CN107214826A - The steel die device and its construction method of a kind of hollow slab girder prefabricated construction - Google Patents

The steel die device and its construction method of a kind of hollow slab girder prefabricated construction Download PDF

Info

Publication number
CN107214826A
CN107214826A CN201710615125.9A CN201710615125A CN107214826A CN 107214826 A CN107214826 A CN 107214826A CN 201710615125 A CN201710615125 A CN 201710615125A CN 107214826 A CN107214826 A CN 107214826A
Authority
CN
China
Prior art keywords
corner trim
inner corner
die device
hollow slab
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201710615125.9A
Other languages
Chinese (zh)
Inventor
和孙文
李坚
冯时
付敏
崔健
罗宗强
王阳
马滔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 14 Co Ltd
Original Assignee
Sinohydro Bureau 14 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 14 Co Ltd filed Critical Sinohydro Bureau 14 Co Ltd
Priority to CN201710615125.9A priority Critical patent/CN107214826A/en
Publication of CN107214826A publication Critical patent/CN107214826A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/28Cores; Mandrels
    • B28B7/30Cores; Mandrels adjustable, collapsible, or expanding

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

The invention discloses a kind of steel die device of hollow slab girder prefabricated construction and its construction method, it is desirable to provide the steel die device and its construction method of a kind of high hollow slab girder prefabricated construction of efficiency of construction.Steel die device therein includes two first inner corner trim punching blocks, two second inner corner trim punching blocks, the first support adjusting part, the second support adjusting part and locating rod;One end of first inner corner trim punching block described in two, which is hinged, constitutes Contraband shape;The first support adjusting part is located at the inner side of two first inner corner trim punching blocks, and it includes multigroup first connecting plate group, the first crossbeam set along the first inner corner trim punching block length direction, and the first fixed plate;Relative internal face is hinged two connecting plates of multigroup first connecting plate group with the two of two first inner corner trim punching blocks respectively, and the other end is bolted with first crossbeam;First fixed plate is located at the end on the inside of two first inner corner trim punching blocks, and its middle part is hinged with first crossbeam, and relative internal face is detachably connected with the two of two first inner corner trim punching blocks respectively at two ends.

Description

The steel die device and its construction method of a kind of hollow slab girder prefabricated construction
Technical field
The present invention relates to construction technical field of mold, filled more particularly, to a kind of punching block of hollow slab girder prefabricated construction Put and its construction method.
Background technology
During municipal administration, highway engineering construction, current more bridge superstructure uses precast hollow slab structure, therefore How by matter, according to quantity, quickly, easily construction precast hollow slab is particularly important.Precast hollow slab inner membrance one relatively common at present As for ordinary steel, wooden internal model, be divided into four sides up and down, this steel internal model using it is artificial one by one it is assembled, remove, such fixation Installation, dismounting mode are although feasible, but working procedure is more complicated in practical operation, and the engineering time is longer, need to put into substantial amounts of Manpower and materials, and during cored slab inner template is removed one by one, it is most likely that concrete can be damaged, concrete need to be repaiied It is multiple, and cored slab hollow parts space is smaller, removes inconvenience.Also the use inflatable inner mould having, although this Inner moulds convenient disassembly, But easily float and deform, it is impossible to ensure that the pouring quality of cored slab, or even the cored slab completed can not meet construction requirement, make Into unnecessary loss.
Above hollow board prefabrication beam inner template, the degree of accuracy is difficult to control to, efficiency of construction is reduced, expend a large amount of manpower and materials. Hardly possible meets construction demand instantly efficiently, quick, environmentally friendly.
The content of the invention
The purpose of the present invention is intended to overcome the shortcomings of that prior art is present there is provided a kind of efficiency of construction height, easy to use, Can Reusability and easily controllable hollow slab girder prefabricated construction steel die device and its construction method.
In order to solve the above-mentioned technical problem, the present invention is achieved by the following technical solutions:
A kind of steel die device of hollow slab girder prefabricated construction, it is referred to as inner side towards the side at center, otherwise is outside;Including two First inner corner trim punching block, two second inner corner trim punching blocks, the first support adjusting part, the second support adjusting part and locating rod;
One end of first inner corner trim punching block described in two, which is hinged, constitutes Contraband shape;It is cloudy that the first support adjusting part is located at two first The inner side of angle steel mould, it include it is multigroup using two pieces of connecting plates as one group of the first connecting plate group, along the first inner corner trim punching block length side To the first crossbeam for setting and being located at midline on the inside of two first inner corner trim punching blocks, and the first fixed plate;Multigroup described first connects Relative internal face is hinged two connecting plates of fishplate bar group with the two of two first inner corner trim punching blocks respectively, and the other end passes through spiral shell with first crossbeam Tether and connect;First fixed plate is located at the end on the inside of two first inner corner trim punching blocks, and its middle part is hinged with first crossbeam, two ends Relative internal face is detachably connected with the two of two first inner corner trim punching blocks respectively;
One end of second inner corner trim punching block described in two, which is hinged, constitutes Contraband shape;It is cloudy that the second support adjusting part is located at two second The inner side of angle steel mould, it include it is multigroup using two pieces of connecting plates as one group of the second connecting plate group, along the second inner corner trim punching block length side To the second cross beam for setting and being located at midline on the inside of two second inner corner trim punching blocks, and the second fixed plate;Multigroup described second connects Relative internal face is hinged two connecting plates of fishplate bar group with the two of two second inner corner trim punching blocks respectively, and the other end passes through spiral shell with second cross beam Tether and connect;Second fixed plate is located at the end on the inside of two second inner corner trim punching blocks, and its middle part is hinged with second cross beam, two ends Relative internal face is detachably connected with the two of two second inner corner trim punching blocks respectively;
Two stretching side end portions of the first inner corner trim punching block described in two are respectively provided with the first lap body with inclined-plane, the second inner corner trim steel described in two Two stretching side end portions of mould are respectively provided with the second lap body with inclined-plane;First lap body of the same side and the inclined-plane of the second lap body The parallel each other and laminating in construction;
The positioning hole penetrated for locating rod is correspondingly arranged in first lap body and in the second lap body
Preferably, first inner corner trim punching block articulated structure is described in two:Is respectively provided with the inside of two first inner corner trim punching block hinge sides One angle steel, the adjacent surface of two first angle steel, which interlocks, welds multiple the first coaxial annulus, and each first annulus passes through the first connecting shaft Through connection.
Preferably, second inner corner trim punching block articulated structure is described in two:It is all provided with the inside of two second inner corner trim punching block hinge sides The second angle steel is put, the adjacent surface of two second angle steel, which interlocks, welds multiple the second coaxial annulus, and each second annulus passes through second and connected Spindle is through connection.
Preferably, the first otic placode being hinged with the first connecting plate group is set on the first inner corner trim punching block internal face.
Preferably, the second otic placode being hinged with the second connecting plate group is set on the second inner corner trim punching block internal face.
Preferably, the first inner corner trim punching block include inner corner trim plate body and it is some be arranged on the inside of inner corner trim plate body put more energy into Plate.
Preferably, one end of the first crossbeam is provided with the first draw ring.
Preferably, one end of the second cross beam is provided with the second draw ring.
Preferably, the first crossbeam and second cross beam use I-steel.
A kind of construction method of hollow slab girder prefabricated construction, it uses steel die device as described above, and it includes following step Suddenly:
(1)Installation form:After the completion of hollow slab girder baseplate reinforcing bar and both sides reinforcing bar colligation, install outside precast hollow slab both sides Mould, corresponding height, the concrete pad of thickness are then placed in bottom plate and left and right sides reinforcing bar, whole steel die device is put Relevant position is put, the two ends of the first fixed plate and the second fixed plate are disengaged, and removes locating rod, first is adjusted after adjusting loose bolt Crossbeam and second cross beam make steel die device adjust to desired size size, and its headroom is met design requirement, then will positioning Bar loads on positioning hole, while fastening bolt, and the two ends of the first fixed plate and the second fixed plate are fixed, then filled in punching block Upper ends respective thickness concrete pad is put, last colligation superstructure reinforcing bar, measurement is checked, checked, adjusting template position After carry out concreting;
(2)Form removal:After the completion of concreting, locating rod is removed, and by the two of the first fixed plate and the second fixed plate End is disengaged, and adjusts adjustment first crossbeam and second cross beam after loose bolt to make steel die device is overall inwardly to reduce, when narrowing down to certain journey After degree, bundle the first draw ring using hoist engine steel strand wires and the second draw ring pulls out steel die device.
Compared with prior art, the invention has the advantages that:
The present invention solves the inner template degree of accuracy in existing cored slab work progress and is difficult to control to, and efficiency of construction reduction, template is difficult It is fixed, remove the technical barrier for expending a large amount of manpower and materials.Its not only simple operation, accurate positioning, and also the construction period is short, applies Work cost is low, and can be further ensured that concrete construction quality.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing There is the accompanying drawing used required in technology description to be briefly described, it should be apparent that, drawings in the following description are only this Some embodiments of invention, for those of ordinary skill in the art, on the premise of not paying creative work, can be with Other accompanying drawings are obtained according to these accompanying drawings.
Structural representation when Fig. 1 uses for the present invention.
Fig. 2 is the A direction views in Fig. 1, wherein illustrate only the knot of two second inner corner trim punching blocks and the second support adjusting part Structure.
Fig. 3 is the schematic diagram of two second inner corner trim punching block contraction states in Fig. 2.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments.It is based on Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under the premise of creative work is not paid Embodiment, belongs to the scope of protection of the invention.
The steel die device of hollow slab girder prefabricated construction shown in Fig. 1-3, it is referred to as inner side towards the side at center, otherwise is outer Side;Including two first inner corner trim punching blocks 1, two second inner corner trim punching blocks 2, the first support adjusting part 3, the second support adjusting part 4 with And locating rod 5;
One end of first inner corner trim punching block 1 described in two, which is hinged, constitutes Contraband shape;The first support adjusting part 3 is located at two first The inner side of inner corner trim punching block 1, it include it is multigroup using two pieces of connecting plates as one group of the first connecting plate group 31, along the first inner corner trim punching block 1 Length direction is set and positioned at the first crossbeam 32 of the inner side midline of two first inner corner trim punching block 1, and the first fixed plate(In figure not Show, structure is identical with the second fixed plate);Two connecting plates of multigroup first connecting plate group 31 respectively with two first inner corner trim steel The two of mould 1 are relative, and internal face is hinged, and the other end is bolted with first crossbeam 32;First fixed plate 33 is located at two the The end of the inner side of one inner corner trim punching block 1, its middle part is hinged with first crossbeam 32, two ends respectively with two first inner corner trim punching blocks 1 two Opposed inner walls face is detachably connected, such as bolt connection or clamping;
One end of second inner corner trim punching block 2 described in two, which is hinged, constitutes Contraband shape;The second support adjusting part 4 is located at two second The inner side of inner corner trim punching block 2, it include it is multigroup using two pieces of connecting plates as one group of the second connecting plate group 41, along the second inner corner trim punching block 2 Length direction is set and positioned at the second cross beam 42 of the inner side midline of two second inner corner trim punching block 2, and the second fixed plate 43;It is multigroup Relative internal faces are hinged two connecting plates of the second connecting plate group 41 with the two of two second inner corner trim punching blocks 2 respectively, the other end with Second cross beam 42 is bolted;Second fixed plate 43 is located at the end of the inner side of two second inner corner trim punching block 2, its middle part It is hinged with second cross beam 42, relative internal face is detachably connected with the two of two second inner corner trim punching blocks 2 respectively at two ends, such as bolt connection Or clamping etc.;
Two stretching side end portions of the first inner corner trim punching block 1 described in two are respectively provided with the first lap body 7 with inclined-plane, the second inner corner trim described in two Two stretching side end portions of punching block 2 are respectively provided with the second lap body 8 with inclined-plane;First lap body 7 and the second lap body 8 of the same side Inclined-plane construction when it is parallel each other and laminating;
The positioning hole penetrated for locating rod 5 is correspondingly arranged in first lap body 7 and in the second lap body 8(Do not show in figure Go out).
As preferred technical scheme, the articulated structure of first inner corner trim punching block 1 is described in two:Two first inner corner trim punching blocks 1 are hinged The first angle steel 11 is respectively provided with the inside of side, the adjacent surface of two first angle steel 11, which interlocks, welds multiple the first coaxial annulus 12, respectively First annulus 12 is by the first connecting shaft 13 through connection;Obviously also can be using articulated structures such as hinges.
As preferred technical scheme, the articulated structure of second inner corner trim punching block 2 is described in two:Two second inner corner trim punching blocks 2 are hinged The second angle steel 21 is respectively provided with the inside of side, the adjacent surface of two second angle steel 21, which interlocks, welds multiple the second coaxial annulus 22, respectively Second annulus 22 is by the second connecting shaft 23 through connection;Obviously also can be using articulated structures such as hinges.
Set and be hinged with the first connecting plate group 31 as preferred technical scheme, on the internal face of the first inner corner trim punching block 1 The first otic placode 14.
Set and be hinged with the second connecting plate group 41 as preferred technical scheme, on the internal face of the second inner corner trim punching block 2 The second otic placode 24.
As preferred technical scheme, the first inner corner trim punching block 1 includes inner corner trim plate body 15 and some is arranged at inner corner trim plate The stiffener 16 of the inner side of body 15.The second inner corner trim punching block can be used and the identical structure of the first inner corner trim punching block 1.
As preferred technical scheme, one end of the first crossbeam 32 is provided with the first draw ring(Not shown in figure, structure Substantially it is identical with the second draw ring).
As preferred technical scheme, one end of the second cross beam 42 is provided with the second draw ring 44.
As preferred technical scheme, the first crossbeam 32 and second cross beam 42 use I-steel.
A kind of construction method of hollow slab girder prefabricated construction, it uses steel die device as described above, and it includes following step Suddenly:
(1)Installation form:After the completion of hollow slab girder baseplate reinforcing bar and both sides reinforcing bar colligation, install outside precast hollow slab both sides Mould, then in bottom plate(Beam making bench)And corresponding height, the concrete pad of thickness are placed on left and right sides reinforcing bar, will be whole Steel die device places relevant position, and the two ends of the first fixed plate 33 and the second fixed plate 43 are disengaged, and removes locating rod 5, adjusts First crossbeam 32 and second cross beam 42 are adjusted after loose bolt makes steel die device adjust to desired size size, and meets its headroom Design requirement, then loads locating rod on positioning hole, while fastening bolt, and by the first fixed plate 33 and the second fixed plate 43 Two ends fix, then in steel die device upper ends respective thickness concrete pad, last colligation superstructure reinforcing bar, measurement Check, check, adjusting concreting is carried out after template position;
(2)Form removal:After the completion of concreting, locating rod is removed, and by the first fixed plate 33 and the second fixed plate 43 Two ends disengage, adjust adjustment first crossbeam 32 and second cross beam 42 after loose bolt to make steel die device is overall inwardly to reduce, work as diminution After to a certain extent, bundle the first draw ring using hoist engine steel strand wires and the second draw ring pulls out steel die device.
Steel die device need to be determined when removing according to the specific initial set of concrete, final setting time.If steel die device is except relatively early meeting Cause part concrete to come off, influence integral construction quality, and cause template to shrink difficulty as party is crossed in form removable, it is difficult to tear open Remove.The solidifying native setting time of C50 coagulations is shorter, or so general 12 hours for removing time control after the completion of concreting compared with To be suitable.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention God is with principle, and any modification, equivalent substitution and improvements made etc. should be included in the scope of the protection.

Claims (10)

1. a kind of steel die device of hollow slab girder prefabricated construction, it is referred to as inner side towards the side at center, otherwise is outside;Including Two first inner corner trim punching blocks, two second inner corner trim punching blocks, the first support adjusting part, the second support adjusting part and locating rod;Its It is characterised by:
One end of first inner corner trim punching block described in two, which is hinged, constitutes Contraband shape;It is cloudy that the first support adjusting part is located at two first The inner side of angle steel mould, it include it is multigroup using two pieces of connecting plates as one group of the first connecting plate group, along the first inner corner trim punching block length side To the first crossbeam for setting and being located at midline on the inside of two first inner corner trim punching blocks, and the first fixed plate;Multigroup described first connects Relative internal face is hinged two connecting plates of fishplate bar group with the two of two first inner corner trim punching blocks respectively, and the other end passes through spiral shell with first crossbeam Tether and connect;First fixed plate is located at the end on the inside of two first inner corner trim punching blocks, and its middle part is hinged with first crossbeam, two ends Relative internal face is detachably connected with the two of two first inner corner trim punching blocks respectively;
One end of second inner corner trim punching block described in two, which is hinged, constitutes Contraband shape;It is cloudy that the second support adjusting part is located at two second The inner side of angle steel mould, it include it is multigroup using two pieces of connecting plates as one group of the second connecting plate group, along the second inner corner trim punching block length side To the second cross beam for setting and being located at midline on the inside of two second inner corner trim punching blocks, and the second fixed plate;Multigroup described second connects Relative internal face is hinged two connecting plates of fishplate bar group with the two of two second inner corner trim punching blocks respectively, and the other end passes through spiral shell with second cross beam Tether and connect;Second fixed plate is located at the end on the inside of two second inner corner trim punching blocks, and its middle part is hinged with second cross beam, two ends Relative internal face is detachably connected with the two of two second inner corner trim punching blocks respectively;
Two stretching side end portions of the first inner corner trim punching block described in two are respectively provided with the first lap body with inclined-plane, the second inner corner trim steel described in two Two stretching side end portions of mould are respectively provided with the second lap body with inclined-plane;First lap body of the same side and the inclined-plane of the second lap body The parallel each other and laminating in construction;
The positioning hole penetrated for locating rod is correspondingly arranged in first lap body and in the second lap body.
2. the steel die device of hollow slab girder prefabricated construction according to claim 1, it is characterised in that:First inner corner trim steel described in two Mould articulated structure is:The first angle steel is respectively provided with the inside of two first inner corner trim punching block hinge sides, the adjacent surface of two first angle steel interlocks Multiple the first coaxial annulus of welding, each first annulus is by the first connecting shaft through connection.
3. the steel die device of hollow slab girder prefabricated construction according to claim 1, it is characterised in that:Second inner corner trim steel described in two Mould articulated structure is:The second angle steel is respectively provided with the inside of two second inner corner trim punching block hinge sides, the adjacent surface of two second angle steel interlocks Multiple the second coaxial annulus of welding, each second annulus is by the second connecting shaft through connection.
4. the steel die device of hollow slab girder prefabricated construction according to claim 1, it is characterised in that:The first inner corner trim punching block The first otic placode being hinged with the first connecting plate group is set on internal face.
5. the steel die device of hollow slab girder prefabricated construction according to claim 1, it is characterised in that:The second inner corner trim punching block The second otic placode being hinged with the second connecting plate group is set on internal face.
6. the steel die device of hollow slab girder prefabricated construction according to claim 1, it is characterised in that:The first inner corner trim punching block Including inner corner trim plate body and some stiffeners being arranged on the inside of inner corner trim plate body.
7. the steel die device of hollow slab girder prefabricated construction according to claim 1, it is characterised in that:The one of the first crossbeam End is provided with the first draw ring.
8. the steel die device of hollow slab girder prefabricated construction according to claim 1, it is characterised in that:The one of the second cross beam End is provided with the second draw ring.
9. the steel die device of hollow slab girder prefabricated construction according to claim 1, it is characterised in that:The first crossbeam and Two crossbeams use I-steel.
10. a kind of construction method of hollow slab girder prefabricated construction, it uses the steel die device as described in claim 1-9 is any, It is characterized in that comprising the following steps:
(1)Installation form:After the completion of hollow slab girder baseplate reinforcing bar and both sides reinforcing bar colligation, install outside precast hollow slab both sides Mould, corresponding height, the concrete pad of thickness are then placed in bottom plate and left and right sides reinforcing bar, whole steel die device is put Relevant position is put, the two ends of the first fixed plate and the second fixed plate are disengaged, and removes locating rod, first is adjusted after adjusting loose bolt Crossbeam and second cross beam make steel die device adjust to desired size size, and its headroom is met design requirement, then will positioning Bar loads on positioning hole, while fastening bolt, and the two ends of the first fixed plate and the second fixed plate are fixed, then filled in punching block Upper ends respective thickness concrete pad is put, last colligation superstructure reinforcing bar, measurement is checked, checked, adjusting template position After carry out concreting;
(2)Form removal:After the completion of concreting, locating rod is removed, and by the two of the first fixed plate and the second fixed plate End is disengaged, and adjusts adjustment first crossbeam and second cross beam after loose bolt to make steel die device is overall inwardly to reduce, when narrowing down to certain journey After degree, bundle the first draw ring using hoist engine steel strand wires and the second draw ring pulls out steel die device.
CN201710615125.9A 2017-07-26 2017-07-26 The steel die device and its construction method of a kind of hollow slab girder prefabricated construction Withdrawn CN107214826A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710615125.9A CN107214826A (en) 2017-07-26 2017-07-26 The steel die device and its construction method of a kind of hollow slab girder prefabricated construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710615125.9A CN107214826A (en) 2017-07-26 2017-07-26 The steel die device and its construction method of a kind of hollow slab girder prefabricated construction

Publications (1)

Publication Number Publication Date
CN107214826A true CN107214826A (en) 2017-09-29

Family

ID=59954717

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710615125.9A Withdrawn CN107214826A (en) 2017-07-26 2017-07-26 The steel die device and its construction method of a kind of hollow slab girder prefabricated construction

Country Status (1)

Country Link
CN (1) CN107214826A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111037718A (en) * 2019-12-31 2020-04-21 广西建工集团第五建筑工程有限责任公司 Interior-free integral quick-dismantling box girder inner mold and mounting and dismounting method thereof
CN111688002A (en) * 2020-06-18 2020-09-22 中北大学 Coincide prefabricated hollow floor centre form
CN112962961A (en) * 2021-02-05 2021-06-15 绍兴市城投建筑工业化制造有限公司 Inner template for hollow upright post

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201609922U (en) * 2010-02-05 2010-10-20 浙江永峰模具制造有限公司 Pull type prefabricated small box girder iron core
CN201753439U (en) * 2010-07-19 2011-03-02 山东铁鹰建设工程有限公司 Adjustable internal mould of hollow plate beam by highway pretensioning method
CN102294741A (en) * 2011-07-14 2011-12-28 中铁二局股份有限公司 Hinged draw type steel internal mould and construction method for prefabricating hollow slab beams
CN204094925U (en) * 2014-09-11 2015-01-14 中交一公局第三工程有限公司 The internal mould device of prefabricated small box girder
CN204309092U (en) * 2014-11-29 2015-05-06 中铁三局集团有限公司 Rotary shaft box girder inner formwork
CN204450819U (en) * 2015-02-03 2015-07-08 山东瑞鸿重工机械有限公司 Template retractor device
CN206066666U (en) * 2016-08-31 2017-04-05 国强建设集团有限公司 A kind of detachable steel core for making pre-stressed concrete hollow beam
CN207088136U (en) * 2017-07-26 2018-03-13 中国水利水电第十四工程局有限公司 A kind of steel die device of hollow slab girder prefabricated construction

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201609922U (en) * 2010-02-05 2010-10-20 浙江永峰模具制造有限公司 Pull type prefabricated small box girder iron core
CN201753439U (en) * 2010-07-19 2011-03-02 山东铁鹰建设工程有限公司 Adjustable internal mould of hollow plate beam by highway pretensioning method
CN102294741A (en) * 2011-07-14 2011-12-28 中铁二局股份有限公司 Hinged draw type steel internal mould and construction method for prefabricating hollow slab beams
CN204094925U (en) * 2014-09-11 2015-01-14 中交一公局第三工程有限公司 The internal mould device of prefabricated small box girder
CN204309092U (en) * 2014-11-29 2015-05-06 中铁三局集团有限公司 Rotary shaft box girder inner formwork
CN204450819U (en) * 2015-02-03 2015-07-08 山东瑞鸿重工机械有限公司 Template retractor device
CN206066666U (en) * 2016-08-31 2017-04-05 国强建设集团有限公司 A kind of detachable steel core for making pre-stressed concrete hollow beam
CN207088136U (en) * 2017-07-26 2018-03-13 中国水利水电第十四工程局有限公司 A kind of steel die device of hollow slab girder prefabricated construction

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111037718A (en) * 2019-12-31 2020-04-21 广西建工集团第五建筑工程有限责任公司 Interior-free integral quick-dismantling box girder inner mold and mounting and dismounting method thereof
CN111688002A (en) * 2020-06-18 2020-09-22 中北大学 Coincide prefabricated hollow floor centre form
CN112962961A (en) * 2021-02-05 2021-06-15 绍兴市城投建筑工业化制造有限公司 Inner template for hollow upright post
CN112962961B (en) * 2021-02-05 2022-05-27 绍兴市城投建筑工业化制造有限公司 Inner template for hollow upright post

Similar Documents

Publication Publication Date Title
CN106758856B (en) The construction method of the pretensioned prestressing corrugated steel web plate composite box girder of precast block
CN103161126A (en) Road bridge variable section hollow high pier slip-form construction method
CN108978434B (en) Bracket-free industrialized construction method of steel-concrete combined continuous box girder bridge
CN101424073A (en) Bridge deck and steel girder second combination method for whole arch precasted steel-concrete composite continuous box girder
CN106894326A (en) The construction method of assembled pretensioned prestressing corrugated steel web plate composite box girder
CN109024225A (en) Ultra-high performance concrete truss arch blade unit, truss arch piece bridge and construction method
CN110331675B (en) Construction method for rebuilding and expanding bridge
CN107214826A (en) The steel die device and its construction method of a kind of hollow slab girder prefabricated construction
CN109440634A (en) The prefabricated high strength concrete hollow bent cap structure that internal model can be taken off
CN108301545A (en) A kind of big module overlapping contignation of the assembled with space truss temporary support
CN206599919U (en) A kind of integral prefabricated reinforcing bar web frame of shear wall
CN109162204B (en) Construction method for transverse block rapid assembling of bridge substructure
CN209585431U (en) Frame column formwork and exempt from template reinforced column
CN107829408B (en) Rectangular aqueduct construction steel mould trolley
CN110042743A (en) The hydraulic climbing die block system of twin legged thin wall hollow pier with synchronize climb construction technology
CN112281663B (en) Construction method for widening connection of upper structures of new and old bridges
CN102206934B (en) Method for block-by-block casting of concrete continuous beam bridge by using military truss shift mould
CN110700105B (en) Synchronous construction method for high pier column and tie beam and template used in same
CN207088136U (en) A kind of steel die device of hollow slab girder prefabricated construction
CN112982162A (en) Steel bar truss type steel-concrete combined bridge deck and construction method
CN211735098U (en) Wide construction equipment is transversely pieced together to built-up connection formula concrete T roof beam
CN111893889A (en) Main bridge closure section construction method
CN207376882U (en) A kind of assembly concrete variable cross-section newel post type shearing wall member and its making mold
CN114561873B (en) Bridge high pier construction method
CN207452684U (en) Stiff skeleton straining beam structure built in high pier

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20170929