CN107201779A - A kind of batter post couples the structure of stress with wide span house cap - Google Patents
A kind of batter post couples the structure of stress with wide span house cap Download PDFInfo
- Publication number
- CN107201779A CN107201779A CN201710254721.9A CN201710254721A CN107201779A CN 107201779 A CN107201779 A CN 107201779A CN 201710254721 A CN201710254721 A CN 201710254721A CN 107201779 A CN107201779 A CN 107201779A
- Authority
- CN
- China
- Prior art keywords
- batter post
- truss
- steel
- house cap
- stress
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/342—Structures covering a large free area, whether open-sided or not, e.g. hangars, halls
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/58—Connections for building structures in general of bar-shaped building elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B7/00—Roofs; Roof construction with regard to insulation
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/02—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
- E04C3/04—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal
- E04C3/11—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal with non-parallel upper and lower edges, e.g. roof trusses
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Joining Of Building Structures In Genera (AREA)
Abstract
The present invention relates to the structure that a kind of batter post couples stress with wide span house cap, reduce the thickness of wide span house cap, reduce the tilting moment that batter post is produced to overall structure, batter post is added to contribute integrally-built integral rigidity, larger post bottom moment of flexure and horizontal force that batter post is caused to basis are also reduced simultaneously, structure ductility is added, reliability of structure is improved.
Description
Technical field
The invention belongs to Structural Engineering long strands field, more particularly to a kind of batter post couples stress with wide span house cap
Structure.
Background technology
With a large amount of constructions of large span spatial structure, building is sent out towards complicated, the vdiverse in function comprehensive direction of build
Exhibition, architect has been not content with the shape of rule, larger span, or even is not content with and only makes an issue of in the plane, examines
Consider the aesthetic effect on facade, so that batter post component is by bold utilization, but batter post overall structure produces outside power of toppling
Square, weakens integrally-built integral rigidity, while oblique pillar causes larger post bottom moment of flexure and horizontal thrust to basis.Such as
What reduces the tilting moment that batter post is produced to overall structure, and increase is contributed integrally-built integral rigidity, and is reduced to base
Larger post bottom moment of flexure and horizontal force that plinth is caused, while ensureing batter post degree of safety again, increase ductility, improve safety stock,
It is the problem of needing in engineering to solve.
The content of the invention
The present invention relates to the structure that a kind of batter post couples stress with wide span house cap, the thickness of wide span house cap is reduced,
The tilting moment that batter post is produced to overall structure is reduced, batter post is added and integrally-built integral rigidity is contributed, also simultaneously
Larger post bottom moment of flexure and horizontal force that batter post is caused to basis are reduced, structure ductility is added, improves the reliable of structure
Property.
The structure that a kind of batter post couples stress with wide span house cap is made up of wide span house cap, batter post, right cylinder, described
Wide span house cap be large span steel truss, be made up of plane girder, space truss, plane girder include main couple, jack truss,
Space truss includes outer ring annular stereo truss and internal straight across space truss composition, and the ring truss and inside are straight across three-dimensional purlin
Frame is inverted triangle space truss, and described peripheral batter post is formed by hypomere steel reinforced concrete batter post and epimere steel batter post, described
Hypomere steel reinforced concrete column length accounts for 1/5th of whole peripheral batter post length, and epimere steel batter post accounts for whole peripheral batter post length
4/5ths, the right cylinder be uiform section reinforced column.The large span steel truss and uiform section armored concrete are straight
Post is connected by hinged-support, and the large span steel truss is connected with batter post by bridle iron.The batter post and right cylinder pass through
Long-span roof forms the structure that a kind of batter post couples stress with long-span roof.A kind of batter post coupled with wide span house cap by
The structure erection sequence of power is then pacified to set up peripheral batter post hypomere, batter post epimere and right cylinder and internal framework successively
Wide span house cap is filled, the internal framework and right cylinder reach intensity rear collapsible die, and the outer shroud batter post need to be in large span
Just collapsible die after steel worm-gearing is installed completely.
Further, the lower ear plate of the hinged-support is connected with uiform section armored concrete capital slugging, the hinge
The upper ear plate of bearing is with the lower boom on wide span house cap ring truss by being welded to connect, and the upper ear plate passes through pin with lower ear plate
Axle is connected.
Further, the main couple top boom of the wide span house cap with jack truss top boom by mutually passing through steel node weld
Connection, the main couple lower edge and jack truss lower edge are connected by mutually passing through steel node weld.The main couple winds up and ring truss
Wind up and connected by mutually passing through steel node weld, the main couple lower edge meets node weld company with ring truss lower edge by mutually passing through steel
Connect, the jack truss winds up to wind up with ring truss and is connected by mutually passing through steel node weld, and the jack truss lower edge passes through two circles
Steel pipe is welded to connect with ring truss lower edge.
Beneficial effect
(1)The batter post is when without wide span house cap, and batter post is equivalent to cantilever batter post, it is impossible to independently undertake load, to foundation
Into larger post bottom moment of flexure and horizontal force, larger tilting moment is produced to overall structure, at the same batter post capital produce it is larger
Displacement, much larger than the capital limit displacement value of code requirement.When batter post and right cylinder by long-span roof form a kind of batter post with it is big
During the structure of across roof system coupling stress, wide span house cap forms a sidewise restraint to batter post capital, by the displacement of batter post capital
Very little is reduced to, the capital limit displacement value of code requirement is met.
So that batter post significantly reduces to the tilting moment that overall structure is produced, the relatively huge pillar bottom moment of flexure that is caused to basis and
Horizontal force also accordingly reduces.Simultaneously because sidewise restraint of the wide span house cap to batter post capital so that batter post can undertake roofing
The vertical load transmitted, now batter post is while also serve as a strong point of wide span house cap, this coupling stress so that
Truss top-bottom chord between right cylinder and batter post is in tension state, reduces truss member section and thickness.
(2)The structure that a kind of batter post couples stress with wide span house cap not only meets architectural appearance requirement, also carries
The high safety and reliability of total.
(3)Standard construction form is provided, facilitates engineers and technicians to use.
Brief description of the drawings
Fig. 1 is the structure partial graphics that batter post couples stress with wide span house cap;
Fig. 2 is the section of structure that batter post couples stress with wide span house cap;
Fig. 3 is the overall graphics of structure that batter post couples stress with wide span house cap;
Fig. 4 is the overall side view of structure that batter post couples stress with wide span house cap;
Fig. 5 pivoting support lateral plans.
In each accompanying drawing:1 plane girder(Main couple);2 plane girders(Jack truss);3 ring truss;4 straight across space truss;5
Long-span steel roof;6 batter post epimeres;7 batter post hypomeres;8 batter posts;9 right cylinders;10 pivoting supports;11 affixed bearings;12 round steel
Pipe;13 upper ear plates;14 lower ear plates;15 bearing pins;16 internal frameworks;
Embodiment
By taking certain stadium project as an example, to illustrate that the batter post of the present invention couples the structure of stress with wide span house cap.
Set up peripheral batter post hypomere 7, batter post epimere 6 and right cylinder 9 successively first, wherein integral planar is ellipse, week
Enclosing batter post, totally 52 and ground angle are 50 ° or so, in diverging, as shown 1, diagram 2, diagram 3.And internal framework
16, as shown 4, internal framework 16 and right cylinder reach intensity rear collapsible die, and outer shroud batter post 8 need to be in long-span steel roof 5
Rear collapsible die is installed completely.Wherein batter post is put on when only individually being calculated with substructure using roof system as load
Batter post top, capital displacement is 125mm to the maximum, when the overall calculation together with wide span house cap, takes corresponding measure by batter post and big
During across roof system coupling stress, capital displacement is 36.3mm to the maximum.Maximum horizontal displacement limit value in capital as defined in specification is that batter post is high
51 percent, threshold limit value is 75mm in this project.
Hold-down support 11 is then installed on batter post top, then outer collarette truss 3, periphery are installed on hold-down support 11
The erection sequence of ring truss 3 is that Liang Ge fitting-up gangs install since the peak of gymnasium, is symmetrically installed successively from periphery from high to low
Complete.
Complete after outer shroud truss installa-tion, hinged-support 10 then is installed on the top of right cylinder 9, then installed on hinged-support 10
Straight across space truss 4.
After being installed straight across space truss 4 use gliding construction method, successively the main couple of mounting plane truss and
Jack truss so that the shape integral framework of wide span house cap 5.
After each concealed work detection is finished, form removal is carried out to batter post, batter post is formed and couples stress with wide span house cap
Structure.
Claims (5)
1. a kind of batter post couples the structure of stress with wide span house cap, it is made up of wide span house cap, batter post, right cylinder, its feature exists
In:Described wide span house cap be large span steel truss, be made up of plane girder, space truss, plane girder include main couple,
Jack truss, space truss includes outer ring annular stereo truss and internal straight across space truss composition, and the ring truss and inside are straight
It is inverted triangle space truss across space truss, described peripheral batter post is by hypomere steel reinforced concrete batter post and epimere steel batter post shape
Into the hypomere steel reinforced concrete column length accounts for 1/5th of whole peripheral batter post length, and epimere steel batter post accounts for whole periphery
4/5ths of batter post length, the right cylinder is uiform section reinforced column;The large span steel truss and uiform section reinforcing bar
Concrete right cylinder is connected by hinged-support, and the large span steel truss is connected with batter post by bridle iron;The batter post and
Right cylinder forms the structure that a kind of batter post couples stress with long-span roof by long-span roof.
2. a kind of batter post as claimed in claim 1 couples the structure of stress with wide span house cap, it is characterised in that:Described one kind
Batter post the structure erection sequence of stress is coupled with wide span house cap for set up successively peripheral batter post hypomere, batter post epimere and right cylinder with
And internal framework, wide span house cap is subsequently mounted, the internal framework and right cylinder reach intensity rear collapsible die, institute
State outer shroud batter post need to after long-span steel roof is installed completely ability collapsible die.
3. a kind of batter post as described in claim 1-2 couples the structure of stress with wide span house cap, it is characterised in that:The hinge
The lower ear plate of bearing is connected with uiform section armored concrete capital slugging, the upper ear plate and wide span house cap of the hinged-support
Lower boom on ring truss is by being welded to connect, and the upper ear plate is connected with lower ear plate by bearing pin.
4. a kind of batter post as described in claim 1-3 couples the structure of stress with wide span house cap, it is characterised in that:It is described big
The main couple top boom of span roof system is connected with jack truss top boom by mutually passing through steel node weld, the main couple lower edge and time
Truss lower edge is connected by mutually passing through steel node weld;The main couple winds up to wind up with ring truss to be connected by mutually passing through steel node weld
Connect, the main couple lower edge and ring truss lower edge connect node weld by mutually passing through steel and be connected, and the jack truss winds up and ring truss
Wind up and connected by mutually passing through steel node weld, the jack truss lower edge is welded to connect by two round steel pipes with ring truss lower edge.
5. a kind of batter post as described in claim 1- couples the structure of stress with wide span house cap, it is characterised in that:1. first
Set up peripheral batter post hypomere 7, batter post epimere 6 and right cylinder 9 successively, wherein integral planar is ellipse, border batter post totally 52 with
Ground angle is 50 ° or so, in diverging;And internal framework 16, internal framework 16 and right cylinder are reached after intensity
Can form removal, outer shroud batter post 8 need to install rear collapsible die completely in long-span steel roof 5.
2. hold-down support 11 is then installed on batter post top, then outer collarette truss 3, outer collarette purlin are installed on hold-down support 11
The erection sequence of frame 3 is that Liang Ge fitting-up gangs install since peak, is symmetrically installed completion successively from periphery from high to low.
3. complete outer shroud truss installa-tion after, then right cylinder 9 top on install hinged-support 10, then installed on hinged-support 10 straight across
Space truss 4.
4. gliding construction method is used after being installed straight across space truss 4, successively the main couple of mounting plane truss and time purlin
Frame so that the shape integral framework of wide span house cap 5.
5. after each concealed work detection is finished, form removal is carried out to batter post, the structure that batter post couples stress with wide span house cap is formed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710254721.9A CN107201779B (en) | 2017-04-18 | 2017-04-18 | A kind of batter post couples the structure of stress with wide span house cap |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710254721.9A CN107201779B (en) | 2017-04-18 | 2017-04-18 | A kind of batter post couples the structure of stress with wide span house cap |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107201779A true CN107201779A (en) | 2017-09-26 |
CN107201779B CN107201779B (en) | 2019-06-14 |
Family
ID=59904899
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710254721.9A Active CN107201779B (en) | 2017-04-18 | 2017-04-18 | A kind of batter post couples the structure of stress with wide span house cap |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107201779B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110573683A (en) * | 2017-08-30 | 2019-12-13 | 四国化成工业株式会社 | Roof structure and construction method thereof |
CN114775801A (en) * | 2022-03-28 | 2022-07-22 | 中建二局安装工程有限公司 | Horseshoe-shaped truss structure steel roof truss and construction method thereof |
CN114837304A (en) * | 2022-04-08 | 2022-08-02 | 上海建工一建集团有限公司 | Batter post truss cable large-span steel construction |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09111943A (en) * | 1995-10-19 | 1997-04-28 | Taisei Corp | Building having domed roof |
CN204703297U (en) * | 2015-03-30 | 2015-10-14 | 江南大学 | Large space light cantilever grid and rope encircle the hybrid structure of self equilibrium systems |
CN105064728A (en) * | 2015-07-15 | 2015-11-18 | 中国建筑第二工程局有限公司 | Skiing field assembling structure and construction method of skiing field assembling structure |
CN205171674U (en) * | 2015-10-14 | 2016-04-20 | 中建二局第三建筑工程有限公司 | Many curved surfaces of encorbelmenting pipe truss net shell |
CN105780995A (en) * | 2014-12-22 | 2016-07-20 | 五冶集团上海有限公司 | Curved surface space pipe truss structure and mounting method thereof |
-
2017
- 2017-04-18 CN CN201710254721.9A patent/CN107201779B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09111943A (en) * | 1995-10-19 | 1997-04-28 | Taisei Corp | Building having domed roof |
CN105780995A (en) * | 2014-12-22 | 2016-07-20 | 五冶集团上海有限公司 | Curved surface space pipe truss structure and mounting method thereof |
CN204703297U (en) * | 2015-03-30 | 2015-10-14 | 江南大学 | Large space light cantilever grid and rope encircle the hybrid structure of self equilibrium systems |
CN105064728A (en) * | 2015-07-15 | 2015-11-18 | 中国建筑第二工程局有限公司 | Skiing field assembling structure and construction method of skiing field assembling structure |
CN205171674U (en) * | 2015-10-14 | 2016-04-20 | 中建二局第三建筑工程有限公司 | Many curved surfaces of encorbelmenting pipe truss net shell |
Non-Patent Citations (1)
Title |
---|
李新利等: "大型钢结构整体平移安装技术在浦东国际机场航站楼工程的应用", 《上海建设科技》 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110573683A (en) * | 2017-08-30 | 2019-12-13 | 四国化成工业株式会社 | Roof structure and construction method thereof |
CN110573683B (en) * | 2017-08-30 | 2021-10-22 | 四国化成工业株式会社 | Roof structure and construction method thereof |
CN114775801A (en) * | 2022-03-28 | 2022-07-22 | 中建二局安装工程有限公司 | Horseshoe-shaped truss structure steel roof truss and construction method thereof |
CN114775801B (en) * | 2022-03-28 | 2023-03-28 | 中建二局安装工程有限公司 | Horseshoe-shaped truss structure steel roof truss and construction method thereof |
CN114837304A (en) * | 2022-04-08 | 2022-08-02 | 上海建工一建集团有限公司 | Batter post truss cable large-span steel construction |
CN114837304B (en) * | 2022-04-08 | 2024-02-06 | 上海建工一建集团有限公司 | Stay cable large-span steel structure of inclined column truss |
Also Published As
Publication number | Publication date |
---|---|
CN107201779B (en) | 2019-06-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202108115U (en) | Bamboo truss string structure | |
CN104912190A (en) | Dry type joggle frame structure | |
CN201785865U (en) | Structure and system for house combining external prestress post tensioning method steel beam and pretensioning method prestress composite beam | |
CN104499413A (en) | Modularized steel die and concrete combined arch bridge and suspending construction method of suspension cable thereof | |
CN202324340U (en) | Combined type large steel-pipe truss | |
CN206903022U (en) | A kind of steel bar truss floor support plate | |
US9366027B2 (en) | Lattice girder structure using innovative multiple joints for roof covering purposes | |
CN106368348B (en) | A kind of superposed type compound shear wall with two benches stress characteristic | |
CN102605885B (en) | Large-sized closed roof formed by light steel truss arch for building | |
CN107201779B (en) | A kind of batter post couples the structure of stress with wide span house cap | |
CN102912972A (en) | Multifunctional lifting steel platform switching jig and construction method | |
CN104988984A (en) | U-shaped steel and concrete combined orthogonal-diagonal spatial grid box type structure and manufacturing method | |
CN107762161B (en) | A kind of energy-saving assembled system of steel residential structure and installation method | |
CN106284838A (en) | A kind of lattice Honeycomb Beam sections and large span lattice girder steel and fabrication and installation method thereof | |
CN103741970A (en) | Assembled machining shed for building construction and manufacture and installation method thereof | |
CN103122691A (en) | Tower crane standard knot bearing upper air supporting formwork steel platform structure and construction method | |
CN107355009B (en) | Steel construction archaize building roof apex angle post roof beam crossing node structure | |
CN211285977U (en) | Tapered weakening beam column joint for high-strength steel beam flange | |
CN211736290U (en) | Shell cross-section large-span cornice high-altitude formwork erecting operation platform | |
CN103225344A (en) | Hollow steel section-concrete combined framework and construction method thereof | |
CN114837483B (en) | High-low span portal steel frame building structure and construction process thereof | |
CN202913677U (en) | Multifunctional conversion scaffold capable of lifting steel platform | |
CN105220609B (en) | Combined beam self-anchored suspension bridge and construction process thereof | |
CN210658671U (en) | Hub type precast concrete beam column assembly type self-resetting system | |
CN105275113A (en) | Rhombus steel grid shear wall structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |