CN107100078B - A kind of packaged type bridges Precast Pier Columns component installation method - Google Patents

A kind of packaged type bridges Precast Pier Columns component installation method Download PDF

Info

Publication number
CN107100078B
CN107100078B CN201710357824.8A CN201710357824A CN107100078B CN 107100078 B CN107100078 B CN 107100078B CN 201710357824 A CN201710357824 A CN 201710357824A CN 107100078 B CN107100078 B CN 107100078B
Authority
CN
China
Prior art keywords
precast pier
pier columns
precast
columns
jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710357824.8A
Other languages
Chinese (zh)
Other versions
CN107100078A (en
Inventor
杨根明
吴玮
罗利
唐丽君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN201710357824.8A priority Critical patent/CN107100078B/en
Publication of CN107100078A publication Critical patent/CN107100078A/en
Application granted granted Critical
Publication of CN107100078B publication Critical patent/CN107100078B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Abstract

The invention discloses a kind of packaged type bridges Precast Pier Columns component installation method, on the cushion cap that the accurate assembly of Precast Pier Columns has been poured in advance, and pier stud is set between Precast Pier Columns and cushion cap and sits slurry, comprising steps of marking docking label before Precast Pier Columns are in place;According to absolute altitude, center cushion block is placed;After hoisting prefabricated pier stud inserts the reserved steel bar on people's cushion cap, docking label is aligned one by one;Adjusting jack is placed, loop wheel machine unloads power, transfers in Precast Pier Columns to center cushion block;Precast Pier Columns verticality is adjusted using jack until meeting design requirement, locks jack, and the piston stroke and pier stud for recording jack sit slurry thickness;Hang Precast Pier Columns;Installation prepares the grouting template that pier stud sits slurry on cushion cap, sits slurry thickness data according to measurement pier stud and prepares grouting material, perfusion pier stud sits slurry, it is formal in place: and then loop wheel machine transfers Precast Pier Columns, Precast Pier Columns are accurately in place, lock jack, it is conserved, is installed by grout hole grouting material.

Description

A kind of packaged type bridges Precast Pier Columns component installation method
Technical field
The present invention relates to a kind of building engineering fields, and in particular to a kind of packaged type bridges Precast Pier Columns component installation side Method.
Background technique
With in Urban Bridge or pier stud construction precast assembly construction technology it is universal, reinforced bar sleeve be in the milk interconnection technique by Gradually it is applied in the vertical connection of the precast concretes such as Precast Pier Columns, prefabricated bent cap.But it is filled using reinforced bar sleeve Starch interconnection technique Precast Pier Columns (that is, pier stud), due to the complexity and high-precision requirement of its assembling construction process, always no To extensive practical application.In the precast assembly process of conventional house building, it can accurately be controlled by the method for axis location Splicing and positioning between prefabricated components processed.Precast Pier Columns in overhead girder, height are differed from more than ten rice to more than tens rice, real Border weight is unable to accurately control the splicing and positioning of Precast Pier Columns by the method that conventional axial positions up to hundred tons.
For volume and the biggish Precast Pier Columns component of weight, when with bottom cushion cap assembly, assembled essence can be generated The uncontrollable problem of degree, while the degree control during its assembly also will affect the assembled quality of superstructure.Therefore, Accurate positioning between Precast Pier Columns and cushion cap is a technical problem urgently to be resolved.
Summary of the invention
The purpose of the present invention is to overcome the shortage of prior art, and it is an object of the present invention to provide a kind of packaged type bridges Precast Pier Columns Component installation method solves splicing and positioning that existing packaged type bridges Precast Pier Columns are unable to accurately control Precast Pier Columns, and The problem of control of Precast Pier Columns installed height mark.
The present invention is achieved through the following technical solutions:
A kind of packaged type bridges Precast Pier Columns component installation method, by the accurate assembled cushion cap poured in advance of Precast Pier Columns On, it is inserted into connection sleeve pre-buried in Precast Pier Columns by cushion cap reserved steel bar, is attached using pressure grouting, including step It is rapid:
Before Precast Pier Columns are in place, marked respectively on the Precast Pier Columns interface to be installed of Precast Pier Columns bottom face and cushion cap Docking label;
According to absolute altitude, the placement center cushion block at Precast Pier Columns interface to be installed center;
After hoisting prefabricated pier stud inserts the reserved steel bar on people's cushion cap, Precast Pier Columns bottom face is adjusted, so that Precast Pier Columns It is aligned one by one with the label that docks of Precast Pier Columns joint face to be installed;
Adjusting jack is placed, loop wheel machine unloads power, transfers in Precast Pier Columns to center cushion block;It is adjusted using jack prefabricated For pier stud verticality until meeting design requirement, locking jack, the piston stroke and pier stud for recording jack sits slurry thickness;
Hang Precast Pier Columns;
Installation prepares the grouting template that pier stud sits slurry on cushion cap, sits slurry thickness data preparation grouting according to measurement pier stud Material, perfusion pier stud sit slurry,
It is formal in place: and then loop wheel machine transfers Precast Pier Columns, Precast Pier Columns are accurately in place, lock jack, pass through grout hole Grouting material maintenance, is installed.
Further, the docking label is found out by the way of in cross point has poured pier stud and Precast Pier Columns to be installed The central point of joint face pops up cross hairs using ink fountain.
Further, the thickness for placing center cushion block designs top mark height according to pier stud and pier stud prefabricated components length determines.
Further, before formal in place, slurry thickness data is sat according to measurement pier stud and prepares grouting material, jack piston is turned up 5mm, then loop wheel machine transfers Precast Pier Columns, overall process measurement in decentralization process, while adjusting jack, the amount control adjusted every time Within 1mm, until deviation is stablized in design error requirement, Precast Pier Columns are i.e. accurately in place at this time, lock jack, fill Slurry maintenance, while Precast Pier Columns are fixed temporarily using strut, it is installed.
Further, the placement adjusting jack, multiple jack are circumferentially positioned at pre- by regulating device Pier stud bottom processed.
Further, the regulating device includes connection frame and supporting block, and the connection frame is mounted on prefabricated by bolt On pier stud, the supporting block is arranged on connection frame, and the jack is by being coupled support Precast Pier Columns tune with supporting block Save verticality and height.
Compared with prior art, the present invention having the following advantages and benefits:
1, a kind of packaged type bridges Precast Pier Columns component installation method of the present invention, by Precast Pier Columns bottom face and cushion cap Precast Pier Columns interface to be installed on mark respectively docking label;And adjusting jack is placed, prefabricated pier may be implemented Column Dock With Precision Position, then the thickness that pier stud sits slurry is calculated by pre-installation, in the case where replacing or retaining center cushion block, make prefabricated Pier stud is installed to precisely in place in accurate adjusting, sits slurry by pier stud to lock with regard to bit space, to guarantee that Precast Pier Columns can essence Quasi- fixed setting is supported adjusting height and verticality mechanical means only with center cushion block relative to existing, of the invention Regulative mode is more simple and convenient, while guaranteeing that Precast Pier Columns can be fixed precisely.
2, a kind of packaged type bridges Precast Pier Columns component installation method of the present invention, for guarantee the accurate installations of Precast Pier Columns with Precision, it is ensured that and pier stud sits the determination of the grouting thickness of slurry, prevents the excessive or very few grouting slurry being added, Precast Pier Columns Installation using it is pre- it is in place by the way of, primarily determine it is each adjust jack height and be in the milk thickness;
3, a kind of packaged type bridges Precast Pier Columns component installation method of the present invention makes Precast Pier Columns in reality using this method Now in the case where accurate installation, installation effectiveness improves 40%, the installation period of Precast Pier Columns is greatly shortened, convenient for Precast Pier Columns Support form promotes and applies, and in bridge construction, building, hydraulic engineering field can obtain extensively sending out practice and application.
Detailed description of the invention
Attached drawing described herein is used to provide to further understand the embodiment of the present invention, constitutes one of the application Point, do not constitute the restriction to the embodiment of the present invention.In the accompanying drawings:
Fig. 1 is a kind of schematic view of the front view of packaged type bridges Precast Pier Columns component installation method of the present invention;
Fig. 2 is a kind of overlooking structure diagram of packaged type bridges Precast Pier Columns component installation method of the present invention;
Label and corresponding parts title in attached drawing:
1- Precast Pier Columns, 2- cushion cap, 3- pier stud, which is sat, to be starched, the center 4- cushion block, 5- regulating device, 6- reserved steel bar, and 7- is very heavy Top, 8- grout hole, 9- connection frame, 10- supporting block.
Specific embodiment
To make the objectives, technical solutions, and advantages of the present invention clearer, below with reference to embodiment and attached drawing, to this Invention is described in further detail, and exemplary embodiment of the invention and its explanation for explaining only the invention, are not made For limitation of the invention.
Embodiment
As shown in Figs. 1-2, a kind of packaged type bridges Precast Pier Columns component installation method of the present invention is accurate by Precast Pier Columns 1 Be assembled on the cushion cap 2 poured in advance, Precast Pier Columns 1 and 2 structure type of cushion cap be all with structure type, cushion cap 2 Reserved steel bar 6 is implanted on Precast Pier Columns interface to be installed in advance, 1 end of Precast Pier Columns is also implanted with the butt muff of F type in advance, And 3 connection of slurry is sat by pier stud between Precast Pier Columns 1 and cushion cap 2 and is supported, Precast Pier Columns 1 are inserted by 2 reserved steel bar 6 of cushion cap Interior pre-buried connection sleeve, is attached using pressure grouting, comprising steps of
Before Precast Pier Columns 1 are in place, divide on the bottom face of Precast Pier Columns 1 and the Precast Pier Columns interface to be installed of cushion cap 2 Docking label is not marked;
According to absolute altitude, the placement center cushion block 4 at Precast Pier Columns interface to be installed center;
After hoisting prefabricated pier stud 1 inserts the reserved steel bar 6 on people's cushion cap, 1 bottom face of Precast Pier Columns is adjusted, so that prefabricated pier Column 1 is aligned one by one with the label that docks of Precast Pier Columns joint face to be installed;
Adjusting jack 7 is placed, loop wheel machine unloads power, transfers in Precast Pier Columns 1 to center cushion block 4;It is adjusted using jack 7 For 1 verticality of Precast Pier Columns until meeting design requirement, locking jack 7, the piston stroke and pier stud for recording jack 7 sits slurry 3 Thickness;
Hang Precast Pier Columns 1;
Installation prepares the grouting template (to prevent grouting material from overflowing pollution finished product) that pier stud sits slurry 3 on cushion cap, and foundation is surveyed Amount pier stud sits 3 thickness datas of slurry and prepares grouting material, and perfusion pier stud sits slurry 3,
It is formal in place: and then loop wheel machine transfers Precast Pier Columns 1, Precast Pier Columns 1 are accurate in place, lock jack 7, pass through grouting The maintenance of 8 grouting material of hole, reserved steel bar 6 connect grouting with the pipe fitting of F type, general using being in the milk from lower row's grout hole 8, install It completes.
Docking label finds out the center of Precast Pier Columns 1 and Precast Pier Columns joint face to be installed by the way of in cross point Point pops up cross hairs using ink fountain.
The thickness of placement center cushion block 4 designs top mark height according to pier stud and pier stud prefabricated components length determines.
Before formal in place, 3 thickness datas of slurry are sat according to measurement pier stud and prepare grouting material, the piston 5mm of jack 7 is turned up, Jack 7 is adjusted convenient for subsequent decline, Precast Pier Columns 1 and pier stud is made to sit 3 Dock With Precision Positions of slurry, then loop wheel machine transfers Precast Pier Columns 1, Overall process measures in decentralization process, while adjusting jack 7, and the amount adjusted every time controls within 1mm, until deviation is stablized In design error requires, Precast Pier Columns 1 are i.e. accurately in place at this time, lock jack 7, grouting material maintenance, while using strut Precast Pier Columns 1 are fixed temporarily, are installed.
Adjusting jack 7 is placed, multiple jack 7 are circumferentially positioned at 1 bottom of Precast Pier Columns by regulating device 5 Portion.
Regulating device 5 includes connection frame 9 and supporting block 10, and connection frame 9 is mounted in Precast Pier Columns 1 by bolt, described Supporting block 10 is arranged on connection frame 9, and the jack 7 is hung down by being coupled support Precast Pier Columns 1 with supporting block 10 and adjusting Straight degree and height.
As shown in Figs. 1-2, a kind of packaged type bridges Precast Pier Columns component installation method of the present invention, Specific construction step, 1, Before pier stud is in place, the central point for having poured pier stud and Precast Pier Columns joint face to be installed, benefit are found out by the way of in cross point Cross hairs is popped up with ink fountain.
2, absolute altitude is measured.Top mark height and pier stud prefabricated components length, the placement center at cross searching are designed according to pier stud Cushion block (steel), it is ensured that pier stud installed height mark meets design requirement, it is ensured that length meets design and wants in pre- doweling depth people's sleeve It asks.
3, pre- in place: for the accurate installation and precision for guaranteeing Precast Pier Columns, it is ensured that and pier stud sits the grouting thickness of slurry Determine, prevent be added excessive or very few grouting slurry, Precast Pier Columns installation using it is pre- it is in place by the way of, primarily determine each tune Save the height and grouting thickness of jack.
After pier stud inserts people's cushion cap reserved steel bar, slowly transfer, make pier stud prefabricated component fall on the cushion block of center and slightly by Power.Plan-position is adjusted, so that Precast Pier Columns middle line is aligned one by one with the center line for having poured pier stud, it is ensured that pier stud does not generate torsion Turn, it is in place accurate.Adjusting jack (jack should be placed below regulating device, and close to inside) is placed, loop wheel machine is slow Power is unloaded, is transferred on pier stud to center cushion block;Pier stud verticality is adjusted using jack until meeting design requirement, is locked very heavy Top records position, piston stroke and the grouting thickness of jack, hangs pier stud.
4, formal in place: slurry template is sat in formal preceding installation in place, it is ensured that grouting material is non-leakage;It is filled according to measurement data preparation Slurry (slightly more than grouting thickness), is turned up jack piston 5mm, then the slow pine hook decentralization pier stud of loop wheel machine, complete in decentralization process Process measurement, while jack is adjusted, the amount adjusted every time controls in 1mm.Until deviation is stablized in design error requirement, Pier stud is i.e. accurately in place at this time, locks jack, grouting material maintenance, while being fixed temporarily Precast Pier Columns using strut, installs It completes.
A kind of packaged type bridges Precast Pier Columns component installation method of the present invention, by Precast Pier Columns bottom face and cushion cap Docking label is marked on Precast Pier Columns interface to be installed respectively;And adjusting jack is placed, Precast Pier Columns may be implemented Dock With Precision Position, then the thickness that pier stud sits slurry is calculated by pre-installation, in the case where replacing or retaining center cushion block, make prefabricated pier Column is installed to precisely in place in accurate adjusting, sits slurry by pier stud to lock with regard to bit space, to guarantee that Precast Pier Columns can be precisely Fixed setting is supported adjusting height and verticality mechanical means, tune of the invention only with center cushion block relative to existing Section mode is more simple and convenient, while guaranteeing that Precast Pier Columns can be fixed precisely.
A kind of packaged type bridges Precast Pier Columns component installation method of the present invention, for the accurate installation and essence for guaranteeing Precast Pier Columns Degree, it is ensured that and pier stud sits the determination of the grouting thickness of slurry, prevents the excessive or very few grouting slurry being added, Precast Pier Columns peace Dress using it is pre- it is in place by the way of, primarily determine it is each adjust jack height and be in the milk thickness;
A kind of packaged type bridges Precast Pier Columns component installation method of the present invention is realizing Precast Pier Columns using this method In the case where accurate installation, installation effectiveness improves 40%, the installation period of Precast Pier Columns is greatly shortened, convenient for the branch of Precast Pier Columns Shield form promotes and applies, and in bridge construction, building, hydraulic engineering field can obtain extensively sending out practice and application.
Above-described specific embodiment has carried out further the purpose of the present invention, technical scheme and beneficial effects It is described in detail, it should be understood that being not intended to limit the present invention the foregoing is merely a specific embodiment of the invention Protection scope, all within the spirits and principles of the present invention, any modification, equivalent substitution, improvement and etc. done should all include Within protection scope of the present invention.

Claims (5)

1. a kind of packaged type bridges Precast Pier Columns component installation method, which is characterized in that be accurately assembled in Precast Pier Columns (1) and mention Before on the cushion cap (2) that has poured, by connection sleeve pre-buried in cushion cap (2) reserved steel bar insertion Precast Pier Columns (1), utilize pressure Power grouting is attached, comprising steps of
Before Precast Pier Columns (1) are in place, on the bottom face of Precast Pier Columns (1) and the Precast Pier Columns interface to be installed of cushion cap (2) Docking label is marked respectively;
According to absolute altitude, the placement center cushion block (4) at Precast Pier Columns interface to be installed center;
After hoisting prefabricated pier stud (1) inserts the reserved steel bar (6) on people's cushion cap, Precast Pier Columns (1) bottom face is adjusted, so that prefabricated Pier stud (1) is aligned one by one with the label that docks of Precast Pier Columns joint face to be installed;
Adjusting is placed with jack (7), loop wheel machine unloads power, transfers on Precast Pier Columns (1) to center cushion block (4);It utilizes jack (7) Precast Pier Columns (1) verticality is adjusted until meeting design requirement, is locked jack (7), record jack (7) piston stroke and Pier stud sits slurry (3) thickness;
Hang Precast Pier Columns (1);
Installation prepares the grouting template that pier stud sits slurry (3) on cushion cap, sits slurry (3) thickness data preparation grouting according to measurement pier stud Material pours into seat slurry, and slightly above pier stud sits slurry (3) measurement thickness;
Before formal in place, slurry (3) thickness data is sat according to measurement pier stud and prepares grouting material, the piston 5mm of jack (7) is turned up, Then loop wheel machine transfers Precast Pier Columns (1), overall process measurement in decentralization process, while adjusting jack (7), the amount control adjusted every time System is within 1mm, until deviation is stablized in design error requirement, Precast Pier Columns (1) are i.e. accurately in place at this time, locks very heavy It pushes up (7), perfusion slurry maintenance, while Precast Pier Columns (1) is fixed temporarily using strut, be installed;
It is formal in place: and then loop wheel machine decentralization Precast Pier Columns (1), Precast Pier Columns (1) are accurate in place, lock jack (7), pass through filling Hole (8) perfusion slurry, maintenance are starched, is installed.
2. a kind of packaged type bridges Precast Pier Columns component installation method according to claim 1, it is characterised in that: described right The central point that label finds out Precast Pier Columns (1) and Precast Pier Columns joint face to be installed by the way of in cross point is connect, ink is utilized Bucket pop-up cross hairs.
3. a kind of packaged type bridges Precast Pier Columns component installation method according to claim 1, it is characterised in that: in placement The thickness of heart cushion block (4) designs top mark height according to pier stud and pier stud prefabricated components length determines.
4. a kind of packaged type bridges Precast Pier Columns component installation method according to claim 1, it is characterised in that: described to put It sets adjusting jack (7), multiple jack (7) are circumferentially positioned at Precast Pier Columns (1) bottom side by regulating device (5) Face.
5. a kind of packaged type bridges Precast Pier Columns component installation method according to claim 1, it is characterised in that: the tune Regulating device (5) includes connection frame (9) and supporting block (10), and the connection frame (9) is mounted on Precast Pier Columns (1) by bolt, The supporting block (10) is arranged on connection frame (9), and the jack (7) is prefabricated by being coupled support with supporting block (10) Pier stud (1) adjusts verticality and height.
CN201710357824.8A 2017-05-19 2017-05-19 A kind of packaged type bridges Precast Pier Columns component installation method Active CN107100078B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710357824.8A CN107100078B (en) 2017-05-19 2017-05-19 A kind of packaged type bridges Precast Pier Columns component installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710357824.8A CN107100078B (en) 2017-05-19 2017-05-19 A kind of packaged type bridges Precast Pier Columns component installation method

Publications (2)

Publication Number Publication Date
CN107100078A CN107100078A (en) 2017-08-29
CN107100078B true CN107100078B (en) 2019-01-08

Family

ID=59669988

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710357824.8A Active CN107100078B (en) 2017-05-19 2017-05-19 A kind of packaged type bridges Precast Pier Columns component installation method

Country Status (1)

Country Link
CN (1) CN107100078B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111305082A (en) * 2020-04-03 2020-06-19 中铁四局集团有限公司 Method for mounting capping beam for mutually constraining adjacent pier columns in prefabricated bridge

Families Citing this family (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107489429B (en) * 2017-08-31 2019-06-07 中交第二航务工程局有限公司 Prefabricated maintenance pipe fitting method
CN107701198B (en) * 2017-08-31 2018-12-21 中交第二航务工程局有限公司 A kind of slip casting fixing means of prefabricated components
CN107642368A (en) * 2017-09-30 2018-01-30 中铁第四勘察设计院集团有限公司 A kind of adjustable height prefabricated box culvert and its adjusting method
CN109138447B (en) * 2018-10-11 2020-11-27 垒知控股集团股份有限公司 Method for mounting vertical component and setting slurry in horizontal seam
CN109208485A (en) * 2018-10-17 2019-01-15 中铁大桥局集团有限公司 The method for rapidly positioning of positioning device and packaged type bridges Precast Pier Columns
CN109881588B (en) * 2019-04-10 2023-11-21 北方工业大学 Pier adjusting device and pier adjusting system
CN112144327A (en) * 2019-06-28 2020-12-29 比亚迪股份有限公司 Track support assembly, assembly method thereof, track and track traffic system
CN112144328B (en) * 2019-06-28 2023-09-05 比亚迪股份有限公司 Rail support assembly, method of assembling the same, and rail transit system
CN110512527A (en) * 2019-08-28 2019-11-29 上海绿地建设(集团)有限公司 The device and adjusting method precisely adjusted for prefabricated stand column verticality
CN110924305B (en) * 2019-11-01 2021-06-15 中交二航局第一工程有限公司 Construction method of prefabricated cover beam installation positioning system
CN110863427A (en) * 2019-12-24 2020-03-06 广州市市政集团有限公司 Connecting structure for assembled bridge pier column and bearing platform and construction method thereof
CN111707525B (en) * 2020-06-30 2023-03-10 中冶建工集团有限公司 Method for forming mortar setting on wall brick detection surface
CN112030753A (en) * 2020-08-18 2020-12-04 中交路桥建设有限公司 Pier column installation method for ensuring thickness of slurry of foundation of assembled pier column
CN112211106B (en) * 2020-10-29 2023-01-10 中铁四局集团第一工程有限公司 Method for installing prefabricated capping beam of viaduct
CN112458905A (en) * 2020-11-09 2021-03-09 中铁大桥局上海工程有限公司 Splicing adjustment method for prefabricated capping beam and prefabricated stand column
CN113215968A (en) * 2021-06-01 2021-08-06 深圳市市政设计研究院有限公司 Connecting structure of bearing platform and prefabricated pier stud with adjustable wet joint form and construction method
CN113235401A (en) * 2021-06-10 2021-08-10 深圳市城市交通规划设计研究中心股份有限公司 Prefabricated pier column and bearing platform connecting structure capable of adjusting wet joint mode and construction method
CN115094778B (en) * 2022-08-10 2023-01-06 北京城建设计发展集团股份有限公司 Method for connecting prefabricated T-shaped piers through bonded prestressed tendons and steel bars

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4344488B2 (en) * 2001-04-10 2009-10-14 新日本製鐵株式会社 Rigid structure of upper and lower composite members
CN205576723U (en) * 2016-02-15 2016-09-14 上海应用技术学院 Adoption is excelled in prefabrication of fibre mortar and bellows joint and is assembled pier
CN205857035U (en) * 2016-06-07 2017-01-04 上海公路投资建设发展有限公司 A kind of prefabricated stand column and the assembled positioner of cushion cap
CN206127864U (en) * 2016-09-29 2017-04-26 上海市政工程设计研究总院(集团)有限公司 Bridge stand and cushion cap assemble device
CN106368117A (en) * 2016-09-29 2017-02-01 上海市政工程设计研究总院(集团)有限公司 Assembling method for bridge stand column and bearing platform
CN106436554A (en) * 2016-09-29 2017-02-22 上海市政工程设计研究总院(集团)有限公司 Device for assembling stand column with bearing platform of bridge
CN106400692A (en) * 2016-10-28 2017-02-15 上海市政工程设计研究总院(集团)有限公司 Construction method for stand column and cover beam assembled structure
CN106400678A (en) * 2016-11-10 2017-02-15 济南轨道交通集团有限公司 Prefabricated column, pier column structure and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111305082A (en) * 2020-04-03 2020-06-19 中铁四局集团有限公司 Method for mounting capping beam for mutually constraining adjacent pier columns in prefabricated bridge
CN111305082B (en) * 2020-04-03 2021-04-06 中铁四局集团有限公司 Method for mounting capping beam for mutually constraining adjacent pier columns in prefabricated bridge

Also Published As

Publication number Publication date
CN107100078A (en) 2017-08-29

Similar Documents

Publication Publication Date Title
CN107100078B (en) A kind of packaged type bridges Precast Pier Columns component installation method
CN105040717B (en) Foundation bolt fixing support and installation method
CN106638940B (en) A kind of assembled high residential building concrete prefabricated element construction
CN104328744B (en) A kind of earth anchored suspension bridge anchorage reinforcing pull rod anchor system construction method
CN107268424A (en) Can fast leveling precast assembly bridge pier structure and its construction method
CN203625921U (en) Precision control device for pre-embedded mounting of foundation bolts
CN104141318A (en) Installation and construction method of column base of large-diameter steel pipe column
CN105951747A (en) Construction method for embedding latticed column through reverse building method
CN106087991B (en) Stake top absolute altitude is in natural ground dug pile construction method below
CN108518067B (en) Assembled wallboard grouting compensation device and construction method thereof
CN208379910U (en) A kind of nodal connection device between prefabricated column
CN204001428U (en) A kind of Large-diameter Steel tubing string suspension column is installed pre-buried location structure and suspension column structure thereof
CN105317052B (en) Tower crane foundation bolt fixing method
CN208966022U (en) A kind of template poured for large-scale beam column
CN107355008A (en) A kind of prefabricated attachment structure and method of newly-increased steel core concrete column and existing structure
CN106759943A (en) A kind of pre-assembled Anchor Bolts in Steel Column Bases structure
CN104727339B (en) Power equipment basis two-step construction method
CN109629449A (en) A kind of steel case arch bridge arch springing toughened internal stress installation locating support and alignment method
CN204001429U (en) A kind of Large-diameter Steel tubing string suspension column structure and suspension column absolute altitude adjustment fixing structure thereof
CN106948267B (en) A kind of memorial archway bar formula bridge cable tower king-post method for synchronously constructing
CN113174942A (en) Precise positioning device for cage core bag anti-floating anchor rod of deep foundation pit and construction method
CN106087934A (en) A kind of coaxality measuring mechanism installed for hydraulic-floating vertical ship lift vertical shaft steel lining and detection method
CN107587770A (en) Disjunctor storehouse synchronization slding form operation method
CN207047889U (en) A kind of device for installing forging machine main frame embedded part
CN215055273U (en) A assembled template for installing support bracket embedded box

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant