CN107152677A - A kind of CFBB slag removing system - Google Patents

A kind of CFBB slag removing system Download PDF

Info

Publication number
CN107152677A
CN107152677A CN201710441733.2A CN201710441733A CN107152677A CN 107152677 A CN107152677 A CN 107152677A CN 201710441733 A CN201710441733 A CN 201710441733A CN 107152677 A CN107152677 A CN 107152677A
Authority
CN
China
Prior art keywords
slag
storehouse
cfbb
removing system
cooler
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710441733.2A
Other languages
Chinese (zh)
Inventor
孙建朝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Huadian Engineering Group Co Ltd
Original Assignee
China Huadian Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Huadian Engineering Group Co Ltd filed Critical China Huadian Engineering Group Co Ltd
Priority to CN201710441733.2A priority Critical patent/CN107152677A/en
Publication of CN107152677A publication Critical patent/CN107152677A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23CMETHODS OR APPARATUS FOR COMBUSTION USING FLUID FUEL OR SOLID FUEL SUSPENDED IN  A CARRIER GAS OR AIR 
    • F23C10/00Fluidised bed combustion apparatus
    • F23C10/18Details; Accessories
    • F23C10/24Devices for removal of material from the bed

Abstract

The invention discloses a kind of CFBB slag removing system, belong to Sector of Cfb Boilers.It includes fluidized-bed combustion boiler (1), rolling-cylinder type slag-cooler (2), conveyer (3), bucket elevator (4), slag storehouse (6), deduster (7) and electric feeder (12), and fluidized-bed combustion boiler (1), rolling-cylinder type slag-cooler (2) are sequentially connected with conveyer (3) through slag dropping tube.The output end of conveyer (3) is connected at the top of the top entry of slag storehouse (6), slag storehouse (6) through bucket elevator (4) and is additionally provided with deduster (7).The output end in slag storehouse (6) is connected through slag dropping tube with electric feeder (12).The system structure design is reasonable, operational effect is good, and automaticity is high, reduce pollution of the dust leakage to environment, improves the service life and operating efficiency of equipment, reduces operating cost.

Description

A kind of CFBB slag removing system
Technical field
The present invention relates to a kind of CFBB slag removing system, belong to Sector of Cfb Boilers.
Background technology
Combustion technology of circulating fluidized is a clean coal burning technology developed in recent years, CFBB Also because its high combustion efficiency, coal adaptability is wide, load regulation range is big, discharged nitrous oxides are low, be easy to desulfurization the advantages of and Favor is enjoyed, is worldwide widely used and promotes.As CFBB is in each private station Or the occupation rate of steam power plant is stepped up, its supporting slag removing system also has extremely important effect.Slag removing system be by Deslagging cooling device, conveying equipment and exhaust apparatus composition, when China's earlier cycles fluidized-bed combustion boiler puts into operation, due to The design and imperfection of slag removing system are covered, automaticity is especially low, causes some enterprise directly to carry out boiler slag removal Discharged outside red slag, bottom ash cannot be utilized effectively, equipment failure rate is high, also enterprise safety operation is caused a hidden trouble, while also making Into environmental pollution.In addition, existing CFBB often uses air-water combined slag cooler mostly, but due to domestic coal Particle size after cracking is big, causes overtemperature in air-water combined slag cooler, slagging, blocking, abrasion, and deslagging is difficult, causes slag cooler can not be just Often work, then influences the operation of boiler.
The content of the invention
It is an object of the present invention to provide a kind of CFBB slag removing system.The system structure design is rationally, even Continuous deslagging is good, automaticity is high, fault rate is low, and operational effect is good, and boiler bottom slag can make full use of, and reduces dust and lets out Reveal the pollution to environment, improve the service life and operating efficiency of equipment, reduce operating cost.
In order to solve the above technical problems, the present invention is adopted the following technical scheme that:
A kind of CFBB slag removing system include fluidized-bed combustion boiler, rolling-cylinder type slag-cooler, conveyer, bucket elevator, Slag storehouse, deduster and electric feeder, the fluidized-bed combustion boiler, rolling-cylinder type slag-cooler are sequentially connected with conveyer through slag dropping tube. Compared to air-water combined slag cooler, rolling-cylinder type slag-cooler is not high to boiler bottom slag Particle size requirements, can adapt to bulky grain bottom ash, protects Demonstrate,prove the normal operation of fluidized-bed combustion boiler.The output end of the conveyer is connected to the top entry in slag storehouse, the slag through bucket elevator Deduster is additionally provided with the top of storehouse.Bottom dregs at fluid bed boiler enters rolling-cylinder type slag-cooler after being discharged through slag notch, and warm sludge is through roller Formula slag cooler is cooled to less than 150 DEG C and enters conveyer, and slag storehouse is delivered into through bucket elevator.Bottom ash is delivered to slag by bucket elevator In storehouse, due to the presence of difference in height, easily cause airborne dust in course of conveying, cause site environment poor, by deduster and When dedusting, it is to avoid whole slag removing system produces dust secondary fly-up.The output end in the slag storehouse is through slag dropping tube and electric feeder Connection, then entrucking is transported outward.
Foregoing rolling-cylinder type slag-cooler is at least two groups, and fluidized-bed combustion boiler bottom left and right ends go out provided with least two Cinder notch, the slag notch of the fluidized-bed combustion boiler is connected through slag dropping tube with rolling-cylinder type slag-cooler respectively.Pass through fluidized-bed combustion boiler bottom The slag notch and rolling-cylinder type slag-cooler arranged parallel, increase heat exchange area, improve cooling effect, it is ensured that the normal fortune of system OK.
Pneumatic slag discharging valve, fluid bed pot are additionally provided with slag dropping tube between foregoing fluidized-bed combustion boiler and rolling-cylinder type slag-cooler After bottom slag is discharged through slag-drip opening, enter rolling-cylinder type slag-cooler by Pneumatic slag discharging valve.Pneumatic slag discharging valve can downstream equipment event By programme-control emergency cut-off in the case of barrier, facilitate overhaul of the equipments.
Closed material blanking tube is additionally provided between foregoing bucket elevator and slag storehouse.Pass through the arrangement of material blanking tube, it is ensured that bottom ash Sealing conveying between bucket elevator and slag storehouse, is prevented effectively from the production of dust leakage pollution on the environment and reentrainment of dust It is raw.The crown center position in the slag storehouse is also equipped with pressure relief valve, and covering slag storehouse is not by the shadow of excessive malleation and negative pressure Ring.
The top in foregoing slag storehouse is additionally provided with silo roof boom hoisting, and described silo roof boom hoisting is electric block, is used for The slinging work of equipment when slag storehouse is overhauled.
Foregoing electric feeder includes 1# electric feeders and 2# electric feeders, and the slag storehouse bottom left and right sides is equal Provided with output end, the setting of multiple output ends can unload wet slag or dry slag respectively, meet the different utilization ways of bottom ash.The left side Side output end is connected to 1# electric feeders through slag dropping tube, and the right side output end is connected to 2# electric feeders through slag dropping tube. The electric feeder is frequency conversion rotary electric batcher, and adjustable continuous-feeding can be achieved.
Foregoing CFBB slag removing system is additionally provided with vibrator, and the vibrator includes 1# vibrators and 2# shakes The top for beating output end on the left of device, the slag storehouse is provided with the top of output end on the right side of 1# vibrators, the slag storehouse provided with 2# rappings Device.The vibrator can prevent that bottom ash is hardened in slag storehouse.
Foregoing CFBB slag removing system is additionally provided with mixer and bulk machine, and the 1# electric feeders are through falling Slag pipe is connected with mixer, and the 2# electric feeders are connected through slag dropping tube with bulk machine.Dry slag is added water and stirred by the mixer Wet slag is mixed, being transported to grey field by dump truck stores, and the humidification of the mixer uses recirculated water, saving water resource with water. Dry slag is loaded closed tank truck by the bulk machine, is transported to the comprehensive utilization of comprehensive utilization place, such as cement plant, brickmaking factory, is built the road.
The side of foregoing bulk machine is also equipped with exhaust apparatus, and the exhaust apparatus is connected to slag silo roof portion by the road, Ensure during entrucking, the dusty gas in bulk machine flows back to slag silo roof portion, and filters heel row by slag silo roof portion deduster Enter air, environment will not be polluted.
Level-sensing device is additionally provided with foregoing slag storehouse, the level-sensing device includes continuous material level meter and high charge level meter, described continuous Level-sensing device is located at the top in slag storehouse, and the high charge level meter is located at the side on slag storehouse top.The continuous material level meter can be measured continuously The high charge level alarm in slag storehouse can be achieved in the material position change in slag storehouse, the high charge level meter.
Compared with prior art, the present invention is advantageous in that:The system structure design is reasonable, operational effect is good, leads to Cross bucket elevator and conveyer etc. and coordinate progress sealing conveying, improve the automaticity of slag removing system;Pass through deduster, blanking Pipe, exhaust apparatus etc. reduce pollution of the dust leakage to environment, also achieve final dusting;Pass through the spy of rolling-cylinder type slag-cooler Different arrangement and vibrator etc. improve the service life of equipment, and multiple output end arrangements etc. improve the work of system 15% Efficiency, reduce 5.4% operating cost.
Brief description of the drawings
Fig. 1 is the structural representation of the present invention.
The implication of reference:1- fluidized-bed combustion boilers, 2- rolling-cylinder type slag-coolers, 3- conveyers, 4- bucket elevators, 5- blankings Pipe, 6- slags storehouse, 7- dedusters, 8- pressure relief valves, 9- level-sensing devices, 901- continuous material level meters, 902- high charge level meters, 10- silo roofs Boom hoisting, 11- vibrators, 1101-1# vibrators, 1102-2# vibrators, 12- electric feeders, the electronic feeds of 1201-1# Machine, 1202-2# electric feeders, 13- mixers, 14- bulk machines, 15- Pneumatic slag discharging valves, 16- exhaust apparatus.
The present invention is further illustrated with reference to the accompanying drawings and detailed description.
Embodiment
Embodiments of the invention 1:As shown in figure 1, a kind of CFBB slag removing system include fluidized-bed combustion boiler 1, Rolling-cylinder type slag-cooler 2, conveyer 3, bucket elevator 4, slag storehouse 6, deduster 7 and electric feeder 12, fluidized-bed combustion boiler 1, drum-type Slag cooler 2 is sequentially connected with conveyer 3 through slag dropping tube.Also set on slag dropping tube between fluidized-bed combustion boiler 1 and rolling-cylinder type slag-cooler 2 Have after Pneumatic slag discharging valve 15, the bottom ash of fluidized-bed combustion boiler 1 discharge through slag-drip opening, enter rolling-cylinder type slag-cooler by Pneumatic slag discharging valve 15 2.Pneumatic slag discharging valve 15 in the case of downstream equipment failure by programme-control emergency cut-off, can facilitate overhaul of the equipments.Compare In air-water combined slag cooler, rolling-cylinder type slag-cooler 2 is not high to boiler bottom slag Particle size requirements, can adapt to bulky grain bottom ash, it is ensured that The normal operation of fluidized-bed combustion boiler 1.Specifically, conveyer 3 is bucket chain conveyor, the output end of conveyer 3 is connected through bucket elevator 4 Top entry in slag storehouse 6, the top in slag storehouse 6 is additionally provided with deduster 7, specifically, deduster 7 is sack cleaner, cloth bag is removed Dirt device maintenance convenience, good dedusting effect, low cost.The bottom ash of fluidized-bed combustion boiler 1 enters rolling-cylinder type slag-cooler after being discharged through slag notch 2, warm sludge is cooled to less than 150 DEG C through rolling-cylinder type slag-cooler 2 and enters conveyer 3, and slag storehouse 6 is delivered into through bucket elevator 4.Bottom ash is led to Cross bucket elevator 4 to be delivered in slag storehouse 6, due to the presence of difference in height, easily cause airborne dust in course of conveying, cause site environment It is poor, pass through the timely dedusting of deduster 7, it is to avoid whole slag removing system produces dust secondary fly-up.The output end in slag storehouse 6 is through falling slag Pipe is connected with electric feeder 12, and then entrucking is transported outward.The power source of deduster 7 and Pneumatic slag discharging valve 15 is compressed air, rolling Cartridge type slag cooler 2, conveyer 3, the power source of bucket elevator 4 and electric feeder 12 are motor.
Wherein, rolling-cylinder type slag-cooler 2 is at least two groups, and the bottom left and right ends of fluidized-bed combustion boiler 1 are slagged tap provided with least two Mouthful, the slag notch of fluidized-bed combustion boiler 1 is connected through slag dropping tube with rolling-cylinder type slag-cooler 2 respectively.It is parallel by the bottom of fluidized-bed combustion boiler 1 The slag notch and rolling-cylinder type slag-cooler 2 of arrangement, increase heat exchange area, improve cooling effect, it is ensured that the normal operation of system. Closed material blanking tube 5 is additionally provided between bucket elevator 4 and slag storehouse 6.Pass through the arrangement of material blanking tube 5, it is ensured that bottom ash bucket elevator 4 with Sealing conveying between slag storehouse 6, is prevented effectively from the generation of dust leakage pollution on the environment and reentrainment of dust.Slag storehouse 6 Crown center position is also equipped with pressure relief valve 8, and covering slag storehouse 6 is not influenceed by excessive malleation and negative pressure.Slag storehouse 6 it is upper Portion is additionally provided with silo roof boom hoisting 10, the slinging work of equipment when being overhauled for slag storehouse 6.Specifically, silo roof boom hoisting 10 For electric block.Level-sensing device 9 is additionally provided with slag storehouse 6, level-sensing device 9 includes continuous material level meter 901 and high charge level meter 902, continuous material Position meter 901 is located at the top in slag storehouse 6, and high charge level meter 902 is located at the side on the top of slag storehouse 6.Continuous material level meter 901 can be measured continuously The material position change in slag storehouse 6, high charge level meter 902 can realize the high charge level alarm in slag storehouse 6.
Electric feeder 12 includes 1# electric feeders 1201 and 2# electric feeders 1202, the bottom left and right sides of slag storehouse 6 Output end is equipped with, the setting of multiple output ends can unload wet slag or dry slag respectively, meet the different utilization ways of bottom ash.Left side Output end is connected to 1# electric feeders 1201 through slag dropping tube, and right side output end is connected to 2# electric feeders through slag dropping tube 1202.Specifically, electric feeder 12 is frequency conversion rotary electric batcher, adjustable continuous-feeding can be achieved.Recirculating fluidized bed Modification of Slag-Handling System for Boiler is additionally provided with vibrator 11, and vibrator 11 includes 1# vibrators 1101 and 2# vibrators 1102, and the left side of slag storehouse 6 is defeated The top for going out end is provided with 1# vibrators 1101, and the top of the right side output end of slag storehouse 6 is provided with 2# vibrators 1102.Vibrator 11 can be with Prevent that bottom ash is hardened in slag storehouse 6.CFBB slag removing system is additionally provided with mixer 13 and bulk machine 14, specifically, stirring Machine 13 is mixed for biaxial rneader.1# electric feeders 1201 are connected through slag dropping tube with mixer 13, and 2# electric feeders 1202 are passed through Slag dropping tube is connected with bulk machine 14.Dry slag is added water and stirs into wet slag by mixer 13, and being transported to grey field by dump truck stores, and stirs The humidification for mixing machine 13 uses recirculated water, saving water resource with water.Dry slag is loaded closed tank truck by bulk machine 14, is transported to comprehensive utilization Place is comprehensively utilized, and such as cement plant, brickmaking factory, is built the road.Wherein, the side of bulk machine 14 is also equipped with exhaust apparatus 16, row Device of air 16 is connected to the top of slag storehouse 6 by the road, it is ensured that during entrucking, the dusty gas in bulk machine 14 flows back to slag storehouse 6 Top, and by being discharged into air after the filtering of the top deduster 7 of slag storehouse 6, environment will not be polluted.
Embodiment 2:As shown in figure 1, a kind of CFBB slag removing system includes fluidized-bed combustion boiler 1, cylinder type cold Slag device 2, conveyer 3, bucket elevator 4, slag storehouse 6, deduster 7 and electric feeder 12, fluidized-bed combustion boiler 1, the and of rolling-cylinder type slag-cooler 2 Conveyer 3 is sequentially connected through slag dropping tube.Compared to air-water combined slag cooler, rolling-cylinder type slag-cooler 2 is to boiler bottom slag Particle size requirements It is not high, it can adapt to bulky grain bottom ash, it is ensured that the normal operation of fluidized-bed combustion boiler 1.The output end of conveyer 3 connects through bucket elevator 4 The top entry in slag storehouse 6 is connected to, the top in slag storehouse 6 is additionally provided with deduster 7.Specifically, deduster 7 is sack cleaner, cloth bag Deduster maintenance convenience, good dedusting effect, low cost.The bottom ash of fluidized-bed combustion boiler 1 enters cylinder type cold slag after being discharged through slag notch Device 2, warm sludge is cooled to less than 150 DEG C through rolling-cylinder type slag-cooler 2 and enters conveyer 3, and slag storehouse 6 is delivered into through bucket elevator 4.Bottom ash It is delivered to by bucket elevator 4 in slag storehouse 6, due to the presence of difference in height, easily causes airborne dust in course of conveying, cause live ring Border is poor, passes through the timely dedusting of deduster 7, it is to avoid whole slag removing system produces dust secondary fly-up.The output end in slag storehouse 6 is through falling Slag pipe is connected with electric feeder 12, and then entrucking is transported outward.
The course of work of the present invention:The high temperature bottom slag of CFBB 1 is after boiler slag removal mouthful discharge, through pneumatic lime-ash Valve 15 falls into rolling-cylinder type slag-cooler 2, and conveyer 3 is entered after roller slag cooler 2 is cooled to below 150 DEG C, passes through conveyer 3 Bucket elevator 4 is delivered to, and the top of slag storehouse 6 is promoted to by bucket elevator 4, entering slag storehouse 6 by material blanking tube 5 stores.The top of slag storehouse 6 is set Sack cleaner 7, pressure relief valve 8, level-sensing device 9 and silo roof boom hoisting 10 are put, sack cleaner 7 was used in filter residue storehouse 6 Dust laden air, the covering slag storehouse 6 of pressure relief valve 8 do not influenceed by excessive malleation and negative pressure, and level-sensing device 9 is used to monitor slag storehouse Material position in 6, equipment lifting when silo roof boom hoisting 10 is used to overhaul.The bottom of slag storehouse 6 sets 14 liang of mixer 13 and bulk machine Discharge way is planted, dry slag is added water and stirs into wet slag by mixer 13, being transported to grey field by dump truck stores;Bulk machine 14 will be dry Slag loads closed tank truck, is transported to the comprehensive utilization of comprehensive utilization place.Set electronic between slag storehouse 6 and mixer 13 and bulk machine 14 Batcher 12, for realizing that the continuously adjustabe of material is fed during entrucking.The top of slag storehouse 6 cone section sets vibrator 11, prevents Only bottom ash is hardened in slag storehouse 6, makes dry slag blanking smooth.This technology can realize the closing conveying of bottom ash and store, and can effectively carry The level of comprehensive utilization of high bottom ash.

Claims (10)

1. a kind of CFBB slag removing system, it is characterised in that including fluidized-bed combustion boiler (1), rolling-cylinder type slag-cooler (2), conveyer (3), bucket elevator (4), slag storehouse (6), deduster (7) and electric feeder (12), the fluidized-bed combustion boiler (1), Rolling-cylinder type slag-cooler (2) is sequentially connected with conveyer (3) through slag dropping tube;The output end of the conveyer (3) connects through bucket elevator (4) It is connected at the top of the top entry of slag storehouse (6), the slag storehouse (6) and is additionally provided with deduster (7);The output end warp of the slag storehouse (6) Slag dropping tube is connected with electric feeder (12).
2. CFBB slag removing system according to claim 1, it is characterised in that the rolling-cylinder type slag-cooler (2) it is at least two groups, fluidized-bed combustion boiler (1) the bottom left and right ends are provided with least two slag notches, the fluidized-bed combustion boiler (1) slag notch is connected through slag dropping tube with rolling-cylinder type slag-cooler (2) respectively.
3. CFBB slag removing system according to claim 2, it is characterised in that the fluidized-bed combustion boiler (1) Pneumatic slag discharging valve (15) is additionally provided with slag dropping tube between rolling-cylinder type slag-cooler (2).
4. CFBB slag removing system according to claim 3, it is characterised in that the bucket elevator (4) and slag Closed material blanking tube (5) is additionally provided between storehouse (6), the crown center position of the slag storehouse (6) is also equipped with pressure relief valve (8)。
5. CFBB slag removing system according to claim 4, it is characterised in that the top of the slag storehouse (6) It is additionally provided with silo roof boom hoisting (10).
6. CFBB slag removing system according to claim 5, it is characterised in that the electric feeder (12) Including 1# electric feeders (1201) and 2# electric feeders (1202), slag storehouse (6) the bottom left and right sides is equipped with output End, the left side output end is connected to 1# electric feeders (1201) through slag dropping tube, and the right side output end is connected through slag dropping tube In 2# electric feeders (1202).
7. CFBB slag removing system according to claim 6, it is characterised in that be additionally provided with vibrator (11), The vibrator (11) includes the top of output end on the left of 1# vibrators (1101) and 2# vibrators (1102), the slag storehouse (6) Provided with 1# vibrators (1101), the top of output end is provided with 2# vibrators (1102) on the right side of the slag storehouse (6).
8. CFBB slag removing system according to claim 7, it is characterised in that be additionally provided with mixer (13) and Bulk machine (14), the 1# electric feeders (1201) are connected through slag dropping tube with mixer (13), the 2# electric feeders (1202) it is connected through slag dropping tube with bulk machine (14).
9. CFBB slag removing system according to claim 8, it is characterised in that the one of the bulk machine (14) Side is also equipped with exhaust apparatus (16), and the exhaust apparatus (16) is connected at the top of slag storehouse (6) by the road.
10. CFBB slag removing system according to claim 9, it is characterised in that also set on the slag storehouse (6) There is level-sensing device (9), the level-sensing device (9) includes continuous material level meter (901) and high charge level meter (902), the continuous material level meter (901) top of slag storehouse (6) is located at, the high charge level meter (902) is located at the side on slag storehouse (6) top.
CN201710441733.2A 2017-06-13 2017-06-13 A kind of CFBB slag removing system Pending CN107152677A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710441733.2A CN107152677A (en) 2017-06-13 2017-06-13 A kind of CFBB slag removing system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710441733.2A CN107152677A (en) 2017-06-13 2017-06-13 A kind of CFBB slag removing system

Publications (1)

Publication Number Publication Date
CN107152677A true CN107152677A (en) 2017-09-12

Family

ID=59796248

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710441733.2A Pending CN107152677A (en) 2017-06-13 2017-06-13 A kind of CFBB slag removing system

Country Status (1)

Country Link
CN (1) CN107152677A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109292394A (en) * 2018-10-25 2019-02-01 南通联振重工机械有限公司 A kind of oscillatory type cinder transportation system
CN110542108A (en) * 2019-08-27 2019-12-06 济宁盛唐能源有限公司 Boiler deslagging system for coal power generation
CN110550413A (en) * 2019-09-29 2019-12-10 中煤大同能源有限责任公司 Slag removal system of chain bucket conveyor and thermal power plant

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002081627A (en) * 2000-09-05 2002-03-22 Babcock Hitachi Kk Fluidized-bed level controller and bed-material treating equipment for industrial waste incinerator
CN201363740Y (en) * 2009-06-24 2009-12-16 山东电力工程咨询院有限公司 Novel boiler bottom slag delivery device
CN103017157A (en) * 2012-11-30 2013-04-03 大连锅炉厂有限公司 Mechanical deslagging device
CN203309897U (en) * 2013-05-15 2013-11-27 山西平朔煤矸石发电有限责任公司 Combined deslagging device of large circulating fluidized bed boiler
CN105180163A (en) * 2015-09-18 2015-12-23 青岛达能环保设备股份有限公司 Classified cooling and slag discharging system for circulating fluidized bed boiler
CN205640887U (en) * 2016-05-03 2016-10-12 中国电力工程顾问集团东北电力设计院有限公司 Sediment waste heat utilization's air -cooled system at bottom of improvement circulating fluidized bed boiler

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002081627A (en) * 2000-09-05 2002-03-22 Babcock Hitachi Kk Fluidized-bed level controller and bed-material treating equipment for industrial waste incinerator
CN201363740Y (en) * 2009-06-24 2009-12-16 山东电力工程咨询院有限公司 Novel boiler bottom slag delivery device
CN103017157A (en) * 2012-11-30 2013-04-03 大连锅炉厂有限公司 Mechanical deslagging device
CN203309897U (en) * 2013-05-15 2013-11-27 山西平朔煤矸石发电有限责任公司 Combined deslagging device of large circulating fluidized bed boiler
CN105180163A (en) * 2015-09-18 2015-12-23 青岛达能环保设备股份有限公司 Classified cooling and slag discharging system for circulating fluidized bed boiler
CN205640887U (en) * 2016-05-03 2016-10-12 中国电力工程顾问集团东北电力设计院有限公司 Sediment waste heat utilization's air -cooled system at bottom of improvement circulating fluidized bed boiler

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨建华: "《循环流化床锅炉设备及运行》", 北京:中国电力出版社, pages: 131 - 134 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109292394A (en) * 2018-10-25 2019-02-01 南通联振重工机械有限公司 A kind of oscillatory type cinder transportation system
CN110542108A (en) * 2019-08-27 2019-12-06 济宁盛唐能源有限公司 Boiler deslagging system for coal power generation
CN110550413A (en) * 2019-09-29 2019-12-10 中煤大同能源有限责任公司 Slag removal system of chain bucket conveyor and thermal power plant

Similar Documents

Publication Publication Date Title
US9945556B2 (en) Fossil-fuel power generation system assisted by waste incineration
CN107152677A (en) A kind of CFBB slag removing system
CN105773835B (en) Ceramic raw material mix grinding centralized system is for Processes and apparatus
CN104803618B (en) annular lime shaft kiln
CN203170266U (en) Dust removal system for sintering mixing machine
CN208218696U (en) A kind of light-burned MgO suspension calcining process units
CN104591556B (en) A kind of Automatic Control lime vertical kiln production line
CN104748508B (en) Coal slurry drying system
CN207080993U (en) A kind of CFBB slag removing system
CN211012481U (en) Vertical preheater
CN203333491U (en) Energy-saving environment-friendly cement clinker preparation system
CN204550403U (en) Annular lime shaft kiln
CN110631378A (en) Vertical preheater
CN106975307A (en) A kind of new type high temperature moisture-resistant bag-type dust removing system
CN207432499U (en) A kind of concrete agitation station sand material stores transportation system
CN103351106A (en) Energy-saving and environment-friendly cement clinker preparation system
CN207078751U (en) A kind of slag storehouse discharge system
CN206730698U (en) Powder tank centralized dust-removing system and there is its concrete mixing plant
CN206817453U (en) A kind of CFBB slag storage is deposited and discharge system
CN205235756U (en) Polymer deNOx systems
CN108483950A (en) A kind of high activity MgO roasting techniques and its dedicated unit
CN107525408A (en) Grate refining moveable collection cigarette charging combined unit and its method of work
CN106517203A (en) Calcium carbide production system
CN108358474B (en) Continuous air supply coal-saving mixing lime kiln
CN107120643A (en) A kind of CFBB slag storage is deposited and discharge system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170912

RJ01 Rejection of invention patent application after publication