CN107218016A - Connecting connection parts under deep sea vertical pipe - Google Patents

Connecting connection parts under deep sea vertical pipe Download PDF

Info

Publication number
CN107218016A
CN107218016A CN201710571762.0A CN201710571762A CN107218016A CN 107218016 A CN107218016 A CN 107218016A CN 201710571762 A CN201710571762 A CN 201710571762A CN 107218016 A CN107218016 A CN 107218016A
Authority
CN
China
Prior art keywords
vertical pipe
deep sea
chamfering
sea vertical
connection parts
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710571762.0A
Other languages
Chinese (zh)
Inventor
朱刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Pera Corp Ltd
Original Assignee
Pera Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pera Corp Ltd filed Critical Pera Corp Ltd
Priority to CN201710571762.0A priority Critical patent/CN107218016A/en
Publication of CN107218016A publication Critical patent/CN107218016A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/01Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells specially adapted for obtaining from underwater installations
    • E21B43/013Connecting a production flow line to an underwater well head
    • E21B43/0135Connecting a production flow line to an underwater well head using a pulling cable

Abstract

Connecting connection parts under a kind of deep sea vertical pipe, including the standpipe being from top to bottom sequentially connected, chamfering forges link unit, two main stay tubes, connecting seat, flexible linker casts interface unit, supervisor and lower flexible linker, two main stay tubes are abreast set, first side of chamfering forging link unit is provided with robot people's mounting interface unit, second side of chamfering forging link unit is provided with box-shaped structural member, the first end of the lower end of chamfering forging link unit and the inner tube of U-shaped is connected, second end of inner tube and one end of the remote chamfering forging link unit of box-shaped structural member are connected, second end of inner tube is provided with underwater connector interface unit.Connecting connection parts use integrated configuration completely under deep sea vertical pipe in the present invention, can meet the intensity under various working conditions comprehensively, the design requirement such as fatigue, can not only mitigate integrally-built weight significantly, and lower processing transport installation cost significantly.

Description

Connecting connection parts under deep sea vertical pipe
Technical field
The present invention relates to drilling at the sea technical field, connecting connection parts under more particularly to a kind of deep sea vertical pipe.
Background technology
In deep-sea oil project, the connection of standpipe and standpipe and FPSO oil tankers is most important.Wherein, marine riser bottom Connection component is critical component.
The design of marine riser bottom connection component involves the dynamic of the dynamic loading, the dynamic loading of standpipe, oil tanker of suspension cylinder Load and the dynamic loading of various connecting lines transmission, thus it is extremely complex.The general high number of marine riser bottom connection component Rice, tens tons of design weight.Deep sea vertical pipe in Large marine project Block31 (31 plate) designs of BP in 2012 Lower connecting connection parts, using tower structure form, although meet all working condition requirements, but it is complicated, and weight is very big, manufacture It is all very high with transport installation cost.Especially deep-sea drilling ship operation, cost is extremely expensive, and the time length of installation is into umbra Ring very big.
The content of the invention
It is complicated in the prior art to solve it is an object of the invention to provide connecting connection parts under a kind of deep sea vertical pipe, The problem of manufacture and installation cost are high.
In order to solve the above technical problems, the invention provides connecting connection parts under a kind of deep sea vertical pipe, including from top to bottom Standpipe, chamfering forging link unit, two main stay tubes, connecting seat, the flexible linkers being sequentially connected cast interface unit, supervisor With lower flexible linker, described two main stay tubes are abreast set, and the first side of the chamfering forging link unit is installed Have robot people's mounting interface unit, the second side of chamfering forging link unit that box-shaped structural member is installed, it is described fall The first end of the lower end of angle forging link unit and the inner tube of U-shaped is connected, the second end and the box-shaped structural member of said inner tube Remote chamfering forging link unit one end connection, the second end of said inner tube is provided with underwater connector interface list Member.
Preferably, connecting connection parts also include standpipe standard shaft mounting interface unit under the deep sea vertical pipe, installed in described At the upper surface of box-shaped structural member.
Preferably, connecting connection parts also include underwater connector supporting construction under the deep sea vertical pipe, described to connect under water Device interface unit is connected by the second end of the underwater connector supporting construction and said inner tube.
Preferably, connecting connection parts are also included in corrosion protection, each main stay tube under the deep sea vertical pipe It is respectively connected with least one described corrosion protection.
Preferably, connecting connection parts also include supervisor's extension tube under the deep sea vertical pipe, and the supervisor passes through the supervisor Extension tube is connected with the lower flexible linker.
Preferably, it is provided with coating on the outer wall of the supervisor and supervisor's extension tube.
Preferably, the both sides of the chamfering forging link unit are also separately installed with interface support tube.
Connecting connection parts use integrated configuration completely under deep sea vertical pipe in the present invention, and various operating mode bars can be met comprehensively Intensity under part, the design requirement such as fatigue can not only mitigate integrally-built weight significantly, and lower processing transport significantly Installation cost.
In addition to objects, features and advantages described above, the present invention also has other objects, features and advantages. The present invention is further detailed explanation below.
Brief description of the drawings
The Figure of description for constituting the part of the present invention is used for providing a further understanding of the present invention, and of the invention shows Meaning property embodiment and its illustrate be used for explain the present invention, do not constitute inappropriate limitation of the present invention.In the accompanying drawings:
Fig. 1 is the structural representation of the present invention;
Fig. 2 is that the present invention removes another structural representation after part.
Reference in Fig. 1:1st, standpipe;2nd, chamfering forging link unit;3rd, main stay tube;4th, connecting seat;5th, flexible chain Connect device casting interface unit;6th, it is responsible for;7th, lower flexible linker;8th, robot people mounting interface unit;9th, box-shaped structural member; 10th, inner tube;11st, underwater connector interface unit;12nd, standpipe standard shaft mounting interface unit;13rd, underwater connector supporting construction; 14th, corrosion protection;15th, it is responsible for extension tube;16th, coating;17th, interface support tube.
Embodiment
It should be noted that in the case where not conflicting, the embodiment in the present invention and the feature in embodiment can phases Mutually combination.The present invention is described in detail with reference to embodiment.
In order that those skilled in the art more fully understand the present invention program, below by the skill in the embodiment of the present invention Art scheme is clearly and completely described, it is clear that described embodiment is only the embodiment of a part of the invention, without It is whole embodiments.Based on the embodiment in the present invention, those of ordinary skill in the art are not before creative work is made The every other embodiment obtained is put, should all belong to the scope of protection of the invention.
The invention provides connecting connection parts under a kind of deep sea vertical pipe, including be from top to bottom sequentially connected standpipe 1, chamfering Forge link unit 2, two main stay tubes 3, connecting seat 4, flexible linkers and cast interface unit 5, supervisor 6 and lower flexible link Device 7, described two main stay tubes 3 are abreast set, and the first side of the chamfering forging link unit 2 is provided with robot people Mounting interface unit 8, the second side of chamfering forging link unit 2 are provided with box-shaped structural member 9, the chamfering forging link The first end connection of the lower end of unit 2 and the inner tube 10 of U-shaped, the second end of said inner tube 10 is remote with the box-shaped structural member 9 From one end connection that the chamfering forges link unit 2, the second end of said inner tube 10 is provided with underwater connector interface unit 11。
Connecting connection parts use integrated configuration completely under deep sea vertical pipe in the present invention, have abandoned traditional in the prior art Rectangular frame topology layout, and using the simulation result of finite element analysis as rely on, meet comprehensively under various working conditions Intensity, the design requirement such as fatigue can not only mitigate integrally-built weight significantly, and lower processing transport significantly and be mounted to This.
By adopting the above-described technical solution, the integrated configuration structure of the present invention is more than structure of the prior art letter It is single, therefore overall weight can be greatly reduced.If it is considered that the operating condition design of Adjacent Sea, integrated deep sea vertical pipe bottom Attachment means weight is between 30 tons to 70 tons.In addition, the design of the present invention has taken into full account all design conditions, design Designed in strict accordance with the serial international standard of Offshore Engineering.According to international standard DNV-OS-F201, steel bends under high temperature Taking intensity has certain degeneration, therefore, the present invention has had contemplated that this factor.
Although integration is of the invention simple in construction, with enough rigidity, deformation under design load can be with It is maintained within safe range, the maximum distortion obtained through FEM calculation is completely within safe range, relative to existing For box-structure in technology, with remarkable advantages such as low, the intensity fatigue life height of lightweight, manufacturing cost.The present invention's Structure is completely different and box-structure of the prior art, due to the particularity of ocean engineering, for different marine sites, it is necessary to Structural parameters are done with partial adjustment, therefore and uncertain specific all structural parameters.
Preferably, connecting connection parts also include standpipe standard shaft mounting interface unit 12 under the deep sea vertical pipe, installed in institute At the upper surface for stating box-shaped structural member 9.
Preferably, connecting connection parts also include underwater connector supporting construction 13 under the deep sea vertical pipe, described to connect under water Device interface unit 11 is connect to be connected with the second end of said inner tube 10 by the underwater connector supporting construction 13.
Preferably, connecting connection parts also include corrosion protection 14, each main stay tube 3 under the deep sea vertical pipe On be respectively connected with least one described corrosion protection 14.
Preferably, connecting connection parts also include supervisor's extension tube 15 under the deep sea vertical pipe, and the supervisor 6 passes through the master Pipe extension tube 15 is connected with the lower flexible linker 7.
Preferably, it is provided with coating 16 on the outer wall of the supervisor 6 and supervisor's extension tube 15.
Preferably, the both sides of the chamfering forging link unit 2 are also separately installed with interface support tube 17.
Too many structure is assembled under deep sea vertical pipe among connecting connection parts by prior art, therefore causes whole deep-sea The structure of connecting connection parts is almost complicated as connecting connection parts structure on deep sea vertical pipe under standpipe.By comparison, it is of the invention Only retain standpipe with connecting connection parts under deep sea vertical pipe to be connected, the major function of connecting connection parts under reduction deep sea vertical pipe, and In other function differentiations to surrounding structure.So, the structure of connecting connection parts under deep sea vertical pipe can be made significantly to be simplified. Although surrounding structure accordingly can structure more of the prior art it is slightly complicated, comprehensive advantage is that each subsystem respectively takes charge of it Duty, is easy to design and installation, especially protrudes the partial function under the deep sea vertical pipe of most critical in connecting connection parts, fully ensures that The reliability of whole system.
By above-mentioned technical proposal, connecting connection parts are relative to prior art under the integrated deep sea vertical pipe in the present invention For, structure is greatly simplified, but the burden for being required to fully meet loads in plane and face external applied load of bulk strength.Meanwhile, Thermal force caused by having taken into full account under production status is superimposed the influence produced with production status loads in plane.In addition, in design Crude oil temperature is by the adjacent of a certain Experimental Area (for example, BP Angola Block 31) in the 118 degree of standpipes considered The operating temperature of crude oil is determined under marine site, and design have passed through the calculating of the various load of detailed finite element, and result of calculation shows Show, fully meet design requirement.
Deep-sea oil production technique is the weakness of China, and China is used as an energy demand big country, following marine stone Oil exploitation has huge demand and prospect.Compared with prior art, it is an advantage of the invention that structure significantly simplifies, and more Rationally, intensity fatigue life significantly improves, and cost can be greatly reduced in the manufacture and installation.
The preferred embodiments of the present invention are the foregoing is only, are not intended to limit the invention, for the skill of this area For art personnel, the present invention can have various modifications and variations.Within the spirit and principles of the invention, that is made any repaiies Change, equivalent substitution, improvement etc., should be included in the scope of the protection.

Claims (7)

1. connecting connection parts under a kind of deep sea vertical pipe, it is characterised in that including be from top to bottom sequentially connected standpipe (1), chamfering Forge link unit (2), two main stay tubes (3), connecting seat (4), flexible linker casting interface unit (5), supervisor (6) and under Portion's flexibility linker (7), described two main stay tubes (3) are abreast set, the first side of the chamfering forging link unit (2) Robot people's mounting interface unit (8), the second side of chamfering forging link unit (2) are installed box-structure is installed The first end of part (9), the lower end of the chamfering forging link unit (2) and the inner tube (10) of U-shaped is connected, said inner tube (10) Second end is connected with one end of the remote chamfering forging link unit (2) of the box-shaped structural member (9), said inner tube (10) The second end underwater connector interface unit (11) is installed.
2. connecting connection parts under deep sea vertical pipe according to claim 1, it is characterised in that the deep sea vertical pipe bottom connection Device also includes standpipe standard shaft mounting interface unit (12), at the upper surface of the box-shaped structural member (9).
3. connecting connection parts under deep sea vertical pipe according to claim 1, it is characterised in that the deep sea vertical pipe bottom connection Device also includes underwater connector supporting construction (13), and the underwater connector interface unit (11) passes through the underwater connector Supporting construction (13) is connected with the second end of said inner tube (10).
4. connecting connection parts under deep sea vertical pipe according to claim 1, it is characterised in that the deep sea vertical pipe bottom connection Device also includes being respectively connected with least one described corrosion protection on corrosion protection (14), each main stay tube (3) Device (14).
5. connecting connection parts under deep sea vertical pipe according to claim 1, it is characterised in that the deep sea vertical pipe bottom connection Device also includes supervisor's extension tube (15), and the supervisor (6) is linked by supervisor's extension tube (15) with the lower flexible Device (7) is connected.
6. connecting connection parts under deep sea vertical pipe according to claim 5, it is characterised in that the supervisor (6) and the master Coating (16) is provided with the outer wall of pipe extension tube (15).
7. connecting connection parts under deep sea vertical pipe according to claim 1, it is characterised in that the chamfering forges link unit (2) both sides are also separately installed with interface support tube (17).
CN201710571762.0A 2017-07-13 2017-07-13 Connecting connection parts under deep sea vertical pipe Pending CN107218016A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710571762.0A CN107218016A (en) 2017-07-13 2017-07-13 Connecting connection parts under deep sea vertical pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710571762.0A CN107218016A (en) 2017-07-13 2017-07-13 Connecting connection parts under deep sea vertical pipe

Publications (1)

Publication Number Publication Date
CN107218016A true CN107218016A (en) 2017-09-29

Family

ID=59952271

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710571762.0A Pending CN107218016A (en) 2017-07-13 2017-07-13 Connecting connection parts under deep sea vertical pipe

Country Status (1)

Country Link
CN (1) CN107218016A (en)

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2497263A1 (en) * 1980-12-29 1982-07-02 Mobil Oil Corp FLEXIBLE UPLANT COLUMN WITH CLEARANCE UNIT FOR OIL FILLING OUTSIDE THE SIDE
US4730677A (en) * 1986-12-22 1988-03-15 Otis Engineering Corporation Method and system for maintenance and servicing of subsea wells
US20040099420A1 (en) * 2002-11-26 2004-05-27 Kotrla Johnnie E. Subsea connection apparatus for a surface blowout preventer stack
CN1516776A (en) * 2001-06-15 2004-07-28 �����ɷ� Underwater pipeline connection jointed to riser
WO2012051148A2 (en) * 2010-10-12 2012-04-19 Bp Corporation North America Inc. Marine subsea assemblies
CN102498258A (en) * 2009-07-15 2012-06-13 迈一技术有限责任公司 Production riser
CN102562009A (en) * 2010-11-01 2012-07-11 韦特柯格雷公司 Efficient open water riser deployment
US20120273213A1 (en) * 2011-04-27 2012-11-01 Bp Corporation North America Inc. Marine subsea riser systems and methods
CN103154424A (en) * 2010-10-12 2013-06-12 Bp北美公司 Marine subsea free-standing riser systems and methods
CN103998716A (en) * 2011-12-23 2014-08-20 诺蒂勒斯矿物太平洋有限公司 A disconnectable method and system for seafloor mining
CN104329044A (en) * 2014-10-09 2015-02-04 中国海洋石油总公司 Free standing type vertical pipe bottom connecting structure
CN105525888A (en) * 2014-09-28 2016-04-27 中国海洋石油总公司 Terminal connector of deep water free standing type vertical pipe system

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2497263A1 (en) * 1980-12-29 1982-07-02 Mobil Oil Corp FLEXIBLE UPLANT COLUMN WITH CLEARANCE UNIT FOR OIL FILLING OUTSIDE THE SIDE
US4730677A (en) * 1986-12-22 1988-03-15 Otis Engineering Corporation Method and system for maintenance and servicing of subsea wells
CN1516776A (en) * 2001-06-15 2004-07-28 �����ɷ� Underwater pipeline connection jointed to riser
US20040099420A1 (en) * 2002-11-26 2004-05-27 Kotrla Johnnie E. Subsea connection apparatus for a surface blowout preventer stack
CN102498258A (en) * 2009-07-15 2012-06-13 迈一技术有限责任公司 Production riser
CN103154424A (en) * 2010-10-12 2013-06-12 Bp北美公司 Marine subsea free-standing riser systems and methods
WO2012051148A2 (en) * 2010-10-12 2012-04-19 Bp Corporation North America Inc. Marine subsea assemblies
MX342754B (en) * 2010-10-12 2016-10-12 Bp Corp North America Inc Marine subsea free-standing riser systems and methods.
CN102562009A (en) * 2010-11-01 2012-07-11 韦特柯格雷公司 Efficient open water riser deployment
US20120273213A1 (en) * 2011-04-27 2012-11-01 Bp Corporation North America Inc. Marine subsea riser systems and methods
CN103998716A (en) * 2011-12-23 2014-08-20 诺蒂勒斯矿物太平洋有限公司 A disconnectable method and system for seafloor mining
CN105525888A (en) * 2014-09-28 2016-04-27 中国海洋石油总公司 Terminal connector of deep water free standing type vertical pipe system
CN104329044A (en) * 2014-10-09 2015-02-04 中国海洋石油总公司 Free standing type vertical pipe bottom connecting structure

Similar Documents

Publication Publication Date Title
CN107110403A (en) Cold water tube assembly for ocean thermal energy conversion
CN201236101Y (en) Equalizer bar for hanging
CN105752861B (en) Using buoyant mass and hang the method for leading dual-purpose rope installation deep-sea underwater heavy facility
CN106760638A (en) Marine Simple module metaplasia work building and the hanging method of a kind of achievable integral hoisting
CN107218016A (en) Connecting connection parts under deep sea vertical pipe
CN207111054U (en) Connecting connection parts under deep sea vertical pipe
CN104340843A (en) Reactor core hoisting tool
CN108590547A (en) Standpipe installation method
CN105220610A (en) A kind of for the new trestle between offshore oil platform
CN102674138A (en) Marine screw shaft hoisting tool
CN104709074A (en) Liquefied natural gas truck gas bottle support
CN102661444B (en) Installation method of deepwater double piping system of offshore platform
CN201152431Y (en) Jam-on type four-way pipe joint
CN108995783B (en) Large-depth ROV main body frame device based on titanium alloy
CN203048399U (en) Special lifting bracket for lifting drilling modules of deepwater drilling ship
CN207110998U (en) Drilling at the sea riser upper attachment means
CN203834448U (en) Novel six-leg platform jacket
CN203867270U (en) Double-oval conjoined chimney
KR101607942B1 (en) Method for loading riser guide tubes
CN107217999A (en) Drilling at the sea riser upper attachment means
CN109368508B (en) The offshore lifting method of large size valve on floating production storage offloading's standpipe
CN201711348U (en) Cast-welded combined box body of main transmission reducer of pipe rolling machine
CN106853576A (en) A kind of deep sea pressure cabin nacelle and its manufacturing process
CN206957614U (en) Production tree transfers the drilling rod leading arm of guided tooling
CN103058046A (en) Deepwater drilling ship drilling module lifting-dedicated hanger

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination