CN107152294A - High hydraulic pressure big flow Karst Tunnel underground water seal blocking method - Google Patents

High hydraulic pressure big flow Karst Tunnel underground water seal blocking method Download PDF

Info

Publication number
CN107152294A
CN107152294A CN201710512079.XA CN201710512079A CN107152294A CN 107152294 A CN107152294 A CN 107152294A CN 201710512079 A CN201710512079 A CN 201710512079A CN 107152294 A CN107152294 A CN 107152294A
Authority
CN
China
Prior art keywords
hydraulic pressure
water
construction
big flow
closure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710512079.XA
Other languages
Chinese (zh)
Inventor
张行道
段丁丁
赵国祝
韩伟辉
朴占华
李晓林
王海峰
董仲飞
王刚
谢波
高国梁
赵磊
乔玉海
兰杰
胡马俊
泊纯光
桑伟浪
衣志勇
唐少强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Original Assignee
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Bridge Engineering Bureau Group Co Ltd filed Critical China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority to CN201710512079.XA priority Critical patent/CN107152294A/en
Publication of CN107152294A publication Critical patent/CN107152294A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

A kind of high hydraulic pressure big flow Karst Tunnel underground water seal blocking method, comprises the following steps:1. the spy water operation being engaged using physical prospecting and probing, determines hydraulic pressure and water;2. the shunting construction of leak is carried out out;3. the closure of the big passage of leak is carried out out;4. the random grouting and reinforcing of tunnel surrounding is carried out;5. closure by different level from the near to the remote, from the top in the end;6. the last closing plugging construction for going out leakage point.The present invention solves closure and the drainage problem of high hydraulic pressure big flow Karst Tunnel, reduces the risk of construction and later stage operation.

Description

High hydraulic pressure big flow Karst Tunnel underground water seal blocking method
Technical field:
The invention belongs to constructing tunnel field, more particularly to a kind of high hydraulic pressure big flow Karst Tunnel underground water closure side Method.
Background technology:
A large amount of with the expansion of the west area railway network, particularly high-speed railway are built, and tunnel is built in karst area Unavoidably.In the presence of the high hydraulic pressure in karst region, waterproof and drainage design and construction turn into an important topic.
The content of the invention:
The purpose of the present invention is that a kind of high hydraulic pressure big flow Karst Tunnel underground water seal blocking method of offer, this method solution The closure for high hydraulic pressure big flow Karst Tunnel of having determined and drainage problem, reduce the risk of construction and later stage operation.
As above conceive, the technical scheme is that:A kind of high hydraulic pressure big flow Karst Tunnel underground water seal blocking method, its It is characterised by:Comprise the following steps:1. the spy water operation being engaged using physical prospecting and probing, determines hydraulic pressure and water;2. carry out Go out the shunting construction of leak;3. the closure of the big passage of leak is carried out out;4. the random grouting and reinforcing of tunnel surrounding is carried out;5. by near To remote, closure by different level from the top in the end;6. the last closing plugging construction for going out leakage point.
The Specific construction process of the step 2. is:According to the result of physical prospecting and probing, concentrated in tunnel in the range of water burst Using water source position as starting point, the shunting decompression hole of different depth and different angles is set, and installs the shunting with high pressure valve and is subtracted Pressure pipe, while in water outlet periphery arrangement water plugged by grouting hole;
The step 2. middle increase caisson ejectment construction:It is first after bottom plate high pressure consolidation and the construction of periphery tap hole are finished Charges or sediment in Limestone Cave Surge are first removed, concentrates position upstream and downstream direction or surrounding to fix respectively in water burst after cleaning out Lay several Steel Tube Specials and carry out ejectments, then make centered on issue concrete caisson, caisson studs with center and is formed with draining Castingin orifice tube around the steel plate of steel pipe, caisson, beneficial to draining and follow-up plugging construction.
3. the step directly carries out grout sealing using form sack grouting technology to original issue.
It is " first to reinforce, seal afterwards that the rich water Karst Tunnel that the present invention is big to water, pressure is big, which discloses the total treatment principle of water, Stifled, first shunting decompression, after progressively close up ".Overall process thinking for " first visits block up afterwards, from the superficial to the deep, block source, block up row combination, Select a good opportunity closure ".Therefore, present invention efficiently solves the closure of high hydraulic pressure big flow Karst Tunnel and drainage problem, reduce Construction and the risk of later stage operation.
Brief description of the drawings:
Fig. 1 is the process chart of the present invention.
Embodiment:
As shown in the figure:A kind of high hydraulic pressure big flow Karst Tunnel underground water seal blocking method, comprises the following steps:
1st, the spy water operation being engaged using physical prospecting and probing, determines hydraulic pressure and water.Leak is gone out according to the tunnel of exposure Geological conditions data and hydrogeologic data that situation and design are provided, the water burst situation for water burst eastern section of being dashed forward to tunnel are divided Analysis, determines mode, the position of physical prospecting and probing.Tunnel Gushing scope is further looked into reference to the physical detecting of progress Visit, and carry out necessary probing work.Result of detection more than, determines the property of underground water water outlet and the position of water-yielding stratum Put, scale.
2nd, the shunting and ejectment construction of leak are carried out out.It is big to single-point flow in constructing tunnel, pressure is high, flow velocity going out soon Water spot, probing and physical prospecting are determined more than water-bearing layer position and property, it is determined that setting depth and setting by shunting decompression hole Position;The order of closure is determined simultaneously, by the EXIT POINT near apart from water source gradually distally drainage, to reduce water pressure, drop Low closure difficulty.
(1) construction in shunting decompression hole:Concentrated in tunnel in the range of water burst and enough shunting decompression holes are set, while Certain water plugged by grouting hole is arranged on water outlet periphery, to create the execution conditions for blocking original issue., be according to thing in this stage The result visited and drilled, using water source position as starting point, sets the shunting decompression hole of different depth and different angles, and install band The shunting decompression pipe of high pressure valve, enables current to be discharged in the drainpipe with valve being embedded to, to reduce original EXIT POINT The pressure of water and head.
(2) caisson ejectment construction (special shunting ejectment construction):After the shunting of some tap holes, decompression, if failing The condition of directly closure main channel is reached, then needs to be handled using the form of construction work (caisson) of special ejectment.Caisson Purpose is not the lid weight and bearing capacity for increasing bottom plate water burst, and is easy for carrying out former issue scattered grouting treatment.For gushing The characteristics of water spot water burst flow is big, after bottom plate high pressure consolidation and the construction of periphery tap hole are finished, removes in Limestone Cave Surge first Charges or sediment, position upstream and downstream direction (or surrounding) fixedly secured several high pressure steels respectively are concentrated after cleaning out in water burst Pipe carries out ejectment (ejectment steel pipe size is determined according to water yield), then makes centered on issue concrete caisson, caisson edge There is center to be formed with the steel plate of draining slip casting orifice tube.Castingin orifice tube around caisson, beneficial to draining and follow-up plugging construction.Such as This, just forms caisson ejectment.
3rd, the closure of the big passage of leak is carried out out.
(1) conventional closure (general closure):After the shunting of some tap holes, decompression, if water burst pressure declines or divided Stream reaches the condition that closure main channel is met compared with low discharge, just directly original issue can be carried out using form sack grouting technology Grout sealing.
(2) special closure (standby closure):Use geological drilling rig cleaning bottom of hole to basement rock after solidifying after lid loaded concrete, pass through lid Draining steel pipe on plate is irrigated, if draining steel pipe is buried under now oozes slurry amount greatly, is just irrigated using form sack grouting technology.
4th, the random grouting and reinforcing of tunnel surrounding is carried out.After shunting ejectment construction terminates, relevant ejectment ports valve door is closed in examination Blocking test is carried out, sees whether new water burst position occur, the new water burst position of appearance and issue are then also tackled and newly occurred Water burst position carry out reinforcing grouting treatment.
5th, closure by different level from the near to the remote, from the top in the end.The random grouting and reinforcing of the tunnel surrounding carried out in the 4th road Closure by different level from the near to the remote, from the top in the end can be carried out afterwards.By by top under, from shallow to deep, and from the near to the remote Progressively irrigate so that slurries are gradually accumulated filling by delivery port, reach the purpose of filling and blocking outlet conduit.
6th, the last closing plugging construction for going out leakage point.Tunnel big flow, high hydraulic pressure underground go out the last of leak closure The grout sealing of vent is shunted during one of formality.Directly remaining high hydraulic pressure shunting decompression hole can now be blocked, sealed The neat slurry for preferably using high pressure, big flow is blocked up, the purpose is to cement injection as much as possible, while increasing the diffusion of slurries Scope, so as to reduce the pressure of underground water.

Claims (4)

1. a kind of high hydraulic pressure big flow Karst Tunnel underground water seal blocking method, it is characterised in that:Comprise the following steps:1. thing is used The spy water operation being engaged is visited and drilled, hydraulic pressure and water is determined;2. the shunting construction of leak is carried out out;3. leak is carried out out big The closure of passage;4. the random grouting and reinforcing of tunnel surrounding is carried out;5. closure by different level from the near to the remote, from the top in the end;6. most The closing plugging construction for going out leakage point afterwards.
2. high hydraulic pressure big flow Karst Tunnel underground water seal blocking method according to claim 1, it is characterised in that:The step Suddenly Specific construction process 2. is:According to physical prospecting and probing result, tunnel concentrate water burst in the range of using water source position for Point, sets the shunting decompression hole of different depth and different angles, and installs the shunting decompression pipe with high pressure valve, while in water outlet Periphery arrangement water plugged by grouting hole.
3. high hydraulic pressure big flow Karst Tunnel underground water seal blocking method according to claim 1, it is characterised in that:The step Suddenly 2. middle increase caisson ejectment construction:After high pressure consolidation and the construction of periphery tap hole are finished, remove filled in Limestone Cave Surge first Thing or sediment are filled out, fixedly secured several Steel Tube Specials enter respectively in water burst concentration position upstream and downstream direction or surrounding after cleaning out Row ejectment, then concrete caisson is made centered on issue, caisson is studded with around the steel plate that center is formed with draining steel pipe, caisson Castingin orifice tube, beneficial to draining and follow-up plugging construction.
4. high hydraulic pressure big flow Karst Tunnel underground water seal blocking method according to claim 1, it is characterised in that:The step Suddenly grout sealing is directly 3. carried out to original issue using form sack grouting technology.
CN201710512079.XA 2017-06-28 2017-06-28 High hydraulic pressure big flow Karst Tunnel underground water seal blocking method Pending CN107152294A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710512079.XA CN107152294A (en) 2017-06-28 2017-06-28 High hydraulic pressure big flow Karst Tunnel underground water seal blocking method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710512079.XA CN107152294A (en) 2017-06-28 2017-06-28 High hydraulic pressure big flow Karst Tunnel underground water seal blocking method

Publications (1)

Publication Number Publication Date
CN107152294A true CN107152294A (en) 2017-09-12

Family

ID=59795034

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710512079.XA Pending CN107152294A (en) 2017-06-28 2017-06-28 High hydraulic pressure big flow Karst Tunnel underground water seal blocking method

Country Status (1)

Country Link
CN (1) CN107152294A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109209289A (en) * 2018-10-26 2019-01-15 青岛天源伟业保温防水工程有限公司 A kind of material filling device for blocking high-pressure underground water
CN109555536A (en) * 2018-11-01 2019-04-02 山东大学 It is a kind of to divide the more slurries joint decompression truncation slip-casting control methods of sequence and system
CN110578493A (en) * 2019-09-16 2019-12-17 中国矿业大学 High-pressure large-flow water inrush blocking method for mine
CN110984120A (en) * 2019-12-31 2020-04-10 桂林电子科技大学 Filling structure of shallow-buried non-pressure water-filled karst cave and construction method thereof
CN113153309A (en) * 2021-03-09 2021-07-23 中铁工程装备集团有限公司 Tunnel construction method
CN113445959A (en) * 2021-08-10 2021-09-28 中铁二院工程集团有限责任公司 Drilling drainage structure of karst or fault tunnel and construction method and construction structure thereof

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109209289A (en) * 2018-10-26 2019-01-15 青岛天源伟业保温防水工程有限公司 A kind of material filling device for blocking high-pressure underground water
CN109209289B (en) * 2018-10-26 2023-12-29 青岛天源伟业保温防水工程有限公司 Filling device for plugging high-pressure underground water
CN109555536A (en) * 2018-11-01 2019-04-02 山东大学 It is a kind of to divide the more slurries joint decompression truncation slip-casting control methods of sequence and system
CN110578493A (en) * 2019-09-16 2019-12-17 中国矿业大学 High-pressure large-flow water inrush blocking method for mine
CN110984120A (en) * 2019-12-31 2020-04-10 桂林电子科技大学 Filling structure of shallow-buried non-pressure water-filled karst cave and construction method thereof
CN110984120B (en) * 2019-12-31 2020-09-25 桂林电子科技大学 Filling structure of shallow-buried non-pressure water-filled karst cave and construction method thereof
CN113153309A (en) * 2021-03-09 2021-07-23 中铁工程装备集团有限公司 Tunnel construction method
CN113153309B (en) * 2021-03-09 2022-03-15 中铁工程装备集团有限公司 Tunnel construction method
CN113445959A (en) * 2021-08-10 2021-09-28 中铁二院工程集团有限责任公司 Drilling drainage structure of karst or fault tunnel and construction method and construction structure thereof
CN113445959B (en) * 2021-08-10 2022-02-01 中铁二院工程集团有限责任公司 Drilling drainage structure of karst or fault tunnel and construction method and construction structure thereof

Similar Documents

Publication Publication Date Title
CN107152294A (en) High hydraulic pressure big flow Karst Tunnel underground water seal blocking method
CN103277120B (en) A kind of non-fully deeply freeze vertical thaw after water burst prevention and controls
WO2019000776A1 (en) Side slope underground water drilling self-starting negative pressure drainage system and method
CN103967507B (en) A kind of curtain-grouting technique being suitable for rich water mine down-hole exploitation water blockoff
CN108547639B (en) Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings
CN212690047U (en) Tunnel fault broken zone excavation outline line edge curtain slip casting body structure
CN107044128A (en) Supporting and dewatering construction method in Deep Excavation
CN105239984A (en) Method for controlling coal mine underground fracturing crack propagation
CN105735055B (en) Imbibition drainage
JP5112976B2 (en) Tunnel construction method under deep and high water pressure
CN209339169U (en) A kind of precipitation well in foundation pit plugging device
CN202323973U (en) Grouting sleeve valve tube structure for seepage insulation, closure and interception for building foundation
CN104314090A (en) Deep foundation pit bedrock drainage culvert and drainage system and drainage construction method thereof
CN109026010A (en) A kind of mine seepage well slip casting type sinking shaft construction method
CN107386309A (en) The prominent water burst method for blocking of the mine big flow high flow rate pipeline crack type karst that is recessed
CN107747312A (en) A kind of method of sand and gravel stratum well cementing construction
CN105443098B (en) A kind of coal mine down-hole drilling segmentation fixed point hydraulic fracturing pore-fixing device and method
CN112746849B (en) Shaft water-carrying digging and building method
CN108729438A (en) A kind of administering method in karst area channel
CN101793154A (en) Method for grouting for stopping up water by using geological parameters of tunnel surrounding rocks and setting relief holes
CN102587400B (en) Leakage-plugging method for water-stopping curtain
CN108867673A (en) A kind of underwater prevention method in the foundation pit based on the curtain that draws water
CN105274994B (en) Anti-suck sludge proof grouting process and grouting device in deep saturated sand
CN204551510U (en) A kind of filled-up ground catchments pressure reduction well drop and drainage structure
CN110130982A (en) A kind of traffic tunnel building safety construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170912

WD01 Invention patent application deemed withdrawn after publication