CN107191207A - A kind of station bottom water shutoff construction method and station bottom water shutoff construction - Google Patents

A kind of station bottom water shutoff construction method and station bottom water shutoff construction Download PDF

Info

Publication number
CN107191207A
CN107191207A CN201710565009.0A CN201710565009A CN107191207A CN 107191207 A CN107191207 A CN 107191207A CN 201710565009 A CN201710565009 A CN 201710565009A CN 107191207 A CN107191207 A CN 107191207A
Authority
CN
China
Prior art keywords
water
construction
water shutoff
tunnel
station
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710565009.0A
Other languages
Chinese (zh)
Other versions
CN107191207B (en
Inventor
杨积凯
吴大胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING SHOUER ENGINEERING TECHNOLOGY Co Ltd
Original Assignee
BEIJING SHOUER ENGINEERING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING SHOUER ENGINEERING TECHNOLOGY Co Ltd filed Critical BEIJING SHOUER ENGINEERING TECHNOLOGY Co Ltd
Priority to CN201710565009.0A priority Critical patent/CN107191207B/en
Publication of CN107191207A publication Critical patent/CN107191207A/en
Application granted granted Critical
Publication of CN107191207B publication Critical patent/CN107191207B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

Constructed the invention discloses a kind of station bottom water shutoff construction method and the water shutoff of station bottom, the content such as preparation, the construction of working face passage and construction of horizontal both wings water-stop curtain before construction of the construction method including working face passage.The station bottom water shutoff construction is included in working face passage and working face passage, the horizontal both wings water-stop curtain that bottom plate lower section middle part is laterally constructed AT STATION, horizontal both wings water-stop curtain formation inverted-triangular curtain structure.Reinforcing bar is inserted in the rotary churning pile of horizontal both wings water-stop curtain to improve the shearing strength and anti-floating ability of structure.The water shutoff construction of the present invention avoids a large amount of precipitation during underground space development, protects water resource, has saved electric power, environmental protection.Construction method of the present invention is simple, and controllability is strong, and cost is relatively low, solves the problems, such as the bottom waterstop of big cross section underground space development in water rich strata.

Description

A kind of station bottom water shutoff construction method and station bottom water shutoff construction
Technical field
The present invention relates to underground space construction field, particularly a kind of subway station bottom waterstop water shutoff construction method and its Bottom seal water structure.
Background technology
As traffic is increasingly crowded, the underground space is built more and more many and more and more deeper.When subway station yet to be built is in richness It is conventional that excavation construction is ensured using dewatering operation when water or pressure-bearing water environment.But a large amount of precipitation easily cause earth's surface and periphery structure Build the sedimentation and deformation of thing and the excessive exploitation of groundwater resources.With the raising of environmental consciousness, some local governments start over the ground Considered critical is made in lower water exploitation.For protection groundwater resources, various regions have been formulated strict control groundwater mining and limited and exploited The laws and regulations of scope, and expand groundwater recharge work.In order to avoid groundwater overdraft, carried out by curtain structure Sealing is a kind of preferable method, but routine applies water-stop curtain from earth's surface and not only involved great expense, and takes spatial surface.With The increase of underground space development depth, the effect of sealing is also worse and worse.
The content of the invention
Construct, to solve existing it is an object of the invention to provide a kind of station bottom water shutoff construction method and the water shutoff of station bottom There is subway station bottom waterstop structural cost expensive, take spatial surface, and with the increase of underground space development depth, only The effect of water also technical problem worse and worse.
To achieve the above object, the present invention is adopted the following technical scheme that:
A kind of station bottom water shutoff construction method, construction procedure is as follows:
Step one, situation about being constructed according to water shutoff around the position in underground station tunnel yet to be built, country rock situation and tunnel, design is dark That digs through excavates route and depth, the excavation route of working face passage and depth and horizontal both wings water-stop curtain, wherein horizontal Require to calculate according to Anti-floating design to both wings water-stop curtain and the vertical angle of horizontal plane formation and determine;
Step 2, excavates dark-excavated passageway:From earth's surface, dark-excavated passageway is excavated in the outside of water shutoff construction downwards, around tunnel, described The construction of dark-excavated passageway includes the construction of tunneling horizontal channel and the construction of tunneling vertical passageway,
The dark-excavated passageway includes tunneling vertical passageway and tunneling horizontal channel, and the tunneling vertical passageway, which is located at around tunnel, to be sealed The outside of water construction, the projected depth position being excavated to vertically downwards from earth's surface below underground station tunnel yet to be built, it is perpendicular from tunneling To the bottom of passage to excavate starting point, towards underground station tunnel excavation tunneling horizontal channel yet to be built, tunneling horizontal channel The axis of axis and underground station tunnel yet to be built keeps spatial vertical, and the front end of tunneling horizontal channel extends to underground station yet to be built Below the bottom plate in tunnel;
Step 3, to be the excavation starting point of working face passage inside the front end of tunneling horizontal channel, changed course is got off along yet to be built Stand the longitudinal excavated surface passage in tunnel, the excavation length of working face passage extends beyond the length in whole underground station tunnel yet to be built Spend and be excavated to the lower section that water shutoff is constructed around tunnel;
Step 4, using working face passage as construction space, horizontal both wings is carried out below the bottom plate in underground station tunnel yet to be built and are stopped The construction of water curtain, horizontal both wings water-stop curtain along vertical angle squeeze into country rock until with around tunnel water shutoff construction be connected untill.
Laterally the middle part from below the bottom plate in underground station tunnel yet to be built is working face passage for the front end of the dark-excavated passageway Excavate starting point.
In the step 3, working face passage is excavated to the other end from the longitudinal one end in underground station tunnel yet to be built or treated certainly Build underground station tunnel longitudinal middle part and be excavated to two ends.
In the step 4, during construction transverse direction both wings water-stop curtain, shearing resistance reinforcing bar is inserted in every rotary churning pile.
A kind of station bottom water shutoff construction of application station bottom water shutoff construction method construction, including excavate together in yet to be built Working face passage below the tunnel of underground station, the length of the working face passage be more than underground station tunnel yet to be built length, The axis keeping parallelism of axis and underground station tunnel yet to be built;
Water shutoff construction in the station bottom also includes two rows horizontal two that country rock is squeezed into from the both sides of working face passage, along vertical angle Wing water-stop curtain, the front end of two rows transverse direction both wings water-stop curtain extend respectively to around tunnel at water shutoff construction and be connected thereto for One.
The working face passage is laterally positioned in below the middle part of bottom plate.
The horizontal both wings water-stop curtain is the rotary churning pile of occlusion.
The rotary churning pile sets single row or multiple rows.
The inside of the rotary churning pile is inserted with shearing resistance reinforcing bar, and the shearing resistance reinforcing bar is I-steel, H profile steel or steel pipe.
The diameter range of the working face passage is 2.5m-4m.
Compared with prior art the invention has the characteristics that and beneficial effect:
The present invention is operated face passage construction in the middle part of bottom plate along station length direction AT STATION, and using working face passage as applying The construction that work working space carries out horizontal both wings water-stop curtain to both sides respectively forms station bottom water shutoff construction, forms inverted triangle The curtain structure of type and then the effect for realizing station bottom waterstop, this tectonic sieving are not take up aboveground space, not only can be The beneath water to station bottom part down is effectively blocked, and can also be in horizontal both wings water-stop curtain when artesian water is abundant Middle insertion shearing resistance reinforcing bar is as increase station anti-floating and the structure of shearing resistance carrying, while working face passage is also used as sealing area Domain internal control water Rendezvous Point, carries out effectively control water.The bottom water shutoff construction of the present invention is also connected with the construction of water shutoff around, and AT STATION four Week and bottom progress are totally-enclosed, reach the purpose that water shutoff is carried out to station.
The construction method of the present invention overcomes the deficiency of existing underground space water-stop technology, and construction method is simple, controllable The potent fruit of property is good, cost is relatively low, solves the problems, such as subway station bottom waterstop in water rich strata, it is to avoid big depth subway station A large amount of precipitation during construction, protect water resource, have saved electric power, and environmental protection provides for wider underground space development Solution.
Brief description of the drawings
The present invention will be further described in detail below in conjunction with the accompanying drawings.
Fig. 1 is the structural representation of station bottom of the present invention water shutoff construction.
Fig. 2 is the side structure schematic view of A-A sections in Fig. 1.
Fig. 3 is the pile body floor map of the horizontal both wings water-stop curtain in working face passage both sides of the present invention.
Reference:1- underground station tunnels yet to be built, 2- dark-excavated passageways, 2.1- tunnelings horizontal channel, 2.2- tunnelings Vertical passageway, 3- waterlines, 4- bottom plates, 5- working faces passage, the horizontal both wings water-stop curtains of 6-, water shutoff around 7- tunnels Water shutoff construction, 8- earth's surfaces, 9- vertical angles before and after construction, 7.1- tunnels both sides water shutoff construction, 7.2- tunnels.
Embodiment
Embodiment is referring to shown in Fig. 1-3, and a kind of metro station tunnel, its waterline 3 is as shown in Figure 1.Explanation in embodiment Transverse direction be underground station tunnel yet to be built cross-sectional direction, longitudinal direction be underground station tunnel yet to be built direct of travel.
This station bottom water shutoff construction method, construction procedure is as follows:
Step one, according to the situation of water shutoff construction 7 around the position in underground station tunnel 1 yet to be built, country rock situation and tunnel, design The excavation route and depth, the excavation route of working face passage 5 and depth of dark-excavated passageway 2 and horizontal both wings water-stop curtain 6, its Middle horizontal both wings water-stop curtain 6 and the vertical angle 9 of horizontal plane formation are required to calculate and determined according to Anti-floating design, it is therefore an objective to AT STATION Inverted-triangular curtain structure is formed on bottom, increases the anti-floating effect of curtain structure.
In general around tunnel water shutoff construction 7 be from earth's surface 8 downwards, squeeze into four sides around underground station tunnel 1 yet to be built Vertical water-stop curtain, vertical water-stop curtain is the rotary churning pile of occlusion, it is necessary to which construction in advance, generally includes tunnel in the present embodiment Water shutoff construction 7.2 before and after both sides water shutoff construction 7.1 and tunnel.
Step 2, excavates dark-excavated passageway:From earth's surface 8, dark-excavated passageway is excavated in the outside of water shutoff construction 7 downwards, around tunnel 2, dark-excavated passageway is excavated to the projected depth position below underground station tunnel yet to be built.
Dark-excavated passageway 2 generally includes tunneling vertical passageway 2.2 and tunneling horizontal channel 2.1.The tunneling vertical passageway 2.2 Can be from the downward excavation of earth's surface 8, one of vertical shaft on the outside of vertical water-stop curtain.The depth of the vertical shaft is more than vertical stop The depth of water curtain.Vertical shaft is set in the side in underground station tunnel yet to be built.The tunneling horizontal channel 2.1 is the bottom with vertical shaft One of horizontal cross passage of connection is held, the axis of the axis of horizontal cross passage and underground station tunnel 1 yet to be built keeps space Vertically, the front end of horizontal cross passage all extends to the lower section of bottom plate 4 in underground station tunnel yet to be built.
The design and construction of dark-excavated passageway 2 are that the construction to be operated face passage is prepared, if tunnel perimeter is present both When having dark-excavated passageway, the part steps can be omitted.
Step 3, to be the excavation starting point of working face passage 5 inside the front end of dark-excavated passageway 2, alters course along underground yet to be built The longitudinal excavated surface passage 5 of station tunnel 1, the excavation length of working face passage 5 extends beyond whole underground station tunnel yet to be built The length in road 1 and the lower section for being excavated to water shutoff construction 7 around tunnel.
In the present embodiment, the front end of the dark-excavated passageway 2 is laterally from the lower section of bottom plate 4 middle part in underground station tunnel 1 yet to be built For the excavation starting point of working face passage 5.Working face passage is located at the middle part below the bottom plate of station, can make horizontal both wings The construction length of water-stop curtain is shorter, and quality height is engaged between stake, and the overall water-stagnating effect of curtain is good.
Working face passage 5 is excavated to the other end or from underground station yet to be built from the longitudinal one end in underground station tunnel yet to be built 1 The longitudinal middle part of tunnel 1 is excavated to two ends.It is to be excavated to the other end from the longitudinal one end in underground station tunnel 1 yet to be built in the present embodiment.
The diameter of the working face passage 5 is not more than the diameter of horizontal cross passage.According to the calculating working face passage 5 Diameter range be 2.5m-4m, the diameter range of horizontal cross passage is 4m-6m, can meet construction requirement.The present embodiment In, a diameter of 4m of horizontal cross passage, a diameter of 3m of working face passage.
Step 4, is construction space with working face passage 5, is carried out laterally below the bottom plate 4 in underground station tunnel yet to be built The construction of both wings water-stop curtain 6, horizontal both wings water-stop curtain 6 squeezes into country rock until constructing 7 with water shutoff around tunnel along vertical angle 9 Untill connection.
Horizontal both wings water-stop curtain 6 can with both sides simultaneously construct can also both sides alternately construct.
In order to increase the shearing strength of horizontal jet grouting stake curtain structure and improve anti-floating ability.The horizontal both wings sealing curtain of construction During curtain 6, shearing resistance reinforcing bar is inserted in every rotary churning pile.The shearing resistance reinforcing bar can be I-steel, H profile steel or steel pipe.
It is a kind of to apply the station bottom water shutoff constructed with bus loading zone bottom water shutoff construction method to construct, including excavate together in The working face passage 5 of the lower section of underground station tunnel 1 yet to be built, the length of the working face passage 5 is more than underground station tunnel 1 yet to be built Length, the axis keeping parallelism in axis and underground station tunnel 1 yet to be built.
Water shutoff construction in the station bottom also includes two rows that country rock is squeezed into from the both sides of working face passage 5, along vertical angle 9 Horizontal both wings water-stop curtain 6, the front end of two rows transverse direction both wings water-stop curtain 6 extends respectively to water shutoff around tunnel and constructed at 7 simultaneously It is connected thereto and is integrated.
Working face passage described in the present embodiment 5 is laterally positioned in below the middle part of bottom plate 4.Working face passage is located at station bottom Middle part below plate, can make the construction length of horizontal both wings water-stop curtain shorter, be engaged that quality is high between stake, curtain it is whole Body water-stagnating effect is good.
The horizontal both wings water-stop curtain 6 is the rotary churning pile of occlusion.The rotary churning pile sets single row or multiple rows.The present embodiment In be single.
In order to increase the shearing strength of horizontal jet grouting stake curtain structure and improve anti-floating ability, the inside of the rotary churning pile is inserted Enter to have shearing resistance reinforcing bar, the shearing resistance reinforcing bar is I-steel, H profile steel or steel pipe.The diameter range of the working face passage 5 is 2.5m-4m。
Jet grouting pile construction is, using high-pressure pump as power source, will to be matched somebody with somebody by horizontal drill, drilling rod, drill bit, nozzle in the present invention The slurries made are ejected into the soil body.Injection stream will be certain with huge energy during nozzle is made slow rotation and retreated In the range of soil cutting, destroy, force soil particle be sufficiently mixed in the original location with slurries, then form approximate horizontal column Soil cement induration is horizontal jet grouting stake.After multiple rotary churning piles are mutually twisted, the horizontal both wings of closing are formed on bottom AT STATION Water-stop curtain, plays precipitation and control water effect.
The construction of the horizontal jet grouting stake mainly includes preparation of construction, equipment is in place, be open and orifice tube is installed, level is bored Hole, withdraw the construction procedures such as churning, sealing of hole after-teeming.Apply utilization of hour rig the Grouting Pipe with nozzle is drilled into out of sleeve pipe it is pre- Positioning is put, and drilling rod is rotated while with certain speed(20cm/min or so)Progressively retract, while making slurry using high-tension apparatus Liquid is ejected with 36MPa~40MPa or so high-pressure spray from nozzle, the impact failure soil body, slurries is forced mixed with grogs Close, after after grout cures, an induration with some strength is just formed in the soil body.
The rotary churning pile of both sides transverse direction both wings water-stop curtain is constructed simultaneously in the present embodiment, and all jet grouting pile constructions are finished Afterwards, it is now convenient under the bottom plate of subway station to form the inverted-triangular curtain structure closed, it can effectively carry out the water shutoff of station bottom And structural anti-buoyancy.When percolating water occurs for station surrounding water shutoff construction, the inverted-triangular curtain below the bottom plate of subway station can also It is enough to carry out control water.

Claims (10)

1. a kind of station bottom water shutoff construction method, it is characterised in that construction procedure is as follows:
Step one, according to underground station tunnel yet to be built(1)Position, water shutoff construction around country rock situation and tunnel(7)Situation, Design dark-excavated passageway(2)Excavation route and depth, working face passage(5)Excavation route and depth and horizontal both wings sealing Curtain(6), wherein horizontal both wings water-stop curtain(6)With the vertical angle of horizontal plane formation(9)Required to calculate true according to Anti-floating design It is fixed;
Step 2, excavates dark-excavated passageway:From earth's surface(8)Downwards, water shutoff is constructed around tunnel(7)Outside excavate dark-excavated passageway (2), the dark-excavated passageway(2)Construction include tunneling horizontal channel(2.1)Construction and tunneling vertical passageway(2.2)Apply Work,
The dark-excavated passageway(2)Including tunneling vertical passageway(2.2)With tunneling horizontal channel(2.1), the tunneling vertical passageway (2.2)Water shutoff is constructed around tunnel(7)Outside, be excavated to vertically downwards below underground station tunnel yet to be built from earth's surface 8 Projected depth position, from tunneling vertical passageway(2.2)Bottom to excavate starting point, towards underground station tunnel yet to be built(1) Excavate tunneling horizontal channel(2.1), tunneling horizontal channel(2.1)Axis and underground station tunnel yet to be built(1)Axis keep Spatial vertical, tunneling horizontal channel(2.1)Front end extend to the bottom plate in underground station tunnel yet to be built(4)Lower section;
Step 3, with tunneling horizontal channel(2.1)Front end inside be working face passage(5)Excavation starting point, changed course is along treating Build underground station tunnel(1)Longitudinal excavated surface passage(5), working face passage(5)Excavation length extend beyond and entirely treat Build underground station tunnel(1)Length and be excavated to around tunnel water shutoff and construct(7)Lower section;
Step 4, with working face passage(5)For construction space, the bottom plate in underground station tunnel yet to be built(4)Lower section is carried out laterally Both wings water-stop curtain(6)Construction, horizontal both wings water-stop curtain(6)Along vertical angle(9)Country rock is squeezed into until with being sealed around tunnel Water is constructed(7)Untill connection.
2. water shutoff construction method in station bottom according to claim 1, it is characterised in that:The tunneling horizontal channel (2.1)Front end laterally from underground station tunnel yet to be built(1)Bottom plate(4)It is working face passage in the middle part of lower section(5)Excavation rise Initial point.
3. water shutoff construction method in station bottom according to claim 1 or 2, it is characterised in that:In the step 3, work Face passage(5)From underground station tunnel yet to be built(1)Longitudinal one end is excavated to the other end or from underground station tunnel yet to be built(1)It is vertical Two ends are excavated to middle part.
4. water shutoff construction method in station bottom according to claim 3, it is characterised in that:In the step 4, construction is horizontal To both wings water-stop curtain(6)When, shearing resistance reinforcing bar is inserted in every rotary churning pile.
5. a kind of station bottom water shutoff of the station bottom water shutoff construction method construction described in application claim 1-4 any one Construction, it is characterised in that:Including excavating together in underground station tunnel yet to be built(1)The working face passage of lower section(5), the work Face passage(5)Length be more than underground station tunnel yet to be built(1)Length, axis and underground station tunnel yet to be built(1)Axis Keeping parallelism;
Water shutoff construction in the station bottom is also included from working face passage(5)Both sides, along vertical angle(9)Two rows for squeezing into country rock Horizontal both wings water-stop curtain(6), two rows transverse direction both wings water-stop curtain(6)Front end extend respectively to around tunnel water shutoff and construct (7)Place and being connected thereto is integrated.
6. station bottom according to claim 5 water shutoff is constructed, it is characterised in that:The working face passage(5)Horizontal position In bottom plate(4)Middle part below.
7. station bottom according to claim 5 water shutoff is constructed, it is characterised in that:The horizontal both wings water-stop curtain(6) For the rotary churning pile of occlusion.
8. station bottom according to claim 7 water shutoff is constructed, it is characterised in that:The rotary churning pile sets single or many Row.
9. station bottom according to claim 8 water shutoff is constructed, it is characterised in that:The inside of the rotary churning pile is inserted with anti- Shear-steel bone, the shearing resistance reinforcing bar is I-steel, H profile steel or steel pipe.
10. station bottom according to claim 5 water shutoff is constructed, it is characterised in that:The working face passage(5)Diameter Scope is 2.5m-4m.
CN201710565009.0A 2017-07-12 2017-07-12 A kind of station bottom water shutoff construction method and station bottom water shutoff construction Active CN107191207B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710565009.0A CN107191207B (en) 2017-07-12 2017-07-12 A kind of station bottom water shutoff construction method and station bottom water shutoff construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710565009.0A CN107191207B (en) 2017-07-12 2017-07-12 A kind of station bottom water shutoff construction method and station bottom water shutoff construction

Publications (2)

Publication Number Publication Date
CN107191207A true CN107191207A (en) 2017-09-22
CN107191207B CN107191207B (en) 2018-10-19

Family

ID=59883072

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710565009.0A Active CN107191207B (en) 2017-07-12 2017-07-12 A kind of station bottom water shutoff construction method and station bottom water shutoff construction

Country Status (1)

Country Link
CN (1) CN107191207B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110042864A (en) * 2019-05-14 2019-07-23 北京首尔工程技术有限公司 The comprehensive water sealing structure and its construction method of artesian water stratum tunneling underground station

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08134944A (en) * 1994-11-15 1996-05-28 Mitsui Fudosan Kensetsu Kk Water proofing construction method for underground structure
JP2009174178A (en) * 2008-01-24 2009-08-06 Kajima Corp Method of constructing underground structure
CN102296621A (en) * 2011-05-27 2011-12-28 深圳市市政设计研究院有限公司 Construction method of ground sectional water-stop curtain
CN104879141A (en) * 2015-06-02 2015-09-02 杨积凯 Tunnel bottom plugging structure and construction method thereof
CN105178326A (en) * 2015-06-03 2015-12-23 福建工程学院 Water stop method for upper-soft and lower-hard water-rich stratum foundation pit engineering retaining structure
CN105909260A (en) * 2016-06-16 2016-08-31 山东省地矿工程勘察院 Subway station water stop structure for protecting groundwater environment and construction method thereof
CN206204973U (en) * 2016-06-16 2017-05-31 山东省地矿工程勘察院 Subway station water stop structure for protecting groundwater environment

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08134944A (en) * 1994-11-15 1996-05-28 Mitsui Fudosan Kensetsu Kk Water proofing construction method for underground structure
JP2009174178A (en) * 2008-01-24 2009-08-06 Kajima Corp Method of constructing underground structure
CN102296621A (en) * 2011-05-27 2011-12-28 深圳市市政设计研究院有限公司 Construction method of ground sectional water-stop curtain
CN104879141A (en) * 2015-06-02 2015-09-02 杨积凯 Tunnel bottom plugging structure and construction method thereof
CN105178326A (en) * 2015-06-03 2015-12-23 福建工程学院 Water stop method for upper-soft and lower-hard water-rich stratum foundation pit engineering retaining structure
CN105909260A (en) * 2016-06-16 2016-08-31 山东省地矿工程勘察院 Subway station water stop structure for protecting groundwater environment and construction method thereof
CN206204973U (en) * 2016-06-16 2017-05-31 山东省地矿工程勘察院 Subway station water stop structure for protecting groundwater environment

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110042864A (en) * 2019-05-14 2019-07-23 北京首尔工程技术有限公司 The comprehensive water sealing structure and its construction method of artesian water stratum tunneling underground station
CN110042864B (en) * 2019-05-14 2024-08-16 北京首尔工程技术有限公司 Omnibearing water stopping structure of underground station under underground excavation of confined water stratum and construction method thereof

Also Published As

Publication number Publication date
CN107191207B (en) 2018-10-19

Similar Documents

Publication Publication Date Title
CN100510274C (en) Construction method of enclosing level rotary-jet pile hole-mouth using double-liquid slip jection method
CN106351662B (en) Cellular-type segmenting slip casting reinforcement means, construction method and application
CN105178326B (en) Upper soft lower hard water rich strata base pit engineering building enclosure water-stopping method
CN101781889B (en) H-shaped waterproof curtain construction process
CN103899323B (en) A kind of construction method of shield crossing rail yard
CN107023300A (en) A kind of use canopy, which is defended the doctrine, builds the construction method of subway station
CN106437726A (en) Ground fracture crushed zone passing construction method for shallow-buried tunnel excavation
CN112343626B (en) Shield tunnel construction and reinforcement method for penetrating existing tunnel under upper soft and lower hard stratum
CN102278130A (en) Process method for reinforcing and grouting of high-pressure water-rich solution cavity of tunnel
CN103696416B (en) A kind of method for processing foundation
DE2011823A1 (en) Method of creating watertight barriers
CN105019913A (en) Base rock uplift region shielding tool-changing in-situ reinforcement method
CN109973115B (en) Construction method for drainage of vault of tunnel in karst area
CN108915705B (en) A kind of baffle grouting construction method blocked for shield export & import leak
CN203835401U (en) Construction structure for arranging construction vertical shaft above underground engineering
CN107191207B (en) A kind of station bottom water shutoff construction method and station bottom water shutoff construction
CN113958324B (en) Method for grouting and reinforcing deep drilling of roadway bottom plate
CN109914390A (en) It is a kind of to construct the slip casting structure and construction method of cold seam for biting connecions campshed
CN213928393U (en) Expandable anchoring device and tunnel supporting structure
CN112610255B (en) Tunnel construction method for penetrating through weak and broken surrounding rock
KR101523948B1 (en) Construction method of underground structure under the established building
CN105586978A (en) Construction method of soil replacement stir waterproof curtain based on gravels
CN205296194U (en) Rich irrigated land layer undercut tunnel interlock pipe curtain
CN113914874A (en) Large-scale geological abnormal fault zone roadway surrounding rock ultra-long distance pre-reinforcement method
CN110485460B (en) Construction method for sealing water at bottom of underground excavation station

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant