CN107254967A - The construction method that a kind of superposed column built-in fitting is vacantly installed - Google Patents
The construction method that a kind of superposed column built-in fitting is vacantly installed Download PDFInfo
- Publication number
- CN107254967A CN107254967A CN201710470756.6A CN201710470756A CN107254967A CN 107254967 A CN107254967 A CN 107254967A CN 201710470756 A CN201710470756 A CN 201710470756A CN 107254967 A CN107254967 A CN 107254967A
- Authority
- CN
- China
- Prior art keywords
- steel
- location
- fitting
- foundation bolt
- angle steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/18—Adjusting tools; Templates
Abstract
The present invention provides the construction method that a kind of superposed column built-in fitting is vacantly installed, and belongs to the hanging field of superposed column built-in fitting, and the invention mainly comprises following several steps:1)Hanging line setting;2)Foundation bolt support makes;3)The fabrication and installation of location-plate;4)The hanging location and installation of pre-embedded anchoring bolts.The construction quality of foundation bolt positioning is ensure that, so as to overcome foundation bolt to be accurately positioned the big mass defect of deviation.
Description
Technical field
The present invention relates to building construction technology, more particularly to the construction method that a kind of superposed column built-in fitting is vacantly installed.
Background technology
Vacantly positioning is fixedly connected simultaneously current superposed column built-in fitting foundation bolt using bar dowel spot welding Screw arbor with nut at both-ends mostly
Artificial bracing wire positioning method, because single foundation bolt is longer, the hanging lower section of positioning stage is determined without fulcrum, the accurate of foundation bolt
Defect that deviation is big etc. for position, directly affects the installation positioning precision of follow-up steel column.
The content of the invention
In order to solve problem above, the present invention proposes the construction method that a kind of superposed column built-in fitting is vacantly installed.Using
This construction method carries out the hanging space orientation of built-in fitting and installed, and solves the pre-buried precision and alignment quality of foundation bolt.
The technical scheme is that:
The construction method that a kind of superposed column built-in fitting is vacantly installed, it is main to include following several steps:
1)Hanging line setting;
2)Foundation bolt support makes;
3)The fabrication and installation of location-plate;
4)The hanging location and installation of pre-embedded anchoring bolts.
Wherein.
1)Hanging line setting
Axis pilot measurement is bound on slab form using BIM modeling auxiliary total powerstation axial line control points, also with principles above
By in another azimuth axis also pilot measurement to template, crossing point of axes is made in bracing wire, and with total Station Measured, this space coordinate put is
For superposed column built-in fitting foundation bolt centre point spatial value.
2)Foundation bolt support makes
Foundation bolt support mainly makes the upper band steel frame and lower band steel frame, the vertical angle steel of level and diagonal brace angle steel be arrangeding in parallel,
Four wide band steels of 6mm thickness 80mm are joined end to end and connect the band steel frame up and down of the side's of being formed shape, perforating and general in the middle part of band steel frame up and down
Foundation bolt is arranged in beaten eye, and vertical angle steel is constituted with the angle steel of four L80 × 50 × 6, vertical angle steel with it is flat up and down
Steel framework is welded and fixed together, and plane where vertical angle steel and band steel up and down is perpendicular so that up and down band steel and vertical angle steel it
Between form cube structure;Diagonal brace angle steel and horizontal corner steel are made using the angle steel of L80 × 50 × 6, horizontal corner steel is welded on down
Band steel frame bottom;The upper end of diagonal brace angle steel is welded on upper band steel frame, lower end is welded on horizontal corner steel so that diagonal brace angle
Right triangular shape is formed between steel, horizontal corner steel and vertical angle steel.
The spacing deviation of each foundation bolt to the band steel frame line of centres up and down is not more than 2 ㎜, each foundation bolt top
Relative relief be not more than 2 ㎜.
3)The fabrication and installation of location-plate
Location-plate is covered in above band steel frame, and location-plate is made of 12mm solid woods, and location-plate is connected with upper band steel frame, makes
Used time draws the line between two relative bolts with ink fountain on location-plate, and intersection point carries out mark.
4)The hanging location and installation of pre-embedded anchoring bolts
It is using hoisting machinery that built-in fitting integral hoisting is in place according to control axis, first with total powerstation by post center of circle space coordinate
With the intersection point positioned in alignment center of circle on the location-plate of built-in fitting top, line and one center line pair of built-in fitting between two bolts
Together, and the datum line of itself and measurement and positioning is made to coincide;Then the absolute altitude of embedded part bolt top surface is measured with spirit level;
According to the line between above bolt to extraction 1.5m control lines on slab form, 3 control points 1,2,3 are set;For
Check the positioning accuracy after pre-embedded anchoring bolts are installed;
Consolidated using the split bolt of diameter 18 and the reinforcing bar keel of ellipse diameter HRB400 levels 25 with L-type 12mm steel plate clips connector
Fixed connection.
The beneficial effects of the invention are as follows
It is an object of the invention to the construction method that invention superposed column pre-embedded anchoring bolts are vacantly positioned, it is ensured that foundation bolt is fixed
The construction quality of position, so as to overcome foundation bolt to be accurately positioned the big mass defect of deviation.
Brief description of the drawings
Fig. 1 is superposed column built-in fitting suspending apparatus structural representation.
Wherein, 1, upper band steel frame, 2, location-plate, 3, diagonal brace angle steel, 4, vertical angle steel, 5, lateral strut, 6, ring-shaped clip,
7th, Screw arbor with nut at both-ends, 8, lower band steel frame, 9, pre-embedded bolt, 10, horizontal corner steel.
Embodiment
More detailed illustrate is carried out to present disclosure below:
It is an object of the invention to the construction method that invention superposed column pre-embedded anchoring bolts are vacantly positioned, it is ensured that foundation bolt is fixed
The construction quality of position, so as to overcome foundation bolt to be accurately positioned the big mass defect of deviation.
1st, hanging line setting
Axis pilot measurement is bound on slab form using BIM modeling auxiliary total powerstation axial line control points, also with principles above
By in another azimuth axis also pilot measurement to template, crossing point of axes is made in bracing wire, and with total Station Measured, this space coordinate put is
For superposed column built-in fitting foundation bolt centre point spatial value.
2nd, foundation bolt support makes
Embedding anchor bolts part is made up of band steel frame, the vertical angle steel of level and diagonal brace angle steel up and down, and foundation bolt support is above and below
Band steel frame is connected by the wide band steels of 6mm thickness 80mm(Depending on size of the band steel width of frame according to superposed column), beaten up and down in the middle part of band steel frame
Eye(Diameter 20mm)Fixed foundation bolt, vertical angle steel band steel frame will be welded and fixed up and down with the angle steel of 4 L80 × 50 × 6;
Diagonal brace angle steel and horizontal corner steel are connected overall with support frame using L80 × 50 × 6.Spacing deviation ≯ 2 of pre-embedded bolt centre to centre
㎜, the ㎜ of the relative relief on pre-embedded bolt top ≯ 2, it is ensured that the installation accuracy of pre-embedded bolt;
Location-plate is covered in above band steel frame, and location-plate is made of 12mm solid woods, and location-plate is connected with band steel, when using
By bolt in length and breadth to the midline with ink fountain testing to small plank on small plank, intersection point carries out mark.
4th, the hanging location and installation of pre-embedded anchoring bolts
It is using hoisting machinery that built-in fitting integral hoisting is in place according to control axis, first with total powerstation by post center of circle space coordinate
The square small plank intersection point positioned in alignment center of circle to the midline in length and breadth, axis of pitch control line and built-in fitting one are customized with built-in fitting top
Bar center line aligns, and the datum line of itself and measurement and positioning is coincide;Then the absolute altitude of embedded part bolt top surface is measured with spirit level;
Vertically and horizontally axis, to extraction 1.5m control lines on slab form, sets 3 control points 1,2,3 more than;For checking
Pre-embedded anchoring bolts install after positioning accuracy;
Consolidated using the split bolt of diameter 18 and the reinforcing bar keel of ellipse diameter HRB400 levels 25 with L-type 12mm steel plate clips connector
Fixed connection, so as to ensure that the positioning accuracy of built-in fitting.
Claims (5)
1. the construction method that a kind of superposed column built-in fitting is vacantly installed, it is characterised in that
It is main to include following several steps:
1)Hanging line setting;
2)Foundation bolt support makes;
3)The fabrication and installation of location-plate;
4)The hanging location and installation of pre-embedded anchoring bolts.
2. construction method according to claim 1, it is characterised in that
1)Hanging line setting
Axis pilot measurement is bound on slab form using BIM modeling auxiliary total powerstation axial line control points, also with principles above
By in another azimuth axis also pilot measurement to template, crossing point of axes is made in bracing wire, and with total Station Measured, this space coordinate put is
For superposed column built-in fitting foundation bolt centre point spatial value.
3. construction method according to claim 2, it is characterised in that
2)Foundation bolt support makes
Foundation bolt support mainly makes the upper band steel frame and lower band steel frame, the vertical angle steel of level and diagonal brace angle steel be arrangeding in parallel,
Four wide band steels of 6mm thickness 80mm are joined end to end and connect the band steel frame up and down of the side's of being formed shape, perforating and general in the middle part of band steel frame up and down
Foundation bolt is arranged in beaten eye, and vertical angle steel is constituted with the angle steel of four L80 × 50 × 6, vertical angle steel with it is flat up and down
Steel framework is welded and fixed together, and plane where vertical angle steel and band steel up and down is perpendicular so that up and down band steel and vertical angle steel it
Between form cube structure;Diagonal brace angle steel and horizontal corner steel are made using the angle steel of L80 × 50 × 6, horizontal corner steel is welded on down
Band steel frame bottom;The upper end of diagonal brace angle steel is welded on upper band steel frame, lower end is welded on horizontal corner steel so that diagonal brace angle
Right triangular shape is formed between steel, horizontal corner steel and vertical angle steel;
The spacing deviation of each foundation bolt to the band steel frame line of centres up and down is not more than 2 ㎜, the phase on each foundation bolt top
It is not more than 2 ㎜ to the discrepancy in elevation.
4. construction method according to claim 3, it is characterised in that
3)The fabrication and installation of location-plate
Location-plate is covered in above band steel frame, and location-plate is made of 12mm solid woods, and location-plate is connected with upper band steel frame, makes
Used time draws the line between two relative bolts with ink fountain on location-plate, and intersection point carries out mark.
5. construction method according to claim 4, it is characterised in that
4)The hanging location and installation of pre-embedded anchoring bolts
It is using hoisting machinery that built-in fitting integral hoisting is in place according to control axis, first with total powerstation by post center of circle space coordinate
With the intersection point positioned in alignment center of circle on the location-plate of built-in fitting top, line and one center line pair of built-in fitting between two bolts
Together, and the datum line of itself and measurement and positioning is made to coincide;Then the absolute altitude of embedded part bolt top surface is measured with spirit level;
According to the line between above bolt to extraction 1.5m control lines on slab form, 3 control points 1,2,3 are set;For
Check the positioning accuracy after pre-embedded anchoring bolts are installed;
Consolidated using the split bolt of diameter 18 and the reinforcing bar keel of ellipse diameter HRB400 levels 25 with L-type 12mm steel plate clips connector
Fixed connection.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710470756.6A CN107254967A (en) | 2017-06-20 | 2017-06-20 | The construction method that a kind of superposed column built-in fitting is vacantly installed |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710470756.6A CN107254967A (en) | 2017-06-20 | 2017-06-20 | The construction method that a kind of superposed column built-in fitting is vacantly installed |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107254967A true CN107254967A (en) | 2017-10-17 |
Family
ID=60024575
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710470756.6A Withdrawn CN107254967A (en) | 2017-06-20 | 2017-06-20 | The construction method that a kind of superposed column built-in fitting is vacantly installed |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107254967A (en) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10184011A (en) * | 1996-12-20 | 1998-07-14 | Sumitomo Forestry Co Ltd | Metal tool set for installing anchor bolt |
CN102493471A (en) * | 2011-12-01 | 2012-06-13 | 中建八局大连建设工程有限公司 | Suspending installation construction process method of structural foot margin anchor bolt |
CN202881968U (en) * | 2012-10-18 | 2013-04-17 | 山西四建集团有限公司 | Factory building bolt embedded precision control structure |
CN204326093U (en) * | 2014-12-06 | 2015-05-13 | 内蒙古兴泰建设集团有限公司 | A kind of rigid steel pile locating support |
-
2017
- 2017-06-20 CN CN201710470756.6A patent/CN107254967A/en not_active Withdrawn
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10184011A (en) * | 1996-12-20 | 1998-07-14 | Sumitomo Forestry Co Ltd | Metal tool set for installing anchor bolt |
CN102493471A (en) * | 2011-12-01 | 2012-06-13 | 中建八局大连建设工程有限公司 | Suspending installation construction process method of structural foot margin anchor bolt |
CN202881968U (en) * | 2012-10-18 | 2013-04-17 | 山西四建集团有限公司 | Factory building bolt embedded precision control structure |
CN204326093U (en) * | 2014-12-06 | 2015-05-13 | 内蒙古兴泰建设集团有限公司 | A kind of rigid steel pile locating support |
Non-Patent Citations (2)
Title |
---|
李卫华等: "超高层建筑地脚锚栓快速预埋技术", 《钢结构》 * |
李邵建: "《欧特克BIM标准丛书 BIM纲要》", 30 November 2015 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102561712B (en) | Precise positioning frame for large steel columns and equipment foundation fixing bolts and construction method of precise positioning frame | |
CN106120559B (en) | A kind of bridge limited bracket construction method and bridge | |
CN108035554B (en) | Construction method of section steel column support frame of super high-rise building frame column | |
CN204703182U (en) | Crab-bolt stock | |
CN103437279B (en) | Overhead cast-in-place box compression struts and construction technology thereof | |
CN204849798U (en) | Rag bolt fixed bolster | |
CN112127641A (en) | Accurate fixing method for anchor plate foundation bolt | |
CN109763569B (en) | Construction method of cantilever awning | |
CN203625921U (en) | Precision control device for pre-embedded mounting of foundation bolts | |
CN103174166A (en) | Recreation facility embedded part integrally arranged in complete-set mode and installation method thereof | |
CN102864934A (en) | Construction method of back-bolt type dry hanging stone curtain wall | |
CN105317052B (en) | Tower crane foundation bolt fixing method | |
CN109267493A (en) | A kind of construction method installed across river steel lid beam | |
CN112095485A (en) | Bridge stay cable anchor cylinder pre-embedded positioning device and using method thereof | |
CN104563525B (en) | A kind of box steel arch beam Integral horizontal type group is to method | |
CN111549815A (en) | Steel structure foundation bolt pre-embedding construction method | |
CN113653199B (en) | Construction method for embedding stiffening anchor plate foundation bolt | |
CN107254967A (en) | The construction method that a kind of superposed column built-in fitting is vacantly installed | |
CN205617664U (en) | Prefabricated pier stud locating rack for steel reinforcement cage | |
CN212477455U (en) | Pre-buried positioner of bridge suspension cable anchor cylinder | |
CN109201971A (en) | For making the positioning device and its construction method of pile foundation steel bar cage | |
CN210529741U (en) | Independent foundation embedded bolt mounting structure | |
CN107938854A (en) | A kind of steel girder erection method using built-in fitting | |
CN107059913A (en) | A kind of reactor built-in fitting supporting construction and method for embedding | |
CN204825665U (en) | Utilize device of laser positioning preparation steel reinforcement cage |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20171017 |
|
WW01 | Invention patent application withdrawn after publication |