CN107152294A - High hydraulic pressure big flow Karst Tunnel underground water seal blocking method - Google Patents
High hydraulic pressure big flow Karst Tunnel underground water seal blocking method Download PDFInfo
- Publication number
- CN107152294A CN107152294A CN201710512079.XA CN201710512079A CN107152294A CN 107152294 A CN107152294 A CN 107152294A CN 201710512079 A CN201710512079 A CN 201710512079A CN 107152294 A CN107152294 A CN 107152294A
- Authority
- CN
- China
- Prior art keywords
- hydraulic pressure
- water
- construction
- big flow
- closure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title claims abstract description 53
- 238000000034 method Methods 0.000 title claims abstract description 16
- 230000000903 blocking effect Effects 0.000 title claims abstract description 13
- 238000010276 construction Methods 0.000 claims abstract description 27
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 6
- 230000006837 decompression Effects 0.000 claims description 12
- 229910000831 Steel Inorganic materials 0.000 claims description 11
- 239000010959 steel Substances 0.000 claims description 11
- 238000005516 engineering process Methods 0.000 claims description 5
- 238000004140 cleaning Methods 0.000 claims description 4
- 239000011440 grout Substances 0.000 claims description 4
- 238000007789 sealing Methods 0.000 claims description 4
- 235000019738 Limestone Nutrition 0.000 claims description 3
- 230000009286 beneficial effect Effects 0.000 claims description 3
- 238000007596 consolidation process Methods 0.000 claims description 3
- 239000006028 limestone Substances 0.000 claims description 3
- 239000013049 sediment Substances 0.000 claims description 3
- 238000011144 upstream manufacturing Methods 0.000 claims description 3
- 239000012141 concentrate Substances 0.000 claims description 2
- 239000002002 slurry Substances 0.000 description 4
- 239000004568 cement Substances 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 238000009792 diffusion process Methods 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- JEGUKCSWCFPDGT-UHFFFAOYSA-N h2o hydrate Chemical compound O.O JEGUKCSWCFPDGT-UHFFFAOYSA-N 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 238000007569 slipcasting Methods 0.000 description 1
- 239000000243 solution Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/38—Waterproofing; Heat insulating; Soundproofing; Electric insulating
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
A kind of high hydraulic pressure big flow Karst Tunnel underground water seal blocking method, comprises the following steps:1. the spy water operation being engaged using physical prospecting and probing, determines hydraulic pressure and water;2. the shunting construction of leak is carried out out;3. the closure of the big passage of leak is carried out out;4. the random grouting and reinforcing of tunnel surrounding is carried out;5. closure by different level from the near to the remote, from the top in the end;6. the last closing plugging construction for going out leakage point.The present invention solves closure and the drainage problem of high hydraulic pressure big flow Karst Tunnel, reduces the risk of construction and later stage operation.
Description
Technical field:
The invention belongs to constructing tunnel field, more particularly to a kind of high hydraulic pressure big flow Karst Tunnel underground water closure side
Method.
Background technology:
A large amount of with the expansion of the west area railway network, particularly high-speed railway are built, and tunnel is built in karst area
Unavoidably.In the presence of the high hydraulic pressure in karst region, waterproof and drainage design and construction turn into an important topic.
The content of the invention:
The purpose of the present invention is that a kind of high hydraulic pressure big flow Karst Tunnel underground water seal blocking method of offer, this method solution
The closure for high hydraulic pressure big flow Karst Tunnel of having determined and drainage problem, reduce the risk of construction and later stage operation.
As above conceive, the technical scheme is that:A kind of high hydraulic pressure big flow Karst Tunnel underground water seal blocking method, its
It is characterised by:Comprise the following steps:1. the spy water operation being engaged using physical prospecting and probing, determines hydraulic pressure and water;2. carry out
Go out the shunting construction of leak;3. the closure of the big passage of leak is carried out out;4. the random grouting and reinforcing of tunnel surrounding is carried out;5. by near
To remote, closure by different level from the top in the end;6. the last closing plugging construction for going out leakage point.
The Specific construction process of the step 2. is:According to the result of physical prospecting and probing, concentrated in tunnel in the range of water burst
Using water source position as starting point, the shunting decompression hole of different depth and different angles is set, and installs the shunting with high pressure valve and is subtracted
Pressure pipe, while in water outlet periphery arrangement water plugged by grouting hole;
The step 2. middle increase caisson ejectment construction:It is first after bottom plate high pressure consolidation and the construction of periphery tap hole are finished
Charges or sediment in Limestone Cave Surge are first removed, concentrates position upstream and downstream direction or surrounding to fix respectively in water burst after cleaning out
Lay several Steel Tube Specials and carry out ejectments, then make centered on issue concrete caisson, caisson studs with center and is formed with draining
Castingin orifice tube around the steel plate of steel pipe, caisson, beneficial to draining and follow-up plugging construction.
3. the step directly carries out grout sealing using form sack grouting technology to original issue.
It is " first to reinforce, seal afterwards that the rich water Karst Tunnel that the present invention is big to water, pressure is big, which discloses the total treatment principle of water,
Stifled, first shunting decompression, after progressively close up ".Overall process thinking for " first visits block up afterwards, from the superficial to the deep, block source, block up row combination,
Select a good opportunity closure ".Therefore, present invention efficiently solves the closure of high hydraulic pressure big flow Karst Tunnel and drainage problem, reduce
Construction and the risk of later stage operation.
Brief description of the drawings:
Fig. 1 is the process chart of the present invention.
Embodiment:
As shown in the figure:A kind of high hydraulic pressure big flow Karst Tunnel underground water seal blocking method, comprises the following steps:
1st, the spy water operation being engaged using physical prospecting and probing, determines hydraulic pressure and water.Leak is gone out according to the tunnel of exposure
Geological conditions data and hydrogeologic data that situation and design are provided, the water burst situation for water burst eastern section of being dashed forward to tunnel are divided
Analysis, determines mode, the position of physical prospecting and probing.Tunnel Gushing scope is further looked into reference to the physical detecting of progress
Visit, and carry out necessary probing work.Result of detection more than, determines the property of underground water water outlet and the position of water-yielding stratum
Put, scale.
2nd, the shunting and ejectment construction of leak are carried out out.It is big to single-point flow in constructing tunnel, pressure is high, flow velocity going out soon
Water spot, probing and physical prospecting are determined more than water-bearing layer position and property, it is determined that setting depth and setting by shunting decompression hole
Position;The order of closure is determined simultaneously, by the EXIT POINT near apart from water source gradually distally drainage, to reduce water pressure, drop
Low closure difficulty.
(1) construction in shunting decompression hole:Concentrated in tunnel in the range of water burst and enough shunting decompression holes are set, while
Certain water plugged by grouting hole is arranged on water outlet periphery, to create the execution conditions for blocking original issue., be according to thing in this stage
The result visited and drilled, using water source position as starting point, sets the shunting decompression hole of different depth and different angles, and install band
The shunting decompression pipe of high pressure valve, enables current to be discharged in the drainpipe with valve being embedded to, to reduce original EXIT POINT
The pressure of water and head.
(2) caisson ejectment construction (special shunting ejectment construction):After the shunting of some tap holes, decompression, if failing
The condition of directly closure main channel is reached, then needs to be handled using the form of construction work (caisson) of special ejectment.Caisson
Purpose is not the lid weight and bearing capacity for increasing bottom plate water burst, and is easy for carrying out former issue scattered grouting treatment.For gushing
The characteristics of water spot water burst flow is big, after bottom plate high pressure consolidation and the construction of periphery tap hole are finished, removes in Limestone Cave Surge first
Charges or sediment, position upstream and downstream direction (or surrounding) fixedly secured several high pressure steels respectively are concentrated after cleaning out in water burst
Pipe carries out ejectment (ejectment steel pipe size is determined according to water yield), then makes centered on issue concrete caisson, caisson edge
There is center to be formed with the steel plate of draining slip casting orifice tube.Castingin orifice tube around caisson, beneficial to draining and follow-up plugging construction.Such as
This, just forms caisson ejectment.
3rd, the closure of the big passage of leak is carried out out.
(1) conventional closure (general closure):After the shunting of some tap holes, decompression, if water burst pressure declines or divided
Stream reaches the condition that closure main channel is met compared with low discharge, just directly original issue can be carried out using form sack grouting technology
Grout sealing.
(2) special closure (standby closure):Use geological drilling rig cleaning bottom of hole to basement rock after solidifying after lid loaded concrete, pass through lid
Draining steel pipe on plate is irrigated, if draining steel pipe is buried under now oozes slurry amount greatly, is just irrigated using form sack grouting technology.
4th, the random grouting and reinforcing of tunnel surrounding is carried out.After shunting ejectment construction terminates, relevant ejectment ports valve door is closed in examination
Blocking test is carried out, sees whether new water burst position occur, the new water burst position of appearance and issue are then also tackled and newly occurred
Water burst position carry out reinforcing grouting treatment.
5th, closure by different level from the near to the remote, from the top in the end.The random grouting and reinforcing of the tunnel surrounding carried out in the 4th road
Closure by different level from the near to the remote, from the top in the end can be carried out afterwards.By by top under, from shallow to deep, and from the near to the remote
Progressively irrigate so that slurries are gradually accumulated filling by delivery port, reach the purpose of filling and blocking outlet conduit.
6th, the last closing plugging construction for going out leakage point.Tunnel big flow, high hydraulic pressure underground go out the last of leak closure
The grout sealing of vent is shunted during one of formality.Directly remaining high hydraulic pressure shunting decompression hole can now be blocked, sealed
The neat slurry for preferably using high pressure, big flow is blocked up, the purpose is to cement injection as much as possible, while increasing the diffusion of slurries
Scope, so as to reduce the pressure of underground water.
Claims (4)
1. a kind of high hydraulic pressure big flow Karst Tunnel underground water seal blocking method, it is characterised in that:Comprise the following steps:1. thing is used
The spy water operation being engaged is visited and drilled, hydraulic pressure and water is determined;2. the shunting construction of leak is carried out out;3. leak is carried out out big
The closure of passage;4. the random grouting and reinforcing of tunnel surrounding is carried out;5. closure by different level from the near to the remote, from the top in the end;6. most
The closing plugging construction for going out leakage point afterwards.
2. high hydraulic pressure big flow Karst Tunnel underground water seal blocking method according to claim 1, it is characterised in that:The step
Suddenly Specific construction process 2. is:According to physical prospecting and probing result, tunnel concentrate water burst in the range of using water source position for
Point, sets the shunting decompression hole of different depth and different angles, and installs the shunting decompression pipe with high pressure valve, while in water outlet
Periphery arrangement water plugged by grouting hole.
3. high hydraulic pressure big flow Karst Tunnel underground water seal blocking method according to claim 1, it is characterised in that:The step
Suddenly 2. middle increase caisson ejectment construction:After high pressure consolidation and the construction of periphery tap hole are finished, remove filled in Limestone Cave Surge first
Thing or sediment are filled out, fixedly secured several Steel Tube Specials enter respectively in water burst concentration position upstream and downstream direction or surrounding after cleaning out
Row ejectment, then concrete caisson is made centered on issue, caisson is studded with around the steel plate that center is formed with draining steel pipe, caisson
Castingin orifice tube, beneficial to draining and follow-up plugging construction.
4. high hydraulic pressure big flow Karst Tunnel underground water seal blocking method according to claim 1, it is characterised in that:The step
Suddenly grout sealing is directly 3. carried out to original issue using form sack grouting technology.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710512079.XA CN107152294A (en) | 2017-06-28 | 2017-06-28 | High hydraulic pressure big flow Karst Tunnel underground water seal blocking method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710512079.XA CN107152294A (en) | 2017-06-28 | 2017-06-28 | High hydraulic pressure big flow Karst Tunnel underground water seal blocking method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107152294A true CN107152294A (en) | 2017-09-12 |
Family
ID=59795034
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710512079.XA Pending CN107152294A (en) | 2017-06-28 | 2017-06-28 | High hydraulic pressure big flow Karst Tunnel underground water seal blocking method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107152294A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109209289A (en) * | 2018-10-26 | 2019-01-15 | 青岛天源伟业保温防水工程有限公司 | A kind of material filling device for blocking high-pressure underground water |
CN109555536A (en) * | 2018-11-01 | 2019-04-02 | 山东大学 | It is a kind of to divide the more slurries joint decompression truncation slip-casting control methods of sequence and system |
CN110578493A (en) * | 2019-09-16 | 2019-12-17 | 中国矿业大学 | High-pressure large-flow water inrush blocking method for mine |
CN110984120A (en) * | 2019-12-31 | 2020-04-10 | 桂林电子科技大学 | Filling structure of shallow-buried non-pressure water-filled karst cave and construction method thereof |
CN113153309A (en) * | 2021-03-09 | 2021-07-23 | 中铁工程装备集团有限公司 | Tunnel construction method |
CN113445959A (en) * | 2021-08-10 | 2021-09-28 | 中铁二院工程集团有限责任公司 | Drilling drainage structure of karst or fault tunnel and construction method and construction structure thereof |
-
2017
- 2017-06-28 CN CN201710512079.XA patent/CN107152294A/en active Pending
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109209289A (en) * | 2018-10-26 | 2019-01-15 | 青岛天源伟业保温防水工程有限公司 | A kind of material filling device for blocking high-pressure underground water |
CN109209289B (en) * | 2018-10-26 | 2023-12-29 | 青岛天源伟业保温防水工程有限公司 | Filling device for plugging high-pressure underground water |
CN109555536A (en) * | 2018-11-01 | 2019-04-02 | 山东大学 | It is a kind of to divide the more slurries joint decompression truncation slip-casting control methods of sequence and system |
CN110578493A (en) * | 2019-09-16 | 2019-12-17 | 中国矿业大学 | High-pressure large-flow water inrush blocking method for mine |
CN110984120A (en) * | 2019-12-31 | 2020-04-10 | 桂林电子科技大学 | Filling structure of shallow-buried non-pressure water-filled karst cave and construction method thereof |
CN110984120B (en) * | 2019-12-31 | 2020-09-25 | 桂林电子科技大学 | Filling structure of shallow-buried non-pressure water-filled karst cave and construction method thereof |
CN113153309A (en) * | 2021-03-09 | 2021-07-23 | 中铁工程装备集团有限公司 | Tunnel construction method |
CN113153309B (en) * | 2021-03-09 | 2022-03-15 | 中铁工程装备集团有限公司 | Tunnel construction method |
CN113445959A (en) * | 2021-08-10 | 2021-09-28 | 中铁二院工程集团有限责任公司 | Drilling drainage structure of karst or fault tunnel and construction method and construction structure thereof |
CN113445959B (en) * | 2021-08-10 | 2022-02-01 | 中铁二院工程集团有限责任公司 | Drilling drainage structure of karst or fault tunnel and construction method and construction structure thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107152294A (en) | High hydraulic pressure big flow Karst Tunnel underground water seal blocking method | |
CN103277120B (en) | A kind of non-fully deeply freeze vertical thaw after water burst prevention and controls | |
WO2019000776A1 (en) | Side slope underground water drilling self-starting negative pressure drainage system and method | |
CN103967507B (en) | A kind of curtain-grouting technique being suitable for rich water mine down-hole exploitation water blockoff | |
CN108547639B (en) | Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings | |
CN212690047U (en) | Tunnel fault broken zone excavation outline line edge curtain slip casting body structure | |
CN107044128A (en) | Supporting and dewatering construction method in Deep Excavation | |
CN105239984A (en) | Method for controlling coal mine underground fracturing crack propagation | |
CN105735055B (en) | Imbibition drainage | |
JP5112976B2 (en) | Tunnel construction method under deep and high water pressure | |
CN209339169U (en) | A kind of precipitation well in foundation pit plugging device | |
CN202323973U (en) | Grouting sleeve valve tube structure for seepage insulation, closure and interception for building foundation | |
CN104314090A (en) | Deep foundation pit bedrock drainage culvert and drainage system and drainage construction method thereof | |
CN109026010A (en) | A kind of mine seepage well slip casting type sinking shaft construction method | |
CN107386309A (en) | The prominent water burst method for blocking of the mine big flow high flow rate pipeline crack type karst that is recessed | |
CN107747312A (en) | A kind of method of sand and gravel stratum well cementing construction | |
CN105443098B (en) | A kind of coal mine down-hole drilling segmentation fixed point hydraulic fracturing pore-fixing device and method | |
CN112746849B (en) | Shaft water-carrying digging and building method | |
CN108729438A (en) | A kind of administering method in karst area channel | |
CN101793154A (en) | Method for grouting for stopping up water by using geological parameters of tunnel surrounding rocks and setting relief holes | |
CN102587400B (en) | Leakage-plugging method for water-stopping curtain | |
CN108867673A (en) | A kind of underwater prevention method in the foundation pit based on the curtain that draws water | |
CN105274994B (en) | Anti-suck sludge proof grouting process and grouting device in deep saturated sand | |
CN204551510U (en) | A kind of filled-up ground catchments pressure reduction well drop and drainage structure | |
CN110130982A (en) | A kind of traffic tunnel building safety construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170912 |
|
WD01 | Invention patent application deemed withdrawn after publication |