CN107140534A - Double-crane lifting construction method for large-grade-difference tower crane - Google Patents
Double-crane lifting construction method for large-grade-difference tower crane Download PDFInfo
- Publication number
- CN107140534A CN107140534A CN201710303577.3A CN201710303577A CN107140534A CN 107140534 A CN107140534 A CN 107140534A CN 201710303577 A CN201710303577 A CN 201710303577A CN 107140534 A CN107140534 A CN 107140534A
- Authority
- CN
- China
- Prior art keywords
- lifting
- crane
- construction
- component
- double
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 60
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 51
- 239000010959 steel Substances 0.000 claims abstract description 51
- 239000000725 suspension Substances 0.000 claims abstract description 23
- 238000013461 design Methods 0.000 claims abstract description 8
- 238000000034 method Methods 0.000 claims description 6
- 230000005484 gravity Effects 0.000 claims description 3
- 238000009434 installation Methods 0.000 abstract description 4
- 230000008901 benefit Effects 0.000 abstract description 3
- 230000002411 adverse Effects 0.000 abstract 1
- 238000004519 manufacturing process Methods 0.000 abstract 1
- 230000009471 action Effects 0.000 description 4
- 230000008569 process Effects 0.000 description 3
- 238000009435 building construction Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000006872 improvement Effects 0.000 description 2
- 238000012544 monitoring process Methods 0.000 description 2
- 241000282326 Felis catus Species 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 238000012937 correction Methods 0.000 description 1
- 230000000916 dilatatory effect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000000686 essence Substances 0.000 description 1
- 238000009408 flooring Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000033764 rhythmic process Effects 0.000 description 1
- 239000003351 stiffener Substances 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
- B66C13/08—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/16—Applications of indicating, registering, or weighing devices
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C15/00—Safety gear
- B66C15/04—Safety gear for preventing collisions, e.g. between cranes or trolleys operating on the same track
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Jib Cranes (AREA)
Abstract
The invention provides a double-crane lifting construction method of a large-grade-difference tower crane, which comprises a construction preparation stage and a component in-place construction stage, wherein the construction preparation stage comprises the steps of load calculation, suspension point position determination, design and manufacture of a lifting carrying pole, selection of lifting ropes and clamping rings and the like; the in-place construction stage comprises the steps of arranging lifting lugs, hanging the components on the hoisting carrying poles through the lifting lugs, preparing before hoisting, hoisting by two machines, and the like. The invention uses the tower crane with large range difference to lift and hang, can effectively avoid the lifting blind area when two tower cranes with the same model carry out double-crane lifting and the adverse factors of crane type selection and arrangement, avoid increasing the steel structure member section, and reduce the steel structure deepening design difficulty; the construction method has the advantages that the field construction machinery is utilized to the maximum extent, the investment and the use of temporary installation mechanical equipment are reduced, the construction period is effectively shortened, the construction cost is saved, and the substantial characteristics and the remarkable progress are realized.
Description
Technical field
The present invention relates to technical field of building construction, and in particular to a kind of big differential derrick crane double-machine lifting crane construction party
Method.
Background technology
At present in technical field of building construction, for the installation of super-heavy component, appoint when a crane can not complete lifting
During business, generally lifted using two model derrick cranes of the same race, this arrangement and method for construction can not during practice of construction
Evade derrick crane lifting blind area, and can also be limited by crane type.Using lifting for big differential derrick crane
Construction, can greatly utilize live existing construction machinery, effectively shorten the construction period, save construction cost, realize
The elementary object of green construction and increase construction benefit, also provides beneficial reference for similar engineering construction.
The content of the invention
The present invention proposes a kind of big differential derrick crane for installation at present in construction for super-heavy component
Double-machine lifting crane construction method, to solve the lifting blind area that can not evade when two model derrick cranes of the same race carry out double-machine lifting crane
Etc. technical problem.
The technical proposal of the invention is realized in this way:A kind of big differential derrick crane double-machine lifting crane construction method, bag
Construction in Preparatory Stage and component construction stage in place are included, wherein, Construction in Preparatory Stage comprises the following steps:
S01)LOAD FOR:According to construction weight and the maximum hoisting weight and brachium of two derrick cranes, two towers are determined
Formula craning weight of same is distributed and component suspension centre region, draws lifting route;
S02)Determine hoisting point position:According to component suspension centre region and Components Shape, suspension centre is arranged symmetrically, and ensure component during lifting
Center is in suspension centre position of centre of gravity;
S03)Select hoisting rope tool and snap ring:According to construction weight and hoisting point position, select quick detachable and meet force request
Hoisting rope and snap ring;
The component construction stage in place comprises the following steps:
T01)Hanger is set:In hoisting point position, component hanger is set;
T02)Lift preceding preparation:Component is hung and stops lifting after 200 ~ 300mm of ground, stability, the braking of crane is checked
Fastness of the reliability of device, the balance of component and colligation etc.;
T03)Double-machine lifting crane:Two derrick cranes should act in agreement, cooperation, and component is slowly lifted to regard to site;
In Construction in Preparatory Stage S02)And S03)Between step, in addition to step S02a)Design and making lifting shoulder pole:According to rise
Hoisting point position and force analysis, design and make suitable lifting shoulder pole;
In component construction stage T01 in place)And T02)Between step, in addition to step T01a)Component is hanged by component hanger
Hang on lifting shoulder pole.
The lifting shoulder pole is H profile steel beam.
The two ends of the H profile steel beam are arranged with shoulder pole hanger.
Multiple lift heavy adjustment holes are provided with the web of the H profile steel beam, in the both sides of the web provided with lifting clamping plate,
The lower end of the lifting clamping plate is fixed on the lift heavy adjustment hole by connecting pivot pin, and the upper end of the lifting clamping plate is by hanging
Dress pivot pin is fixed.Be distributed according to the suspension centre of component and two derrick cranes hoisting weight distribution, lifting clamping plate can with not
Same lift heavy adjustment hole connection, so as to reach rational load distribution.
The lifting pivot pin hoisting component that two derrick cranes pass through the lifting clamping plate upper end.
When distributing load, in order to ensure construction safety, each derrick crane distributes lift heavy can not be specified more than its
The 80% of lifting capacity.
In component construction stage T01a in place)And T02)Between step, in addition to step T01b)Examination is hung:In double-machine lifting crane
Rehearsal is hung in preceding progress examination, and the specific operation route for determining component is hung according to examination.The emphasis that rehearsal is hung in examination is to coordinate two tower
The running speed of heavy-duty machine and the lifting speed of component, it is ensured that coordination is unified.
In step T03)In also include, need to be using prior when lifting components are to regard to location proximate or close to other objects
The cable rope being arranged on component carries out traction guiding, it is to avoid crash, and reduces potential safety hazard.
The advantage of the invention is that:Lifted using big extreme difference derrick crane, can effectively evade two models of the same race tower
Crane carries out the unfavorable factor for lifting blind area and crane type selecting and arrangement during double-machine lifting crane, it is to avoid increase steel structure member
Merogenesis, reduces steel construction Deepen Design difficulty;To the utmost using site operation machinery, interim installation plant equipment is reduced
Put into and use, effectively shorten the construction period, saved construction cost, with prominent substantive distinguishing features and marked improvement.
Brief description of the drawings
In order to illustrate the embodiments of the present invention more clearly, the accompanying drawing used required in being described below to embodiment makees letter
Singly introduce, it should be apparent that, drawings in the following description are only some embodiments of the present invention, for the common skill in this area
For art personnel, on the premise of not paying creative work, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is a kind of big differential derrick crane double-machine lifting crane construction schematic diagram of the present invention;
Fig. 2 is I partial enlarged drawing;
Fig. 3 is lifting shoulder pole structural representation;
Fig. 4 is A-A sectional views;
Fig. 5 is B-B sectional views;
Fig. 6 is that steel column suspension centre sets schematic diagram;
Marked in figure:1st, whipping crane;2nd, flat boom crane;3rd, steel column;4th, shoulder pole is lifted;5th, component hanger;6th, shoulder pole
Hanger;7th, lift heavy adjustment hole;8th, clamping plate is lifted by crane;9th, pivot pin is connected;10th, pivot pin is lifted;11st, flat boom crane suspension centre;12nd, swing arm
Crane suspension centre.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete
Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments.It is based on
Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under the premise of creative work is not made
Embodiment, belongs to the scope of protection of the invention.
In this engineering, two derrick cranes are respectively a whipping crane 1(Model:L500)And a flat arm lifting
Machine 2(Model:TC6010), it is necessary to which the component of lifting is steel column 3.Because the bracket quantity of steel column 3 and stiffener quantity are different,
Steel column 3 is caused to vary in weight, the maximum single amount of steel column 3 is 12.6t, and steel column 3 is with regard to site maximum distance whipping crane 1
52.4m, every layer has four steel columns 3 to carry out double-machine lifting crane.
Before formal construction, Construction in Preparatory Stage is initially entered, Construction in Preparatory Stage comprises the following steps:
LOAD FOR:Only for part is most reconstructed, according to the arrangement and the radius of clean-up of derrick crane, the lifting to steel column 3
Position and change hook position and arranged accordingly, and to drafting and the meter in place for having carried out route map of every steel column 3
Calculate.To ensure the distribution of derrick crane lift heavy in controlled range, flat boom crane 2 is wireless using rear-mounted in hoisting process
The tower crane multifunctional monitoring instrument being equipped with electronic scale, whipping crane 1 is controlled to lifting capacity.
Determine that suspension centre is set:Suspension centre keeps symmetrical, it is ensured that during lifting member center in suspension centre position of centre of gravity to ensure to lift
When steel column 3 it is smoothly in place.During big differential tower crane double-machine lifting crane, three Hes of whipping crane suspension centre 12 are set on steel column 3
Three flat boom crane suspension centres 11.
Design and making lifting shoulder pole:Because the diameter of steel column 3 lifted only has 1400mm, itself do not possess while hanging two
The condition of platform tower crane, in order to ensure the security of hoisting process, lifting steel column 3 need to be changed using lifting shoulder pole 4, i.e., from one
Bar rigidity meets the H profile steel beam for lifting requirement as shoulder pole, and lift heavy is allocated by lifting shoulder pole 4, to ensure lifting
Security.The two ends of lifting shoulder pole 4 are arranged with shoulder pole hanger 6, and steel column 3 is suspended on the lower section of shoulder pole hanger 6.Lift shoulder pole
4 web is provided with multiple lift heavy adjustment holes 7, and in the both sides of web provided with lifting clamping plate 8, the lower end for lifting by crane clamping plate 8 passes through even
Spindle pin 9 is fixed on lift heavy adjustment hole 7, and the upper end of lifting clamping plate 8 is fixed by lifting pivot pin 10.Two derrick cranes lead to
Cross the hoisting component of lifting pivot pin 10 of lifting clamping plate 8 upper end.With two derrick cranes is distributed according to the suspension centre of steel column 3
Lift heavy amount is distributed, and lifting clamping plate 8 can be connected from different lift heavy adjustment holes 7, so as to reach rational load distribution.
Select hoisting rope tool and snap ring:Arranged according to the weight and component hanger 5 of most heavy steel column 3, through adjusting, steel column
During 3 lifting, using shared four 4m steel wire ropes, snap ring uses 6.5t bow shackles.
After the completion of above preparation, into the component construction stage in place, the component construction stage comprises the following steps:
Hanger is set:In hoisting point position welded unit hanger 5.
Steel column 3 is suspended on shoulder pole hanger 6 by component hanger 5.
Examination is hung:Examination is carried out before formal lift and hangs rehearsal, first checks for derrick crane rope tool and whether brake apparatus pacifies
It is complete reliable, the specific operation route for determining steel column 3 is then hung according to examination.
Lift preceding preparation:Before lifting, steel column 3 should be disposed across on chock;When lifting, steel column 3 must not be made on ground
On have dilatory phenomenon;, it is necessary to certain height during revolution;Hook up, rotate, mobile three actions are alternately slowly carried out, when in place
Slow whereabouts, prevents from spoiling bolt silk mouth.When starting to lift, stop after steel column 3 first should being hung into 200 ~ 300mm of ground
Hang, and check the stability of crane, the reliability of brake apparatus, the balance of component and fastness of colligation etc., it is to be confirmed
After errorless, lifting can be continued, the component sling must not be stagnated in the air for a long time.
Double-machine lifting crane:With the commander of signalman, steel column 3 is slowly hung to double-machine lifting crane starting point by whipping crane 1, this
When the position of steel column 3, the central point with regard to site and whipping crane 1 should be on straight line.Whipping crane 1 is slowly
Lower hook, steel column 3 is transferred to flooring about 300mm positions, while full place mat puts the high left and right flitches of 300mm below steel column 3.
Flat boom crane 2 with hook under signalman to shoulder pole hanger 6 at.Under the commander of signalman, flat boom crane 2 is slowly hooked up, together
Shi Tasi should pay close attention to instrument board reading on whipping crane 1(Lift heavy is distributed no more than pre-determined tower crane).This was operated
Cheng Wei:Flat boom crane 2 is slowly hooked up(Hook up speed preferably≤3m/min), flat arm lifting is determined using wireless telecontrol electronic scale
The lift heavy of machine 2, to ensure the flat lift heavy of boom crane 2 no more than the lift heavy that this position is distributed, while hanging jack on whipping crane 1
Two suspension centres in, the jack of the nearly flat suspension centre of boom crane 2, which is performed, receives jack action, and the jack of the remote flat suspension centre of boom crane 2 is held
Capable chain action of falling, treats that two derrick cranes distribution lift heavys reach pre-determined distribution lift heavy, and the shaft of steel column 3 is protected
Hold it is vertical after, whipping crane 1 is slowly lain prone along pre-determined route bar and to be hooked up, the flat correspondence of boom crane 2 rhythm of whipping crane 1
Slow rotation, reclaim dolly, two derrick cranes should act in agreement, matching coordinative, keep steel column 3 along pre-determined route just
Position, while keeping itself lift heavy to be no more than is determined in advance apportioning cost.To ensure that itself lift heavy is no more than itself lift heavy apportioning cost,
Wireless telecontrol electronic scale is used on flat boom crane 2, the flat lift heavy of boom crane 2 is remained at the reliable of specified lift heavy 80%
Under monitoring.After double-machine lifting crane to after with regard to above site, two derrick cranes stop all actions simultaneously, treat the post of steel column 3
After body keeps vertical steady, with the commander of signalman, two derrick cranes act in agreement lower hook, and steel column 3 is slow in place.
Anticollision measure is taken in the hoisting process of steel column 3, i.e., is adopted in the lifting of steel column 3 close in place or during close to other objects
Traction guiding is carried out with the cable wind rope being arranged in advance on steel member, it is to avoid accident occurs for collision.After steel column 3 is lifted in place,
It should be connected firmly in time with lower segmented column shaft, it is ensured that after safety, workmen can carry out tower upwards along shaft steel cat ladder
Heavy-duty machine suspension hook uncoupling.During uncoupling, uncoupling operating personnel must hang up properly catching device, while hanging up properly safety belt.Steel column 3 is lifted
To on-station position, install after interim connecting bolt, by regulation measures such as jack, jack, under the observation of total powerstation, complete
The preliminary corrections of steel column 3.So far, the double-machine lifting crane construction of whole steel column 3 is finished.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention
God is with principle, and any modification, equivalent substitution and improvements made etc. should be included in the scope of the protection.
Claims (8)
1. a kind of big differential derrick crane double-machine lifting crane construction method, including Construction in Preparatory Stage and component are constructed rank in place
Section, wherein, Construction in Preparatory Stage comprises the following steps:
S01)LOAD FOR:According to construction weight and the maximum hoisting weight and brachium of two derrick cranes, two towers are determined
Formula craning weight of same is distributed and component suspension centre region, draws operation route;
S02)Determine hoisting point position:According to component suspension centre region and Components Shape, suspension centre is arranged symmetrically, and ensure component during lifting
Center is in suspension centre position of centre of gravity;
S03)Select hoisting rope tool and snap ring:According to construction weight and hoisting point position, select quick detachable and meet force request
Hoisting rope and snap ring;The component construction stage in place comprises the following steps:
T01)Hanger is set:In hoisting point position, component hanger is set;
T02)Lift preceding preparation:Component is hung and stops lifting after 200 ~ 300mm of ground, stability, the braking of crane is checked
Fastness of the reliability of device, the balance of component and colligation etc.;
T03)Double-machine lifting crane:Two derrick cranes should act in agreement, cooperation, and component is slowly lifted to regard to site;Its
It is characterised by:In Construction in Preparatory Stage S02)And S03)Between step, in addition to step S02a)Design and making lifting shoulder pole:
According to Heave Here position and force analysis, design and make suitable lifting shoulder pole;
In component construction stage T01 in place)And T02)Between step, in addition to step T01a)Component is hanged by component hanger
Hang on lifting shoulder pole.
2. a kind of big differential derrick crane double-machine lifting crane construction method according to claim 1, it is characterised in that:It is described
Lifting shoulder pole is H profile steel beam.
3. a kind of big differential derrick crane double-machine lifting crane construction method according to claim 2, it is characterised in that:It is described
The two ends of H profile steel beam are arranged with shoulder pole hanger.
4. a kind of big differential derrick crane double-machine lifting crane construction method according to claim 3, it is characterised in that:Institute
The web for stating H profile steel beam is provided with multiple lift heavy adjustment holes, in the both sides of the web provided with lifting clamping plate, the lifting clamping plate
Lower end be fixed on by connecting pivot pin on the lift heavy adjustment hole, it is described lifting clamping plate upper end fixed by lifting pivot pin.
5. a kind of big differential derrick crane double-machine lifting crane construction method according to claim 4, it is characterised in that:Two
The lifting pivot pin hoisting component that derrick crane passes through the lifting clamping plate upper end.
6. a kind of big differential derrick crane double-machine lifting crane construction party according to any claim in claim 1 ~ 5
Method, it is characterised in that:Each derrick crane, which distributes lift heavy, can not be more than the 80% of its rated load weight.
7. a kind of big differential derrick crane double-machine lifting crane construction method according to claim 6, it is characterised in that:In structure
Part construction stage T01a in place)And T02)Between step, in addition to step T01b)Examination is hung:Progress examination, which is hung, before double-machine lifting crane drills
Practice, the specific operation route for determining component is hung according to examination.
8. a kind of big differential derrick crane double-machine lifting crane construction method according to claim 7, it is characterised in that:In step
Rapid T03)In also include, need to be using being arranged in advance on component when lifting components are to regard to location proximate or close to other objects
Cable rope carry out traction guiding.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710303577.3A CN107140534A (en) | 2017-05-03 | 2017-05-03 | Double-crane lifting construction method for large-grade-difference tower crane |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710303577.3A CN107140534A (en) | 2017-05-03 | 2017-05-03 | Double-crane lifting construction method for large-grade-difference tower crane |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107140534A true CN107140534A (en) | 2017-09-08 |
Family
ID=59775307
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710303577.3A Pending CN107140534A (en) | 2017-05-03 | 2017-05-03 | Double-crane lifting construction method for large-grade-difference tower crane |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107140534A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108408594A (en) * | 2018-05-15 | 2018-08-17 | 福建省工业设备安装有限公司 | A kind of two-shipper lifting load smart allocation formula balance system and control method |
CN112758803A (en) * | 2021-01-18 | 2021-05-07 | 张鸿杰 | Overhead hook replacement technology for hoisting prefabricated box girder |
CN113919794A (en) * | 2021-08-23 | 2022-01-11 | 北京市机械施工集团有限公司 | Method for rapidly analyzing lifting capacity of components in batches |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4631893A (en) * | 1983-01-26 | 1986-12-30 | Trus-Us Inc. | Single story house addition structure and method |
CN201882763U (en) * | 2010-11-30 | 2011-06-29 | 南京梅山冶金发展有限公司 | Special carrying pole type beam of double-machine lifting crane |
CN204342250U (en) * | 2014-12-24 | 2015-05-20 | 中国化学工程第三建设有限公司 | A kind of multi-state hoisting balance beam |
CN104878928A (en) * | 2015-04-29 | 2015-09-02 | 中国十七冶集团有限公司 | Method for integrally hoisting steel structure galleries across factory buildings in place by aid of multiple machines |
-
2017
- 2017-05-03 CN CN201710303577.3A patent/CN107140534A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4631893A (en) * | 1983-01-26 | 1986-12-30 | Trus-Us Inc. | Single story house addition structure and method |
CN201882763U (en) * | 2010-11-30 | 2011-06-29 | 南京梅山冶金发展有限公司 | Special carrying pole type beam of double-machine lifting crane |
CN204342250U (en) * | 2014-12-24 | 2015-05-20 | 中国化学工程第三建设有限公司 | A kind of multi-state hoisting balance beam |
CN104878928A (en) * | 2015-04-29 | 2015-09-02 | 中国十七冶集团有限公司 | Method for integrally hoisting steel structure galleries across factory buildings in place by aid of multiple machines |
Non-Patent Citations (1)
Title |
---|
徐健 等: "大级差塔式起重机超重构件85m超远吊装施工技术", 《施工技术》 * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108408594A (en) * | 2018-05-15 | 2018-08-17 | 福建省工业设备安装有限公司 | A kind of two-shipper lifting load smart allocation formula balance system and control method |
CN108408594B (en) * | 2018-05-15 | 2024-05-28 | 福建省工业设备安装有限公司 | Control method of intelligent distribution type balance system for double-machine hoisting load |
CN112758803A (en) * | 2021-01-18 | 2021-05-07 | 张鸿杰 | Overhead hook replacement technology for hoisting prefabricated box girder |
CN112758803B (en) * | 2021-01-18 | 2023-12-22 | 张鸿杰 | Method for hanging prefabricated box girder and changing hooks in air |
CN113919794A (en) * | 2021-08-23 | 2022-01-11 | 北京市机械施工集团有限公司 | Method for rapidly analyzing lifting capacity of components in batches |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103043526B (en) | Integral hoisting device and method for super-long steel reinforcement cage of underground continuous wall | |
CN106081870B (en) | A kind of nuclear power station steel dome balances hanging method | |
CN103523683B (en) | Construction method for dismantling tower crane by use of small hoisting equipment | |
CN107140534A (en) | Double-crane lifting construction method for large-grade-difference tower crane | |
CN103832933B (en) | A kind of group tower tower crane with auxiliary | |
CN203728443U (en) | Combined tower crane with main and auxiliary boom structure | |
CN206970045U (en) | A kind of construction hanging device | |
CN108275561B (en) | Active lower shaft rotation hoisting tool | |
CN100567129C (en) | A kind of hoisting device for loop wheel machine | |
CN107720569B (en) | A kind of dismounting inner climbing crane tower is hung with masts type roofing | |
CN103086276B (en) | Construction method for hoisting bridge type crane in high-rise well tower type building | |
CN205603125U (en) | Special hoist device that horizontal water tube cooler heat exchange tube was changed | |
CN103979442B (en) | The method of 6400 tons of Hydraulic double-type crane lifting cost tropsch reactors | |
CN109607384A (en) | The turn-over method of super-large-diameter shield machine knife disk | |
CN110409803A (en) | Dismantle the hanging method of hydraulic mould lifting device center drum circle | |
CN201762053U (en) | Simple automatic hoisting rod | |
CN2910879Y (en) | Single hook four points self-balancing sling of lifter | |
CN207608190U (en) | A kind of major diameter surge shaft brill filling cantilever trolley | |
CN206126652U (en) | Balanced hoist device of nuclear power station steel dome | |
CN201099586Y (en) | Crane lifting device | |
CN203474321U (en) | Tower crane used for constructing and erecting electric transmission line iron towers | |
CN220596780U (en) | Main cage lifting device of reinforcement cage | |
CN106081871A (en) | A kind of nuclear power station steel dome balance crane assembling device | |
CN221625806U (en) | Hoisting structure of air conditioner of passenger car | |
CN214780584U (en) | High-altitude operation lifting device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170908 |
|
RJ01 | Rejection of invention patent application after publication |