CN107201828B - A kind of uncompacted restorative procedure of prestress hole path pressure grouting - Google Patents

A kind of uncompacted restorative procedure of prestress hole path pressure grouting Download PDF

Info

Publication number
CN107201828B
CN107201828B CN201710472293.7A CN201710472293A CN107201828B CN 107201828 B CN107201828 B CN 107201828B CN 201710472293 A CN201710472293 A CN 201710472293A CN 107201828 B CN107201828 B CN 107201828B
Authority
CN
China
Prior art keywords
snorkel
glue
uncompacted
drilling
path pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710472293.7A
Other languages
Chinese (zh)
Other versions
CN107201828A (en
Inventor
郭保林
何韬
康宏伟
邢浩
甘鹏
李昱岐
刘新权
姜瑞双
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gansu Changda Highway Co ltd
Qingdao Linchuan Engineering Technology Consulting Co ltd
Shandong Highway & Bridge Construction Co ltd
First Engineering Co Ltd of CCCC Third Highway Engineering Co Ltd
Original Assignee
GANSU CHANGDA HIGHWAY CO Ltd
QINGDAO LINCHUAN ENGINEERING TECHNOLOGY CONSULTING Co Ltd
Engineering Co Ltd Of Middle Friendship Three Public Office First
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GANSU CHANGDA HIGHWAY CO Ltd, QINGDAO LINCHUAN ENGINEERING TECHNOLOGY CONSULTING Co Ltd, Engineering Co Ltd Of Middle Friendship Three Public Office First filed Critical GANSU CHANGDA HIGHWAY CO Ltd
Priority to CN201710472293.7A priority Critical patent/CN107201828B/en
Publication of CN107201828A publication Critical patent/CN107201828A/en
Application granted granted Critical
Publication of CN107201828B publication Critical patent/CN107201828B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing

Abstract

The invention discloses a kind of uncompacted restorative procedures of prestress hole path pressure grouting, comprising: several drillings are opened up at the crack of prestress hole pipeline outer wall;The snorkel is respectively set in each drilling;The snorkel exposed parts that lowest part is on spatial position are connected with vacuum pump, the gas outlet of vacuum pump is connected with the first container for filling drier self-indicating, snorkel in remaining each drilling is connected by hose with the second container for filling discoloration drier, is emptied the moisture in prestressed pore passage by vacuum pump;At each snorkel install glue-injection base, by glue-injection base of the glue-injecting pump from the snorkel of lowest part successively into prestressed pore passage inject epoxy grouting resin;Until filling epoxy grouting resin by the glue-injection base at the last one snorkel.It is realized using the present invention to the uncompacted reparation of hole path pressure grouting, avoids the corrosion of presstressed reinforcing steel in duct, improve durability and the safety of prestressed structure.

Description

A kind of uncompacted restorative procedure of prestress hole path pressure grouting
Technical field
The invention belongs to field of engineering technology more particularly to a kind of uncompacted restorative procedures of prestress hole path pressure grouting.
Background technique
Post tensioning structure is common structure type in civil engineering, the quality and compaction rate pair of hole path pressure grouting The corrosion regularity of steel strand wires influences very big under high-stress state.The ratio of mud is low, good fluidity, ungauged regions, and no bleeding etc. is all high The necessary condition of quality mud jacking.It is that mud jacking is closely knit in guarantee duct that the quality of circulation mud jacking and grout outlet slurry, which is met the requirements, has Efficacious prescriptions method.
Some grouting material qualities are unqualified, under low water-cement ratio (0.26~0.28), are unsatisfactory for the fluidity requirement of specification (10~17s), during specific mud jacking, operator improves the fluidities of slurries often through the ratio of mud is increased, and this It will cause slurries bleeding.Water lower than the density of cement 2/3, secretes the eminence that Free water out is gathered in prestressed pore passage.
During its wet curing, part curing water may accumulate in duct prestressed structure, in hole path pressure grouting mistake One channel mud jacking is used in journey, and does not wait until that the valve of grout outlet is just closed in even slurry outflow, leads to a certain range under anchor Interior slurry is rich in air and Free water.In anchorage dead astern, in duct only have presstressed reinforcing steel and without grouting material, hereafter one In hole road, the ratio of mud is distributed from infinity to design value, and has been not excluded for a hole road and there was only water and without grouting material.Such as Shown in Fig. 1 of Figure of description, the figure shows a kind of uncompacted structure chart of prestress hole path pressure grouting, anchorage 1 in the figure Dead astern is the fill area 2 that presstressed reinforcing steel and duct gap are mainly filled by air, is presstressed reinforcing steel and hole close to the fill area 2 The fill area 3 that road gap is mainly filled by the grouting material of high water-cement ratio, 3 rear of fill area is only presstressed reinforcing steel and duct gap master It will be by the fill area 4 of qualified grouting material filling.
Under the conditions of subzero temperature, Free water freezing and expansion causes concrete to crack along duct direction, and environment temperature rises to positive temperature When, ice-out Cheng Shui is oozed out by the crack on prestress hole pipeline outer wall, and carries the calcium hydroxide in grouting material to structure Surface meets the carbon dioxide in air and generates white calcium carbonate.Once being formed, moisture, oxygen in air will in crack Presstressed reinforcing steel surface is readily arrived at, accelerates its corrosion, to seriously affect durability and the safety of prestressed structure.
In mechanization relatively advanced today, prestressed structure speed of application is very fast, for example, box beam from it is prefabricated, be lifted into Post-cast strip pours completion, that is, 3~4 months time.But the above problem has to pass through winter subzero temperature again can just be exposed, For that must just can not take measures to implement to repair on the spot to hole path pressure grouting for the prestressed structure got off of unloading.And currently, There has been no corresponding technologies.It can be seen that the existing technology needs further improvement and improves.
Summary of the invention
In view of the serious consequence that above-mentioned existing construction quality lowly causes structure durability to reduce, the present invention provides one kind The uncompacted restorative procedure of prestress hole path pressure grouting, to ensure durability and the safety of prestressed structure.
The technical scheme adopted by the invention is as follows:
A kind of uncompacted restorative procedure of prestress hole path pressure grouting, this method comprises the following steps:
Step 1, several drillings are opened up along fracture length direction at the crack of prestress hole pipeline outer wall, each drilling with The inner hole of prestressed pore passage is connected;
Step 2, the inner wall cleaning of each drilling is clean, it is ensured that be free of dust, clast;
Step 3, it selects and is adapted with drilling and snorkel that quantity is equal, one is respectively set in each drilling and described leads to Tracheae, and each snorkel be installed to drilling in after, each snorkel need to retain certain exposed size;
Step 4, surface-closed is carried out using non-drilled region of the adhesive to prestressed pore passage fracture faces;
Step 5, the snorkel exposed parts that lowest part is on spatial position are connected with vacuum pump, vacuum pump goes out Port is connected with the first container for filling drier self-indicating, when vacuum pump is opened, in the prestressed pore passage that is connected with vacuum pump The Free water of bore portion gasifies discharge under the action of negative pressure, and atmosphere is discharged into after the first container;Ventilation in remaining each drilling Pipe is connected by hose with the second container for filling discoloration drier;
Step 6, when the drier self-indicating in the first container no longer changes colour because of dampness, by vacuum pump and on spatial position Snorkel at height second from the bottom is connected, and repeats the above steps 5, until the moisture in prestressed pore passage empties;
Step 7, the exposed parts of each snorkel are cut away, glue-injection base is installed at each snorkel later, passes through injecting glue It pumps from the glue-injection base at the snorkel for being in lowest part on spatial position and injects epoxy grouting resin into prestressed pore passage;
Step 8, after the glue-injection base stayed at the snorkel being at height third from the bottom on spatial position starts plastic emitting, Stop the glue-injection base injecting glue at the snorkel for being in lowest part on spatial position, then by glue-injecting pump from space bit It sets the glue-injection base at the snorkel at height second from the bottom and injects epoxy grouting resin into crack;And so on, Until filling epoxy grouting resin by the glue-injection base at the last one snorkel;
Step 9, after epoxy grouting resin solidification and after reaching the intensity of design requirement, by the glue on prestressed pore passage surface And the glue-injection base at each ventilation pipe polishes off.
The internal diameter of each drilling is 10~15mm.
The distance between adjacent two described drilling is 20~40cm.
In the step 2, drill hole inner wall is cleared up using to each method for being passed through pressure-air that drills.
In the step 3, snorkel is bonded on drill hole inner wall by using adhesive.
The adhesive is epoxy resin.
Each snorkel is stainless steel tube.
The bottom of each snorkel need to be flush with prestressed pore passage inner wall.
By adopting the above-described technical solution, obtained by the present invention have the beneficial effect that
1, using the present invention, can by using hydrolysis product of cement as the system of cementitious material, by negative pressure by it is extra from By water discharge, the serious cementitious material bigger than normal of the ratio of mud is then injected into because dehydration cracking is to form connectivity gap at this time Epoxy resin adhesive fills up the communication gap between solid particle as packing material, realizes to hole path pressure grouting leakiness Reparation, avoid the corrosion of presstressed reinforcing steel in duct, improve durability and the safety of prestressed structure.
2, present invention is particularly suitable for cause structural concrete to crack along prestressed pore passage to because of the icing of hole path pressure grouting bleeding The reparation of infiltration.
Detailed description of the invention
Fig. 1 shows a kind of uncompacted structure chart of prestress hole path pressure grouting.
Fig. 2 is that vacuum pump of the present invention makes Free water gasify under the action of negative pressure a kind of status diagram of discharge.
Fig. 3 is prestressed pore passage injecting glue distribution schematic diagram in the present invention.
Specific embodiment
The present invention is described in further detail with specific embodiment with reference to the accompanying drawing, but the present invention is not limited to These embodiments.
As shown in Figures 2 and 3, the uncompacted restorative procedure of a kind of prestress hole path pressure grouting, this method comprises the following steps:
Step 1, several drillings 8 are opened up along fracture length direction at the crack of 7 outer wall of prestressed pore passage, respectively drills 8 It is connected with the inner hole of prestressed pore passage 7.The internal diameter of each drilling 8 is between 10mm, 12mm, 15mm or 10~15mm Any number.Any number of the distance between the adjacent two described drilling 8 between 20cm, 30cm, 40cm or 20~40cm.Respectively The bottom of the drilling 8 need to be flush with 7 inner wall of prestressed pore passage.
Step 2, the inner wall cleaning of each drilling 8 is clean, it is ensured that without dust, clast etc..Using logical to each drilling 8 Enter the method cleaning drill hole inner wall of pressure-air.Certainly, the method for cleaning drilling 8 is not limited only to by being blown into high pressure sky The method of gas can also take other measure cleaning drill hole inner walls, as long as ensuring in drilling 8 without dust, clast etc..
Step 3, it selects and is adapted with drilling 8 and snorkel that quantity is equal, each drill is respectively set described in one in 8 Snorkel, and each snorkel be installed to drilling 8 in after, each snorkel need to retain certain exposed size.Each snorkel is equal For stainless steel tube.And the bottom of each snorkel need to be flush with 7 inner wall of prestressed pore passage.When snorkel is installed, it can pass through Snorkel is bonded on 8 inner walls of drilling using adhesives such as epoxy resin.
Step 4, surface envelope is carried out using non-drilled region of the adhesives such as epoxy resin to 7 fracture faces of prestressed pore passage It closes.
Step 5, the snorkel exposed parts that lowest part is on spatial position are connected with vacuum pump 9, vacuum pump 9 Gas outlet is connected with the first container 10 for filling drier self-indicating, when vacuum pump 9 is opened, the prestressing force that is connected with vacuum pump 9 The Free water of 7 bore section of duct gasifies discharge under the action of negative pressure, and is discharged into atmosphere after the first container 10;Remaining respectively drills Snorkel in 8 is connected by hose with the second container 6 for filling discoloration drier.Second container 6 is connected with ventilation pipe 5 It is logical.
Step 6, when the drier self-indicating in the first container 10 no longer changes colour because of dampness, by vacuum pump 9 and in space bit It sets the snorkel at the height second from the bottom to be connected, repeats the above steps 5, until the moisture row in prestressed pore passage 7 Only.
Step 7, the exposed parts of each snorkel are cut away, glue-injection base is installed at each snorkel later, passes through injecting glue Pump 11 injects epoxy grouting tree into prestressed pore passage 7 from the glue-injection base being at the snorkel of lowest part on spatial position Rouge.The epoxy grouting resin need to select low viscosity, high-intensitive product.
Step 8, after the glue-injection base stayed at the snorkel being at height third from the bottom on spatial position starts plastic emitting, Stop the glue-injection base injecting glue at the snorkel for being in lowest part on spatial position, then by glue-injecting pump 11 from space Glue-injection base on position at the snorkel at height second from the bottom injects epoxy grouting resin into crack;With such It pushes away, until filling epoxy grouting resin by the glue-injection base at the last one snorkel.
Step 9, after epoxy grouting resin solidification and after reaching the intensity of design requirement, by the glue on 7 surface of prestressed pore passage Glue-injection base at liquid etc. and each ventilation pipe polishes off.
The part that do not address in the present invention uses or uses for reference prior art and can be realized.
Specific embodiment described herein is only to spiritual example explanation of the invention.Belonging to the present invention Those skilled in the art can make various modifications or additions to the described embodiments or using similar Mode substitutes, and however, it does not deviate from the spirit of the invention or beyond the scope of the appended claims.

Claims (8)

1. a kind of uncompacted restorative procedure of prestress hole path pressure grouting, which is characterized in that this method comprises the following steps:
Step 1, several drillings are opened up along fracture length direction at the crack of prestress hole pipeline outer wall, each drilling with answer in advance The inner hole in power duct is connected;
Step 2, the inner wall cleaning of each drilling is clean, it is ensured that be free of dust, clast;
Step 3, it selects and is adapted and snorkel that quantity is equal with drilling, the ventilation is respectively set in each drilling Pipe, and each snorkel be installed to drilling in after, each snorkel need to retain exposed size;
Step 4, surface-closed is carried out using non-drilled region of the adhesive to prestressed pore passage fracture faces;
Step 5, the snorkel exposed parts that lowest part is on spatial position are connected with vacuum pump, the gas outlet of vacuum pump It is connected with the first container for filling drier self-indicating, when vacuum pump is opened, hole portion in the prestressed pore passage that is connected with vacuum pump Point Free water gasify under the action of negative pressure discharge, and atmosphere is discharged into after the first container;Snorkel in remaining each drilling is logical It crosses hose and is connected with the second container for filling discoloration drier;
Step 6, when the drier self-indicating in the first container no longer changes colour because of dampness, vacuum pump is in on spatial position Snorkel at height second from the bottom is connected, and repeats the above steps 5, until the moisture in prestressed pore passage empties;
Step 7, the exposed parts of each snorkel are cut away, later at each snorkel install glue-injection base, by glue-injecting pump from The glue-injection base at snorkel on spatial position in lowest part injects epoxy grouting resin into prestressed pore passage;
Step 8, after the glue-injection base stayed at the snorkel being at height third from the bottom on spatial position starts plastic emitting, stop To the glue-injection base injecting glue being on spatial position at the snorkel of lowest part, then by glue-injecting pump from spatial position Glue-injection base at the snorkel at height second from the bottom injects epoxy grouting resin into crack;And so on, until Epoxy grouting resin is filled by the glue-injection base at the last one snorkel;
Step 9, after epoxy grouting resin solidification and after reaching the intensity of design requirement, by the glue on prestressed pore passage surface and Glue-injection base at each ventilation pipe polishes off.
2. the uncompacted restorative procedure of a kind of prestress hole path pressure grouting according to claim 1, which is characterized in that each described The internal diameter of drilling is 10~15mm.
3. the uncompacted restorative procedure of a kind of prestress hole path pressure grouting according to claim 1, which is characterized in that adjacent two The distance between described drilling is 20~40cm.
4. the uncompacted restorative procedure of a kind of prestress hole path pressure grouting according to claim 1, which is characterized in that the step In rapid 2, drill hole inner wall is cleared up using to each method for being passed through pressure-air that drills.
5. the uncompacted restorative procedure of a kind of prestress hole path pressure grouting according to claim 1, which is characterized in that the step In rapid 3, snorkel is bonded on drill hole inner wall by using adhesive.
6. the uncompacted restorative procedure of a kind of prestress hole path pressure grouting according to claim 5, which is characterized in that the glue Glutinous agent is epoxy resin.
7. the uncompacted restorative procedure of a kind of prestress hole path pressure grouting according to claim 1, which is characterized in that each described Snorkel is stainless steel tube.
8. the uncompacted restorative procedure of a kind of prestress hole path pressure grouting according to claim 1, which is characterized in that each described The bottom of snorkel need to be flush with prestressed pore passage inner wall.
CN201710472293.7A 2017-06-21 2017-06-21 A kind of uncompacted restorative procedure of prestress hole path pressure grouting Active CN107201828B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710472293.7A CN107201828B (en) 2017-06-21 2017-06-21 A kind of uncompacted restorative procedure of prestress hole path pressure grouting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710472293.7A CN107201828B (en) 2017-06-21 2017-06-21 A kind of uncompacted restorative procedure of prestress hole path pressure grouting

Publications (2)

Publication Number Publication Date
CN107201828A CN107201828A (en) 2017-09-26
CN107201828B true CN107201828B (en) 2019-07-19

Family

ID=59907075

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710472293.7A Active CN107201828B (en) 2017-06-21 2017-06-21 A kind of uncompacted restorative procedure of prestress hole path pressure grouting

Country Status (1)

Country Link
CN (1) CN107201828B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107795072A (en) * 2017-11-28 2018-03-13 北京市地铁运营有限公司地铁运营技术研发中心 Reinforcement type subway prestressing force beam body and manufacture method
CN108344799A (en) * 2017-12-09 2018-07-31 菏泽城建工程发展集团有限公司 A kind of detection method for bridge prestress pore channel slip casting plumpness
CN109928013B (en) * 2017-12-15 2023-11-28 楚天科技股份有限公司 Sample bottle manufacturing method of leak detector

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4659589A (en) * 1985-06-21 1987-04-21 Renbec International Corp. Process for applying a sealing composition
US6527849B2 (en) * 1990-06-19 2003-03-04 Carolyn M. Dry Self-repairing, reinforced matrix materials
CN103195468A (en) * 2013-04-02 2013-07-10 重庆市能源投资集团科技有限责任公司 System process for conducting efficient strengthened extraction in surrounding rock
CN104481560B (en) * 2014-12-09 2017-08-22 中煤第一建设有限公司 Back water-bearing layer administering method
CN204570685U (en) * 2015-02-26 2015-08-19 北京公联信达智能交通技术有限责任公司 Repair the mud jacking formula anchor pole of U-shaped abutment longitudinal cracking

Also Published As

Publication number Publication date
CN107201828A (en) 2017-09-26

Similar Documents

Publication Publication Date Title
CN107201828B (en) A kind of uncompacted restorative procedure of prestress hole path pressure grouting
CN104088254B (en) Pressure-bearing reinforced concrete structure leakage repair device and construction method thereof
CN104912574B (en) A kind of tunnel-liner percolating water Treatment Methods
CN106544961A (en) A kind of distress in concrete blocking method
CN207739264U (en) A kind of Grouting Pipe
CN101891445A (en) Back-injected clay slurry of composite lining tunnel and injection method thereof
CN104895581A (en) Tunnel lining rapid repair structure based on carbon fiber woven mesh and repair method thereof
CN110195444A (en) Basement leakage back side processing method
CN105274967A (en) Repairing method for hydraulic concrete crack
CN214885801U (en) A slip casting leaking stoppage system for floor infiltration point
KR101619218B1 (en) Fiber reinforcement grouting method of construction
CN107869116A (en) A kind of light-weight thermal-insulating and sound-insulating batten and preparation method thereof
CN207919360U (en) A kind of vacuum aid grouting system
CN206816274U (en) A kind of repairing and reinforcement structure of shield duct piece
CN106761841B (en) Working face tailgate fractured coal grouting reinforcement method
CN109235668A (en) Residential building curtain wall and wall crack plugging structure
CN110453672B (en) Loose shallow earth covering double-liquid grouting reinforcement method
CN107975249A (en) A kind of crack repairing method of concrete walls or terrace
CN105297771B (en) A kind of reinforcement means of highway masonry retaining wall
CN204282229U (en) Hole injecting glue reinforced structure is drawn in a kind of prestressing force prefabricated case beam crack
CN218027470U (en) Take glutinous rice mortar stone structure of building of multidirectional hole
CN106939700A (en) The vacuum aided sealing off and covering anchorage construction method of back-off anchor recess
CN105781580A (en) Tunnel crack repair method
CN108867709A (en) A kind of waterproofing for basement method
KR101930495B1 (en) Injection Method of Grout Material

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20190626

Address after: 100012 No. 18 Laiguangying West Road, Chaoyang District, Beijing

Applicant after: Engineering Co., Ltd of middle friendship three public office first

Applicant after: Qingdao Linchuan Engineering Technology Consulting Co., Ltd.

Applicant after: Gansu Changda Highway Co., Ltd.

Address before: 266500 Jinshatan Road, Qingdao economic and Technological Development Zone, Shandong 182

Applicant before: Qingdao Linchuan Engineering Technology Consulting Co., Ltd.

GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200601

Address after: 100012 Beijing City, Chaoyang District, No. 18 West Road

Co-patentee after: QINGDAO LINCHUAN ENGINEERING TECHNOLOGY CONSULTING Co.,Ltd.

Patentee after: THE FRIST ENGINEERING CO., LTD. OF THE CCCC THIRD HIGHWAY ENGINEERING Co.,Ltd.

Co-patentee after: GANSU CHANGDA HIGHWAY Co.,Ltd.

Co-patentee after: SHANDONG HIGHWAY & BRIDGE CONSTRUCTION Co.,Ltd.

Address before: 100012 Beijing City, Chaoyang District, No. 18 West Road

Co-patentee before: QINGDAO LINCHUAN ENGINEERING TECHNOLOGY CONSULTING Co.,Ltd.

Patentee before: THE FRIST ENGINEERING CO., LTD. OF THE CCCC THIRD HIGHWAY ENGINEERING Co.,Ltd.

Co-patentee before: GANSU CHANGDA HIGHWAY Co.,Ltd.