CN107100196A - Spell the combined method in many cabins in box culvert list cabin - Google Patents

Spell the combined method in many cabins in box culvert list cabin Download PDF

Info

Publication number
CN107100196A
CN107100196A CN201710252943.7A CN201710252943A CN107100196A CN 107100196 A CN107100196 A CN 107100196A CN 201710252943 A CN201710252943 A CN 201710252943A CN 107100196 A CN107100196 A CN 107100196A
Authority
CN
China
Prior art keywords
cabin
culvert
cabins
box
interconnected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710252943.7A
Other languages
Chinese (zh)
Inventor
李冀龙
荣文婷
孙成涛
李航
吕兆锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongxin Road & Bridge Material Co Ltd
Original Assignee
Zhongxin Road & Bridge Material Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongxin Road & Bridge Material Co Ltd filed Critical Zhongxin Road & Bridge Material Co Ltd
Priority to CN201710252943.7A priority Critical patent/CN107100196A/en
Publication of CN107100196A publication Critical patent/CN107100196A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Chemical & Material Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Compositions Of Macromolecular Compounds (AREA)

Abstract

The present invention relates to the combined method that many cabins are spelled in box culvert list cabin, belong to box and duct works technical field, including:Concrete floor, No. three culvert cabins, a culvert cabin and No. two culvert cabins, concrete floor is laid on ground, a number culvert cabin is interconnected to by box culvert, No. two culvert cabins are interconnected to by box culvert, contain cabin laminating for No. two to be arranged on the right side of a culvert cabin, contain at No. two on the right side of cabins or No. one contains directly over cabin or No. two contain directly over cabins or No. one contains cabin and contains with No. two above the seams of cabin, laminating is provided with No. three culvert cabins that box culvert is interconnected to.Flexible connection is employed between culvert of the present invention and solves side culvert because soil settles the phenomenon that breakage causes adjacent culvert to be destroyed, while being provided with modified asphalt waterproof layer between adjacent culvert, the problem of adjacent side's leak of culvert one influences the opposing party is solved.

Description

Spell the combined method in many cabins in box culvert list cabin
Technical field
The present invention relates to the combined method that many cabins are spelled in box culvert list cabin, belong to box and duct works technical field.
Background technology
Prefabricated reinforced concrete box culvert is as by electric power, communication, and the various utilities pipelines such as combustion gas, heat supply, plumbing are combined in The tunnel space of one, constructs more convenient, compares pipe culvert more economical.At present, many compartment-boxs, which contain the adjacent culvert cabin constituted, kind It is proposed with carrying out rigid connection each other by bolt, this connected mode has the drawback that, when a side contains cabin because of ground soil Earth sedimentation causes to damage, and adjacent rigid connection can be influenceed to contain cabin while causing damage in various degree, form unnecessary loss.
The content of the invention
The invention aims to solve above-mentioned technical problem, and then the combined method in many cabins is spelled in offer box culvert list cabin, Box culvert system stability is improved, it is cost-effective.
Technical scheme:
The combined method in many cabins is spelled in box culvert list cabin, is comprised the following steps,
Step 1: laying concrete floor on ground;
Step 2: on concrete floor, a culvert cabin is interconnected to by box culvert;
Step 3: on concrete floor, being interconnected to No. two culvert cabins by box culvert, containing cabin laminating for No. two and be arranged on one Number contain the right side of cabin 1;
Step 4: No. two contain cabins on the right side of or No. one contain cabin directly over No. two contain cabins directly over or No. one contain cabin with No. two Contain above the seam of cabin, laminating is provided with No. three culvert cabins that box culvert is interconnected to.
Further, described No. one connected modes contained between cabin, No. two culvert cabins and No. three culvert compartment-boxs culverts are identical.
Further, No. two culverts cabin, a culvert cabin and No. three are provided with modified asphalt waterproof floor between containing cabins.
The invention has the advantages that:
Flexible connection is employed between present invention culvert cabin and solves side culvert cabin because soil sedimentation breakage causes adjacent culvert cabin The phenomenon destroyed, while being provided with modified asphalt waterproof layer between adjacent culvert cabin, solves the adjacent side's leak shadow of culvert cabin one The problem of ringing the opposing party.
Brief description of the drawings
Fig. 1 is the structural representation of the embodiment of the present invention one;
Fig. 2 is the structural representation of the embodiment of the present invention two;
Fig. 3 is the structural representation of the embodiment of the present invention three;
Fig. 4 is the structural representation of the embodiment of the present invention four.
Embodiment
Below with reference to accompanying drawing, the present invention is described in detail.
Embodiment one, with reference to the accompanying drawings 1:
The combined method in many cabins is spelled in box culvert list cabin, is comprised the following steps,
Step 1: laying concrete floor 3 on ground;
Step 2: on concrete floor 3, a culvert cabin 1 is interconnected to by box culvert;
Step 3: on concrete floor 3, being interconnected to No. two culvert cabins 2 by box culvert, containing the laminating of cabin 2 for No. two and set Contain the right side of cabin 1 at No. one;
Step 4: containing the right side of cabin 2 at No. two, laminating is provided with No. three culvert cabins 4 that box culvert is interconnected to.
Described No. one connected modes contained between cabin 1, No. two culvert cabins 2 and No. three culvert box culverts of cabin 4 are identical.No. two culverts cabin 2nd, a culvert cabin 1 and No. three culvert cabins 4 are provided with modified asphalt waterproof floor each other.
Embodiment two, with reference to the accompanying drawings 2:
The combined method in many cabins is spelled in box culvert list cabin, is comprised the following steps,
Step 1: laying concrete floor 3 on ground;
Step 2: on concrete floor 3, a culvert cabin 1 is interconnected to by box culvert;
Step 3: on concrete floor 3, being interconnected to No. two culvert cabins 2 by box culvert, containing the laminating of cabin 2 for No. two and set Contain the right side of cabin 1 at No. one;
Step 4: No. one contains directly over cabin 1, laminating is provided with No. three culvert cabins 4 that box culvert is interconnected to.
Described No. one connected modes contained between cabin 1, No. two culvert cabins 2 and No. three culvert box culverts of cabin 4 are identical.No. two culverts cabin 2nd, a culvert cabin 1 and No. three culvert cabins 4 are provided with modified asphalt waterproof floor each other.
Embodiment three, with reference to the accompanying drawings 3:
The combined method in many cabins is spelled in box culvert list cabin, is comprised the following steps,
Step 1: laying concrete floor 3 on ground;
Step 2: on concrete floor 3, a culvert cabin 1 is interconnected to by box culvert;
Step 3: on concrete floor 3, being interconnected to No. two culvert cabins 2 by box culvert, containing the laminating of cabin 2 for No. two and set Contain the right side of cabin 1 at No. one;
Step 4: No. two contain directly over cabin 2, laminating is provided with No. three culvert cabins 4 that box culvert is interconnected to.
Described No. one connected modes contained between cabin 1, No. two culvert cabins 2 and No. three culvert box culverts of cabin 4 are identical.No. two culverts cabin 2nd, a culvert cabin 1 and No. three culvert cabins 4 are provided with modified asphalt waterproof floor each other.
Example IV, with reference to the accompanying drawings 4:
The combined method in many cabins is spelled in box culvert list cabin, is comprised the following steps,
Step 1: laying concrete floor 3 on ground;
Step 2: on concrete floor 3, a culvert cabin 1 is interconnected to by box culvert;
Step 3: on concrete floor 3, being interconnected to No. two culvert cabins 2 by box culvert, containing the laminating of cabin 2 for No. two and set Contain the right side of cabin 1 at No. one;
Step 4: No. one contains above cabin 1 and No. two culvert seams of cabin 2, laminating is provided with box culvert is interconnected to three Number contain cabin 4.
Described No. one connected modes contained between cabin 1, No. two culvert cabins 2 and No. three culvert box culverts of cabin 4 are identical.No. two culverts cabin 2nd, a culvert cabin 1 and No. three culvert cabins 4 are provided with modified asphalt waterproof floor each other.

Claims (3)

1. the combined method in many cabins is spelled in box culvert list cabin, it is characterised in that comprised the following steps,
Step 1: laying concrete floor (3) on ground;
Step 2: on concrete floor (3), being interconnected to No. one by box culvert and containing cabin (1);
Step 3: on concrete floor (3), being interconnected to No. two by box culvert and containing cabin (2), contain cabin (2) laminating for No. two and set Put and contain at No. one on the right side of cabin (1);
Step 4: containing at No. two on the right side of cabin (2) or directly over culvert cabin (1) or directly over No. two culverts cabin (2) or culvert cabin (1) contain with No. two above cabin (2) seam, laminating is provided with No. three culverts cabin (4) that box culvert is interconnected to.
2. the combined method in many cabins is spelled in box culvert list cabin according to claim 1, it is characterised in that culvert cabin (1), No. two connected modes contained between cabin (2) and No. three culvert cabin (4) box culverts are identical.
3. the combined method in many cabins is spelled in box culvert list cabin according to claim 1, it is characterised in that No. two culverts cabin (2), Contain for No. one and be provided with modified asphalt waterproof floor between cabin (1) and No. three culverts cabin (4).
CN201710252943.7A 2017-04-18 2017-04-18 Spell the combined method in many cabins in box culvert list cabin Pending CN107100196A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710252943.7A CN107100196A (en) 2017-04-18 2017-04-18 Spell the combined method in many cabins in box culvert list cabin

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710252943.7A CN107100196A (en) 2017-04-18 2017-04-18 Spell the combined method in many cabins in box culvert list cabin

Publications (1)

Publication Number Publication Date
CN107100196A true CN107100196A (en) 2017-08-29

Family

ID=59656668

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710252943.7A Pending CN107100196A (en) 2017-04-18 2017-04-18 Spell the combined method in many cabins in box culvert list cabin

Country Status (1)

Country Link
CN (1) CN107100196A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103132594A (en) * 2011-11-21 2013-06-05 旭混凝土工业株式会社 Joining method of concrete structure
CN105756089A (en) * 2016-03-17 2016-07-13 上海同预建筑科技有限公司 Transverse laminated connection type single compartment precast multiple-compartment assembled comprehensive pipe gallery
CN205662945U (en) * 2016-06-05 2016-10-26 傅琼阁 Precast concrete piping lane
KR101682541B1 (en) * 2016-02-25 2016-12-07 대실테크 주식회사 Culvert crossing buried pipeline construction and pipeline laying method using the same

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103132594A (en) * 2011-11-21 2013-06-05 旭混凝土工业株式会社 Joining method of concrete structure
KR101682541B1 (en) * 2016-02-25 2016-12-07 대실테크 주식회사 Culvert crossing buried pipeline construction and pipeline laying method using the same
CN105756089A (en) * 2016-03-17 2016-07-13 上海同预建筑科技有限公司 Transverse laminated connection type single compartment precast multiple-compartment assembled comprehensive pipe gallery
CN205662945U (en) * 2016-06-05 2016-10-26 傅琼阁 Precast concrete piping lane

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
安晶等: "《建筑材料》", 31 July 2016 *
雷升祥等: "《综合管廊与管道盾构》", 31 July 2015, 中国铁道出版社 *

Similar Documents

Publication Publication Date Title
CN105350572B (en) Assembled underground pipe gallery
CN102734556B (en) Trenchless construction method for power pipes
CN105113354B (en) Suitable for the pre-buried pipeline of pavement shallow
CN207176738U (en) A kind of staggered joint erection comprehensive pipe gallery structure based on prestress system
WO2017071113A1 (en) Cement-soil mixing pile protected underground pipe gallery
CN203583526U (en) Waterproof structure of peat soft soil stratum subway station
CN104963705A (en) Underground space excavating and constructing method
CN104947708A (en) Combined foundation bed for immersed tube tunnels and construction method thereof
CN105926422B (en) The monolithic construction of bridge and underground pipe gallery and its construction method
CN105525632A (en) Waterproof structure for bellmouths and sockets of fabricated prefabricated composite pipe gallery
CN206157762U (en) Prefabricate piecemeal assembled utility tunnel entirely
CN104482298A (en) HDPE (high-density polyethylene) steel-plastic composite spiral winding drainage pipe installation construction method
CN105401593A (en) Assembly type square underground pipe gallery
KR101820872B1 (en) Reinforcement and waterproof structure of vertical shafts-utility tunnels interface
CN107134660A (en) Underground pipe gallery electrical grounding net
CN108661075A (en) Assembled underground one corridor
CN207378273U (en) A kind of direct-buried thermal insulation pipe duct device
CN105065040A (en) Top-plate-prefabricated underground space underground excavation building method
CN105041348A (en) Underground space subsurface excavation construction method adopting combined roof
CN107100196A (en) Spell the combined method in many cabins in box culvert list cabin
CN205224088U (en) Cement mixing method protection underground pipe gallery
CN208123740U (en) Vertical reinforcement concrete connectors reinforce regularization hoop bracket system
CN104294859A (en) Stability judgment method of foundation pit basal-heave resistant system
CN103595001A (en) Composite reinforced HDPE cable sheath tube
CN207298164U (en) A kind of socket joint type pipeline socket connecting elements

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170829