CN107146641A - The method of nuclear power system and control nuclear power system - Google Patents

The method of nuclear power system and control nuclear power system Download PDF

Info

Publication number
CN107146641A
CN107146641A CN201710329665.0A CN201710329665A CN107146641A CN 107146641 A CN107146641 A CN 107146641A CN 201710329665 A CN201710329665 A CN 201710329665A CN 107146641 A CN107146641 A CN 107146641A
Authority
CN
China
Prior art keywords
reactor
neutron
power system
nuclear power
nuclear
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710329665.0A
Other languages
Chinese (zh)
Inventor
詹文龙
杨磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Institute of Modern Physics of CAS
Original Assignee
Institute of Modern Physics of CAS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Institute of Modern Physics of CAS filed Critical Institute of Modern Physics of CAS
Priority to CN201710329665.0A priority Critical patent/CN107146641A/en
Publication of CN107146641A publication Critical patent/CN107146641A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G21NUCLEAR PHYSICS; NUCLEAR ENGINEERING
    • G21CNUCLEAR REACTORS
    • G21C1/00Reactor types
    • G21C1/30Subcritical reactors ; Experimental reactors other than swimming-pool reactors or zero-energy reactors
    • GPHYSICS
    • G21NUCLEAR PHYSICS; NUCLEAR ENGINEERING
    • G21CNUCLEAR REACTORS
    • G21C7/00Control of nuclear reaction
    • G21C7/34Control of nuclear reaction by utilisation of a primary neutron source
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Plasma & Fusion (AREA)
  • General Engineering & Computer Science (AREA)
  • High Energy & Nuclear Physics (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Structure Of Emergency Protection For Nuclear Reactors (AREA)

Abstract

The embodiment provides a kind of nuclear power system and a kind of method of control nuclear power system, nuclear power system includes:Burner subsystem, burner subsystem includes the first reactor and neutron-producing target, the neutron produced by neutron-producing target makes the first reactor carry out nuclear reaction under subcritical state, and after the expiration of the predetermined period of time, the first reactor carries out nuclear reaction under critical conditions;And post-process subsystem for the fuel reproduction of core weary material processing.The method of control nuclear power system includes:The neutron produced by neutron-producing target makes the first reactor carry out nuclear reaction under subcritical state;And after the expiration of the predetermined period of time, the first reactor carries out nuclear reaction under critical conditions.Thus nuclear fuel utilization rate can at least be improved.

Description

The method of nuclear power system and control nuclear power system
Technical field
Embodiments of the invention are related to a kind of nuclear power system and a kind of method of control nuclear power system.
Background technology
At present, reactor is mainly water cooling thermal-neutron reactor, neutron pile using it is disposable by or U-Pu (uranium-plutonium) it is multiple Nuclear fuel cycle mode.But it is low to there is nuclear fuel utilization rate, core weary material toxicity, post processing financial cost and core production peace The problem of full blast is nearly high.
The content of the invention
The purpose of embodiments of the invention is to provide a kind of nuclear power system and a kind of method of control nuclear power system, thus extremely Nuclear fuel utilization rate can be improved less.
The embodiment provides a kind of nuclear power system, the nuclear power system includes:First reactor and neutron-producing target, lead to Crossing the neutron of neutron-producing target generation makes the first reactor carry out nuclear reaction under subcritical state, and is passing through predetermined time period Afterwards, the first reactor carries out nuclear reaction under critical conditions.
Embodiments in accordance with the present invention, described nuclear power system also includes:Second reactor, in being produced by neutron-producing target Son makes the second reactor carry out nuclear reaction under subcritical state, and after the expiration of the predetermined period of time, the second reactor exists Nuclear reaction is carried out under critical condition.
Embodiments in accordance with the present invention, described nuclear power system also includes:Proton precessional magnetometer, the proton precessional magnetometer produces matter Beamlet, and the proton beam incident neutron target produced by proton precessional magnetometer, produce neutron.
Embodiments in accordance with the present invention, the strength range for the proton beam that proton precessional magnetometer is produced is 800MeV~1500MeV.
Embodiments in accordance with the present invention, the flux for the neutron that neutron-producing target is produced is 1E+18n/s~3E+18n/s.
Embodiments in accordance with the present invention, neutron-producing target includes ceramic particle, and the ceramic particle can bear 10MW~30MW lines Power.
Embodiments in accordance with the present invention, the particle diameter of ceramic particle is in millimeter magnitude
Under embodiments in accordance with the present invention, at least one in subcritical state and critical condition, the first reactor The thermal power of reactor core is 600MW~2000MW.
Embodiments in accordance with the present invention, described nuclear power system also includes:Solid particle, by the use of the solid particle as cold But medium is cooled down to the first reactor, under at least one in subcritical state and critical condition, and the cooling media exists The temperature of the outlet of first reactor is 650~900 DEG C.
Embodiments in accordance with the present invention, described nuclear power system also includes:For locating after the fuel reproduction of core weary material processing Manage subsystem.
Embodiments in accordance with the present invention, the nuclear power system is nuclear reactor system.
The embodiment provides a kind of method for controlling nuclear power system, the method for control nuclear power system includes:It is logical Crossing the neutron of neutron-producing target generation makes the first reactor carry out nuclear reaction under subcritical state;And passing through predetermined time period Afterwards, the first reactor carries out nuclear reaction under critical conditions.
Embodiments in accordance with the present invention, the method for described control nuclear power system also includes:In being produced by neutron-producing target Son makes the second reactor carry out nuclear reaction under subcritical state.
Embodiments in accordance with the present invention, the method for described control nuclear power system also includes:Passing through predetermined time period Afterwards, the second reactor carries out nuclear reaction under critical conditions.
Embodiments in accordance with the present invention, the method for described control nuclear power system also includes:Produced using proton precessional magnetometer Proton beam;And the proton beam incident neutron target produced by proton precessional magnetometer, produce neutron.
Embodiments in accordance with the present invention, the strength range for the proton beam that proton precessional magnetometer is produced is 800MeV~1500MeV.
Embodiments in accordance with the present invention, the flux for the neutron that neutron-producing target is produced is 1E+18n/s~3E+18n/s.
Embodiments in accordance with the present invention, neutron-producing target includes ceramic particle, and the ceramic particle can bear 10MW~30MW lines Power.
Embodiments in accordance with the present invention, the particle diameter of ceramic particle is in millimeter magnitude.
Under embodiments in accordance with the present invention, at least one in subcritical state and critical condition, the first reactor The thermal power of reactor core is 600MW~2000MW.
Embodiments in accordance with the present invention, the method for described control nuclear power system also includes:By the use of solid particle as cold But medium is cooled down to the first reactor, under at least one in subcritical state and critical condition, and the cooling media exists The temperature of the outlet of first reactor is 650~900 DEG C.
Embodiments in accordance with the present invention, the nuclear power system is nuclear reactor system.
According to an embodiment of the invention nuclear power system and control nuclear power system method, can at least improve nuclear fuel makes With rate.
Brief description of the drawings
Fig. 1 is the nuclear power system overall schematic of the Accelerator driven of the embodiment of the present invention;
Fig. 2 is burner subsystem schematic diagram in the nuclear power system of the Accelerator driven of the embodiment of the present invention;And
Fig. 3 is fuel reproduction post processing subsystem schematic diagram in the nuclear power system of the Accelerator driven of the embodiment of the present invention.
Embodiment
Below in conjunction with the accompanying drawings and embodiment the present invention will be further described.
Referring to Fig. 1 to 2, nuclear power system is controlled according to an embodiment of the invention, and (for example nuclear reactor system (for example burns Device subsystem 101)) method include:The neutron produced by neutron-producing target 3 makes the first reactor (such as burner 2) face secondary Nuclear reaction is carried out under boundary's state;And after section is asked when predetermined, the first reactor (such as burner 2) is in critical condition Lower carry out nuclear reaction.This method can also include:The neutron produced by neutron-producing target 3 makes the second reactor, and (for example another fires Burner 2) nuclear reaction is carried out under subcritical state, after the expiration of the predetermined period of time, (for example another burns the second reactor Device 2) nuclear reaction is carried out under critical conditions.This method can also include:Proton beam is produced using proton precessional magnetometer 1;And it is logical The proton beam incident neutron target 3 of the generation of proton precessional magnetometer 1 is crossed, neutron is produced.For example, with reference to Fig. 1 to 2, according to the reality of the present invention Applying the nuclear power system (such as nuclear reactor system (such as burner subsystem 101)) of example includes:First reactor (for example burns Device 2) and by neutron-producing target 3, the neutron produced by neutron-producing target 3 makes the first reactor (such as burner 2) in subcritical state Lower progress nuclear reaction and after the expiration of the predetermined period of time, the first reactor (such as burner 2) is carried out under critical conditions Nuclear reaction.The nuclear power system can also include:Second reactor (such as another burner 2), in being produced by neutron-producing target 3 Son makes the second reactor (such as another burner 2) carry out nuclear reaction under subcritical state, is passing through predetermined time period Afterwards, the second reactor (such as another burner 2) carries out nuclear reaction under critical conditions.The nuclear power system can also include: Proton precessional magnetometer 1, the proton precessional magnetometer 1 produces proton beam and the proton beam incident neutron target produced by proton precessional magnetometer 1 3, produce neutron.
According to the example of the present invention, this method is also carried out using solid particle as cooling media to the first reactor Under cooling, at least one in subcritical state and critical condition, temperature of the cooling media in the outlet of the first reactor For 650~900 DEG C.For example, nuclear power system also includes solid particle, reacted by the use of the solid particle as cooling media first Heap is cooled down, under at least one in subcritical state and critical condition, and the cooling media is in the outlet of the first reactor Temperature be 650~900 DEG C.
Nuclear power system according to an embodiment of the invention is specifically described with reference to example.
As shown in figure 1, the nuclear power system of the Accelerator driven of the embodiment of the present invention includes:Burner subsystem 101 and combustion Material regeneration post processing subsystem 102.
As illustrated in fig. 1 and 2, burner subsystem 101 includes:At least one proton precessional magnetometer 1, such as superconduction straight line high current Proton precessional magnetometer 1 and at least one burner 2.In order to obtain higher economy, it is extended to by many superconduction straight line high currents Proton precessional magnetometer 1 drives the accelerator redundant mode of many burners 2.
Superconduction straight line high current proton precessional magnetometer 1 is the building block of burner subsystem 101, and its main function is for producing Raw high current, high-power proton beam.In embodiments of the invention accelerator produce proton beam strength range for 800MeV~ 1500MeV.Bombard the generation high flux neutron of Spallation target 3 (about 1E+18n/s~3E+18n/s) to remain anti-by proton beam Chain reaction lasting in heap 4 is answered, so as to reach the purpose of production capacity and transmuting nuke rubbish.
Burner 2 includes neutron-producing target 3 (such as high power Spallation target 3), (preferably high temperature is fast for modular reactor 4 Heap), target material after-treatment device 5, target heat-exchange system 6, reactor coolant after-treatment device 7 and reactor heat-exchange system 8 etc. Device.Wherein, high power Spallation target 3 uses the windowless target design configuration of particle stream, target body overall diameter 30-50cm;Modularization Reactor 4 heat transferring medium is used as using particle stream.
Spallation target 3 is located at the reactor core center of reactor 4, it is preferred to use intensive ceramic particle stream target scheme, the selection of its particle For the material that neutron yield is high, fusing point is high, thermal capacitance is big, such as radiation hardness, resistant to elevated temperatures carbide, nitride or oxide ceramics Material is (for example:Zirconium oxide, aluminum oxide, zirconium nitride, carborundum etc., and be made up of these material blends radiation hardness, resistance to height Adiabator), diameter is in millimeter magnitude.Its basic functional principle is, the particle of flowing is both spallation target material and cooling medium, Particle produces wide power spectrum neutron by the bombardment of high energy proton line, and the line deposition torrid zone is gone out into target area by flowing, carry out from Line radiates.Fluidization solid particle target has the ability for bearing 10MW~30MW beam powers.Particle stream target has liquid target simultaneously With the feature of solid target, the inherent defect that can not only overcome the liquid spallation targets such as mercury, LBE (liquid lead bismuth alloy) to exist, and And can effectively solve the problem that the hot removal problem of high power of solid target.In reactor 4 thermal power of reactor core be about 600MW~ 2000MW, in low helium pressure environment, cooling agent particle is flowed through in reactor fuel component by fuel member under gravity What part was constituted is vertically arranged cooling duct, the heat derives that will be produced in reactor fuel element.Coolant outlet temperature may be configured as 650~900 DEG C or so, the outlet temperature of high cooling agent ensure that the electrical efficiency of heap, and these optimizations substantially increase the warp of system Ji property.The operation of reactor takes 20-30 long periods to reload strategy, and nuclear fuel can choose presurized water reactor spentnuclear fuel and depleted uranium Carbide ceramics fuel.
The effect of target material after-treatment device 5 and reactor coolant after-treatment device 7 is by reacted target respectively Particle flowing coolant after material and cooling reactor core carries out dedusting, sorting, removes a small amount of disintegrating slag wherein produced by long-play And dust etc..
The effect of target heat-exchange system 6 and reactor heat-exchange system 8 is by the target particle after being reacted in spallation target 3 and anti- The heat for answering the Core cooling agent particle of heap 4 to be taken out of carries out heat exchange, waste heat is exported, it is ensured that fluidization solid particle in system Within rational temperature range, the heat after export can carry out production capacity generating.The particle heat-exchanger rig of the embodiment of the present invention can Using several form structures such as roller cooler, fluid-bed heat exchanger, plate type heat exchanger, wherein it is preferred that plate type heat exchanger structure. Target particle and cooling agent after post processing and heat exchange can be again injected into spallation target 3 and reactor 4 by lifting device Carry out subsequent cycle.
Fig. 3 be the Accelerator driven of the embodiment of the present invention nuclear power system in fuel reproduction post processing subsystem schematic diagram, The nuclear fuel processing procedure of the present invention is that the process for the spentnuclear fuel through separating at high temperature being processed into transmuting fuel, i.e. exclusive segment split Become product, mainly neutron toxicity nucleic, this process is not present the enrichment of fissioner, its radioactivity can be greatly reduced, this The increase of nuclear proliferation difficulty and action of terror risk is set to decline to a great extent.Embodiments of the invention mainly use simple dry method to post-process Technology makes full use of the uranium resource in nuclear fuel, and basic ideas are to divide from LWR (light-water reactor) spentnuclear fuel involucrum layer Separating out spentnuclear fuel pellet, --- oxidation --- reduction --- powdered spentnuclear fuel sinters new nuclear fuel into through compressing, so that again Secondary to utilize, all processes are carried out in the hot cell of shielding, and the product extracted is efficient by physical method and ionic liquid method Lanthanide series is separated, the main nucleic based on neutron toxicity is obtained, surplus material can reuse to improve making for fuel With rate.
Detailed process is as shown in figure 3, nuclear fuel in burner 2 after burned for long time is from burner subsystem 101 Drawn off in the reactor core of nuclear reactor 4, be transported to fuel reproduction post processing subsystem 102, need to be handled by following steps: (1) spentnuclear fuel pellet is isolated from spentnuclear fuel involucrum layer, the method centrifuged using pyro-oxidation-reduction and physics is segmented Change spentnuclear fuel, remove volatile fission product and gas, it is weary that this step can add the core discarded in other reactors after burning Expect that A1 (core weary material of such as light water reactor) together handles (H1);(2) fission such as rare earth element is further excluded using high-temperature dry Product, the elimination factor of fission product is more than 50% (H2);(3) it is the fission product after exclusion is further by Rare Earth Separation method again The rich rare earth of separation and transuranic element, are the transuranium member in final disposal thing (A2), final disposal thing (A2) by rich rare-earth transition Cellulose content is less than 0.1% (H3);(4) the final disposal thing (A2) of premenstrual 3 step processing can store up progress simply by dry type Disposal, and remaining transuranic element, particularly time actinium series nucleic are reclaimed again after H3 step separation, with high-temperature oxydation before also The weary material of major part after original is regenerated as carbide particle fuel (H4) by carbonization together;(5) granular fuel (diameter range 0.01mm~0.1mm) it is fitted into the involucrum of composite material of silicon carbide, generative fuel (H5) is made by sintering again;(6) regeneration combustion Material is reentered to be burnt (H6) in the burner 2 of combustion subsystem 101.So carry out core weary material and nuke rubbish processing and The regeneration cycle of nuclear fuel.
It is as follows that the nuclear power system of example of the present invention implements process:
The operation of this nuclear power system is initially that one or more superconduction straight line high current proton precessional magnetometer 1 drives a burner 2, Now the burner 2 of the system is operated in subcritical state.Superconduction straight line high current proton precessional magnetometer 1 produces high current, high-power matter Beamlet, proton beam continuously bombards Spallation target 3 and produces high flux neutron, and these high-throughout neutrons act on reactor On fuel assembly in 4 reactor cores, make to continue chain reaction in reactor 4, so as to reach the purpose of production capacity and transmuting nuke rubbish.
Reacted target particle and reactor coolant can pass through target material after-treatment device 5 and reactor coolant respectively After-treatment device 7 carries out the processing such as dedusting, sorting, removes wherein because of a small amount of disintegrating slag and dust of long-play generation etc..
Next target particle and reactor coolant by post processing respectively enter target heat-exchange system 6 and reactor heat exchange Heat exchange is carried out in system 8, by heat derives, fluidization solid particle is reduced within certain temperature range after heat exchange, it Satisfactory target particle and reactor coolant are refilled in spallation target 3 and reactor 4 respectively by lifting device afterwards Next circulation is carried out, derived heat generates electricity for production capacity.
Nuclear fuel in burner 2 after burned for long time is removed from the reactor core of nuclear reactor 4 of burner subsystem 101 Go out, be transported to fuel reproduction post processing subsystem 102, after step as shown in Figure 3 is handled, reenter burning Burnt in the burner 2 of subsystem 101, to realize the transmuting of core weary material and the regeneration cycle of nuclear fuel.
Burner passes through the subcritical operation of 3~5 years, and nuclear fuel switchs to critical conduction mode operation after certain propagation.It is super Lead straight line high current proton precessional magnetometer 1 and cut off its external neutrons source driving to burner 2, burner 2 is completely transformed into self-holding combustion Burning state, the now burner 2 i.e. operation is under critical conditions.At the same time, the superconduction straight line high current proton precessional magnetometer 1 again with Another burner 2 is coupled, and it is driven, and reconstitutes a subcritical reactor, is thusly-formed an accelerator 1 and is driven Move the pattern of several burners 2.More than one accelerator of the economy of the pattern only accelerates to drive the economy of a sub-critical reactor Property it is high.Distinguish the pattern that driving number platform burner 2 is run parallel, more economy according to many accelerators 1.Moreover, each Core weary material for remainder can be used as the fresh fuel of enlarging heap.
The nuclear power system of Accelerator driven includes:Burner subsystem and nuclear fuel regeneration post processing subsystem.Wherein, fire Burner subsystem is main by device groups such as high current superconducting proton linac, high power Spallation target and modular high temperature fast reactors Into;Nuclear fuel regeneration post processing subsystem is mainly produced by economy nuke rubbish high-temperature post-treatment flow, new nuclear fuel Flow (production of such as fuel element and its involucrum) process is realized.The burner subsystem of the embodiment of the present invention can be by many Platform superconduction straight line high current proton precessional magnetometer drives the accelerator redundant mode of many burners.The accelerator of the embodiment of the present invention drives Dynamic nuclear power system may operate at subcritical, also may operate under critical condition.Just during dress heap, superconduction straight line high current Proton emission is needed Device driving burner is burnt, and the system is run under subcritical state, after running 3~5 years, superconduction straight line high current proton Accelerator cuts off its external neutrons source driving to burner, and burner is completely transformed into self-sustaining burning state, now the system As run under critical conditions.
The transmuting of Accelerator driven nuclear power system collection nuke rubbish, Nuclear fuel breeding and the nuclear energy safety in production of the present invention is one Body, is a kind of strategic energy for providing more than one thousand years safety, low emission, high performance-price ratio.For waste material transmuting:In different abundance MA Under (secondary actinium series nucleic) fuel, its MA transmuting supports ratio between 1~12, and the waste material that system is produced is neutron toxicity nucleic.It is right In Nuclear fuel breeding:System fuel breeding ratio >=1.2, the ability with propagation Pu;There is large development in Isotope production Space, when the accelerator redundant mode of many sub-critical reactor operations of many Accelerator drivens is extended to this system, system possesses The ability of volume production isotope.For nuclear energy production:When the operation of accelerator redundant mode is extended to this system, including outer neutron Under the energy use in source, its capacity efficiency will maintain an equal level with current presurized water reactor;Involved content, can on the basis of uranium element in text More than one thousand years safety, low emission, the strategic energy of high performance-price ratio are provided, if using thorium fuel, energy total amount can be increased considerably.
The beneficial effect of embodiments of the invention:
1) collect multi-functional operation, effectively the various possible fertile materials including simply dealt spentnuclear fuel are changed For nuclear fuel, the nuclear fission energy of more than one thousand years is supported;Transmuting, deep burnup also make core while burning up most long-life nuke rubbish Amount of waste seldom, is easy to dispose and managed.
2) security of system:The sub-critical reactor inherent safety of system ensures can shutdown automatically, high temperature nuclear reactor under accident conditions Design using passive residual heat discharge system run than existing reactor safety and reliability, reactor simultaneously transmuting, breed Make "hot" material inside and outside heap limited with production capacity, the accident treatment of extremely low probability can be limited in control area.
3) economy:New system reduces the expense to fuel and post processing, and hot operation improves sub-critical reactor production capacity Efficiency is additionally consumed energy with offset accelerator, and factory's manufacture of modularization heap, the refulling cycle of extension heap, which are reduced, to be made, run and provide Originally the cost raised, these optimizations greatly improve the cost performance of system.
4) nuclear fuel security:It is to exclude most of fission that spentnuclear fuel through separating at high temperature, which is processed into fresh fuel process, Product, enrichment in the absence of fissioner and is greatly reduced its radioactivity, and this makes the increase of nuclear proliferation difficulty and action of terror risk Decline to a great extent.

Claims (13)

1. a kind of nuclear power system, including:
First reactor and neutron-producing target, it is anti-that the neutron produced by neutron-producing target makes the first reactor carry out core under subcritical state Should, and after the expiration of the predetermined period of time, the first reactor carries out nuclear reaction under critical conditions.
2. nuclear power system according to claim 1, in addition to:
Second reactor, the neutron produced by neutron-producing target makes the second reactor carry out nuclear reaction under subcritical state, and After the expiration of the predetermined period of time, the second reactor carries out nuclear reaction under critical conditions.
3. nuclear power system according to claim 1 or 2, in addition to:
Proton precessional magnetometer, the proton precessional magnetometer produces proton beam, and the proton beam incident neutron produced by proton precessional magnetometer Target, produces neutron,
It is preferred that the strength range for the proton beam that proton precessional magnetometer is produced is 800MeV~1500MeV.
4. nuclear power system according to claim 1, wherein:
The flux for the neutron that neutron-producing target is produced is 1E+18n/s~3E+18n/s;
Neutron-producing target includes ceramic particle, and the ceramic particle can bear 10MW~30MW beam powers;
The particle diameter of ceramic particle is in millimeter magnitude;And/or
Under at least one in subcritical state and critical condition, the thermal power of the reactor core of the first reactor for 600MW~ 2000MW。
5. nuclear power system according to claim 1, in addition to:
Solid particle, is cooled down using the solid particle as cooling media to the first reactor, subcritical state and is being faced Under at least one in boundary's state, temperature of the cooling media in the outlet of the first reactor is 650~900 DEG C.
6. nuclear power system according to claim 1, in addition to:
Fuel reproduction for core weary material processing post-processes subsystem;And/or
The nuclear power system is nuclear reactor system.
7. a kind of method for controlling nuclear power system, including:
The neutron produced by neutron-producing target makes the first reactor carry out nuclear reaction under subcritical state;And
After the expiration of the predetermined period of time, the first reactor carries out nuclear reaction under critical conditions.
8. the method for control nuclear power system according to claim 7, in addition to:
The neutron produced by neutron-producing target makes the second reactor carry out nuclear reaction under subcritical state.
9. the method for control nuclear power system according to claim 8, in addition to:
After the expiration of the predetermined period of time, the second reactor carries out nuclear reaction under critical conditions.
10. the method for the control nuclear power system according to claim 7 or 8, in addition to:
Proton beam is produced using proton precessional magnetometer;And
The proton beam incident neutron target produced by proton precessional magnetometer, produces neutron,
It is preferred that the strength range for the proton beam that proton precessional magnetometer is produced is 800MeV~1500MeV.
11. the method for control nuclear power system according to claim 7, wherein:
The flux for the neutron that neutron-producing target is produced is 1E+18n/s~3E+18n/s;
Neutron-producing target includes ceramic particle, and the ceramic particle can bear 10MW~30MW beam powers;
The particle diameter of ceramic particle is in millimeter magnitude;And/or
Under at least one in subcritical state and critical condition, the thermal power of the reactor core of the first reactor for 600MW~ 2000MW。
12. the method for control nuclear power system according to claim 7, in addition to:
The first reactor is cooled down as cooling media using solid particle, in subcritical state and critical condition extremely Under few one, temperature of the cooling media in the outlet of the first reactor is 650~900 DEG C.
13. the method for control nuclear power system according to claim 7, wherein:
The nuclear power system is nuclear reactor system.
CN201710329665.0A 2017-05-11 2017-05-11 The method of nuclear power system and control nuclear power system Pending CN107146641A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710329665.0A CN107146641A (en) 2017-05-11 2017-05-11 The method of nuclear power system and control nuclear power system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710329665.0A CN107146641A (en) 2017-05-11 2017-05-11 The method of nuclear power system and control nuclear power system

Publications (1)

Publication Number Publication Date
CN107146641A true CN107146641A (en) 2017-09-08

Family

ID=59777316

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710329665.0A Pending CN107146641A (en) 2017-05-11 2017-05-11 The method of nuclear power system and control nuclear power system

Country Status (1)

Country Link
CN (1) CN107146641A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107767966A (en) * 2017-11-29 2018-03-06 中国科学院近代物理研究所 Nuclear reactor system

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101061552A (en) * 2002-10-25 2007-10-24 通用原子公司 System and method for radioactive waste destruction
CN103096610A (en) * 2012-12-11 2013-05-08 中国科学院近代物理研究所 Coupling system of accelerator and windowless spallation target interface and liquid level stabilizing method
CN103533740A (en) * 2013-03-04 2014-01-22 中国科学院近代物理研究所 Target device for neutron generating device, accelerator-driven neutron generating device and beam coupling method of accelerator-driven neutron generating device
CN104167226A (en) * 2014-09-05 2014-11-26 中国科学院合肥物质科学研究院 Liquid metal cooling reactor experimental system capable of realizing critical and subcritical running test
CN104464842A (en) * 2014-12-22 2015-03-25 中国科学院合肥物质科学研究院 Accelerator driven lead bismuth cooling subcritical traveling wave reactor
CN104751906A (en) * 2015-02-13 2015-07-01 中国科学院近代物理研究所 Heat exchange system and nuclear reactor system
CN205004048U (en) * 2015-09-09 2016-01-27 中国科学院近代物理研究所 Reactive control system and nuclear reactor
US20160027534A1 (en) * 2013-03-15 2016-01-28 Sutherland Cook ELLWOOD Accelerator-driven subcritical reactor system
CN105788666A (en) * 2014-12-23 2016-07-20 福建福清核电有限公司 Nuclear reactor critical process control method

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101061552A (en) * 2002-10-25 2007-10-24 通用原子公司 System and method for radioactive waste destruction
CN103096610A (en) * 2012-12-11 2013-05-08 中国科学院近代物理研究所 Coupling system of accelerator and windowless spallation target interface and liquid level stabilizing method
CN103533740A (en) * 2013-03-04 2014-01-22 中国科学院近代物理研究所 Target device for neutron generating device, accelerator-driven neutron generating device and beam coupling method of accelerator-driven neutron generating device
US20160027534A1 (en) * 2013-03-15 2016-01-28 Sutherland Cook ELLWOOD Accelerator-driven subcritical reactor system
CN104167226A (en) * 2014-09-05 2014-11-26 中国科学院合肥物质科学研究院 Liquid metal cooling reactor experimental system capable of realizing critical and subcritical running test
CN104464842A (en) * 2014-12-22 2015-03-25 中国科学院合肥物质科学研究院 Accelerator driven lead bismuth cooling subcritical traveling wave reactor
CN105788666A (en) * 2014-12-23 2016-07-20 福建福清核电有限公司 Nuclear reactor critical process control method
CN104751906A (en) * 2015-02-13 2015-07-01 中国科学院近代物理研究所 Heat exchange system and nuclear reactor system
CN205004048U (en) * 2015-09-09 2016-01-27 中国科学院近代物理研究所 Reactive control system and nuclear reactor

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
徐雅晨等: "加速器驱动次临界系统(ADS)及其散裂靶的研究现状", 《核科学与技术》 *
李辉波等: "高温氧化挥发法_一种先进乏燃料后处理的首端工艺技术", 《原子能科学技术》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107767966A (en) * 2017-11-29 2018-03-06 中国科学院近代物理研究所 Nuclear reactor system

Similar Documents

Publication Publication Date Title
JP3494652B2 (en) Energy amplifier driven by a particle accelerator for the production of clean nuclear energy
Vijayan et al. Role of thorium in the Indian nuclear power programme
US20070297555A1 (en) Reactor tray vertical geometry with vitrified waste control
US8279994B2 (en) Tokamak reactor for treating fertile material or waste nuclear by-products
US20140064432A1 (en) Particulate metal fuels used in power generation, recycling systems, and small modular reactors
CN104240772B (en) Z constriction drives Fusion-fission energy mix heap
US11342084B2 (en) Passive reactivity control in a nuclear fission reactor
Chen et al. Conceptual study on high performance blanket in a spherical tokamak fusion-driven transmuter
Moir et al. Mirror-based hybrids of recent design
JP2005503568A (en) Radioactive waste conversion method and converter
CN107146641A (en) The method of nuclear power system and control nuclear power system
Moir et al. Axisymmetric magnetic mirror fusion-fission hybrid
Zhang et al. Improved resource utilization by advanced burner reactors with breed-and-burn blankets
Wade et al. ATW neutronics design studies
CN112599259A (en) Fusion-fission hybrid reactor transmutation fuel assembly
Najmabadi et al. The ARIES tokamak fusion reactor study
Wong et al. Blanket design for the ARIES-I tokamak reactor
Asif et al. Advancement of Integral Fast Reactor
Maddox et al. Fuel cycle analysis of a subcritical fast helium-cooled transmutation reactor with a fusion neutron source
KR102523857B1 (en) Molten salt reactor and passive fuel injection method therefor
US20240079153A1 (en) Thermal bridge
Batta et al. Window target unit for the XADS lead-bismuth cooled primary system
Wu et al. Neutronics Design of Hybrid Nuclear Systems
Boyes A neutronic study to reduce the costs of pebble bed reactors by varying fuel compositions
Kotschenreuther et al. Near term fusion-fission hybrids

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170908