CN107074478A - Doffer clamper with two-part housing - Google Patents
Doffer clamper with two-part housing Download PDFInfo
- Publication number
- CN107074478A CN107074478A CN201580059561.1A CN201580059561A CN107074478A CN 107074478 A CN107074478 A CN 107074478A CN 201580059561 A CN201580059561 A CN 201580059561A CN 107074478 A CN107074478 A CN 107074478A
- Authority
- CN
- China
- Prior art keywords
- holding element
- clamper
- tightening member
- air duct
- barrier film
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65H—HANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
- B65H67/00—Replacing or removing cores, receptacles, or completed packages at paying-out, winding, or depositing stations
- B65H67/02—Arrangements for removing spent cores or receptacles and replacing by supply packages at paying-out stations
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65H—HANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
- B65H67/00—Replacing or removing cores, receptacles, or completed packages at paying-out, winding, or depositing stations
- B65H67/06—Supplying cores, receptacles, or packages to, or transporting from, winding or depositing stations
- B65H67/069—Removing or fixing bobbins or cores from or on the vertical peg of trays, pallets or the pegs of a belt
-
- D—TEXTILES; PAPER
- D01—NATURAL OR MAN-MADE THREADS OR FIBRES; SPINNING
- D01H—SPINNING OR TWISTING
- D01H9/00—Arrangements for replacing or removing bobbins, cores, receptacles, or completed packages at paying-out or take-up stations ; Combination of spinning-winding machine
- D01H9/001—Bobbin-taking arrangements
- D01H9/003—Graspers operating under the action of a fluid
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65H—HANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
- B65H2701/00—Handled material; Storage means
- B65H2701/30—Handled filamentary material
- B65H2701/31—Textiles threads or artificial strands of filaments
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Textile Engineering (AREA)
- Spinning Or Twisting Of Yarns (AREA)
Abstract
The present invention relates to a kind of clamper for being used to clamp spool or spool pipe(1), the clamper(1)With tightening member(11)With with longitudinal axis(10)Cylindrical holding element(2), wherein holding element(2)With inwall(4)And outer wall(20), and can be via air duct(12)The clamping element that can be pneumatically actuated worked by compressed air(5)Positioned at inwall(4)On.In order to simplify clamper(1)Design, via retaining element(19)By holding element(2)It is maintained at tightening member(11)On, the retaining element(19)Partly surround holding element(2)Outer wall(20).
Description
Technical field
The present invention relates to a kind of clamper for being used to clamp spool or spool pipe, the clamper has tightening member and had
The cylindrical holding element of longitudinal axis, wherein holding element have inner and outer wall, and can pass through warp via air duct
The clamping element that can be pneumatically actuated that compressed air works is located on inwall, and holding element is maintained at via retaining element
On tightening member.
Background technology
In many spinning machine, particularly ring spinner, during spool replacement operation, at the spinning station of spinning machine
Multiple spools wound completely or cop are removed jointly, and are replaced with ceases to be busy bobbin.Therefore, spinning machine has doffer
(doffer)Device, the doffer device has doffer bar, and the doffer bar is located on spinning machine, so as to via such as scissors
Mechanism may move.It can clamp and remove jointly or be attached the multiple clampers or doffer clamper of spool or ceases to be busy bobbin again
On doffer bar.Single clamper is preferably can be pneumatically actuated, and the clamping element including iris-diaphragm, the clamping
Element can be worked by compressed air and be taken in spool or spool pipe, and then by introducing compressed sky
Gas clamps spool or spool pipe.In order to make single clamper work by compressed air, the pipe of compressed air is supplied
Road is located in doffer bar, is directed to the single barrier film of clamper via supply line respectively from the compressed air of doffer bar.
The Y of CN 2 873 813 describe the clamper with this design.Clamper has for accommodating spool or spool
The cylindrical holding element of pipe.The clamping element for the diaphragm of rubber form that can be adjusted via pneumatic means is located in holding element
On wall.Using barrier film, the outside grasping of the end of spool that can be from the inside for being inserted into holding element or spool pipe.Barrier film
Holding element is fixed to via direction of two closing caps along longitudinal axis, a closing cap is located on bottom side, another closing
Lid is on the top side of holding element.Two closing caps are clamped to holding element via buckle-type connection.Clamper includes being used for
It is fastened to the tightening member of doffer bar.Tightening member is fixedly connected to holding element, and including for being supplied to barrier film
The air duct of compressed air.Tightening member has hook in its top side, in the flexible holding tab in its bottom side.Clamper is passed through
Container is fixed to by hook, and via elastically keeping in the locking groove that tab is fixed on doffer bar.In the A1 of EP 0303877
Describe the clamper with similar Design.Compared with above-mentioned clamper, the tightening member of clamper is in its bottom side and top side
Upper flexible holding tab.Tab is elastically kept by two, clamper can depart from and be removably attached to doffer bar
On two parallel locking grooves in.Locking groove allows multiple single clampers to be fastened along doffer bar.
When replacing spool or spool pipe, barrier film is worked via air duct by compressed air.As a result, barrier film exists
Shunk in holding element, and spool or spool pipe are grasped from outside in its end region.In order to discharge the line in holding element
Cylinder or spool pipe, the pressure of barrier film is mitigated by interrupting compressed air.Continuous due to the stress on barrier film is alternately applied
Plus and mitigate and barrier film against spool or the frictional force of spool pipe, barrier film weares and teares after certain operation time period.Wear tables
Now become porous for barrier film, and be not airtight in some positions.As a result, no longer ensure that spool or the safety of spool pipe are replaced
Change., it is necessary to replace the barrier film of abrasion with new barrier film after certain operation time period.
One of described clamper significantly has the disadvantage that the barrier film worn and torn with new membrane replacement is comprising a considerable amount of
Effort.In order to replace barrier film, operator must remove clamper from doffer bar first.Therefore, for from CN 2873813
Y clamper, hook is removed from the container in doffer bar, and elastically keeps tab from locking groove release, or for from
The A1 of EP 0303877 clamper, two elastically keep tab from two parallel locking groove releases.Doffer device it
Outside, then upper closing cap and lower closing cap are removed from holding element.Then the barrier film of abrasion is separated with holding element, be used in combination
New membrane replacement.Then the longitudinal axis direction by closing cap by new barrier film along holding element is again fixed to holding member
Part, and clamper is arranged on doffer bar.Due to the design of clamper, the barrier film for replacing abrasion be it is very laborious, because
It must be removed for whole clamper from doffer bar.Therefore, the long downtime that barrier film includes spinning machine is replaced.Further, since
Frequent assembly and disassembly of the clamper on doffer bar, the tab that elastically keeps of clamper is unnecessarily worn and torn.As a result,
It cannot ensure to elastically keep enough clamping effects in locking groove of the tab on doffer bar.
The content of the invention
The purpose of the present invention is this shortcoming for eliminating known clamper.
It is that holding element is maintained on tightening member by retaining element according to the purpose of the realization of the present invention.Via
Retaining element, holding element is secured transverse on tightening member relative to the longitudinal axis of holding element.With the folder of prior art
Holder is compared, and tightening member and holding element are separated each other, i.e. tightening member and the holding element part that to represent two different.Cause
This, in order to replace clamping element, clamper must no longer be removed from doffer bar.But, clamper can be stayed in doffer
On bar, and by dismantle retaining element by holding element together with clamping element from tightening member remove.Then can be simple
The clamping element of abrasion is replaced with new clamping element in ground.Therefore, during clamping element is replaced, the downtime of spinning machine protects
Hold relatively low.In addition, preventing the unnecessary abrasion for elastically keeping tab on tightening member.Falling so that it is guaranteed that elastically keeping tab
Enough clamping effects on yarn machine bar.
In addition, when retaining element partly surrounds the outer wall of holding element or partly installs outer wall against holding element
When, it has proved that it is favourable.This ensures that element is fully held and locate on tightening member.Therefore, except fastening
Outside element, retaining element is also represented by a part for the housing of clamper.Retaining element advantageously surrounds the outer wall of holding element
180 ° and 270 ° between.
When retaining element is connected to tightening member via buckle-type, it is also advantageous.As a result, retaining element is easy
Separated with tightening member, and holding element together with clamping element therefore, it is possible to rapidly being removed from tightening member.Buckle-type
Connection is designed so that tightening member has projection, and retaining element has the raised recess of encirclement.Conversely, however,
It can make retaining element that there is projection, and make tightening member that there is the recess for surrounding projection.
In addition, when clamping element at least one of the end of clamping element along the direction of longitudinal axis via clamping member
The Part I region of periphery of the part above tightening member, and of periphery via clamping element above retaining element
It is favourable when two subregions are fixed to holding element.When at two ends(I.e. at the lower end and upper end of holding element)'s
Clamping element or barrier film, along the direction of the longitudinal axis of holding element, via clamping element or barrier film above tightening member
The Part II region of the Part I region of periphery and the periphery via clamping element or barrier film above retaining element is consolidated
When arriving holding element surely, it is also advantageous.Compared with prior art, therefore eliminate for clamping element to be axially fixed into guarantor
Hold two closing caps of element.In order to realize clamping element to enough axial restraints of holding element, it has proved that work as clamping
Element via 180 ° of tops in the periphery of clamping element tightening member and via on 180 ° of the periphery of clamping element
It is favourable when the retaining element of side is fixed to holding element.
In order to relative to holding element preferably sealed holding element, when sealing ring be located at clamping element and tightening member it
Between holding element at least one end on when, be also advantageous.Sealing ring is located on the lower end of holding element or on upper end, or position
In on the lower end of holding element and upper end.Sealing ring, which is installed into, to be caused first end face surface against tightening member and causes the
Biend surface clamping element is pressed against holding element.Can also install into sealing ring causes sealing ring periphery against fastening member
Part, and make sealing ring inner circumferential that clamping element is pressed against into holding element.
When the circular protrusions extended in the length in holding element are located on the inwall of holding element, also demonstrate that it is favourable
's.The length of holding element represents the size of holding element in their longitudinal direction.Circular protrusions ensure that clamping element is not adhered to
To the inwall of holding element.It is ensured that the safety replacement of spool or spool pipe.It is raised that advantageously there is semi-circular design.
In addition, when at least one rib is located on the outer wall of the holding element at least a portion of the periphery of holding element
When, this is favourable.Rib is used as the support surface for retaining element, and ensures that element via retaining element fully
Hold and locate on tightening member.Rib is advantageously located in holding element, and circumferentially direction extends.Rib surrounds holding member completely
A part for the periphery of part or holding element, preferably between 90 ° and 270 °.However, rib can also be located in holding element,
It is extendable in the longitudinal direction.The multiple ribs being spaced apart from each other can be located in holding element.
Furthermore it is advantageous that when air duct links into an integrated entity with holding element, and tightening member has is used for air
The container of pipeline.Term " one " means that air duct is fixedly integrated in holding element, i.e., air duct can not be with guarantor
Hold element separation.This has advantages below:Holding element and air duct can be manufactured in the form of single injection molding part.
Holding element is loosely connected to the container in tightening member via air duct, i.e. holding element can pass through air duct
It is inserted into container.Therefore, container is dimensioned slightly smaller than air duct.Container in the length of air duct completely or partially
Extension.
In this respect, seal point is formed between air duct and tightening member when air duct has on the outer surface
During at least one annular shoulder, also demonstrate that it is favourable.Shoulder extends on the 2-10 mm lengths of air duct, and by elasticity
Plastics are made.Shoulder links into an integrated entity with air duct.When clamping element is worked by compressed air, air duct exists
Radially expanded in container.Therefore shoulder is pressed against tightening member, and relative to container seal gas pipeline.
Finally, it is favourable when additional potted component is located in container between tightening member and air duct.It is close
Element is sealed relative to tightening member and doffer bar seal gas pipeline.Potted component is advantageously designed to rubber bush, and
Part is extended in the length of air duct.In order to preferably seal, potted component has circumferentially direction on its outer surface
Be spaced apart from each other two ribs of extension.
Brief description of the drawings
Following description of the other feature from one embodiment shown in accompanying drawing of the present invention, accompanying drawing shows following:
Fig. 1 shows the perspective view of the clamper from prior art,
Fig. 2 shows the longitudinal cross-section of the clamper according to Fig. 1,
Fig. 3 shows the perspective view of the clamper according to the present invention,
Fig. 4 shows the longitudinal cross-section of the clamper according to Fig. 3, and
Fig. 5 shows the section of the clamper according to Fig. 3.
Fig. 1 shows the clamper 1 from prior art.Clamper 1 is made of plastics, and with for spool or spool
Pipe 3(Fig. 2)Cylindrical holding element 2.Cylindrical holding element 2 have inwall 4, the iris-diaphragm being made up of rubber it is annoying
The clamping element 5 of dynamic regulation is located on the inwall 4., can be from the spool in the inside for being inserted into holding element 2 using barrier film 5
Or the outside grasping of the end regions of spool pipe 3.Direction of the regulation of barrier film 5 via pneumatic means along double-head arrow 6 is carried out.Barrier film
5 via two closing caps 7 or fixture(One is located on the bottom side 8 of holding element 2, and another is located at the top side 9 of holding element 2
On)Holding element 2 is fixed to along the direction of longitudinal axis 10.Two closing caps 7 are clamped to holding element via buckle-type connection
2。
Clamper 1 has the tightening member 11 for being used for that clamper 1 to be fastened to the doffer bar not shown in Fig. 1 or Fig. 2.
Tightening member 11 is fixedly connected to holding element 2, and includes the air duct for supplying compressed air to barrier film 5
12.Air duct 12 is connected to compressed air line extendable in the longitudinal direction on doffer bar.Air duct 12 via
The first potted component 13 on tightening member 11 is sealed relative to doffer bar.Tightening member 11 also has the second sealing
Element 14, it is relative to compressed air signal linear sealing clamper, and the compressed air signal line is same on doffer bar
It is extendable in the longitudinal direction.Two elastically keep tab 15 on tightening member 11.Tab 15 is elastically kept in their first
Hold and tightening member 11 is connected at 16.Clamper 1, which can depart from and be detachably fixed at its second free end 17, to doff
Machine bar.The holding or clamping effect for keeping tab 15 are increased or aided in, steel bomb by the steel spring 18 being embedded in tightening member 11
Spring 18 is being kept below tab 15.
When replacing spool or spool pipe 3, barrier film 5 is worked via air duct 12 by compressed air.Therefore, every
Film 5 departs from from the inwall 4 of holding element 2, and grasping spool or spool pipe 3 at spool or the outer end region of spool pipe.Then,
Spool or spool pipe 3 can be transferred to unshowned conveyer or main shaft.In order to discharge the spool or line in holding element 2
Bobbin 3, barrier film 5 is eased off the pressure by interrupting compressed air.Barrier film 5 is after certain operation time period, due to keeping
The alternating of the stress on barrier film 5 in element 2 applies and mitigated and barrier film 5 is against the friction of spool or spool pipe 3, barrier film 5
Abrasion.It is porous that abrasion, which shows as barrier film 5, and is not airtight in some positions.As a result, spool or spool are no longer ensured
The safety replacement of pipe 3.After certain operation time period, it is therefore desirable to the barrier film 5 of abrasion is replaced with new barrier film 5.
The significant drawback of clamper 1 shown in Fig. 1 and Fig. 2 is that the barrier film 5 for replacing abrasion with new barrier film 5 includes phase
When substantial amounts of effort.In order to replace barrier film 5, operator must remove clamper 1 from doffer bar first.Therefore, release elasticity
Keep tab 15.Dismounting closing cap 7 is may then pass through to separate the barrier film 5 of abrasion and holding element 2, and with new barrier film 5
Replace.New barrier film 5 is then once again secured in holding element 2 vertically by closing cap 7, and clamper 1 is via elasticity
Tab 15 is kept to be clamped on doffer bar.Due to the design of clamper 1, it is very laborious to replace the barrier film 5 of abrasion, because
Whole clamper 1 must be removed from doffer bar.Therefore, the long downtime that barrier film 5 includes spinning machine is replaced.Further, since
Frequent assembly and disassembly of the clamper 1 on doffer bar, clamper elastically keeps tab 15 by unnecessary abrasion.Knot
Really, no longer ensure to elastically keep enough clamping effect of the tab 15 on doffer bar.
Fig. 3 shows the perspective view of the clamper 1 according to the present invention.Clamper 1 is made of plastics, and with for spool
Or spool pipe 3(Fig. 4)Cylindrical holding element 2.Holding element 2 have inwall 4, the iris-diaphragm being made up of rubber it is annoying
The clamping element 5 of dynamic regulation is located on the inwall 4., can be from the spool in the inside for being inserted into holding element 2 using barrier film 5
Or the outside grasping of the end regions of spool pipe 3.Direction of the regulation of barrier film 5 via pneumatic means along double-head arrow 6 is carried out.Clamping
Device 1 includes the tightening member 11 for being used to being fastened to clamper 1 into unshowned doffer bar.Two elastically keep tab 15 and are located at
On tightening member 11, and tightening member 11 is connected at their first end 16.Second free end 17 of the clamper 1 at it
Place can depart from and be detachably fixed to doffer bar.The holding of holding tab 15 or clamping effect are by being embedded in tightening member 11
In steel spring 18 increase or aid in, steel spring 18 keep tab 15 below.
With compared with the known clamper 1 in Fig. 1 and Fig. 2, holding element 2 is maintained at tightening member via retaining element 19
On 11.Retaining element 19 surrounds 180 ° of the outer wall 20 of holding element 2, or is installed in 180 ° of angular range against holding
The outer wall 20 of element 2(Fig. 5).Therefore in addition to tightening member 11, tightening member 19 is also represented by one of the housing of clamper 1
Point.Via retaining element 19, holding element 2 is secured transverse on tightening member 11 relative to its longitudinal axis 10.Rib 21 is located at
On the outer wall 20 of holding element 2, on the whole periphery of holding element 2.Rib 21 is used as the support surface of retaining element 19, and really
Holding element 2 is protected fully to keep and be positioned on tightening member 11 via retaining element 19.It is evident that fixed from Fig. 5
Element 19 connects detachably connected together with tightening member 11 via buckle-type.Buckle-type connection is designed so that tightening member
11 have projection 22, and retaining element 19 has tab 23, and it is recessed that the tab is engaged with encirclement projection 22 or with projection 22
Portion 24.
Barrier film 5 via 180 ° of tops in the periphery of barrier film 5 tightening member 11, and via in the periphery of barrier film 5
The retaining element 19 of 180 ° of tops, at the lower end 8 and upper end 9 of holding element 2, in axial direction fixed to holding element 2.With
Prior art is compared, therefore eliminates two closing caps 7 or fixture for barrier film 5 to be axially fixed to holding element 2.In order to
Preferably relative to holding element 2 seal barrier film 5, sealing ring 25 respectively positioned at holding element 2 lower end 8 and upper end 9 on, every
Between film 5 and tightening member 11 and retaining element 19.Sealing ring 25 is installed against tightening member using first end face surface 26
11, and barrier film 5 is pressed against to using second end face surface 27 lower end 8 and lower end 8 of holding element 2.Holding element 2 is in it
Wall 4 is provided with the semi-cylindrical hill 28 extended in the length of holding element 2(Fig. 5).
Holding element 2 is additionally provided with air duct 12.Air duct 12 is fixedly connected to the outer wall 20 of holding element 2;
That is holding element 2 and air duct 12 forms as one.Air duct 12 has annular shoulder 31 on its outer surface 30.Shoulder
Portion 31 extends in the 8mm of air duct 12 length 32, and is made up of elastoplast.Shoulder 31 is connected with air duct 12
Integrally.Tightening member 11 has the container 33 for air duct 12.Container 33 is cylindrical, and in air duct 12
Length on extend.Holding element 2 is loosely connected to tightening member 11 via the shoulder 31 of air duct 12.When barrier film 5 is logical
When crossing compressed air and working, air duct 12 radially expands in container 33.Therefore, shoulder 31 is pressed against fastening member
Part 11, and relative to the seal gas pipeline 12 of tightening member 11.
Additional potted component 13 is located between tightening member 11 and air duct 12.Air duct 12 is via potted component
13 are connected to compressed air line extendable in the longitudinal direction on doffer bar.Potted component 13 is designed to rubber bush.
Potted component 13 with first end 35 installs the annular shoulder 31 against air duct 12.Utilize the second end 36, potted component
13 relative to the compressed air line seal gas pipeline 12 on doffer bar.In order to preferably seal, potted component 13
There are two ribs 37 being spaced apart from each other on their outer circumference.It is another potted component 14 to be similarly positioned on tightening member 11,
Another potted component is equally falling relative to compressed air signal linear sealing clamper 1, the compressed air signal line
It is extendable in the longitudinal direction on yarn machine bar.Potted component 14 also has two ribs 37 being spaced apart from each other on their outer circumference, for
Preferably seal.
Compared with known clamper, according to the present invention clamper 1 no longer must integrally be removed from doffer bar with
Just barrier film 5 is replaced.Instead, clamper 1 can be stayed on doffer bar and removes holding element 2 from tightening member 11.
Therefore, retaining element 19 is dismantled from tightening member 11.Then holding element 2 can separate with tightening member 11, and with newly
Barrier film 5 replace abrasion barrier film 5.Therefore, keep relatively low in the downtime for replacing barrier film 5 period spinning machine.Further, since
Holding element 2 must only be removed from clamper 1, it is therefore prevented that elastically keep tab 15 unnecessary on tightening member 11
Abrasion.So that it is guaranteed that elastically keeping enough clamping effect of the tab 15 on doffer bar.
Claims (13)
1. one kind is used to clamp spool or spool pipe(3)Clamper(1), the clamper(1)With tightening member(11)With
With longitudinal axis(10)Cylindrical holding element(2), wherein the holding element(2)With inwall(4)And outer wall(20),
And can be via air duct(12)The clamping element that can be pneumatically actuated worked by compressed air(5)Positioned at described interior
Wall(4)On, and the holding element(2)Via retaining element(19)It is maintained at the tightening member(11)On, its feature exists
In the retaining element(19)Partly surround the holding element(2)The outer wall(20).
2. clamper according to claim 1, it is characterised in that the retaining element(19)Connect and connect via buckle-type
It is connected to the tightening member(11).
3. clamper according to claim 1 or 2, it is characterised in that the clamping element(5)In clamping element end
Along the longitudinal axis at least one(10)Direction via in the tightening member(11)The clamping element periphery of top
Part I region, and via in the retaining element(19)The Part II region of the clamping element periphery of top, it is fixed
To the holding element(2).
4. clamper according to claim 3, it is characterised in that the clamping element(5)At least one in its end
Along the longitudinal axis on individual(10)Direction, via in the clamping element(5)The periphery 180 ° of tops it is described
Tightening member(11), and via in the clamping element(5)The periphery 180 ° of tops the retaining element(19),
Fixed to the holding element(2).
5. clamper according to any one of claim 1 to 4, it is characterised in that sealing ring(25)Kept positioned at described
Element(2)At least one end(8,9)On, in the clamping element(5)With the tightening member(11)Between.
6. clamper according to any one of claim 1 to 5, it is characterised in that in the holding element(2)Length
(29)The circular protrusions of upper extension(28)Positioned at the holding element(2)The inwall(4)On.
7. clamper according to any one of claim 1 to 6, it is characterised in that at least one rib(21)Positioned at described
Holding element(2)The outer wall(20)On in the holding element(2)The periphery at least a portion above.
8. clamper according to any one of claim 1 to 7, it is characterised in that the air duct(12)With it is described
Holding element(2)Link into an integrated entity, and the tightening member(11)With for the air duct(12)Container(33).
9. clamper according to claim 8, it is characterised in that the air duct(12)In outer surface(30)On have
At least one annular shoulder(31), at least one described annular shoulder(31)In the air duct(12)With the tightening member
(11)Between form seal point.
10. clamper according to claim 8 or claim 9, it is characterised in that additional potted component(13)Positioned at the container
(33)In, in the tightening member(11)With the air duct(12)Between.
11. one kind includes having at least one clamper according to any one of claim 1 to 10(1)Doffer bar
Doffer device.
12. a kind of spinning machine with doffer device according to claim 11.
13. a kind of have the clamper being used for according to claim 8 or claim 9(1)Air duct(12)Holding element
(2).
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CH01676/14 | 2014-11-03 | ||
CH01676/14A CH710323A1 (en) | 2014-11-03 | 2014-11-03 | Doffergreifer with zweigeteiltem housing. |
PCT/IB2015/058109 WO2016071789A1 (en) | 2014-11-03 | 2015-10-21 | Doffer gripper having a split housing |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107074478A true CN107074478A (en) | 2017-08-18 |
CN107074478B CN107074478B (en) | 2019-07-16 |
Family
ID=54477038
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201580059561.1A Active CN107074478B (en) | 2014-11-03 | 2015-10-21 | Doffer clamper with two-part shell |
Country Status (4)
Country | Link |
---|---|
EP (1) | EP3215659B1 (en) |
CN (1) | CN107074478B (en) |
CH (1) | CH710323A1 (en) |
WO (1) | WO2016071789A1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110952177A (en) * | 2018-09-27 | 2020-04-03 | 里特机械公司 | Doffer gripper with two-part housing |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107345324A (en) * | 2017-07-28 | 2017-11-14 | 贵州金州兔产业有限公司 | A kind of new rabbit hair spinning machine |
DE102018201097A1 (en) | 2018-01-24 | 2019-07-25 | AUDI HUNGARIA Zrt. | Handling device for gripping and handling a stator of an electrical machine, in particular for a motor vehicle |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR1364639A (en) * | 1962-04-18 | 1964-06-26 | Eugen Maier Fa C | Pneumatic gripper for spinning machine spool changer |
US3831995A (en) * | 1973-06-08 | 1974-08-27 | Molson Co Ltd | Uncaser cup |
DE4128216A1 (en) * | 1991-08-26 | 1993-03-04 | Chemnitzer Spinnereimaschinen | Spinning frame - has pneumatic cop or tube grips with automatic air shut off when removed |
JPH0571686B2 (en) * | 1987-08-18 | 1993-10-07 | Rieter Ag Maschf | |
JPH1193025A (en) * | 1997-07-19 | 1999-04-06 | Mas Fab Rieter Ag | Oil-exchange for ring spinning frame or ring twister, tape-exchange for draft apparatus of ring spinning frame or ring twister and apparatus for performing the tape-exchange |
CN2873813Y (en) * | 2006-01-04 | 2007-02-28 | 东台纺织机械有限责任公司 | Yarn holder of spinning frame integral doffer |
CN200992611Y (en) * | 2007-01-05 | 2007-12-19 | 铜陵市松宝机械有限公司 | Bobbin gripper for spinning frame |
CN201010733Y (en) * | 2007-03-22 | 2008-01-23 | 铜陵市精特机械有限责任公司 | Air cylinder type pipe grasping device |
EP2226572A2 (en) * | 2009-03-04 | 2010-09-08 | WEMEFA Horst Christopeit GmbH | Device for holding a heater |
DE102012104667A1 (en) * | 2012-05-30 | 2013-12-05 | Maschinenfabrik Rieter Ag | Device for common changing of sleeves at spinning locations of textile machine i.e. ring spinning machine, has gripper joist comprising carrier profile arranged inside outer, open hollow section, and grippers arranged at carrier profile |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1180285B (en) * | 1962-04-18 | 1964-10-22 | Eugen Maier C | Pneumatic gripper for pulling devices on continuously working bobbin changers for spinning machines |
SE430881B (en) * | 1981-02-20 | 1983-12-19 | Lars Erik Trygg | bottle grippers |
DE3214128C2 (en) * | 1982-04-16 | 1984-11-15 | Schubert & Salzer Maschinenfabrik Ag, 8070 Ingolstadt | Pneumatic gripper |
DE3912332A1 (en) * | 1989-04-14 | 1990-10-18 | Zinser Textilmaschinen Gmbh | SPOOL GRIP DEVICE |
DE4103729C2 (en) * | 1991-02-07 | 1997-05-28 | Tyrolon Schulnig Gmbh & Co Kg | Gripping device for bottles or the like |
CN102296393B (en) * | 2011-08-11 | 2013-09-11 | 铜陵市松宝机械有限公司 | Rotary bobbin pulling device |
CN103482421B (en) * | 2012-06-08 | 2015-11-18 | 高在甲 | For the bobbin delivery clamp of spinning frame |
-
2014
- 2014-11-03 CH CH01676/14A patent/CH710323A1/en not_active Application Discontinuation
-
2015
- 2015-10-21 WO PCT/IB2015/058109 patent/WO2016071789A1/en active Application Filing
- 2015-10-21 CN CN201580059561.1A patent/CN107074478B/en active Active
- 2015-10-21 EP EP15791038.1A patent/EP3215659B1/en active Active
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR1364639A (en) * | 1962-04-18 | 1964-06-26 | Eugen Maier Fa C | Pneumatic gripper for spinning machine spool changer |
US3831995A (en) * | 1973-06-08 | 1974-08-27 | Molson Co Ltd | Uncaser cup |
JPH0571686B2 (en) * | 1987-08-18 | 1993-10-07 | Rieter Ag Maschf | |
DE4128216A1 (en) * | 1991-08-26 | 1993-03-04 | Chemnitzer Spinnereimaschinen | Spinning frame - has pneumatic cop or tube grips with automatic air shut off when removed |
JPH1193025A (en) * | 1997-07-19 | 1999-04-06 | Mas Fab Rieter Ag | Oil-exchange for ring spinning frame or ring twister, tape-exchange for draft apparatus of ring spinning frame or ring twister and apparatus for performing the tape-exchange |
CN2873813Y (en) * | 2006-01-04 | 2007-02-28 | 东台纺织机械有限责任公司 | Yarn holder of spinning frame integral doffer |
CN200992611Y (en) * | 2007-01-05 | 2007-12-19 | 铜陵市松宝机械有限公司 | Bobbin gripper for spinning frame |
CN201010733Y (en) * | 2007-03-22 | 2008-01-23 | 铜陵市精特机械有限责任公司 | Air cylinder type pipe grasping device |
EP2226572A2 (en) * | 2009-03-04 | 2010-09-08 | WEMEFA Horst Christopeit GmbH | Device for holding a heater |
DE102012104667A1 (en) * | 2012-05-30 | 2013-12-05 | Maschinenfabrik Rieter Ag | Device for common changing of sleeves at spinning locations of textile machine i.e. ring spinning machine, has gripper joist comprising carrier profile arranged inside outer, open hollow section, and grippers arranged at carrier profile |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110952177A (en) * | 2018-09-27 | 2020-04-03 | 里特机械公司 | Doffer gripper with two-part housing |
Also Published As
Publication number | Publication date |
---|---|
WO2016071789A1 (en) | 2016-05-12 |
EP3215659A1 (en) | 2017-09-13 |
CH710323A1 (en) | 2016-05-13 |
CN107074478B (en) | 2019-07-16 |
EP3215659B1 (en) | 2021-03-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107074478A (en) | Doffer clamper with two-part housing | |
CN200992611Y (en) | Bobbin gripper for spinning frame | |
CN106457418A (en) | Clamping bushing and clamping device | |
CN107512145A (en) | Air suspension component | |
CN106536389A (en) | Chuck | |
JP2014527464A5 (en) | ||
CN110194368A (en) | Vacuum electric tool | |
CN105051431A (en) | Piston for a compressed air control valve | |
JP2013517190A (en) | Winding spindle | |
KR20200103124A (en) | Creel | |
JP2011179140A (en) | Textile machine and pipe joint | |
KR970702209A (en) | Thread store with thread draw-off brake | |
US20160102755A1 (en) | Cartridge valve | |
CN101680585B (en) | Method for manufacturing detachable pneumatic connection | |
CN108150829A (en) | Pressurized gas cylinder | |
US9802783B1 (en) | Yarn cone holder with yarn retention arm | |
CN104302818B (en) | Fastening means for a compression module on a spinning machine | |
CN102921564A (en) | Filter bag fixing device of pull bag centrifugal machine | |
CN103801738A (en) | Drill chuck | |
EP2646666B1 (en) | Insert, holder and post-treatment unit for exhaust gases | |
KR20200036758A (en) | Doffer gripper with a two-part housing | |
AU2017206408B2 (en) | Pneumatic spring for axles of vehicles with air suspension | |
US2071742A (en) | Brake cylinder protector | |
US20140373325A1 (en) | Arrangement for forming a seal | |
US20180290091A1 (en) | Securing System and Method for Assembling or Disassembling the Securing System |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |