CN107191004B - Brick column reinforced construction method - Google Patents

Brick column reinforced construction method Download PDF

Info

Publication number
CN107191004B
CN107191004B CN201710537097.3A CN201710537097A CN107191004B CN 107191004 B CN107191004 B CN 107191004B CN 201710537097 A CN201710537097 A CN 201710537097A CN 107191004 B CN107191004 B CN 107191004B
Authority
CN
China
Prior art keywords
steel
brick column
brick
presstressed reinforcing
spacing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710537097.3A
Other languages
Chinese (zh)
Other versions
CN107191004A (en
Inventor
叶长青
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Hengyiming New Material Technology Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710537097.3A priority Critical patent/CN107191004B/en
Publication of CN107191004A publication Critical patent/CN107191004A/en
Application granted granted Critical
Publication of CN107191004B publication Critical patent/CN107191004B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Reinforcement Elements For Buildings (AREA)
  • Working Measures On Existing Buildindgs (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a kind of brick column reinforced construction methods, it is characterized in that construction procedure includes: that (1) makes brick column be in unloaded state;(2) the pre-buried U-shaped built-in fitting of brick column transverse direction mortar joint;(3) billet is inserted into the vertical mortar joint of brick column, welded gasket reinforcing bar on the outside of billet forms and turns to bloom;(4) from setting angle steel at 250~300mm of brick styletable head;(5) presstressed reinforcing steel is hung;(6) presstressed reinforcing steel is tentatively fixed on angle steel with anchorage, carries out first time electrified regulation;(7) jet expansion concrete;(8) second of electrified regulation is carried out after gunite concrete 45min;(9) third time electrified regulation is carried out after 12 hours of gunite concrete;(10) steel batten plate and U-shaped built-in fitting are welded.

Description

Brick column reinforced construction method
Technical field
The present invention relates to a kind of reinforced construction methods, in particular to brick column reinforced construction method.
Background technique
Brick columns bearing capacity will be reinforced when inadequate, and traditional reinforcement means is section-increased method, due to original structure Body is in stress, has generated ess-strain, then plus structural body there is no ess-strain, cause original structural body and Afterwards plus structural body ess-strain it is uncoordinated, after causing plus structural body and original structural body be difficult to form entirety.It is necessary to This is improved, certain prestressing force is applied to the rear structural body added, so that its is generated ess-strain, is conducive to original structural body Coordinate stress with the rear structural body added.
Summary of the invention
The present invention is to provide a kind of brick column reinforced construction method, solves to carry out consolidation effect not when brick columns bearing capacity is inadequate Good problem.
Two presstressed reinforcing steels are hung after brick column removing surface painting mortar, presstressed reinforcing steel diameter is 18~25mm, prestressing force Muscle interlude is to be arranged vertically, and segment length is 0.45~0.55 times of brick pillar height degree, two presstressed reinforcing steel spacing among presstressed reinforcing steel It is determined according to brick column section, when brick column section length is 250mm, two presstressed reinforcing steel spacing are 60mm;When brick column section Length is 300mm, and two presstressed reinforcing steel spacing are 75mm;When brick column section length is 350mm, two presstressed reinforcing steel spacing are 90mm;When brick column section length is 400mm, two presstressed reinforcing steel spacing are 100mm;When brick column section length be 450mm, two Presstressed reinforcing steel spacing is 110mm;When brick column section length be 500mm and more than when, two presstressed reinforcing steel spacing are 120mm. The turnover position setting that presstressed reinforcing steel vertical section becomes oblique section turns to bloom, turns to bloom and is made of billet and pad reinforcing bar, Billet pads the round steel that reinforcing bar is 12~14mm of diameter with a thickness of 10mm, and pad steel-bar and stress technique muscle contact site according to answering in advance Power myospasm folding radian is polished, and is contacted after so that presstressed reinforcing steel is transferred with pad reinforcing bar as face contact.It is vertical that billet is inserted into brick column Mortar joint, from angle steel is arranged at 250~300mm of brick styletable head, angle steel is inserted into brick column transverse direction mortar joint, leads to after tension of prestressed tendon It crosses anchorage and is fixed on angle steel.Gunite concrete is set outside presstressed reinforcing steel, and gunite concrete uses expansive concrete, expands coagulation Native intensity be C30 or more than, with a thickness of 25~35mm, steel batten plate is set outside expansive concrete, steel batten plate and is embedded in brick U-shaped built-in fitting welds in column, and steel batten plate width is 150~200mm, and wrapping up gunite concrete by steel batten plate makes reinforced concrete In three-dimensional stress state, playing ruggedized construction mechanical function ahead of time has very big effect, and steel batten plate is arranged spacing and reinforces The stress performance of concrete has very big relationship, carries out a large number of experiments thus, between being determined that steel batten plate is arranged according to test result Away from.The stress mobilization factor situation of table 1 is brick column section length when being the 400mm setting of steel batten plate spacing and reinforced concrete, table Middle brick column section is square, and the stress mobilization factor of reinforced concrete refers to the reinforced concrete bearing stress under upper load With the ratio of limit stress.According to table 1 as a result, with bearing capacity increase, the stress mobilization factor of reinforced concrete can be It is promoted, when steel batten plate setting spacing is greater than 550mm, stress mobilization factor is reduced larger, and when steel batten plate setting spacing is less than The variation of stress mobilization factor is little when 500mm.Therefore brick column section length be 400mm when, steel batten plate be arranged spacing be greater than 500mm And it is less than or equal to 550mm.The stress of table 2 is brick column section length when being the 450mm setting of steel batten plate spacing and reinforced concrete Mobilization factor situation, according to 2 situation of table, when brick column section length is 450mm, steel batten plate be arranged spacing be greater than 550mm and Less than or equal to 600mm.Successively test determine: when brick column section length be 500mm when, steel batten plate be arranged spacing be greater than 600mm and be less than or equal to 650mm.When brick column section length is 550mm or is greater than 550mm, it is big that spacing, which is arranged, in steel batten plate In 650mm and it is less than or equal to 700mm.When brick column section length is 350mm or is less than 350mm, steel batten plate setting spacing is More than or equal to 450mm and it is less than or equal to 550mm.
The stress mobilization factor feelings of table 1 is brick column section length when being the 400mm setting of steel batten plate spacing and reinforced concrete Condition
The stress mobilization factor feelings of table 2 is brick column section length when being the 450mm setting of steel batten plate spacing and reinforced concrete Condition
Construction procedure includes:
(1) brick column is made to be in unloaded state.
(2) mortar, the pre-buried U-shaped built-in fitting of brick column transverse direction mortar joint are painted in removing brick column removing surface.
(3) billet is inserted into the vertical mortar joint of brick column, welded gasket reinforcing bar on the outside of billet forms and turns to bloom.
(4) from angle steel is arranged at 250~300mm of brick styletable head, angle steel is inserted into brick column transverse direction mortar joint.
(5) presstressed reinforcing steel is hung, deformed bar end is coupled with three-phase low-voltage transformer, transformer is equipped with can power transformation Resistance, while the electric wire on deformed bar should be connected to using insulation soft copper silk twisted wire from electric heating transformer with cooling equipment.
(6) presstressed reinforcing steel is tentatively fixed on angle steel with anchorage, carries out first time electrified regulation, electrified regulation 5min is built Vertical primary stress, is then fixed on angle steel for deformed bar by anchorage.
(7) jet expansion concrete.
(8) second of electrified regulation, electrified regulation 5min are carried out after gunite concrete 45min.
(9) third time electrified regulation is carried out after 12 hours of gunite concrete, electrified regulation 10min will by anchorage Deformed bar is fixed on angle steel.
(10) steel batten plate and U-shaped built-in fitting are welded, fusion length is greater than 80mm.
Mechanical property of the present invention is good, and quality is easily obtained guarantee.
Detailed description of the invention
Fig. 1 is brick column ruggedized construction elevational schematic view, and Fig. 2 is brick column ruggedized construction schematic cross-section, and Fig. 3 is to turn to bloom Structural schematic diagram.
In each attached drawing: 1, brick column, 2, steering bloom, 3, presstressed reinforcing steel, 4, angle steel, 5, steel batten plate, 6, anchorage, 7, swelled mixture Solidifying soil, 8, U-shaped built-in fitting, 9, billet, 10, pad reinforcing bar.
Specific embodiment
Fig. 1 is brick column ruggedized construction elevational schematic view, and Fig. 2 is brick column ruggedized construction schematic cross-section, and Fig. 3 is to turn to bloom Structural schematic diagram.Two presstressed reinforcing steels 3 are hung after 1 removing surface of brick column painting mortar in embodiment, 3 diameter of presstressed reinforcing steel is 22mm, 3 interlude of presstressed reinforcing steel are to be arranged vertically, and the intermediate segment length of presstressed reinforcing steel 3 is 0.5 times of brick column, 1 height, 1 section of brick column Length is 400mm, and two 3 spacing of presstressed reinforcing steel are 100mm.3 vertical section of presstressed reinforcing steel becomes oblique section of turnover position setting Bloom 2 is turned to, bloom 2 is turned to and is made of billet 9 and pad reinforcing bar 10, for billet 9 with a thickness of 10mm, pad reinforcing bar 10 is diameter The round steel of 12mm, pad reinforcing bar 10 are polished with 3 contact site of presstressed reinforcing steel according to the turnover radian of presstressed reinforcing steel 3, and prestressing force is made Muscle 3 contacts after transferring with pad reinforcing bar 10 as face contact.Billet 9 is inserted into the vertical mortar joint of brick column 1, from setting at 1 end 300mm of brick column Angle setting steel 4, angle steel 4 are inserted into the lateral mortar joint of brick column 1, are fixed on angle steel 4 by anchorage 6 after 3 tensioning of presstressed reinforcing steel.Prestressing force Gunite concrete is set outside muscle 3, gunite concrete uses expansive concrete 7, and 7 intensity of expansive concrete is C30, with a thickness of 30mm, is arranged steel batten plate 5 outside expansive concrete 7, steel batten plate 5 and is embedded in U-shaped built-in fitting 8 in brick column 1 and welds, steel batten plate 5 Width is 180mm.It is greater than 520mm that spacing, which is arranged, in steel batten plate 5.
Construction procedure includes:
(1) brick column 1 is made to be in unloaded state.
(2) mortar, the pre-buried U-shaped built-in fitting 8 of the lateral mortar joint of brick column 1 are painted in removing 1 removing surface of brick column.
(3) billet 9 is inserted into the vertical mortar joint of brick column 1,9 outside welded gasket reinforcing bar 10 of billet forms and turns to bloom 2.
(4) from angle steel 4 is arranged at 1 end 300mm of brick column, angle steel 4 is inserted into the lateral mortar joint of brick column 1.
(5) presstressed reinforcing steel 3 is hung, deformed bar end is coupled with three-phase low-voltage transformer, transformer is equipped with variable Resistance, while the electric wire on deformed bar should be connected to using insulation soft copper silk twisted wire from electric heating transformer with cooling equipment.
(6) presstressed reinforcing steel 3 is tentatively fixed on angle steel 4 with anchorage 6, carries out first time electrified regulation, electrified regulation 5min, Primary stress is established, deformed bar is then fixed on by angle steel 4 by anchorage 6.
(7) jet expansion concrete seven.
(8) second of electrified regulation, electrified regulation 5min are carried out after gunite concrete 45min.
(9) third time electrified regulation is carried out after 12 hours of gunite concrete, electrified regulation 10min will by anchorage 6 Deformed bar is fixed on angle steel 4.
(10) steel batten plate 5 and U-shaped built-in fitting are welded, fusion length is greater than 80mm.

Claims (1)

1. a kind of brick column reinforced construction method, it is characterized in that hanging two presstressed reinforcing steels after brick column removing surface painting mortar, in advance Stress rib interlude is to be arranged vertically, and segment length is 0.45~0.55 times of brick pillar height degree among presstressed reinforcing steel, and presstressed reinforcing steel is vertical Oblique section of Duan Bianwei turnover position setting turn to bloom, billet be inserted into the vertical mortar joint of brick column, from brick styletable head 250~ Angle steel is set at 300mm, and angle steel is inserted into brick column transverse direction mortar joint, is fixed on angle steel by anchorage after tension of prestressed tendon;In advance Gunite concrete is set outside stress rib, and gunite concrete uses expansive concrete, steel batten plate, steel is arranged outside expansive concrete Batten plate is welded with U-shaped built-in fitting in brick column is embedded in, and steel batten plate width is 150~200mm;
Two presstressed reinforcing steel spacing are determined according to brick column section, when brick column section length is 250mm, between two presstressed reinforcing steels Away from for 60mm;When brick column section length is 300mm, two presstressed reinforcing steel spacing are 75mm;When brick column section length be 350mm, Two presstressed reinforcing steel spacing are 90mm;When brick column section length is 400mm, two presstressed reinforcing steel spacing are 100mm;When brick column is cut Face length is 450mm, and two presstressed reinforcing steel spacing are 110mm;When brick column section length be 500mm and more than when, two are pre- Stress rib spacing is 120mm;
Bloom is turned to be made of billet and pad reinforcing bar, billet pads the round steel that reinforcing bar is 12~14mm of diameter with a thickness of 10mm, Pad steel-bar and stress technique muscle contact site according to presstressed reinforcing steel transfer radian polish, make presstressed reinforcing steel transfer after with pad reinforcing bar Contact is face contact;
When brick column section length is 400mm, it is greater than 500mm and to be less than or equal to 550mm that spacing, which is arranged, in steel batten plate;When brick column is cut When face length is 450mm, it is greater than 550mm and to be less than or equal to 600mm that spacing, which is arranged, in steel batten plate;When brick column section length is When 500mm, it is greater than 600mm and to be less than or equal to 650mm that spacing, which is arranged, in steel batten plate;When brick column section length is 550mm or big When 550mm, it is greater than 650mm and to be less than or equal to 700mm that spacing, which is arranged, in steel batten plate;When brick column section length be 350mm or When less than 350mm, it is more than or equal to 450mm and to be less than or equal to 550mm that spacing, which is arranged, in steel batten plate;
Construction procedure includes:
(1) it is arranged around brick column, brick column is made to be in unloaded state;
(2) mortar, the pre-buried U-shaped built-in fitting of brick column transverse direction mortar joint are painted in removing brick column removing surface;
(3) billet is inserted into the vertical mortar joint of brick column, welded gasket reinforcing bar on the outside of billet forms and turns to bloom;
(4) from angle steel is arranged at 250~300mm of brick styletable head, angle steel is inserted into brick column transverse direction mortar joint;
(5) presstressed reinforcing steel is hung, deformed bar end is coupled with three-phase low-voltage transformer, transformer is equipped with variable resistance, Simultaneously the electric wire on deformed bar should be connected to using insulation soft copper silk twisted wire from electric heating transformer with cooling equipment;
(6) presstressed reinforcing steel is tentatively fixed on angle steel with anchorage, carries out first time electrified regulation, electrified regulation 5min is established just Then deformed bar is fixed on angle steel by anchorage by beginning stress;
(7) jet expansion concrete;
(8) second of electrified regulation, electrified regulation 5min are carried out after gunite concrete 45min;
(9) third time electrified regulation is carried out after 12 hours of gunite concrete, electrified regulation 10min will be answered in advance by anchorage Power reinforcing bar is fixed on angle steel;
(10) steel batten plate and U-shaped built-in fitting are welded, fusion length is greater than 80mm.
CN201710537097.3A 2016-03-10 2016-03-10 Brick column reinforced construction method Active CN107191004B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710537097.3A CN107191004B (en) 2016-03-10 2016-03-10 Brick column reinforced construction method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201610181674.5A CN105696805B (en) 2016-03-10 2016-03-10 Brick column reinforcing method
CN201710537097.3A CN107191004B (en) 2016-03-10 2016-03-10 Brick column reinforced construction method

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201610181674.5A Division CN105696805B (en) 2016-03-10 2016-03-10 Brick column reinforcing method

Publications (2)

Publication Number Publication Date
CN107191004A CN107191004A (en) 2017-09-22
CN107191004B true CN107191004B (en) 2019-06-04

Family

ID=56232939

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201710537097.3A Active CN107191004B (en) 2016-03-10 2016-03-10 Brick column reinforced construction method
CN201610181674.5A Active CN105696805B (en) 2016-03-10 2016-03-10 Brick column reinforcing method

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201610181674.5A Active CN105696805B (en) 2016-03-10 2016-03-10 Brick column reinforcing method

Country Status (1)

Country Link
CN (2) CN107191004B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106836604B (en) * 2017-02-07 2022-08-12 叶长青 Method for manufacturing large-span inclined roof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1401873A (en) * 2002-09-05 2003-03-12 杜旌 Method for pre-stressed reinforcing concrete compression member
CN101832035A (en) * 2010-05-15 2010-09-15 朱虹 Construction method for reinforced concrete column
CN202925924U (en) * 2012-11-04 2013-05-08 西安建筑科技大学 Combination reinforcing device for brick pillar
CN103306492A (en) * 2013-05-29 2013-09-18 朱奎 Method for reinforcing concrete weak beam
CN103388408A (en) * 2013-07-28 2013-11-13 桂林理工大学 External pre-stressed tendon reinforcing steering block for building structure
EA020664B1 (en) * 2010-08-16 2014-12-30 Федеральное Государственное Автономное Образовательное Учреждение Высшего Профессионального Образования "Сибирский Федеральный Университет" Device for reinforcing bearing frame

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3050108B2 (en) * 1995-12-01 2000-06-12 鹿島建設株式会社 Column reinforcement method
CN201531124U (en) * 2009-09-24 2010-07-21 马人乐 Graded external pre-stress strengthening masonry structure
CN102080454B (en) * 2010-12-02 2012-05-30 西安建筑科技大学 Method for reinforcing pillars in buildings
CN202925926U (en) * 2012-11-04 2013-05-08 西安建筑科技大学 Reinforcing device for brick pillar
JP5411367B1 (en) * 2013-01-17 2014-02-12 株式会社サンヨーホーム Concrete column reinforcement structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1401873A (en) * 2002-09-05 2003-03-12 杜旌 Method for pre-stressed reinforcing concrete compression member
CN101832035A (en) * 2010-05-15 2010-09-15 朱虹 Construction method for reinforced concrete column
EA020664B1 (en) * 2010-08-16 2014-12-30 Федеральное Государственное Автономное Образовательное Учреждение Высшего Профессионального Образования "Сибирский Федеральный Университет" Device for reinforcing bearing frame
CN202925924U (en) * 2012-11-04 2013-05-08 西安建筑科技大学 Combination reinforcing device for brick pillar
CN103306492A (en) * 2013-05-29 2013-09-18 朱奎 Method for reinforcing concrete weak beam
CN103388408A (en) * 2013-07-28 2013-11-13 桂林理工大学 External pre-stressed tendon reinforcing steering block for building structure

Also Published As

Publication number Publication date
CN107191004A (en) 2017-09-22
CN105696805B (en) 2017-11-28
CN105696805A (en) 2016-06-22

Similar Documents

Publication Publication Date Title
CN103321444B (en) Concrete floor reinforced construction method
CN107191004B (en) Brick column reinforced construction method
CN102251674A (en) Bunker-skipping type seamless construction method of ultra-long concrete structure
CN103306493B (en) The reinforcement means of fabric structure
CN206174120U (en) Prefabricated constructional column and structure thereof
CN202627500U (en) External vibration type setting combination steel template for binding supporting beam
CN105908885A (en) Great-width multi-hole lightweight core formwork and construction method thereof
CN103374865A (en) Construction method for longitudinally connecting and laying ballastless track slabs
CN208502075U (en) A kind of constructional column upper reinforcement connection pre-embedded device
CN107916797B (en) Construction method for improving bearing performance of old building
CN103306492B (en) The reinforcement means of concrete weak beam
CN202745392U (en) Simple split heads capable of being repeatedly used
CN106894554A (en) The Sloping roof structure and its construction method of prefabricated board Cast-in-situ Beam
CN203498850U (en) Raft foundation reinforcement support of super high-rising building
CN204899041U (en) Protective layer control split heads about board muscle
CN105442628B (en) Construction method for cantilever foundation side wall heavy embedded part
JP6057329B2 (en) Rack bar induction hardening equipment
CN202622969U (en) Mould of prefabricating hollow plate beam of drawing-pulling type steel core die
CN208251172U (en) The double-deck sealing belt construction limiting card
CN105862572A (en) Super-long vertical unbonded prestress structure and assembling method thereof
CN207944479U (en) A kind of piping lane slope board concrete isolating device
CN105220884A (en) Cast-in-situ concrete floor reinforced mesh paving method
CN204456226U (en) One is exempted to clear up ater-casting
CN205742615U (en) A kind of construction wall floor construction
CN101653818A (en) Method for continuously casting and blocking dummy ingot

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 325000 No. 48 Xinghai Road, Jingshan Street, Ouhai District, Wenzhou City, Zhejiang Province

Applicant after: Ye Changqing

Address before: 325000 Jinchuan Road, Tianhe Street, Wenzhou Economic and Technological Development Zone, Wenzhou City, Zhejiang Province

Applicant before: Ye Changqing

CB02 Change of applicant information
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20201125

Address after: No. 100, North Ring Road, Hede Town, Sheyang County, Yancheng City, Jiangsu Province

Patentee after: Gu Yaobin

Address before: 325000, No. 48, Jingshan Hill Road, Ouhai District, Wenzhou, Zhejiang

Patentee before: Ye Changqing

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20230110

Address after: West side of Jinhai Avenue, south side of Dianchang Road, Sheyang Port Economic Zone, Sheyang County, Yancheng City, Jiangsu Province, 224300

Patentee after: Jiangsu Hengyiming New Material Technology Co.,Ltd.

Address before: No. 100, North Ring Road, Hede Town, Sheyang County, Yancheng City, Jiangsu Province

Patentee before: Gu Yaobin

TR01 Transfer of patent right