CN107081497A CN201710451944.4A CN201710451944A CN107081497A CN 107081497 A CN107081497 A CN 107081497A CN 201710451944 A CN201710451944 A CN 201710451944A CN 107081497 A CN107081497 A CN 107081497A
Authority
CN
China
Prior art keywords
soldering
cooling chamber
cellular board
air
rubber tire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710451944.4A
Other languages
Chinese (zh)
Inventor
金建伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Sheng Xing Metal Plate Co Ltd
Original Assignee
Jiangsu Sheng Xing Metal Plate Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Sheng Xing Metal Plate Co Ltd filed Critical Jiangsu Sheng Xing Metal Plate Co Ltd
Priority to CN201710451944.4A priority Critical patent/CN107081497A/en
Publication of CN107081497A publication Critical patent/CN107081497A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K1/00Soldering, e.g. brazing, or unsoldering
    • B23K1/0008Soldering, e.g. brazing, or unsoldering specially adapted for particular articles or work
    • B23K1/0014Brazing of honeycomb sandwich structures
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K3/00Tools, devices, or special appurtenances for soldering, e.g. brazing, or unsoldering, not specially adapted for particular methods
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K3/00Tools, devices, or special appurtenances for soldering, e.g. brazing, or unsoldering, not specially adapted for particular methods
    • B23K3/08Auxiliary devices therefor

Abstract

The invention belongs to cellular board technical field, production line specifically related to without glue aluminum cellular board, including tunnel type soldering unit, feeding platform on front side of soldering unit, soldering unit includes frame, the preheating furnace set gradually in frame, soldering oven, water cooling chamber, air-cooling chamber and soldering feed mechanism, soldering feed mechanism, which is sequentially passed through, includes preheating furnace, soldering oven, water cooling chamber, air-cooling chamber simultaneously extends to air-cooling chamber rear portion formation discharge pedestal, soldering feed mechanism includes feeding belt, rubber tire, the motor for driving rubber tire to rotate, rubber tire is fixed on support two ends, feeding guipure is around being located on rubber tire, motor is connected by transmission mechanism with rubber tire, pneumatic motor is additionally provided with support, pneumatic motor is led to standby transmission mechanism and is connected with rubber tire, continous way production can be carried out to Large-dimension honeycomb plate, production efficiency is high, soldering is firm, after power-off, so that quickly workpiece in stove to be pulled out, workpiece is avoided to scrap.

Description

Production line without glue aluminum cellular board
Technical field
The invention belongs to cellular board technical field, and in particular to the production line without glue aluminum cellular board.
Background technology
Aluminum cellular board is widely used in by manufacturing industry due to lightweight, a variety of functions such as heat-insulation noise-reduction.It is existing The aluminum cellular board of technology, using honeycomb core and bottom plate, panel is Nian Jie forms, and glue is used in production, not environmentally friendly enough.To solve The problem, it is now many that cellular board is manufactured using brazing mode, soldering connection mode will be used between panel, honeycomb core, bottom plate.The bottom of by Plate, honeycomb core, panel combination enough send into soldering oven and carry out soldering, and soldering cellular board is made, and the current soldering mode of production is Discontinuous, assembling, welding and other processes of honeycomb board member are individually carried out, and mutual divergence between production process is raw Production is discontinuous, low production efficiency.
The content of the invention
The technical problems to be solved by the invention are to be directed to drawbacks described above there is provided the production line without glue aluminum cellular board, can Continous way production is carried out to Large-dimension honeycomb plate, production efficiency is high, and soldering is firm, after power-off, quickly to pull out workpiece in stove, Workpiece is avoided to scrap.
The technical scheme that the present invention solves the use of its technical problem is as follows:
Feeding platform on front side of production line without glue aluminum cellular board, including tunnel type soldering unit, soldering unit, soldering list First preheating furnace, soldering oven, water cooling chamber, air-cooling chamber and soldering feed mechanism including being set gradually in frame, frame, soldering are sent Material mechanism, which is sequentially passed through, to be included preheating furnace, soldering oven, water cooling chamber, air-cooling chamber and extends to air-cooling chamber rear portion formation discharge pedestal, soldering Feed mechanism includes the motor that feeding belt, rubber tire, driving rubber tire are rotated, and rubber tire is fixed on support two ends, and feeding guipure is around being located at On rubber tire, motor is connected by transmission mechanism with rubber tire, and pneumatic motor is additionally provided with support, and pneumatic motor leads to standby transmission mechanism It is connected with rubber tire, water cooling chamber is chuck overflow-type structure, water cooling chamber is provided with multisection type water collar, and multistage water cooling inner room passes through flange Connection, water collar is provided with water inlet, overfall, and water inlet, which is provided with water pump, water collar, is provided with temperature controller, water level control Device, temperature controller is connected with water pump, and water cooling chamber bottom is provided with front side of sewage draining exit, soldering unit and is additionally provided with drying unit, drying Spray chamber is provided between unit and feeding platform, pneumatic motor can drive feeding belt to continue to run with rapidly after power failure, by work in stove Part is pulled out, it is to avoid workpiece is scrapped, continuously acting production lines, is mutually linked between each production process, and Large-dimension honeycomb plate can be connected Continuous formula production, production efficiency is high.
Further, described soldering oven is added by soldering body of heater, the soldering inner cover of soldering furnace interior, plug-in type soldering Thermal element is constituted, and is provided between graphite cake, adjoining graphite plate and is coordinated using splicing construction inside inner cover, inner cover bottom is provided with It is provided with multiple V-structures arranged side by side, soldering oven body inside support rail of the correspondence inner cover bottom provided with support inner cover, inner cover Multiple nitrogen pipelines, temperature thermocouple, oxygen determination pipe, bell of the soldering body of heater at the top of U-shaped body of heater, body of heater are constituted, bell with Bolt connection between body of heater, inboard wall of furnace body is provided with the inside of needle punched blanket fibrous face insulation material, bell and is again provided with needle punched blanket fibrous face Insulation material at insulation material and bell is detachably connected with bell, and soldering heating element heater is distributed in inner cover surrounding, by pricker Inserted outside brazier body.
Further, described soldering heating element heater is heating tube, and heating tube includes the spiral shell in porcelain tube, porcelain tube Shape heater strip is revolved, porcelain tube is inserted outside soldering oven body, corresponding position is provided with ceramic chock plug outside soldering oven body.
Further, preceding curtain room, preceding curtain room, preheating furnace, soldering oven, the outside of water cooling chamber are provided with front side of described preheating furnace Provided with cover body, cover body is located to be provided with air curtain curtain on front side of preceding curtain room, and air curtain curtain is detachably connected with cover body corresponding position, and air curtain curtain is not by Steel foil band, high temperature resistance polyester fiber cloth become rusty into provided with nitrogen inlet in preceding curtain room, nitrogen inlet connects nitrogen supply (NS) equipment.
Further, described preheating furnace structure is identical with soldering furnace structure.
Further, it is additionally provided with Slag Room between described soldering oven, water cooling chamber.
Further, described air-cooling chamber is provided with multiple fans, and the airflow direction of fan is from top to bottom.
Further, described soldering unit and spray are interval provided with drying oven.
Further, the production line of no glue aluminum cellular board also includes switch board, switch board connection control preheating furnace, soldering Stove, water cooling chamber, the operating mechanism of air-cooling chamber, and connection controlled motor, pneumatic motor.
The beneficial effects of the invention are as follows:Using such scheme, continuously acting production lines are mutually linked between each production process, can The continous way production of Large-dimension honeycomb plate is carried out, production efficiency is high, and production line is after power-off is met with, and pneumatic motor can directly drive Feeding belt is continued to run with, and workpiece in production line is pulled out, it is to avoid workpiece is scrapped, and reduces production cost.
Brief description of the drawings
By detailed description below in conjunction with the accompanying drawings, the present invention is foregoing will to be become with other objects, features and advantages Obviously.
Fig. 1 is the overall schematic at soldering unit of the present invention.
Fig. 2 is preheating furnace of the present invention, spray chamber, the schematic diagram at operating desk.
Fig. 3 is the structural representation at motor in frame of the present invention.
Fig. 4 is the schematic cross-section of soldering oven of the present invention.
Wherein:1 is frame, and 2 be preceding curtain room, and 3 be preheating furnace, and 4 be soldering oven, and 41 be soldering body of heater, and 42 be soldering Muffle Cover, 43 be graphite cake, and 44 be heating tube, and 5 be Slag Room, and 6 be water cooling chamber, and 7 be rear curtain room, and 8 be air-cooling chamber, and 9 be feeding belt, 10 It is operating desk for spray chamber, 11,12 be tunnel-type drying furnace, and 13 be motor, and 14 be rubber roll, and 15 be pneumatic motor, and 16 be atmosphere Cover.
Embodiment
The present invention will be further described below in conjunction with the accompanying drawings.
Shown in reference picture 1, figure, the production line of no glue aluminum cellular board includes operating desk 11, spray chamber successively from front to back 10th, tunnel-type drying furnace 12, tunnel type soldering unit, operating desk is is spliced by steel, the settable transmission of operating desk table top Band or fixed mesa, for placing clamping tooling, are assembled to cellular board, carry out the preparatory process before soldering.
Spray chamber includes the clamping bench of the spray hood with form, the spray nozzle in spray hood and clamping workpiece, workpiece It is placed on clamping bench, spray nozzle is towards clamping bench, and spray nozzle is conveyed to scaling powder is sprayed on workpiece after scaling powder is sprayed Dried in tunnel-type drying furnace, after drying, workpiece weld surface can form scaling powder layer.
Tunnel-type drying furnace is arranged on rear side of spray chamber, after the workpiece drying for having sprayed scaling powder, condenses in scaling powder Workpiece surface, is easy to improve the effect of soldering.The front and rear sides of spray chamber are equipped with manipulator, manipulator and activity at spray chamber Connection, can be turned down, and manipulator is used for transporting work pieces, after workpiece is clamping on operating desk, is transported to by manipulator Spray chamber be transferred to after the completion of the spray of scaling powder, spray in the manipulator through rear side in drying oven, drying oven and soldering Set before and after unit, front and rear correspondence, the workpiece after drying is directly sent to soldering unit and carries out soldering processing.
Tunnel type soldering unit includes the preceding curtain room 2 set gradually in frame 1, frame 1, preheating furnace 3, soldering oven 4, scarfing cinder Room 5, water cooling chamber 6, rear curtain room 7, air-cooling chamber 8, and soldering feed mechanism, reference picture 3, soldering feed mechanism include feeding belt 9, Rubber roll 14, driving rubber roll 91 rotate motor 13, feeding belt 9 sequentially pass through preceding curtain room 2, preheating furnace 3, soldering oven 4, Slag Room 5, Water cooling chamber 6, rear curtain room 7, air-cooling chamber 8 simultaneously extend to the rear portion of air-cooling chamber 8 formation discharge pedestal, and feeding belt 9 is compiled using 316L stainless steels Guipure processed, the width of feeding belt 9 is not less than 1500mm, and the axle center of rubber roll 14 is provided with rubber roller, and rubber roll betwist-mountain is provided with bearing, support 1 Corresponding position is provided with the bearing holder (housing, cover) of fixing bearing, and rubber roll 14 is spindle rotationally arranged at the two ends of support 1, and feeding belt 9 is around being located at rubber roll On 14, one end of rubber roller is provided with driven sprocket, and the mountain of support 1 is provided with motor 13, and the output end of motor 13 is connected with reductor, slows down Machine output end is provided with drive sprocket, is connected between drive sprocket, driven sprocket by chain, and motor 13 uses Delta variable-frequency governor Driving, speed can be adjusted freely in the range of, and the speed of service of feeding belt 9 is correspondence rubber roll 14 in 200-1200mm/min, frame 1 Be provided with wire brush at bottom, the brazing flux of cementation on feeding belt of going out, on corresponding support 1 and preceding curtain room 2, preheating furnace 3, Soldering oven 4, Slag Room 5, water cooling chamber 6, rear curtain room 7, corresponding position is provided with the carrying roller of multiple support feeding belts 9 on air-cooling chamber 8, it is ensured that Pneumatic motor 15 is additionally provided with the stable operation of feeding belt 9, support 1, the output end of pneumatic motor 15 connects standby reductor, standby Output end of reducer is provided with standby drive sprocket, and rubber roller one end is provided with standby driven sprocket, standby drive sprocket, standby Connected between driven sprocket by standby chain, be equipped with freewheel clutch in driven sprocket, standby driven sprocket, driven sprocket, Standby driven sprocket individually unidirectional drive rubber roll 14 can only be rotated, non-interference between two sets of drive mechanisms, when power is off, can be led to Cross the driving rubber roll 14 of pneumatic motor 15 to rotate, run feeding belt 9, it is to avoid workpiece overstays in soldering unit and influences pricker Effect is welded, the effect and yield rate of cellular board soldering is improved, the security of soldering is improved.
Preceding curtain room 2, preheating furnace 3, soldering oven 4, Slag Room 5, water cooling chamber 6, the outside of rear curtain room 7 are provided with atmosphere cover 16, atmosphere Nitrogen pipeline is provided with cover, nitrogen is passed through each work chamber, the front end two ends of atmosphere cover are designed with air curtain curtain, air curtain curtain pair The sealing of atmosphere is carried out at preceding curtain room 2, rear curtain room 7, reduction atmosphere consumption, air curtain curtain is fine by stainless steel foil band, high temperature resistance polyester Wei Bu is made, and air curtain curtain is detachably connected with the corresponding position of atmosphere cover 16, and preceding curtain room 2 is provided with nitrogen inlet, and nitrogen inlet connection is outer The nitrogen supply (NS) pipeline in portion, and the nitrogen heater being provided with supply line, nitrogen heater are heated to nitrogen, Nitrogen after heating is passed through preceding curtain room 2, and preceding curtain room 2 is preheating section, to carrying out protection preheating to workpiece using the nitrogen after heating.
Preheating furnace 3 includes preheating body of heater, preheats the preheating inner cover of furnace interior, and feeding belt 9 is worn in preheating inner cover Cross, the support rail provided with support preheating inner cover at preheating furnace interior correspondence preheating inner cover bottom preheats body of heater ecto-entad Heat supply galvanic couple is inserted with, heat supply galvanic couple is arranged on preheating inner cover surrounding, and preheating inner cover corresponding position is penetrated provided with heat supply galvanic couple Short tube, heat supply galvanic couple is nested in short tube, and channel of nitrogen is provided with preheating furnace body, and nitrogen is passed through in preheating inner cover, with The workpiece of preheating is protected, and the size inside preheating inner cover is 1650*300mm, wide 1650mm, high 300mm, highly to send Distance at the top of the top of material strip 9 to preheating inner cover, preheating inner cover uses 8mm thickness, material is made for 316L, bottom has a plurality of V-groove, for strengthening, has appropriate short tube heat supply galvanic couple and nitrogen to enter, the length of preheating furnace 3 is 9M, in advance on preheating inner cover It is divided into Shang Qu, lower area inside hot stove 3 in the vertical direction, upper area is the top of feeding belt 9, and lower area is the bottom of feeding belt 9, preheating furnace 3 be divided into from front to back in the longitudinal direction first paragraph, second segment, the 3rd section, the power of the heat supply galvanic couple in three sections is separately adjustable, Heat supply galvanic couple power in first paragraph is 85KW, and second segment, the heat supply galvanic couple power in the 3rd section are 75KW, the temperature of heat supply galvanic couple Degree control mode is PID temperature controls, or Power Regulation pressure regulation, program segment temperature control, temperature adjustment are controllable, and preheating body of heater is by U-shaped body of heater, preheating Bell is constituted, and body of heater and preheating furnace supporting construction are made of mild steel, and stove preheating stove outer covering is made of 10mm low carbon steel plates, and Strengthened with shaped steel, preheating bell is connected by screw with body of heater top, junction is provided with sealing gasket, inboard wall of furnace body, preheating bell Internal face is incubated provided with mineral wool ceramic wool insulation material, and the insulation material on preheating bell internal face passes through screw with it Asbestos are free of in connection, insulation material, top dismounting is easily installed and safeguarded, circulating fan is equipped with every section of preheating furnace 3, Circulating fan cools down motor by nitrogen and driven.
Shown in reference picture 4, soldering inner cover 42, plug-in type pricker of the soldering oven 4 inside soldering body of heater 41, soldering body of heater 41 Weld heating element heater to constitute, be provided between graphite cake 43, adjoining graphite plate 43 and matched somebody with somebody using splicing construction staggeredly inside soldering inner cover Close, it is more close that splicing construction can make to splice each other, make graphite cake smooth after splicing, lay graphite cake, be easy to reduction Friction and control furnace deformation, the inner passage size 1650mm*270mm of soldering inner cover 42,270mm is straight side length, 1650mm is width, and the bottom of soldering inner cover 42 is provided with multiple V-structures arranged side by side, correspondence soldering Muffle in soldering body of heater 41 Support rail of 42 bottoms provided with support inner cover is covered, bottom support rail facilitates Muffle to expand with heat and contract with cold slip, and soldering body of heater 41 is by U-shaped stove Bell at the top of body, body of heater is constituted, and bolt connection between bell and body of heater, inboard wall of furnace body is provided with needle punched blanket fibrous face insulation material, The insulation material being again provided with the inside of bell at needle punched blanket fibrous face insulation material and bell is detachably connected with bell, with pin The cellucotton insulation of thorn blanket can ensure storage low in calories, and easily temperature is controlled, and soldering inner cover 42 uses Sweden 316L import sheet materials, by large-scale folding brake bending and molding, 12 meters of the stove Muffle flanging length reduces it while reducing weld seam Deformation coefficient,
Soldering oven 4 by it is front and rear to be divided into from front to back first paragraph, second segment, the 3rd section, the 4th section, the 5th section, above and below Direction is divided into Shang Qu, lower area, therefore, and each segmentation Jun Youshang areas, lower area, soldering heating element heater are distributed in inner cover surrounding, by Inserted outside soldering oven body, soldering heating element heater is heating tube 44, heating tube includes the helical form in porcelain tube, porcelain tube Heater strip, porcelain tube is inserted outside soldering oven body, and corresponding position is provided with ceramic chock plug outside soldering oven body, and ceramic chock plug is prevented Thermal loss, changes convenient, will be divided into 5 independent regions in soldering oven, the power in each region is separately provided, and first The upper and lower area's power of section is 75KW, and the upper and lower area's power of second segment is 75KW, and the 3rd section of upper and lower area's power is 55KW, the 4th section it is upper, Lower area power is 55KW, and the 5th section of upper and lower area's power is 55KW, and Discrete control is easy to in-furnace temperature constant, and meets soldering The demand of technique, is conveniently adjusted temperature, the temperature of soldering oven 4 is 600-650 degrees Celsius.
The inside of soldering inner cover 42 is provided with above and below three nitrogen pipelines, temperature thermocouple, oxygen determination pipe, every section of soldering oven and is all provided with Have a temperature measuring point, temperature measuring point connection temperature thermocouple, the temperature to each section is monitored, it is ensured that soldering effect, temperature control mode with it is pre- Hot stove temperature control mode is consistent, and nitrogen pipeline is provided with flowmeter, monitors nitrogen conveying capacity, and nitrogen is adjusted in soldering by flowmeter The nitrogen amount that each point needs in conveying capacity and Muffle in inner cover.Using plug-in type heating element heater by 0Cr25Al5 in soldering room Alloy makes, surrounding in the Muffle of soldering room, is provided with snail blower fan at the top of soldering oven, carries out air draft.
The rear side of soldering oven 4 is Slag Room 5, because soldering oven is during high temperature brazing, and brazing area is by high-temperature heating Brazing flux under molten condition runs into the low temperature of Slag Room, slowly can precipitate and solidify, when reaching Slag Room, in molten Brazing flux under state can fall into scarfing cinder frame along guipure traffic direction, while can easily enter stove when clearing up flue residual brazing flux Courage.
The rear side of Slag Room 5 is water cooling chamber 6, and the long 9M in water cooling chamber 6, its inner passage is 1650mm × 250mm, and water cooling chamber is folder Overflow-type structure is covered, water cooling chamber is provided with two-part water collar, and two sections of water cooling inner rooms are connected by flange, and water collar is provided with water inlet Mouth, overfall, water inlet, which is provided with water pump, water collar, is provided with temperature controller, water level controller, temperature controller and water pump Connection, water cooling chamber bottom is provided with sewage draining exit, and the water cooling chamber of chuck overflow-type structure, water is consistently circulated along whole inwalls, with band The heat on soldering work piece is walked, water jacket can directly control the operation of water pump, prevent water cooling chamber from going out built with temperature controller Existing unnecessary failure.Water level controller is alarmed water level is low, it is ensured that the water in water jacket, after water cooling, workpiece Temperature be down to 150 DEG C.
Curtain room 7 is consistent with the structure of preceding curtain room 2 afterwards, and the air curtain curtain of rear curtain room 7 is thickness 0.05mm stainless steel foil band and thickness 0.18mm high temperature resistance polyester fiber cloth is into for reducing atmosphere consumption, while slow down the abrasion of air curtain curtain, rear curtain room length For 3M, provided with nitrogen inlet all the way, it is passed through nitrogen and is protected, makes to be full of nitrogen atmosphere in case.
The rear side of curtain room 7 is air-cooling chamber 8 afterwards, and air-cooling chamber 8 from top to bottom includes three parts, and top is aircooling cabinet, and middle part is logical Road, bottom is circulation aircooling cabinet, and aircooling cabinet 8 connects two external fans, and fan is conveyed extraneous air by ventilation shaft Into aircooling cabinet, aircooling cabinet is with interchannel with baffle interval, and dividing plate is provided with downward air outlet, and feeding belt is worn in passage Cross, air outlet makes the air inside aircooling cabinet be directly blown onto on the workpiece on feeding belt, cold air carries out heat exchange with workpiece, follows Ring aircooling cabinet is provided with lower clapboard with interchannel, and lower clapboard is provided with the hot blast behind hole, with workpiece heat exchange and enters circulation by hole Gas-recycling plant, heat exchanger are set in aircooling cabinet, circulation aircooling cabinet, hot-air is carried out after heat exchange cooling, passage is being passed through It is interior, air cooling is carried out to workpiece, higher than room temperature 15 DEG C, workpiece is dropped to after the cooling effect of air-cooling chamber, at a temperature of workpiece Temperature is substantially reduced, after air-cooling chamber 8 is exported, and is continued to convey backward by feeding belt, is delivered on discharge pedestal, in the output, work Part temperature is down to room temperature.Production line is arranged successively, and the equipment work department such as soldering oven size is big, and the cellular board of large-size can be entered The continuous production of row, greatly improves production efficiency.
Production line without glue aluminum cellular board also includes being provided with touch screen in switch board, switch board, is connected by touch screen Preheating furnace, soldering oven, water cooling chamber, the operating mechanism of air-cooling chamber, and connection controlled motor, pneumatic motor, can by touch screen To operate and detect in the working condition of control stove, touch screen connection control system, control system having multiple process datas, Among operating process, the process menu that oneself is stored for from PLC can be selected by touch-screen, after technique is chosen, process Start, temperature and the control of motor order are full-automatic.The different temperatures of each workspace, conveyer belt, wind can be set Friction speed of machine etc..Touch-screen scene is simple to operate on the spot, and RS485 communications are carried out with instrument and frequency converter, can be to instrument Enter trip temperature setting, temperature is read, frequency converter setting can disposably record the temperature curve and guipure operation speed in each area in real time Spend, and can data be downloaded with → processing → and analyze, data storage >=1 year;And various blower fans, mixer, guipure can be passed Row fault alarm is sent into, shows and records.
It is described above, be only presently preferred embodiments of the present invention, any formal limitation not done to the present invention, it is every according to According to any simple modification, equivalent variations made in technical spirit of the invention to above example, the guarantor of the present invention is each fallen within Within the scope of shield.

Claims (9)

1. the production line without glue aluminum cellular board, it is characterised in that including the feeding on front side of tunnel type soldering unit, soldering unit Platform, soldering unit includes frame, the preheating furnace, soldering oven, water cooling chamber, air-cooling chamber and the soldering feeder that set gradually in frame Structure, soldering feed mechanism, which is sequentially passed through, to be included preheating furnace, soldering oven, water cooling chamber, air-cooling chamber and extends to air-cooling chamber rear portion and formed out Expect platform, soldering feed mechanism includes the motor that feeding belt, rubber tire, driving rubber tire are rotated, and rubber tire is fixed on support two ends, feeding net Band is around being located on rubber tire, and motor is connected by transmission mechanism with rubber tire, and pneumatic motor is additionally provided with support, and pneumatic motor is led to standby Transmission mechanism is connected with rubber tire, and water cooling chamber is chuck overflow-type structure, and water cooling chamber is provided with multisection type water collar, multistage water cooling inner room Connected by flange, water collar is provided with water inlet, overfall, water inlet is provided with water pump, in water collar provided with temperature controller, Water level controller, temperature controller is connected with water pump, and water cooling chamber bottom, which is provided with to be additionally provided with front side of sewage draining exit, soldering unit, dries list Spray chamber is provided between member, drying unit and feeding platform.
2. the production line according to claim 1 without glue aluminum cellular board, it is characterised in that:Described soldering oven is by soldering Body of heater, the soldering inner cover of soldering furnace interior, plug-in type soldering heating element heater are constituted, and graphite cake, phase are provided with inside inner cover Coordinated between adjacent graphite cake using splicing construction, inner cover bottom is provided with multiple V-structures arranged side by side, correspondence horse in soldering oven body Not cover bottom is provided with the support rail for supporting inner cover, and inner cover inside is provided with multiple nitrogen pipelines, temperature thermocouple, oxygen determination pipe, pricker Bell of the brazier body at the top of U-shaped body of heater, body of heater is constituted, bolt connection between bell and body of heater, and inboard wall of furnace body is provided with needle punched blanket The insulation material being again provided with the inside of fibrous face insulation material, bell at needle punched blanket fibrous face insulation material and bell can with bell Dismounting connection, soldering heating element heater is distributed in inner cover surrounding, is inserted outside soldering oven body.
3. the production line according to claim 2 without glue aluminum cellular board, it is characterised in that:Described soldering heating element heater For heating tube, heating tube includes the helical form heater strip in porcelain tube, porcelain tube, and porcelain tube is inserted outside soldering oven body Enter, corresponding position is provided with ceramic chock plug outside soldering oven body.
4. the production line according to claim 1 without glue aluminum cellular board, it is characterised in that:Set on front side of described preheating furnace There is preceding curtain room, preceding curtain room, preheating furnace, soldering oven, the outside of water cooling chamber are provided with cover body, and cover body is located to be provided with air curtain on front side of preceding curtain room Curtain, air curtain curtain is detachably connected with cover body corresponding position, and air curtain curtain is by stainless steel foil band, high temperature resistance polyester fiber cloth into preceding curtain Interior is provided with nitrogen inlet, nitrogen inlet connection nitrogen supply (NS) equipment.
5. the production line according to claim 1 without glue aluminum cellular board, it is characterised in that:Described preheating furnace structure with Soldering furnace structure is identical.
6. the production line according to claim 1 without glue aluminum cellular board, it is characterised in that:Described soldering oven, water cooling Slag Room is additionally provided between room.
7. the production line according to claim 1 without glue aluminum cellular board, it is characterised in that:Described air-cooling chamber is provided with more Individual fan, the airflow direction of fan is from top to bottom.
8. the production line according to claim 1 without glue aluminum cellular board, it is characterised in that:Described soldering unit and spray Drench interval provided with drying oven.
9. the production line according to claim 1 without glue aluminum cellular board, it is characterised in that:Life without glue aluminum cellular board Producing line also includes switch board, switch board connection control preheating furnace, soldering oven, water cooling chamber, the operating mechanism of air-cooling chamber, and connection Controlled motor, pneumatic motor.
CN201710451944.4A 2017-06-15 2017-06-15 Production line without glue aluminum cellular board Pending CN107081497A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710451944.4A CN107081497A (en) 2017-06-15 2017-06-15 Production line without glue aluminum cellular board

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710451944.4A CN107081497A (en) 2017-06-15 2017-06-15 Production line without glue aluminum cellular board

Publications (1)

Publication Number Publication Date
CN107081497A true CN107081497A (en) 2017-08-22

Family

ID=59606795

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710451944.4A Pending CN107081497A (en) 2017-06-15 2017-06-15 Production line without glue aluminum cellular board

Country Status (1)

Country Link
CN (1) CN107081497A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111300070A (en) * 2019-12-09 2020-06-19 首都航天机械有限公司 Novel honeycomb intermediate layer product automatic weld system
CN113084285A (en) * 2021-04-25 2021-07-09 郑州机械研究所有限公司 Spectacle frame brazing equipment
US11589488B1 (en) * 2021-07-28 2023-02-21 Ableprint Iechnology Co., Ltd. Warpage suppressing reflow oven

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101104216A (en) * 2007-04-09 2008-01-16 盐城市康杰机械制造有限公司 Intermittent type gas protecting soldering furnace
CN101913006A (en) * 2010-08-25 2010-12-15 盐城市康杰机械制造有限公司 Aluminum brazing furnace
CN202824914U (en) * 2012-09-18 2013-03-27 三一重工股份有限公司 Brazing furnace
CN104858520A (en) * 2015-05-25 2015-08-26 浙江创新汽车空调有限公司 Nitrogen protective continuous type brazing furnace
CN205074634U (en) * 2015-10-19 2016-03-09 长兴恒达炉业有限公司 Braze stove with horse positioner not
CN207104036U (en) * 2017-06-15 2018-03-16 江苏晟兴和金属板业有限公司 Production line without glue aluminum cellular board

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101104216A (en) * 2007-04-09 2008-01-16 盐城市康杰机械制造有限公司 Intermittent type gas protecting soldering furnace
CN101913006A (en) * 2010-08-25 2010-12-15 盐城市康杰机械制造有限公司 Aluminum brazing furnace
CN202824914U (en) * 2012-09-18 2013-03-27 三一重工股份有限公司 Brazing furnace
CN104858520A (en) * 2015-05-25 2015-08-26 浙江创新汽车空调有限公司 Nitrogen protective continuous type brazing furnace
CN205074634U (en) * 2015-10-19 2016-03-09 长兴恒达炉业有限公司 Braze stove with horse positioner not
CN207104036U (en) * 2017-06-15 2018-03-16 江苏晟兴和金属板业有限公司 Production line without glue aluminum cellular board

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111300070A (en) * 2019-12-09 2020-06-19 首都航天机械有限公司 Novel honeycomb intermediate layer product automatic weld system
CN111300070B (en) * 2019-12-09 2021-07-09 首都航天机械有限公司 Automatic welding system for honeycomb sandwich products
CN113084285A (en) * 2021-04-25 2021-07-09 郑州机械研究所有限公司 Spectacle frame brazing equipment
US11589488B1 (en) * 2021-07-28 2023-02-21 Ableprint Iechnology Co., Ltd. Warpage suppressing reflow oven

Similar Documents

Publication Publication Date Title
CN100471606C (en) Intermittent type gas protecting soldering furnace
CN104858520B (en) A kind of nitrogen protection continuous type soldering oven
CN101956056B (en) Multifunctional same-furnace multi-band bimetal strip saw blade heat treatment full-automatic production line and process thereof
CN107081497A (en) Production line without glue aluminum cellular board
CN102686965B (en) For carrying out the apparatus and method of preheating to the steel band of motion continuously
CN208913319U (en) Soldering oven based on controlled atmosphere
CN207104036U (en) Production line without glue aluminum cellular board
CN201041454Y (en) Nitrogen protection brazing furnace intermittent furnace drying device
CN100529627C (en) Sealed hot-air agitating device for nitrogen-protective soldering furnace
CN203869496U (en) Calcination equipment of carrier
CN102002559B (en) Annealing method and device of bell type furnaces
CN101979190A (en) Multifunctional furnace for continuously degreasing, sintering, quenching and tempering powder metallurgical products
CN201086166Y (en) Discontinuous mode gas protecting brazier
CN207050434U (en) A kind of net belt type sintering furnace
CN101284325A (en) Network bringing type brazing furnace
CN201020583Y (en) Nitrogen protected brazing furnace batch furnace preheating purification device
TW201202432A (en) Method and device for recovering energy downstream of a continuous casting installation
CN100577823C (en) Heat treatment furnace with built-in euthermic gas generation device
CN2370019Y (en) Fast isothermal spheroidization annealing furnace
CN202733934U (en) Air preheater
CN205999414U (en) A kind of homogeneous furnace furnace binding
CN105202910B (en) A kind of high power low power consuming roller furnace
CN202830087U (en) Induction heating device for thin steel strip coil
JPS6219265B2 (en)
CN205002591U (en) High power low power consuming roller hearth furnace

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170822