CN107268458A/en
Application granted granted Critical
Publication of CN107268458B publication Critical patent/CN107268458B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D12/00Bridges characterised by a combination of structures not covered as a whole by a single one of groups E01D2/00 - E01D11/00
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Abstract

A kind of double width continuous rigid frame bridge tied arch ruggedized construction, main arch ring is made up of concrete arch rib and steel skewback, and steel skewback is embedded in the skewback crossbeam above bridge pier between two endosternums;The tie-rod for having in skewback crossbeam by the way that conduit is embedded, being anchored after tensioning;Along the suspension rod anchorage beam being symmetrically placed in along bridge to having centered in bridge across center line between two endosternums;The upper and lower ends of suspension rod are each passed through corresponding conduit on concrete arch rib and suspension rod anchorage beam, are anchored after tensioning.The radical of steel strand wires is tried to achieve by company in the size of skewback crossbeam and per pass tie-rod in the ruggedized construction, it is ensured that the horizontal displacement of skewback crossbeam is no more than [Δ], and reliable basis is provided for main arch ring;Tie-rod in skewback crossbeam can balanced car load, tensioning suspension rod and main arch ring from the horizontal force that is produced on skewback crossbeam is focused on, skewback crossbeam and main arch ring is in optimal stress;To solve the construction technical schemes for providing complete set in double width continuous rigid frame bridge across the excessive disease of middle span deflexion.

Description

A kind of double width continuous rigid frame bridge tied arch ruggedized construction and its construction method
Technical field
The present invention relates to science of bridge building, particularly a kind of tied arch ruggedized construction suitable for double width continuous rigid frame bridge and its Construction method.
Background technology
After substantial amounts of double width continuous rigid frame bridge comes into operation, some diseases often occur, wherein more typical disease is In continuous rigid frame bridge across span centre produce excessive downwarp.
For this technical problem, CN102322019A patent documents disclose a kind of tied arch-T-shaped firm structure co-operative system Bridge.The system is that concrete arch rib, tie-rod and suspension rod are set up in general T-shaped firm structure girder, and T-shaped firm structure uses concrete material Material.Its construction costs is lower than the cable-stayed bridge or suspension bridge of equal across footpath, is suitable for long-span bridge girder construction;Using donor system, make Structure does not have horizontal thrust, low to fundamental importance.
But there is following technology barrier when being applied to solve the above-mentioned disease of double width continuous rigid frame bridge by the technology:
(1) complete, effective construction technical schemes are lacked;
(2) effective anchoring process is lacked at tied arch arch springing;
(3) above-mentioned patent document does not determine the stretching force of tie-rod, and excessive application tie member tensioning power is likely to result in skewback horizontal stroke The destruction of beam and redistributing for main arch ring stress;Tie member tensioning power is not enough, then main arch ring can produce horizontal thrust at arch springing.
The content of the invention:
The purpose of the present invention is that a kind of simple in construction, construction technical schemes are provided the problem of presence for above-mentioned prior art Perfect, quick construction, safe and reliable and good economy performance double width continuous rigid frame bridge tied arch ruggedized construction and its construction method.
To achieve these goals, the double width continuous rigid frame bridge tied arch ruggedized construction that the present invention is provided, including main arch ring, Tie-rod and suspension rod;It is characterized in:
Two steel skewbacks that the main arch ring connects by concrete arch rib and respectively with concrete arch rib two ends are constituted, main The arch of arch ring is second-degree parabola;Described two steel skewbacks are embedded in skewback crossbeam respectively, and skewback crossbeam is placed in bridge Above pier, between the endosternum of the width of double width continuous rigid frame bridge two;The quantity of the tie-rod is that the horizontal stroke of skewback crossbeam (is pressed in 3~10 roads Bridge is chosen to width), per pass tie-rod is each passed through the conduit a that horizontal homogeneous interval is embedded in skewback crossbeam, after the tensioning of two ends It is anchored on two skewback crossbeams;Along along bridge to have centered in continuous rigid frame bridge across center line it is symmetrical, uniform between Have vertical embedded in suspension rod anchorage beam between the endosternum of the width of double width continuous rigid frame bridge two is arranged in, suspension rod anchorage beam Conduit b;Have in concrete arch rib and conduit b corresponding, vertical embedded conduit c vertically up and down;The upper and lower ends of the suspension rod Mutual corresponding conduit c and conduit b are each passed through, is anchored at after tensioning on concrete arch rib and suspension rod anchorage beam;
The skewback crossbeam is along bridge to length bGZ=0.3L0~0.6L0, direction across bridge width is equal to Db, height hGZAs the following formula Calculate:
Wherein:
L0:No. zero block length (m) of girder,
Any real number that roundup [number, Num_digits], number are rounded up to for needs, Num_digits After rounding-off digital decimal digits (such as roundup [5.325,1]=5.4, for another example roundup [3,1]=3.0),
Ec:The modulus of elasticity (MPa) of skewback crossbeam concrete,
bGZ:Skewback crossbeam along bridge to length (m),
Db:The clear distance (m) of two endosternums,
f:The rise (m) of arch,
L:In across across footpath (m),
Nml:The maximum axial pressure (kN) that carload is produced at arch springing, can be by setting up bridge structure finite element mould Type is calculated,
Nd:The axial compressive force (kN) that tensioning suspension rod is produced at arch springing, can be by setting up bridge structure FEM model meter Draw,
NG:Main arch ring, can be by setting up bridge structure FEM model from the axial compressive force (kN) for focusing on generation at arch springing Calculate,
[Δ]:The permissible value (mm) of skewback crossbeam horizontal displacement, can be calculated by setting up bridge structure FEM model Go out;
The radical n of steel strand wires, which is calculated as follows, in the per pass tie-rod draws:
In formula:
Any real number that roundup [number, Num_digits], number are rounded up to for needs, Num_digits After rounding-off digital decimal digits (such as roundup [5.325,1]=5.4, for another example roundup [3,1]=3.0),
f:The rise (m) of arch,
L:In across across footpath (m),
σcon:The control stress for prestressing of steel strand wires, its value is 1302~1395 (MPa),
AP1:Area of section (the mm of single steel strand2),
NPS:The road number of tie-rod,
Nml:The maximum axial pressure (kN) that carload is produced at arch springing, can be by setting up bridge structure finite element mould Type is calculated,
Nd:The axial compressive force (kN) that tensioning suspension rod is produced at arch springing, can be by setting up bridge structure FEM model meter Draw,
NG:Main arch ring, can be by setting up bridge structure FEM model from the axial compressive force (kN) for focusing on generation at arch springing Calculate.
The construction method of above-mentioned double width continuous rigid frame bridge tied arch ruggedized construction, comprises the following steps:
Step 1: constructing skewback crossbeam
Brushwork epoxy resin after dabbing, bar planting is carried out to the endosternum surface of the double width being equipped with skewback crossbeam, so After set up template, colligation skewback crossbeam reinforcing bar, casting concrete formation skewback crossbeam, while opening up hole above skewback crossbeam Hole, by hole in each skewback crossbeam pre-buried steel skewback, and the conduit a that pre-buried confession tie-rod is passed through in skewback crossbeam;
Step 2: constructing suspension rod anchorage beam
Brushing asphalt mixtures modified by epoxy resin after dabbing, bar planting is carried out to the endosternum surface of the double width being equipped with suspension rod anchorage beam Fat, then sets up template, assembling reinforcement, casting concrete formation suspension rod anchorage beam, while being opened above suspension rod anchorage beam Apertured hole, through the hole conduit b that vertical pre-buried confession suspension rod is passed through inside suspension rod anchorage beam;
Step 3: constructing concrete arch rib
Template, assembling reinforcement, the concrete arch rib that connects with steel skewback of casting concrete formation are set up, while in coagulation The conduit c that the pre-buried confession suspension rod is passed through in native arch rib;
Step 4: installing and stretch tie-bar
The two ends of tie-rod are each passed through in two skewback crossbeams mutual corresponding conduit a, after taken stretching force tensioning It is anchored on skewback crossbeam;
Step 5: tensioning suspension rod
By suspension rod one by one through vertical mutually corresponding conduit b and conduit c up and down, carry out anchoring after tensioning according to a conventional method On suspension rod anchorage beam and concrete arch rib, terminate construction.
The beneficial effects of the invention are as follows:
(1) present invention constructs skewback crossbeam by the physical dimension of restriction, can effectively ensure that carload encircles in skewback crossbeam The maximum axial pressure N produced at pinml, the axial compressive force N that is produced at arch springing of tensioning suspension roddFocused on certainly at arch springing with main arch ring The axial compressive force N of generationGDeng load to (contribution for disregarding the horizontal pull of tie-rod) under the collective effect of skewback crossbeam, horizontal position Move and be no more than [Δ], it is ensured that the rigidity of skewback crossbeam can make main arch ring be in good stress, can be failed again in tie-rod Extreme case under the safety of main arch ring is effectively ensured, so as to provide reliable basis for main arch ring.
(2) because excessive application tie member tensioning power is likely to result in the destruction of skewback crossbeam and redistributing for main arch ring stress, In the present invention in skewback crossbeam the road number of tie-rod press skewback crossbeam direction across bridge width it is selected after, the root of steel strand wires in single track tie-rod Number presses calculation formulaTry to achieve, can properly balanced carload arch The maximum axial pressure N produced at pinml, the axial compressive force N that is produced at arch springing of tensioning suspension roddFocused on certainly at arch springing with main arch ring The axial compressive force N of generationGThe horizontal force produced Deng load on skewback crossbeam, makes skewback crossbeam and main arch ring be in optimal stress State.
(3) present invention on skewback crossbeam by setting main arch ring, it is only necessary to which 1 set of tied arch ruggedized construction can complete double width The reinforcing of continuous rigid frame bridge, compared with prior art, can save half quantities, save the duration, good economy performance.
(4) present invention in effectively solution double width continuous rigid frame bridge across the excessive disease of middle span deflexion provide it is a set of complete Whole, effective, unique construction technical schemes.
Brief description of the drawings:
Fig. 1 is the elevational schematic view of double width continuous rigid frame bridge tied arch ruggedized construction of the present invention, span centre during ZXX is represented in figure Heart line, GZX represents the arch of main arch ring;
Fig. 2 is Fig. 1 A-A sectional views;
Fig. 3 is Fig. 1 B-B sectional drawings;
In figure:1- double width continuous rigid frame bridges, 2- skewback crossbeams, 3- endosternums, 4- anchorage beams, 51- conduits a, 52- conduit B, 53- conduit c, 6- main arch ring, 61- concrete arch ribs, 62- steel skewbacks, 7- suspension rods, 8- tie-rods, 9- bridge piers.
Embodiment:
The invention will be further described with reference to the accompanying drawings and examples.
As shown in figure 1, the bridge of the present embodiment double width continuous rigid frame bridge 1 to be reinforced is combined as (65+120+65) m, the bridge In across across footpath L=120m, No. zero block length L of girder0=10m, the clear distance D of the endosternum 3 of two widthb=10m, wherein across span centre Downwarp 18.0cm.
The ruggedized construction reinforced using the present invention to it includes main arch ring 6, tie-rod 8 and suspension rod 7;The main arch ring 6 The two steel skewbacks 62 connected by concrete arch rib 61 and respectively with concrete arch rib two ends are constituted, the arch of main arch ring 6 For second-degree parabola, the rise f=26.7m of arch, the section of concrete arch rib 61 be 4m (along bridge to) × 2.4m (direction across bridge), Wall thickness is 0.6m;The section of steel skewback 62 be 4m (along bridge to) × 2.4m (direction across bridge), wall thickness is 40mm, using Q345 steels Into;Described two steel skewbacks 62 are respectively buried in skewback crossbeam 2, and skewback crossbeam is respectively placed in the interior abdomen of two width of the top of bridge pier 9 Between plate 3;The quantity of the tie-rod 8 is 4 roads, passes through a diameter of Φ 200mm spaced 200cm water of 4 conduit a51 respectively It is flat to be embedded in skewback crossbeam 2, it is anchored at after the two ends tensioning of per pass tie-rod on two skewback crossbeams;Along bridge to continuous with double width Have in rigid frame bridge centered on center line between the endosternum 3 for being symmetrically arranged in two width, spaced 9 suspension rods for 10m Anchorage beam 4, the long 2m of suspension rod anchorage beam, the wide 10m of direction across bridge (are equal to the clear distance D of two endosternumsb), high 1m, suspension rod anchoring is horizontal Liang Zhongyou is vertically buried, a diameter of Φ 100mm conduit b52;Have corresponding, perpendicular vertically up and down with conduit b in concrete arch rib 61 To embedded, a diameter of Φ 100mm conduit c53;The upper and lower ends of the suspension rod of nine different lengths are each passed through mutually corresponding Conduit c and conduit b, is anchored at after tensioning on concrete arch rib and suspension rod anchorage beam.
Calculated by the bridge structure FEM model of foundation:
(1) the maximum axial pressure N that carload is produced at arch springingml=1700kN,
(2) main arch ring focuses on the axial compressive force N produced at arch springing certainlyG=15580kN,
(3) the axial compressive force N that tensioning suspension rod is produced at arch springingd=2100kN,
(4) permissible value [Δ]=0.5mm of skewback crossbeam horizontal displacement;
The clear distance D of described 2 liang of endosternums of skewback crossbeamb=8.5m (being equal to skewback crossbeam direction across bridge width), skewback crossbeam 2 Along bridge to long bGZ=0.3L0~0.6L0, take bGZ=3.5m;Skewback crossbeam 2 is constructed using C50 concrete, is looked into《Highway reinforcing bar is mixed Solidifying soil and prestressed concrete bridge contain design specification》(D62-2004) elastic modulus E of the concrete of skewback crossbeam 2 can be obtainedc= 3.45×104MPa, skewback beam height hGZFor:
Tie-rod 8 sets 4 roads (the i.e. road number N of tie-rod 8 altogetherPS=4), wherein, single track tie-rod by n root nominal diameters 15.20mm, 1 × 7 standard steel section twisted wire is constituted;The area of section A of single steel strandP1=140mm2, the control stress for prestressing σ of steel strand wirescon= The radical n of steel strand wires is in 1395MPa, single track tie-rod:
The construction of the present embodiment tied arch ruggedized construction comprises the following steps:
Step 1: constructing skewback crossbeam
Brushwork epoxy resin after dabbing, bar planting is carried out to the endosternum surface of two width being equipped with skewback crossbeam, so After set up template, colligation skewback crossbeam reinforcing bar, pour C50 concrete formation skewback crossbeam, while being opened above skewback crossbeam Apertured hole, by hole in each skewback crossbeam pre-buried steel skewback, and the leading of passing through of pre-buried confession tie-rod in skewback crossbeam Pipe a;
Step 2: constructing suspension rod anchorage beam
Brushing asphalt mixtures modified by epoxy resin after dabbing, bar planting is carried out to the endosternum surface of two width being equipped with suspension rod anchorage beam Fat, then sets up template, assembling reinforcement, C50 concrete formation suspension rod anchorage beam is poured, while above suspension rod anchorage beam Hole is opened up, through the hole conduit b that vertical pre-buried confession suspension rod is passed through inside suspension rod anchorage beam;
Step 3: constructing concrete arch rib
Set up template, assembling reinforcement, pour the concrete arch rib that the formation of C50 concrete connects with steel skewback, while The conduit c that the pre-buried confession suspension rod is passed through in concrete arch rib;
Step 4: installing and stretch tie-bar
The two ends of 4 road tie-rods are each passed through in two skewback crossbeams mutual corresponding conduit a, by taken stretching force σcon It is anchored at after=1395MPa tensioning on skewback crossbeam;
Step 5: tensioning suspension rod
By suspension rod one by one through vertical mutually corresponding conduit b and conduit c up and down, carry out anchoring after tensioning according to a conventional method On suspension rod anchorage beam and concrete arch rib, terminate construction.

Claims (2)

1. a kind of double width continuous rigid frame bridge tied arch ruggedized construction, including main arch ring (6), tie-rod (8) and suspension rod (7);Its feature It is:
Two steel skewbacks (62) that the main arch ring (6) connects by concrete arch rib (61) and respectively with concrete arch rib two ends Constitute, the arch of main arch ring is second-degree parabola;Described two steel skewbacks are embedded in skewback crossbeam (2) respectively, skewback Crossbeam is placed between bridge pier (9) top, the endosternum (3) of the width of double width continuous rigid frame bridge two;The quantity of the tie-rod (8) be 3~ 10 roads, per pass tie-rod is each passed through the conduit a (51) that horizontal homogeneous interval is embedded in skewback crossbeam (2), anchor after the tensioning of two ends Gu on two skewback crossbeams (2);Have symmetrical, equal to centered in continuous rigid frame bridge (1) across center line along along bridge Suspension rod anchorage beam (4) of the even arranged for interval between the endosternum (3) of the width of double width continuous rigid frame bridge two, suspension rod anchorage beam (4) there is vertically embedded conduit b (52) in;Have in concrete arch rib (61) and conduit b is corresponding, vertically embedded vertically up and down leads Pipe c (53);The upper and lower ends of the suspension rod (7) are each passed through mutual corresponding conduit c and conduit b, and coagulation is anchored at after tensioning On native arch rib and suspension rod anchorage beam (4);
The skewback crossbeam is along bridge to length bGZ=0.3L0~0.6L0, direction across bridge width is equal to Db, height hGZIt is calculated as follows Go out:
<mrow> <msub> <mi>h</mi> <mrow> <mi>G</mi> <mi>Z</mi> </mrow> </msub> <mo>=</mo> <mi>r</mi> <mi>o</mi> <mi>u</mi> <mi>n</mi> <mi>d</mi> <mi>u</mi> <mi>p</mi> <mo>&amp;lsqb;</mo> <mfrac> <mrow> <msubsup> <mi>D</mi> <mi>b</mi> <mn>3</mn> </msubsup> <mrow> <mo>(</mo> <msub> <mi>N</mi> <mrow> <mi>m</mi> <mi>l</mi> </mrow> </msub> <mo>+</mo> <msub> <mi>N</mi> <mi>d</mi> </msub> <mo>+</mo> <msub> <mi>N</mi> <mi>G</mi> </msub> <mo>)</mo> </mrow> <mo>&amp;CenterDot;</mo> <mi>c</mi> <mi>o</mi> <mi>s</mi> <mo>&amp;lsqb;</mo> <mi>arctan</mi> <mrow> <mo>(</mo> <mfrac> <mrow> <mn>4</mn> <mi>f</mi> </mrow> <mi>L</mi> </mfrac> <mo>)</mo> </mrow> <mo>&amp;rsqb;</mo> </mrow> <mrow> <mn>4</mn> <msub> <mi>E</mi> <mi>c</mi> </msub> <msubsup> <mi>b</mi> <mrow> <mi>G</mi> <mi>Z</mi> </mrow> <mn>3</mn> </msubsup> <mo>&amp;lsqb;</mo> <mi>&amp;Delta;</mi> <mo>&amp;rsqb;</mo> </mrow> </mfrac> <mo>,</mo> <mn>1</mn> <mo>&amp;rsqb;</mo> </mrow>
Wherein:
L0:No. zero block length of girder,
Roundup [number, Num_digits], number is need any real number being rounded up to, and Num_digits is rounded Digital decimal digits afterwards,
Ec:The modulus of elasticity of skewback crossbeam concrete,
bGZ:Skewback crossbeam along bridge to length,
Db:The clear distance of two endosternums,
f:The rise of arch,
L:In across across footpath,
Nml:The maximum axial pressure that carload is produced at arch springing, can be calculated by setting up bridge structure FEM model Go out,
Nd:The axial compressive force that tensioning suspension rod is produced at arch springing, can be calculated by setting up bridge structure FEM model,
NG:Main arch ring can be calculated from the axial compressive force for focusing on generation at arch springing by setting up bridge structure FEM model,
[Δ]:The permissible value of skewback crossbeam horizontal displacement, can be calculated by setting up bridge structure FEM model;
The radical n of steel strand wires, which is calculated as follows, in the per pass tie-rod draws:
<mrow> <mi>n</mi> <mo>=</mo> <mi>r</mi> <mi>o</mi> <mi>u</mi> <mi>n</mi> <mi>d</mi> <mi>u</mi> <mi>p</mi> <mo>&amp;lsqb;</mo> <mfrac> <mrow> <mn>1000</mn> <mrow> <mo>(</mo> <msub> <mi>N</mi> <mrow> <mi>m</mi> <mi>l</mi> </mrow> </msub> <mo>+</mo> <msub> <mi>N</mi> <mi>d</mi> </msub> <mo>+</mo> <msub> <mi>N</mi> <mi>G</mi> </msub> <mo>)</mo> </mrow> <mo>&amp;CenterDot;</mo> <mi>c</mi> <mi>o</mi> <mi>s</mi> <mo>&amp;lsqb;</mo> <mi>arctan</mi> <mrow> <mo>(</mo> <mfrac> <mrow> <mn>4</mn> <mi>f</mi> </mrow> <mi>L</mi> </mfrac> <mo>)</mo> </mrow> <mo>&amp;rsqb;</mo> </mrow> <mrow> <msub> <mi>&amp;sigma;</mi> <mrow> <mi>c</mi> <mi>o</mi> <mi>n</mi> </mrow> </msub> <msub> <mi>A</mi> <mrow> <mi>P</mi> <mn>1</mn> </mrow> </msub> <msub> <mi>N</mi> <mrow> <mi>P</mi> <mi>S</mi> </mrow> </msub> </mrow> </mfrac> <mo>,</mo> <mn>0</mn> <mo>&amp;rsqb;</mo> </mrow>
In formula:
Roundup [number, Num_digits], number is need any real number being rounded up to, and Num_digits is rounded Digital decimal digits afterwards,
f:The rise of arch,
L:In across across footpath,
σcon:The control stress for prestressing of steel strand wires,
AP1:The area of section of single steel strand,
NPS:The road number of tie-rod,
Nml:The maximum axial pressure that carload is produced at arch springing, can be calculated by setting up bridge structure FEM model Go out,
Nd:The axial compressive force that tensioning suspension rod is produced at arch springing, can be calculated by setting up bridge structure FEM model,
NG:Main arch ring can be calculated from the axial compressive force for focusing on generation at arch springing by setting up bridge structure FEM model.
2. the construction method of double width continuous rigid frame bridge tied arch ruggedized construction described in claim 1, it is characterised in that including following Step:
Step 1: constructing skewback crossbeam
Brushwork epoxy resin after dabbing, bar planting is carried out to the endosternum surface of the double width being equipped with skewback crossbeam, then taken If template, colligation skewback crossbeam reinforcing bar, casting concrete formation skewback crossbeam, while hole is opened up above skewback crossbeam, By hole in each skewback crossbeam pre-buried steel skewback, and the conduit a that pre-buried confession tie-rod is passed through in skewback crossbeam;
Step 2: constructing suspension rod anchorage beam
Brushwork epoxy resin after dabbing, bar planting is carried out to the endosternum surface of the double width being equipped with suspension rod anchorage beam, so After set up template, assembling reinforcement, casting concrete formation suspension rod anchorage beam, while opening up hole above suspension rod anchorage beam Hole, through the hole conduit b that vertical pre-buried confession suspension rod is passed through inside suspension rod anchorage beam;
Step 3: constructing concrete arch rib
Template, assembling reinforcement, the concrete arch rib that connects with steel skewback of casting concrete formation are set up, while in concrete arch The conduit c that the pre-buried confession suspension rod is passed through in rib;
Step 4: installing and stretch tie-bar
The two ends of tie-rod are each passed through in two skewback crossbeams mutual corresponding conduit a, anchored by after taken stretching force tensioning On skewback crossbeam;
Step 5: tensioning suspension rod
By suspension rod one by one through vertical mutually corresponding conduit b and conduit c up and down, carry out being anchored at after tensioning according to a conventional method hanging On bar anchorage beam and concrete arch rib, terminate construction.
CN201710445588.5A 2017-06-14 2017-06-14 Double-width continuous rigid frame bridge tie rod arch reinforcing structure and construction method thereof Active CN107268458B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710445588.5A CN107268458B (en) 2017-06-14 2017-06-14 Double-width continuous rigid frame bridge tie rod arch reinforcing structure and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710445588.5A CN107268458B (en) 2017-06-14 2017-06-14 Double-width continuous rigid frame bridge tie rod arch reinforcing structure and construction method thereof

Publications (2)

Publication Number Publication Date
CN107268458A true CN107268458A (en) 2017-10-20
CN107268458B CN107268458B (en) 2023-01-31

Family

ID=60066756

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710445588.5A Active CN107268458B (en) 2017-06-14 2017-06-14 Double-width continuous rigid frame bridge tie rod arch reinforcing structure and construction method thereof

Country Status (1)

Country Link
CN (1) CN107268458B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111218893A (en) * 2020-01-20 2020-06-02 浙江大学城市学院 Construction method for reinforcing existing line-crossing bridge by newly-added pier column bearing steel truss girder
CN111877121A (en) * 2020-07-21 2020-11-03 詹刚毅 Novel tied arch bridge structure and auxiliary tied bar arrangement method
CN113789712A (en) * 2021-09-17 2021-12-14 上海建工一建集团有限公司 Longitudinal beam and arch rib forming control method of steel arch bridge

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60133104A (en) * 1983-12-19 1985-07-16 松本 嘉司 Continuous arch bridge
JPH08209631A (en) * 1995-02-03 1996-08-13 Kajima Corp Construction method for multispan continuous bridge
CN203295957U (en) * 2013-05-28 2013-11-20 中铁上海设计院集团有限公司 Continuous beam and arch combination bridge
CN203603028U (en) * 2013-11-26 2014-05-21 中铁第四勘察设计院集团有限公司 Railway concrete filled steel tube rigid frame tied arch-steel box connecting beam composite bridge
CN104264594A (en) * 2014-09-10 2015-01-07 北京工业大学 Self-balancing tied arch system for improving bearing force of PSC continuous box girder bridge and reinforcing method by applying self-balancing tie bar arch system
CN104631348A (en) * 2015-02-03 2015-05-20 东南大学 Transversely-widening splicing structure of three-dimensional prestress concrete continuous box girder bridge
CN104631303A (en) * 2015-02-10 2015-05-20 福建省交通规划设计院 Single-rib-arch reinforced V-shaped supporting rigid-frame-continuous beam bridge and construction method thereof
CN104652242A (en) * 2015-02-01 2015-05-27 北京工业大学 Derrick connecting structure used for reinforcing PSC (Pre-stressed Concrete) continuous box girder bridge and construction method
CN104652293A (en) * 2015-02-01 2015-05-27 北京工业大学 Cable-stayed bridge structure used for reinforcing PSC (Pre-stressed Concrete) continuous box girder bridge and construction method
CN105821777A (en) * 2016-05-13 2016-08-03 安徽省交通规划设计研究总院股份有限公司 Prestressed concrete diaphragm for connection of old bridge and new bridge and construction method of prestressed concrete diaphragm

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60133104A (en) * 1983-12-19 1985-07-16 松本 嘉司 Continuous arch bridge
JPH08209631A (en) * 1995-02-03 1996-08-13 Kajima Corp Construction method for multispan continuous bridge
CN203295957U (en) * 2013-05-28 2013-11-20 中铁上海设计院集团有限公司 Continuous beam and arch combination bridge
CN203603028U (en) * 2013-11-26 2014-05-21 中铁第四勘察设计院集团有限公司 Railway concrete filled steel tube rigid frame tied arch-steel box connecting beam composite bridge
CN104264594A (en) * 2014-09-10 2015-01-07 北京工业大学 Self-balancing tied arch system for improving bearing force of PSC continuous box girder bridge and reinforcing method by applying self-balancing tie bar arch system
CN104652242A (en) * 2015-02-01 2015-05-27 北京工业大学 Derrick connecting structure used for reinforcing PSC (Pre-stressed Concrete) continuous box girder bridge and construction method
CN104652293A (en) * 2015-02-01 2015-05-27 北京工业大学 Cable-stayed bridge structure used for reinforcing PSC (Pre-stressed Concrete) continuous box girder bridge and construction method
CN104631348A (en) * 2015-02-03 2015-05-20 东南大学 Transversely-widening splicing structure of three-dimensional prestress concrete continuous box girder bridge
CN104631303A (en) * 2015-02-10 2015-05-20 福建省交通规划设计院 Single-rib-arch reinforced V-shaped supporting rigid-frame-continuous beam bridge and construction method thereof
CN105821777A (en) * 2016-05-13 2016-08-03 安徽省交通规划设计研究总院股份有限公司 Prestressed concrete diaphragm for connection of old bridge and new bridge and construction method of prestressed concrete diaphragm

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
丁国强: "风陵渡黄河公路大桥增设钢箱系杆拱加固施工关键技术", 《山西交通科技》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111218893A (en) * 2020-01-20 2020-06-02 浙江大学城市学院 Construction method for reinforcing existing line-crossing bridge by newly-added pier column bearing steel truss girder
CN111218893B (en) * 2020-01-20 2021-04-20 浙江大学城市学院 Construction method for reinforcing existing line-crossing bridge by newly-added pier column bearing steel truss girder
CN111877121A (en) * 2020-07-21 2020-11-03 詹刚毅 Novel tied arch bridge structure and auxiliary tied bar arrangement method
CN113789712A (en) * 2021-09-17 2021-12-14 上海建工一建集团有限公司 Longitudinal beam and arch rib forming control method of steel arch bridge
CN113789712B (en) * 2021-09-17 2023-10-13 上海建工一建集团有限公司 Longitudinal beam and arch rib forming control method of steel arch bridge

Also Published As

Publication number Publication date
CN107268458B (en) 2023-01-31

Similar Documents

Publication Publication Date Title
CN106677049B (en) Assembled steel-concrete combined structure bridge and construction method
CN102877407B (en) Concrete continuous box girder of corrugated steel web for curved bridge
CN103074941A (en) Assembly type recycled concrete node with steel bar truss girders at end parts and manufacturing method thereof
CN105926440A (en) Steel-concrete combined continuous beam bridge deck as well as manufacturing method and application thereof
CN107268458A (en) A kind of double width continuous rigid frame bridge tied arch ruggedized construction and its construction method
CN206941424U (en) A kind of double width continuous rigid frame bridge tied arch ruggedized construction
CN108660908A (en) A kind of prestressed concrete cable-stayed bridge of the beam prefabricated pin-connected panel of tower
CN206800225U (en) A kind of continuous rigid frame bridge tied arch ruggedized construction
CN104631436A (en) Method for improving integral type bridge abutment sustaining pile stress performance by H-shaped concrete pile
CN107100094A (en) A kind of continuous rigid frame bridge tied arch ruggedized construction and its construction method
CN203795292U (en) Bearing-free prestressed concrete continuous rigid frame bridge with double-wall piers
CN106835955A (en) Steel K supports hollow concrete columnar pier
KR101251118B1 (en) A manufacturing method of a composite steel box girder using prestressed concrete for a positive moment area of a bridge
Bertagnoli et al. Safety format for the nonlinear analysis of concrete structures
CN107386133B (en) A kind of the oblique pull ruggedized construction and its construction method of continuous rigid frame bridge
CN202831388U (en) Small beam high pre-stress pre-cast beam
CN105178165B (en) Tension face layer compound-reinforced reinforced concrete continuous rigid frame bridge and construction method thereof
CN108316150A (en) The construction system and construction method of Cable stayed Bridge Main Tower and steel anchor beam
CN107245959B (en) A kind of the oblique pull ruggedized construction and its construction method of double width continuous rigid frame bridge
CA1234257A (en) Support structure, particularly for a long span bridge
KR101751724B1 (en) Concrete structure constructed integral abutment bridge having shallow height psc i girder due to moment redistribution through control of member stiffness
CN107100095A (en) A kind of T-shaped rigid frame bridge oblique pull ruggedized construction and its construction method
CN105714669B (en) A kind of variable cross-section box girder bridge kingpost baseplate structure and its construction method
CN210439720U (en) Reinforced structure for increasing cross section of concrete beam side
CN206539057U (en) A kind of reinforced beam bracing means

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant