CN107152964A - A kind of Blast Vibration Monitoring method of buried underground water supply pipelines in tunnel benching tunnelling method construction - Google Patents
A kind of Blast Vibration Monitoring method of buried underground water supply pipelines in tunnel benching tunnelling method construction Download PDFInfo
- Publication number
- CN107152964A CN107152964A CN201710562972.3A CN201710562972A CN107152964A CN 107152964 A CN107152964 A CN 107152964A CN 201710562972 A CN201710562972 A CN 201710562972A CN 107152964 A CN107152964 A CN 107152964A
- Authority
- CN
- China
- Prior art keywords
- tunnel
- measuring point
- top bar
- pipeline
- vibration velocity
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01H—MEASUREMENT OF MECHANICAL VIBRATIONS OR ULTRASONIC, SONIC OR INFRASONIC WAVES
- G01H1/00—Measuring characteristics of vibrations in solids by using direct conduction to the detector
- G01H1/12—Measuring characteristics of vibrations in solids by using direct conduction to the detector of longitudinal or not specified vibrations
Abstract
The present invention proposes a kind of Blast Vibration Monitoring method of buried underground water supply pipelines, comprises the following steps:Computer tube linear distance tunnel top bar Bao Yuan centers apart from ROn;Got out of a predicament or an embarrassing situation in tunnel explosion when, arrange measuring point N simultaneously at top bar and face rear1And N2, it is ensured that two measuring points to the quick-fried heart of getting out of a predicament or an embarrassing situation (take tunnel get out of a predicament or an embarrassing situation height half be quick-fried heart point) distance be equal to ROn;Test top bar measuring point N1With tunnel tunnel face rear N2The vibration velocity for locating country rock is V1、V2;Measurement 3 times more than repeating, according to measuring point N1And N2Locate vibration velocity relation, it can be deduced that V1=nV2;Face rear L' is measured in top bar explosionAfterwardsN ' at distance2The vibration velocity V ' of measuring point2;Deduce the vibration velocity V at pipelinePipe=nV '2;By vibration velocity V at the pipeline of acquisitionPipeIt is compared with the control standard of pipeline blasting vibration safety, evaluates the security situation of pipeline, is optimized blast working scheme, instruct tunnel control explosion, it is ensured that pipeline safety.The present invention effectively solves this technical barrier of the Tunnel Blasting vibration monitoring of buried underground utilities, has far-reaching influence for constructing tunnel industry.
Description
Technical field
The present invention relates to technical field of tunnel construction, buried groundwater supply in being constructed more particularly, to a kind of tunnel benching tunnelling method
The Blast Vibration Monitoring method of pipeline.
Background technology
In recent years, the Tunnel Engineering that underground water supply pipelines are worn under low coverage is more and more.When being excavated using drilling and blasting method, tunnel
Blasting vibration constitutes safely serious threat to underground water supply pipelines closely, and blasting vibration is easy to cause pipeline to damage,
Even ftracture, cause immeasurable economic loss.
(2013) are saved in Li Jun《Underground utilities safeguard measure is worn under Metro gateway and analysis is calculated》In, calculate and divide
Influence of the concussion of blasting to pipeline is not considered in analysis, blast monitoring method is not proposed yet;And in beam forward (2009)《Underground utilities
Blasting vibration safety test with monitoring》With《Middle Line Project For Transferring Water From South To North Beijing-to-Shijiazhuang section blasting vibration Study on Safety Problem》In, it is proposed that
The ground surface monitoring method of shallow embedding (5m) underground utilities:First, by having laid 4 groups of sensors at earth's surface, underground 5,10,19m,
Every group is buried level to (excavating axis perpendicular to pipeline) and vertical to two sensors, as shown in figure 1, test explosion earthquake
Explosive Vibrating Velocity in ripple, research rock mass at different depth, show that earth's surface vibration velocity value is significantly greater tnan the vibration velocity value at the 5m of underground, two
Person differs 2~3 times;Then, by being surveyed to ground vibration velocity, 5 sights are arranged altogether from quick-fried source to natural gas line direction
Measuring point, minimum distance 36.1m, maximum distance 226.2m (pipeline location), measuring point spacing about presses logarithm equidistantly distributed, draws
Propagation attenuation rule of the attenuation of seismic waves along ground, Charge control is released with this, blast working is instructed.As shown in figure 1, being existing
Have in technology along depth direction sensor arrangement figure, its subject matter and weak point that exist:First, pipeline 5m located underground
Left and right, belongs to the pipeline for comparing shallow embedding, and the Blast Vibration Monitoring problem of deep-buried pipeline is not related to;Secondly, on the other hand pass through
The vibration velocity at different depth in rock mass is tested, show that earth's surface vibration velocity value is significantly greater tnan the vibration velocity value at the 5m of underground, the conclusion is simultaneously
Without generality;Again, by carrying out the attenuation law that actual measurement draws attenuation of seismic waves to ground vibration velocity, do not have to obtain outlet pipe
Explosive Vibrating Velocity at line, the blasting vibration safety of pipeline is controlled with this, and this control is very inaccurate, also relatively dangerous.
For buried (buried depth >=20m) underground water supply pipelines apart from the relatively near (distance≤2D in tunnel it can be seen from more than
(D is tunnel span)) in the case of, there is presently no corresponding Blast Vibration Monitoring method.Existing Blast Vibration Monitoring side
Method is mainly for Shallow-Embedded Under-Ground pipeline, by testing ground blasting vibration velocity, carrys out the blasting vibration safety of indirect control shallow embedding pipeline.
For deep-buried pipeline monitoring problem, due to deep-buried pipeline apart from ground farther out, it is and nearer apart from tunnel, ground vibration velocity with pipeline
Vibration velocity is differed greatly, and in the method for ground vibration velocity control pipeline vibration velocity, for buried underground utilities, then significant discomfort is used.It is another
Existing method, by setting the blasting vibration at deep hole direct measurement pipeline bottom position, party's hair implements very difficult, performance
:One is not allow to set deep hole in many cases;Two be to enable punching, and the installation of sensor is also very difficult, it is difficult to
Ensure the precision installed, implement very difficult.
Therefore, the present invention is directed to the Blast Vibration Monitoring method of buried underground water supply pipelines, because buried depth is big, if still adopted
It is monitored, then will be differed greatly with the actual blasting vibration of pipeline, it is impossible to ensure Tunnel Blasting on ground with above method
Vibrate the safety of underground pipelines, it would be highly desirable to propose a kind of new monitoring method.
The content of the invention
The present invention proposes a kind of Blast Vibration Monitoring method of buried underground water supply pipelines, effectively solves buried underground
This technical barrier of the Tunnel Blasting vibration monitoring of pipeline, has far-reaching influence for constructing tunnel industry.
The technical proposal of the invention is realized in this way:A kind of buried underground water supply pipelines is quick-fried in tunnel benching tunnelling method explosion
Broken vibration monitoring method, comprises the following steps:
S1, computer tube linear distance tunnel top bar Bao Yuan centers apart from ROn;The half for taking tunnel top bar height is quick-fried
Heart point, then
S2, get out of a predicament or an embarrassing situation in tunnel explosion when, arrange measuring point N simultaneously in top bar and face rear1And N2, it is ensured that two
Measuring point to the quick-fried heart of getting out of a predicament or an embarrassing situation (take tunnel get out of a predicament or an embarrassing situation height half be quick-fried heart point) distance be equal to ROn;
S3, top bar measuring point N is derived according to S21Horizontal range
S4, face rear measuring point N is derived according to S22Horizontal range
S5, test top bar measuring point N1With tunnel tunnel face rear N2The vibration velocity for locating country rock is V1、V2;
More than S6, repetition measurement 3 times, according to measuring point N1And N2Locate vibration velocity relation, it can be deduced that V1=nV2;
S7, tunnel top bar explosion influence maximum to the water supply line of front of tunnel heading, to obtain front feed pipe
The vibration velocity of line, only need to measure face rear L' in top bar explosionAfterwardsN ' at distance2The vibration velocity V ' of measuring point2,
S8, deduce according to S6 vibration velocity V at pipelinePipe=nV '2;
S9, by vibration velocity V at the pipeline of acquisitionPipeIt is compared with the control standard of pipeline blasting vibration safety, evaluates pipeline
Security situation, optimize blast working scheme, instruct tunnel control explosion, it is ensured that pipeline safety.
As a kind of perferred technical scheme, the specific method of testings of step S2-S7 are that measurement respectively obtains tunnel span D,
Tunnel top bar height HOnWith the height H that gets out of a predicament or an embarrassing situationUnder, underground utilities diameter d, tunnel water supply line distance from top ground H1, tunnel
Water supply line distance from bottom tunnel vault H2, then got out of a predicament or an embarrassing situation in tunnel explosion when in top bar LBeforeMeasuring point N is arranged at distance1With
Explosion face rear country rock side wall LAfterwardsMeasuring point N is arranged at distance2, test top bar measuring point N1With tunnel tunnel face rear N2Place
The vibration velocity of country rock is V1、V2;Face rear L' is measured in top bar explosionAfterwardsN ' at distance2Measuring point, tests N '2Measuring point shakes
Fast V '2。
Above-mentioned technical proposal is employed, beneficial effects of the present invention are:The monitoring method of the present invention is simple and easy to apply, Ke Yi
Tunnel Blasting face rear directly tests, it is to avoid set the difficulty of deep hole test, it also avoid in ground test can not
Reflect the disadvantage of vibration velocity at deep-buried pipeline, the Explosive Vibrating Velocity at accurate pipeline can be obtained by solving algebraic mean value
Data, can directly make an appraisal to the vibration safety of pipeline, instruct blast working.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing
There is the accompanying drawing used required in technology description to be briefly described, it should be apparent that, drawings in the following description are only this
Some embodiments of invention, for those of ordinary skill in the art, without having to pay creative labor, may be used also
To obtain other accompanying drawings according to these accompanying drawings.
Fig. 1 is in the prior art along depth direction sensor arrangement figure;
Fig. 2 is that tunnel of the present invention is got out of a predicament or an embarrassing situation the side view of blasting vibration measurement;
Fig. 3 is that tunnel of the present invention is got out of a predicament or an embarrassing situation the front elevation of blasting vibration measurement;
Fig. 4 is the side view of top bar blasting vibration measurement in tunnel of the present invention;
Fig. 5 is the front elevation of top bar blasting vibration measurement in tunnel of the present invention;
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete
Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments.It is based on
Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under the premise of creative work is not made
Embodiment, belongs to the scope of protection of the invention.
As shown in Figures 2 and 3,
Implementation steps:
(1) tunnel uses benching tunnelling method explosion, H0=10m, HOn=6m, HUnder=4m, D=16m, h1=1m;It is assumed that tunnel axis
It is parallel with pipeline axis, the vertical distance=H in pipeline distance from bottom Tunnel Blasting face center2+HOn/ 2=10+6/2=13m,
Horizontal range is LOn=5m, then calculate R1=13.93m;
(2) assume that certain separate explosion obtains test top bar measuring point LBeforeN at=13.60m distances1With tunnel tunnel face rear LAfterwards
N at=11.36m distances2The vibration velocity for locating country rock is V1=3.0cm/s, V2=1.0cm/s;
(3) measurement is amounted to 3 times more than repeating, V1=3.3cm/s, V2=1.1cm/s;V1=2.7cm/s, V2=0.9cm/
s;According to measuring point N1And N2Locate vibration velocity relation, it can be deduced that V1=3V2;
(4) during the explosion of tunnel top bar, L' at the distance of tunnel tunnel face rearAfterwardsN ' at=11.23m distances2Measuring point, test
N’2The vibration velocity V ' of measuring point2=1.5cm/s,
(5) according to V1=3V2, calculate vibration velocity V at pipelinePipe=3 × 1.5=4.5cm/s;
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention
God is with principle, and any modification, equivalent substitution and improvements made etc. should be included in the scope of the protection.
Claims (1)
1. in tunnel step method, a kind of Blast Vibration Monitoring method of buried underground water supply pipelines, it is characterised in that
Comprise the following steps:
S1, computer tube linear distance tunnel top bar Bao Yuan centers apart from ROn;The half for taking tunnel top bar height is quick-fried heart point,
Then
S2, get out of a predicament or an embarrassing situation in tunnel explosion when, arrange measuring point N simultaneously in top bar and face rear1And N2, it is ensured that two measuring points
To the quick-fried heart of getting out of a predicament or an embarrassing situation (take tunnel get out of a predicament or an embarrassing situation height half be quick-fried heart point) distance be equal to ROn;
S3, top bar measuring point N is derived according to S21Horizontal range
S4, face rear measuring point N is derived according to S22Horizontal range
S5, test top bar measuring point N1With tunnel tunnel face rear N2The vibration velocity for locating country rock is V1、V2;
More than S6, repetition measurement 3 times, according to measuring point N1And N2Locate vibration velocity relation, it can be deduced that V1=nV2;
S7, tunnel top bar explosion influence maximum to the water supply line of front of tunnel heading, to obtain the vibration velocity of front water supply line, only need
Face rear L' is measured in top bar explosionAfterwardsN ' at distance2The vibration velocity V of measuring point2',
S8, deduce according to S6 vibration velocity V at pipelinePipe=nV '2;
S9, by vibration velocity V at the pipeline of acquisitionPipeIt is compared with the control standard of pipeline blasting vibration safety, evaluates the peace of pipeline
Full situation, optimizes blast working scheme, instructs tunnel control explosion, it is ensured that pipeline safety.
As a kind of perferred technical scheme, the specific method of testings of step S2-S7 are that measurement respectively obtains tunnel span D, tunnel
Top bar height HOnWith the height H that gets out of a predicament or an embarrassing situationUnder, underground utilities diameter d, tunnel water supply line distance from top ground H1, tunnel supplies water
Pipeline distance from bottom tunnel vault H2, then got out of a predicament or an embarrassing situation in tunnel explosion when in top bar LBeforeMeasuring point N is arranged at distance1And explosion
Face rear country rock side wall LAfterwardsMeasuring point N is arranged at distance2, test top bar measuring point N1With tunnel tunnel face rear N2Locate country rock
Vibration velocity be V1、V2;Face rear L' is measured in top bar explosionAfterwardsN ' at distance2Measuring point, tests N '2The vibration velocity V ' of measuring point2。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710562972.3A CN107152964B (en) | 2017-07-11 | 2017-07-11 | The Blast Vibration Monitoring method of buried underground water supply pipelines in a kind of construction of tunnel benching tunnelling method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710562972.3A CN107152964B (en) | 2017-07-11 | 2017-07-11 | The Blast Vibration Monitoring method of buried underground water supply pipelines in a kind of construction of tunnel benching tunnelling method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107152964A true CN107152964A (en) | 2017-09-12 |
CN107152964B CN107152964B (en) | 2019-11-22 |
Family
ID=59796875
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710562972.3A Active CN107152964B (en) | 2017-07-11 | 2017-07-11 | The Blast Vibration Monitoring method of buried underground water supply pipelines in a kind of construction of tunnel benching tunnelling method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107152964B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108362583A (en) * | 2017-12-28 | 2018-08-03 | 武汉科技大学 | A kind of simulation explosive load is on closing on the experimental rig and method that buried oil-gas pipeline influences |
CN108489601A (en) * | 2018-03-28 | 2018-09-04 | 青岛理工大学 | A kind of tunnel low coverage passes through the Blast Vibration Monitoring and control method of underground utilities |
CN114674418A (en) * | 2022-02-18 | 2022-06-28 | 深圳大学 | Method and device for monitoring particle vibration in tunnel shaft blasting construction surrounding rock |
CN115371791A (en) * | 2022-07-19 | 2022-11-22 | 青岛理工大学 | Underground pipeline vibration velocity measuring method and system |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003075247A (en) * | 2001-08-31 | 2003-03-12 | Nishimatsu Constr Co Ltd | Method for measuring elastic wave speed in face in tunnel pit |
CN103217703A (en) * | 2013-04-11 | 2013-07-24 | 中国科学院武汉岩土力学研究所 | Method and device for tunnel advance geology forecast with tunnel face blasting as focus |
CN104390537A (en) * | 2014-09-23 | 2015-03-04 | 武汉大学 | Method for controlling damage of slope pre-splitting blasting digging based on blast vibration test |
CN105954357A (en) * | 2016-04-25 | 2016-09-21 | 宏大矿业有限公司 | Method for simultaneous measurement of sound velocity of multi-step horizontal rock body |
CN105973456A (en) * | 2016-04-25 | 2016-09-28 | 宏大矿业有限公司 | Field measurement method of matching relationship between deep hole blasting explosives and rocks |
-
2017
- 2017-07-11 CN CN201710562972.3A patent/CN107152964B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003075247A (en) * | 2001-08-31 | 2003-03-12 | Nishimatsu Constr Co Ltd | Method for measuring elastic wave speed in face in tunnel pit |
CN103217703A (en) * | 2013-04-11 | 2013-07-24 | 中国科学院武汉岩土力学研究所 | Method and device for tunnel advance geology forecast with tunnel face blasting as focus |
CN104390537A (en) * | 2014-09-23 | 2015-03-04 | 武汉大学 | Method for controlling damage of slope pre-splitting blasting digging based on blast vibration test |
CN105954357A (en) * | 2016-04-25 | 2016-09-21 | 宏大矿业有限公司 | Method for simultaneous measurement of sound velocity of multi-step horizontal rock body |
CN105973456A (en) * | 2016-04-25 | 2016-09-28 | 宏大矿业有限公司 | Field measurement method of matching relationship between deep hole blasting explosives and rocks |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108362583A (en) * | 2017-12-28 | 2018-08-03 | 武汉科技大学 | A kind of simulation explosive load is on closing on the experimental rig and method that buried oil-gas pipeline influences |
CN108489601A (en) * | 2018-03-28 | 2018-09-04 | 青岛理工大学 | A kind of tunnel low coverage passes through the Blast Vibration Monitoring and control method of underground utilities |
CN114674418A (en) * | 2022-02-18 | 2022-06-28 | 深圳大学 | Method and device for monitoring particle vibration in tunnel shaft blasting construction surrounding rock |
CN114674418B (en) * | 2022-02-18 | 2022-11-22 | 深圳大学 | Monitoring method and device for particle vibration inside tunnel shaft blasting construction surrounding rock |
CN115371791A (en) * | 2022-07-19 | 2022-11-22 | 青岛理工大学 | Underground pipeline vibration velocity measuring method and system |
Also Published As
Publication number | Publication date |
---|---|
CN107152964B (en) | 2019-11-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Fang et al. | Effects of twin tunnels construction beneath existing shield-driven twin tunnels | |
CN107165678A (en) | A kind of Blast Vibration Monitoring method of buried underground water supply pipelines | |
CN107152964B (en) | The Blast Vibration Monitoring method of buried underground water supply pipelines in a kind of construction of tunnel benching tunnelling method | |
CN104390537B (en) | A kind of side slope pre split Blasting Excavation damage control method based on blasting vibration test | |
Zhao et al. | Experimental and numerical investigation of the effect of blast-induced vibration from adjacent tunnel on existing tunnel | |
Chen et al. | Applicability of the principle of superposition in estimating ground surface settlement of twin-and quadruple-tube tunnels | |
CN105604066B (en) | Application of the resistivity profiling in the detection of building foundation pit building enclosure percolating water | |
CN103293560B (en) | A kind of method of testing adopting triple stress court | |
CN103410516B (en) | Minor diameter tunnel full face tunneling surrouding rock deformation early warning engineering method | |
CN101251498B (en) | Method for testing and evaluating wall rock loosening ring based on electromagnetic radiation principle | |
CN103017822B (en) | High Ground Stress Areas underground power house surrouding rock deformation failure evolvement method of testing and structure | |
CN112965136B (en) | Multi-means advanced detection method for water-rich karst tunnel | |
CN107861157A (en) | A kind of underground water seal cave depot runs phase micro seismic monitoring method | |
CN109238161A (en) | A kind of observation device and observation method of tunnel surface absolute convergence amount | |
CN109470101B (en) | Method for researching influence of adjacent tunnel blasting on existing tunnel based on field model | |
Gao et al. | Dynamic monitoring of water in a working face floor using 2D electrical resistivity tomography (ERT) | |
CN108489601A (en) | A kind of tunnel low coverage passes through the Blast Vibration Monitoring and control method of underground utilities | |
CN113960695A (en) | Fine exploration method for water-rich karst in complex urban environment | |
CN103399342A (en) | Method for forecasting transient unloading induced vibrations based on strain energy of rock masses | |
Li et al. | The detection of the boulders in metro tunneling in granite strata using a shield tunneling method and a new method of coping with boulders | |
CN109612356A (en) | The acquisition methods of concrete duct dynamic response characteristics are closed on when excavation of foundation pit explosion | |
US20240044740A1 (en) | Method and system for blast-induced vibration monitoring of tunnels in high asymmetric in-situ stresses | |
CN103389524A (en) | Method and system for forecasting tunnel geology | |
CN103630938A (en) | Imaging system and imaging method for well earthquake using hammer head of down-hole hammer as focus | |
CN110005467A (en) | The monitoring of tunnel face and optimum design method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |