CN107257040A - Pull back swing arm short circuit earthing clamp and ground connection and method for dismounting - Google Patents

Pull back swing arm short circuit earthing clamp and ground connection and method for dismounting Download PDF

Info

Publication number
CN107257040A
CN107257040A CN201710388566.XA CN201710388566A CN107257040A CN 107257040 A CN107257040 A CN 107257040A CN 201710388566 A CN201710388566 A CN 201710388566A CN 107257040 A CN107257040 A CN 107257040A
Authority
CN
China
Prior art keywords
swing arm
wire
clamping plate
push rod
ground wire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710388566.XA
Other languages
Chinese (zh)
Other versions
CN107257040B (en
Inventor
姜晓东
王国文
李勇
张春明
欧希野
肖鹏
赵宇
曲显海
王舒
姜泽谦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MAINTENANCE Co OF STATE GRID HEILONGJIANG ELECTRIC POWER Co
State Grid Corp of China SGCC
Original Assignee
MAINTENANCE Co OF STATE GRID HEILONGJIANG ELECTRIC POWER Co
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MAINTENANCE Co OF STATE GRID HEILONGJIANG ELECTRIC POWER Co, State Grid Corp of China SGCC filed Critical MAINTENANCE Co OF STATE GRID HEILONGJIANG ELECTRIC POWER Co
Priority to CN201710388566.XA priority Critical patent/CN107257040B/en
Publication of CN107257040A publication Critical patent/CN107257040A/en
Application granted granted Critical
Publication of CN107257040B publication Critical patent/CN107257040B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01RELECTRICALLY-CONDUCTIVE CONNECTIONS; STRUCTURAL ASSOCIATIONS OF A PLURALITY OF MUTUALLY-INSULATED ELECTRICAL CONNECTING ELEMENTS; COUPLING DEVICES; CURRENT COLLECTORS
    • H01R11/00Individual connecting elements providing two or more spaced connecting locations for conductive members which are, or may be, thereby interconnected, e.g. end pieces for wires or cables supported by the wire or cable and having means for facilitating electrical connection to some other wire, terminal, or conductive member, blocks of binding posts
    • H01R11/11End pieces or tapping pieces for wires, supported by the wire and for facilitating electrical connection to some other wire, terminal or conductive member
    • H01R11/12End pieces terminating in an eye, hook, or fork
    • H01R11/14End pieces terminating in an eye, hook, or fork the hook being adapted for hanging on overhead or other suspended lines, e.g. hot line clamp
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01RELECTRICALLY-CONDUCTIVE CONNECTIONS; STRUCTURAL ASSOCIATIONS OF A PLURALITY OF MUTUALLY-INSULATED ELECTRICAL CONNECTING ELEMENTS; COUPLING DEVICES; CURRENT COLLECTORS
    • H01R11/00Individual connecting elements providing two or more spaced connecting locations for conductive members which are, or may be, thereby interconnected, e.g. end pieces for wires or cables supported by the wire or cable and having means for facilitating electrical connection to some other wire, terminal, or conductive member, blocks of binding posts
    • H01R11/11End pieces or tapping pieces for wires, supported by the wire and for facilitating electrical connection to some other wire, terminal or conductive member
    • H01R11/22End pieces terminating in a spring clip
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables

Abstract

One kind is pulled back swing arm short circuit earthing clamp and ground connection and method for dismounting.At present, existing short-circuit grounding wire is made up of wire clamp, ground wire, earth clip etc..During line maintenance, temporary short-circuit ground wire must just be installed by falling the injury to the person or equipment such as power transmission or induced voltage for electric, the other branch roads of preventing from misdelivering.One kind is pulled back swing arm short circuit earthing clamp, and its composition includes:Left side clamping plate(1), right side clamping plate(2), swing arm of pulling back(3), push rod(5), U-shaped pressing plate(11)And torsion spring(18), right side clamping plate passes through bolt two(7)Install a swing arm of pulling back additional, swing arm one end of pulling back is provided with swing arm axis hole(25)With card face(8), the other end is provided with swing arm head bore(29), two locking nut holes(22)With U-shaped pressing plate, described swing arm of pulling back is J-type hardware, and outside is provided with arc-shaped slot.The present invention is applied to draw swing arm short circuit earthing clamp.

Description

Pull back swing arm short circuit earthing clamp and ground connection and method for dismounting
Technical field:
Pulled back swing arm short circuit earthing clamp and ground connection and method for dismounting the present invention relates to one kind.
Background technology:
At present, existing short-circuit grounding wire is made up of wire clamp, ground wire, earth clip etc..During line maintenance, to prevent from missing Power transmission, other branch roads fall power transmission or induced voltage etc. must just install temporary short-circuit ground wire to the person or the injury of equipment.But It is that traditional duckbilled impacting type earthing clamp is the supporting post-rod in the own wt slamming down wire clamp using wire clamp and is allowed to de- Elastic force from support release torsion spring clamps wire.Because ground wire is longer, thicker own wt be much larger than the weight of wire clamp, to Not enough, wire clamp inner support push rod can not depart from support to lower punch power, and some install pouring weight additional in wire clamp both sides clamping plate, and which increase wire clamp Deadweight, improved effect is not also obvious.The interference of wind-force often makes wire clamp duckbilled dehisce that wire, increase dress can not accurately be directed at If difficulty.Also the drainage thread of angle tower interior angle side below cross-arm due to that can not install.
In order to overcome the drainage thread of difficult existing ground wire installing, wind-force interference and angle tower interior angle side not it is horizontal but under The problem of Fang Buneng is directly installed, the present invention provides a kind of novel conductive wire wire clamp, and the wire clamp is on the basis of existing wire clamp form Increase a swing arm of pulling back, make the duckbilled that wire clamp opens be changed to be pulled back up motion by moving downward, can be achieved simply, easily Install, do not disturbed by wind-force, it is to avoid Danger Electric shock risk on the drainage thread of tangent tower wire and angle tower interior angle side.
The content of the invention:
Pulled back swing arm short circuit earthing clamp it is an object of the invention to provide one kind, be related to high pressure and super, extra-high voltage electric power line The short-circuit grounding wire wire clamp on road, can especially overcome traditional wire to clamp and set difficulty, easily disturbed and can not directly existed by wind-force The short circuit earthing clamp installed on the drainage thread of angle tower interior angle side.
Above-mentioned purpose is realized by following technical scheme:
1. the present invention is simple to operate, quick and can not installed in drainage wire in the angle tower interior angle side of horizontal but lower section, no Disturbed by wind-force, it is to avoid Danger Electric shock risk.Pulled back pendulum using a metal J-type being connected through the hinge with wire clamp side clamping plate Arm, changes the application point to the pulling force of wire clamp, realizes and vertically, is laterally filled in the mode of pulling back, tears operation open.Line is replaced with pulling force Folder deadweight triggering wire clamp, is not being influenceed and wind-force is disturbed by ground connection line length, is adapted to each high pressure, super(It is special)High pressure level Circuit.
The present invention designs a swing arm of pulling back on the basis of existing wire clamp form, wire clamp is in hook-type state of pulling back, by The pulling force of people replaces gravity, and so pulling up wire clamp by operating personnel just can easily install short-circuit grounding wire.Return It is that an one end is connected by hinge with wire clamp side clamping plate to draw swing arm, the J-type aluminium alloy casting hook of opposite side dead earth line Part.When installing ground wire, first swing arm is rotated to duckbilled direction, until swing arm and clamping plate side are combined, firmly separated wire clamp duck Mouth(Both sides clamping plate), meanwhile, swing arm card face is also blocked by the clamping plate top surface of wire clamp opposite side, and hook-type state of pulling back just is presented in wire clamp .Then, wire clamp is placed in below wire, the de- branch of the supporting post-rod being pulled upwardly in insulating cord or ground wire, wire clamp, which is clamped, to be led Line, is installed successfully, meanwhile, the top surface of wire clamp clamping plate loses the clamping lock effect to swing arm card face, and swing arm is swung back rapidly upward, makes line Lower turn of duckbilled direction is pressed from both sides, secondary pulling insulating cord or ground wire, wire clamp are just disassembled.
The present invention is used for the short circuit grounding of high-voltage electric power circuit, can overcome installing difficulty, not by wind-force interference and in corner Install tower interior angle side.It is one swing arm of pulling back of design on existing wire clamp, wire clamp is in hook-type state of pulling back, by the pulling force of people Instead of gravity impact wire, wire clamp is pulled to fill, tear open.Swing arm of pulling back is that an one end passes through hinge and wire clamp side clamping plate Connection, the J-type aluminium alloy casting hook of opposite side dead earth line.Swing arm of pulling back changes the application point of pulling force suffered by wire clamp, Realize and vertically, laterally filled in the mode of pulling back, tear operation open.
Brief description of the drawings:
Accompanying drawing 1 is the structural representation of the present invention.
Accompanying drawing 2 is each exploded view in accompanying drawing 1.
Wire clamp is pulled back swinging arm demonstration graph when accompanying drawing 3 is installing ground wire.
Accompanying drawing 4 is that wire clamp is pulled back swinging arm demonstration graph.
Wire clamp is pulled back swinging arm demonstration graph when accompanying drawing 5 is dismounting ground wire.
Accompanying drawing 6 is in angle tower interior angle dress, tears operation chart open.
Accompanying drawing 7 is in tangent tower dress, tears operation chart open.
In figure:1. left side(Single shaft hole)Clamping plate, 2. right sides(Double-shaft-and-hole)Clamping plate, 3. pull back swing arm, 4. ground wires, 5. tops Bar, 6. bolts one, 7. bolts two, 8. card faces, 9. ground wire casing joints, 10. bolts three, 11.U type pressing plates, 12. bolts four, 13. clamping screw, 14. push rod rotating shafts one, 15. push rod axis, 16. push rod axis holes one, 17. push rod axis holes two, 18. torsion springs, 19 Nut one, 20. or so clamping plate turn holes, 21. pull back swing arm turn hole, 22. locking nut holes, 23. push rod loose slots, 24. ground wires Casing joint nut bore, 25. axis holes, 26. push rod axis holes three, 27. left clamping plate screws, 28.U type plate holes, 29. swing arm head bore, 30. nut two, 31. wires, 32. insulating cords, 33. drainage wires, 34. insulator chains, 35. pull back swing arm wire clamp, 36. traditional wires Folder, 37. earth clips, 38. steel tower cross-arms.
Embodiment:
Embodiment 1:
One kind is pulled back swing arm short circuit earthing clamp, and its composition includes:Left side clamping plate 1, right side clamping plate 2, pull back swing arm 3, push rod 5th, U-shaped pressing plate 11 and torsion spring 18, described right side clamping plate 2 install the swing arm 3 of pulling back described in one additional by bolt 27, described The one end of swing arm 3 pull back provided with swing arm axis hole 25 and card face 8, the other end is provided with swing arm head bore 29, two locking nut holes 22 and U-shaped Pressing plate 11, described swing arm 3 of pulling back is J-type hardware, and outside is provided with arc-shaped slot, and bolt 1 penetrates a described left side, side folder Hole 20 on plate, then penetrate torsion spring 18, then penetrate the tightening nut 1 of clamping plate lower opening 20, and bolt 27 penetrates described right side folder Hole 21 on plate, then penetrate the described axis hole 25 of swing arm 3 of pulling back, then penetrate lower opening 21, tightening nut 1, push rod rotating shaft 1 Push rod axis hole 1 is penetrated, then penetrates push rod axis hole 3 26, push rod axis 15 is penetrated into push rod axis hole 2 17, bolt 3 10 is worn Enter ground wire casing joint nut bore 24 to be tightened on left side clamping plate screw 27, described U-shaped pressing plate 11 is pushed down into ground wire 4 again Bolt 4 12 is penetrated into U-shaped plate hole 28 and the tightening nut 2 30 of swing arm head bore 29, clamping screw 13 is screwed in into locking nut hole 22 locking ground wires 4.
Embodiment 2:
The earthing method of swing arm short circuit earthing clamp of pulling back according to embodiment 1, this method comprises the following steps:
(1)When installing ground wire:Pull downward on ground wire 4 or the wire 31 of insulating cord 32 can upward relative motion shock push rod 5, top Bar 5 is swung up departing from support around push rod rotating shaft 1, and left side clamping plate 1 and right side clamping plate 2 are under the effect of the elastic force of torsion spring 18 around spiral shell The rotation release elastic force of bolt 1 clamps wire 31, meanwhile, left side clamping plate and swing arm card face 8 are separated from each other, and the resistance of swing arm 3 of pulling back disappears Lose, can freely rotate up.
(2)When dismantling ground wire:Pull up ground wire 4 or the wire 31 of insulating cord 32 can downward relative motion disengaging line Folder, reply installing ground wire when installing readiness, as long as will pull back swing arm 3 along clockwise direction lower swing arrive with right clamping plate knot Close, overcoming torsion spring elastic force to separate left side clamping plate 1 and right side clamping plate 2 to 5 times cavings of push rod untill push rod axis 15 with hand, Ground wire installing readiness work is just completed.
(3)When filling in angle tower interior angle side, tear behaviour open, ground wire 4 is installed on steel tower cross-arm 38, due to drainage wire 33 not Below steel tower cross-arm 38, traditional wire clamp 36 can not be installed.The swing arm wire clamp 35 that will pull back laterally is dished out to drainage wire, is being pulled Insulating cord 32 or ground connection 4 lines triggering wire clamp push rod 5, are achieved that installing, in secondary pulling insulating cord 32 or ground wire 4 during dismounting, Complete dismounting.
(4)When tangent tower fills, tears operation open, traditional wire clamp 36 is impacted downwards by pull-up insulating cord 32 or ground wire 4, Trigger push rod 5 and realize installing, pull realize dismounting again, swing arm wire clamp of pulling back is, as below wire, to pull up wire clamp Dynamic insulating cord 32 or ground wire 4, triggering push rod 5 realize installing, pull realize dismounting again.

Claims (2)

  1. The swing arm short circuit earthing clamp 1. one kind is pulled back, its composition includes:Left side clamping plate, right side clamping plate, swing arm of pulling back, push rod, U Type pressing plate and torsion spring, it is characterized in that:Described right side clamping plate installs the swing arm of pulling back described in one additional by bolt two, and described returns Swing arm one end is drawn to be provided with swing arm axis hole and card face, the other end is provided with swing arm head bore, two locking nut holes and U-shaped pressing plate, described Swing arm of pulling back be J-type hardware, outside is provided with arc-shaped slot, and bolt one penetrates a described left side, hole on the clamping plate of side, then wears Enter torsion spring, then penetrate clamping plate lower opening tightening nut one, bolt two penetrates hole on described right side clamping plate, then penetrate described return Swing arm axis hole is drawn, then penetrates lower opening, tightening nut one, push rod rotating shaft one penetrates push rod axis hole one, then penetrates push rod axis hole three, will Push rod axis penetrates push rod axis hole two, and bolt three is penetrated into ground wire casing joint nut bore is tightened on the clamping plate screw of left side, Described U-shaped pressing plate is pushed down into ground wire 4 bolt four is penetrated into U-shaped plate hole and swing arm head bore tightening nut two again, will locked Bolt screws in locking nut hole locking ground wire.
  2. 2. ground connection and the method for dismounting of the swing arm short circuit earthing clamp of pulling back described in a kind of claim 1, it is characterized in that:The party Method comprises the following steps:
    (1)When installing ground wire:Pull downward on ground wire or insulating cord wire can upward relative motion hit push rod, push rod is around top Bar rotating shaft one is swung up departing from support, and left side clamping plate and right side clamping plate discharge bullet under the effect of torsion spring elastic force around the rotation of bolt one Power clamps wire, meanwhile, left side clamping plate and swing arm card face are separated from each other, and swing arm resistance of pulling back disappears, and can freely rotate up.
    (2)When dismantling ground wire:Pull up ground wire or insulating cord wire can downward relative motion disengaging wire clamp, reply installing Installing readiness during ground wire, if will pull back swing arm along clockwise direction lower swing to and right clamping plate combine, with hand gram Take torsion spring elastic force to separate left side clamping plate and right side clamping plate to 5 times cavings of push rod untill push rod axis, ground wire installing preparation Operation is just completed.
    (3)When filling in angle tower interior angle side, tear behaviour open, ground wire is installed on steel tower cross-arm, because drainage wire is horizontal not in steel tower Load lower section, traditional wire clamp can not be installed.The swing arm wire clamp that will pull back laterally is dished out to drainage wire, is pulling insulating cord or ground wire Wire clamp push rod is triggered, installing is achieved that, in secondary pulling insulating cord or ground wire during dismounting, dismounting is completed.
    (4)When tangent tower fills, tears operation open, traditional wire clamp is impacted downwards by pull-up insulating cord or ground wire, triggers push rod Realize installing, pull realize dismounting again, swing arm wire clamp of pulling back be by wire clamp as below wire, pull up insulating cord or Ground wire, triggering push rod realizes installing, pulls realize dismounting again.
CN201710388566.XA 2017-05-27 2017-05-27 Pull-back swing arm type short circuit grounding wire clamp and grounding and disassembling method Active CN107257040B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710388566.XA CN107257040B (en) 2017-05-27 2017-05-27 Pull-back swing arm type short circuit grounding wire clamp and grounding and disassembling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710388566.XA CN107257040B (en) 2017-05-27 2017-05-27 Pull-back swing arm type short circuit grounding wire clamp and grounding and disassembling method

Publications (2)

Publication Number Publication Date
CN107257040A true CN107257040A (en) 2017-10-17
CN107257040B CN107257040B (en) 2020-04-17

Family

ID=60027782

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710388566.XA Active CN107257040B (en) 2017-05-27 2017-05-27 Pull-back swing arm type short circuit grounding wire clamp and grounding and disassembling method

Country Status (1)

Country Link
CN (1) CN107257040B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109921330A (en) * 2018-12-27 2019-06-21 国网浙江龙游县供电有限公司 A kind of insulation lapping bar for medial potential working
CN111342393A (en) * 2020-04-02 2020-06-26 国网浙江武义县供电有限公司 Hook-type insulating rod

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201638948U (en) * 2010-01-27 2010-11-17 山东电力集团公司淄博供电公司 Throw-pull earth wire for transmission line
JP2013013173A (en) * 2011-06-28 2013-01-17 Chugoku Electric Power Co Inc:The Earth cable mounting tool
CN104201490A (en) * 2014-08-01 2014-12-10 国家电网公司 Throwing and hanging type grounding wire clamp of high-voltage line
CN204030023U (en) * 2014-07-04 2014-12-17 国家电网公司 Throw hanging earthing clamp
CN104409890A (en) * 2014-12-11 2015-03-11 国家电网公司 Throwing and hanging type grounding wire clamp
CN204257855U (en) * 2014-12-26 2015-04-08 国网河南省电力公司检修公司 Earth connection hangs the self-locking earth connection fixture on car

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201638948U (en) * 2010-01-27 2010-11-17 山东电力集团公司淄博供电公司 Throw-pull earth wire for transmission line
JP2013013173A (en) * 2011-06-28 2013-01-17 Chugoku Electric Power Co Inc:The Earth cable mounting tool
CN204030023U (en) * 2014-07-04 2014-12-17 国家电网公司 Throw hanging earthing clamp
CN104201490A (en) * 2014-08-01 2014-12-10 国家电网公司 Throwing and hanging type grounding wire clamp of high-voltage line
CN104409890A (en) * 2014-12-11 2015-03-11 国家电网公司 Throwing and hanging type grounding wire clamp
CN204257855U (en) * 2014-12-26 2015-04-08 国网河南省电力公司检修公司 Earth connection hangs the self-locking earth connection fixture on car

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109921330A (en) * 2018-12-27 2019-06-21 国网浙江龙游县供电有限公司 A kind of insulation lapping bar for medial potential working
CN109921330B (en) * 2018-12-27 2020-12-08 国网浙江龙游县供电有限公司 Insulating lap joint rod for intermediate potential operation
CN111342393A (en) * 2020-04-02 2020-06-26 国网浙江武义县供电有限公司 Hook-type insulating rod

Also Published As

Publication number Publication date
CN107257040B (en) 2020-04-17

Similar Documents

Publication Publication Date Title
CN208608370U (en) A kind of good power grounding pile of stability
CN107257040A (en) Pull back swing arm short circuit earthing clamp and ground connection and method for dismounting
CN201038346Y (en) Transmission line short circuit grounding wire clamp device
CN110233449A (en) A kind of gantry attachment device convenient for fixed installation
CN108512177B (en) A kind of windage yaw angle control applied to suspension insulator
CN106229700B (en) A kind of firm protective device of grounding rod installation
CN105846378B (en) Rotary spacer capable of being installed rapidly and installation method thereof
CN204030023U (en) Throw hanging earthing clamp
CN201868587U (en) Power grounding pile
CN205335796U (en) Transmission line windage yaw defensive installation
CA2823137C (en) Maintenance tool used for double insulator strings of direct current transmission line
CN204633293U (en) The adjustable fastening device that lightning protection needle body is fixing on steel tower
CN201868588U (en) Grounding pile for power equipment
CN207625267U (en) The lightning protection device of 10kV distribution lines
CN203645279U (en) Slidable suspension clamp
CN207490112U (en) A kind of torque tightly locks attachment device
CN203398639U (en) Vibration-proof hammer moving recovering device for overhead ground wire
CN110429398A (en) A kind of harness cable connection connecting terminal block
CN104157532B (en) A kind of support of single-column all insulation crane
CN201741514U (en) Lightning rod installing support
CN205248009U (en) 35kV line insulator goes here and there discharge gap
CN205136819U (en) Strain insulator UT fastener
CN204615267U (en) With the rope ladder head of self-locking device
CN103352808A (en) Fan hub lightning guiding wire connecting method and lightning guiding system
CN105336454A (en) Discharge gap of 35kV line insulator string

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant