CN107062475A - A kind of ice-storage air-conditioning economic benefit on-line monitoring method - Google Patents

A kind of ice-storage air-conditioning economic benefit on-line monitoring method Download PDF

Info

Publication number
CN107062475A
CN107062475A CN201710187732.XA CN201710187732A CN107062475A CN 107062475 A CN107062475 A CN 107062475A CN 201710187732 A CN201710187732 A CN 201710187732A CN 107062475 A CN107062475 A CN 107062475A
Authority
CN
China
Prior art keywords
ice
conditioning
data
storage air
cold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710187732.XA
Other languages
Chinese (zh)
Inventor
张利
张宇
甘智勇
李丛林
张宝栋
王梓越
屈斌
王坤
李国豪
何少聪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Tianjin Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710187732.XA priority Critical patent/CN107062475A/en
Publication of CN107062475A publication Critical patent/CN107062475A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F5/00Air-conditioning systems or apparatus not covered by F24F1/00 or F24F3/00, e.g. using solar heat or combined with household units such as an oven or water heater
    • F24F5/0007Air-conditioning systems or apparatus not covered by F24F1/00 or F24F3/00, e.g. using solar heat or combined with household units such as an oven or water heater cooling apparatus specially adapted for use in air-conditioning
    • F24F5/0017Air-conditioning systems or apparatus not covered by F24F1/00 or F24F3/00, e.g. using solar heat or combined with household units such as an oven or water heater cooling apparatus specially adapted for use in air-conditioning using cold storage bodies, e.g. ice
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/30Control or safety arrangements for purposes related to the operation of the system, e.g. for safety or monitoring
    • F24F11/46Improving electric energy efficiency or saving
    • F24F11/47Responding to energy costs
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02E60/14Thermal energy storage

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Economics (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Health & Medical Sciences (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Development Economics (AREA)
  • Operations Research (AREA)
  • Primary Health Care (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Public Health (AREA)
  • Quality & Reliability (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Sustainable Development (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Air Conditioning Control Device (AREA)

Abstract

The present invention relates to a kind of ice-storage air-conditioning economic benefit on-line monitoring method, this method step has:Ice-storage air-conditioning real-time running data needed for the collection of real-time running data acquisition module;Real-time data acquisition net is recompiled to the transmission data of reception, isolated;Real time data processing module carries out the judgement of data area to raw operational data and averaged;Economic benefit calculation module, which is calculated, is currently entering system general refrigeration ability and discharge system general refrigeration ability, calculates economic benefit;Data storage server is while the data of receiving real-time data collection net and economic benefit calculation module, complete classification and store;Economic benefit and history data are presented in the form of form and curve in main display.The present invention reflects ice-storage air-conditioning economic benefit and history data in the form of form and history curve, helps operations staff to grasp ice-storage air-conditioning situation, reference is provided for the economical operation of ice-storage air-conditioning.

Description

A kind of ice-storage air-conditioning economic benefit on-line monitoring method
Technical field
The invention belongs to energy-conserving product running technology field, particularly a kind of ice-storage air-conditioning economic benefit on-line monitoring side Method.
Background technology
As the use of the energy-conserving products such as ice-storage air-conditioning is more and more extensive, the economic effect of ice-storage air-conditioning is grasped at any time Benefit, can provide guidance for the adjustment operation of operations staff and advise.But, current ice-storage air-conditioning economic benefit can only pass through Statistics, which is calculated, to be obtained, and currently without the method that can monitor ice-storage air-conditioning economic benefit in real time, causes the warp of ice-storage air-conditioning Ji operation lacks necessary technical support.
The content of the invention
The purpose of the present invention is in view of the shortcomings of the prior art, and to propose a kind of ice-storage air-conditioning economic benefit on-line monitoring Method.
The present invention solves its technical problem and takes following technical scheme to realize:
A kind of ice-storage air-conditioning economic benefit on-line monitoring method, including step are as follows:
(1) system is constituted
The system include ice-storage air-conditioning service data acquisition module, real-time data acquisition net, real time data processing module, Economic benefit calculation module, data storage server and on-line monitoring main display;
(2) ice needed for ice-storage air-conditioning service data acquisition module from ice-storage air-conditioning operation control system collection of server Cold accumulation air-conditioner real-time running data, and real-time running data is sent to real-time data acquisition net;
(3) ice-storage air-conditioning real-time data acquisition net is recompiled to the transmission data of reception, isolation with it is outside its The contact of its data transmission network, and result will be recompiled send to real time data processing module and data storage server;
(4) real time data processing module ice-storage air-conditioning raw operational data judge by the data that receive and Processing, is sequentially completed the judgement of data area for data-signal and averages, and result is sent to economic benefit Computing module;
(5) economic benefit calculation module to receive data calculate under current operating condition ice-storage air-conditioning power consumption totle drilling cost and User converts totle drilling cost with cold, and then calculates ice-storage air-conditioning economic benefit, and result of calculation is sent to on-line monitoring System main display and data storage server;
(6) data storage server receives the number for coming from real-time data acquisition net and economic benefit calculation module simultaneously According to, and the classification and storage of data are completed, for user of service's transferring and subsequent treatment to historical data;
(7) ice-storage air-conditioning economic benefit reality is presented in on-line monitoring system main display simultaneously in the form of form and curve When data and history data.
Moreover, ice-storage air-conditioning real-time running data is specifically included in the step (2):The period power consumption of ice-storage air-conditioning peak Measure Pf, usually section power consumption Pp, paddy period power consumption Pg;The user peak period uses cold Qf, usually section cold Qp, the paddy period is with cold Measure Qg
Moreover, it is by the ice-storage air-conditioning peak of reception that the transmission data of reception, which recompile, in the step (3) Period power consumption Pf, usually section power consumption Pp, paddy period power consumption Pg;The user peak period uses cold Qf, usually section cold Qp, paddy Period uses cold QgTransmission data are combined II binary datas coding with time data bag again.
Moreover, being comprised the concrete steps that in the step (4) for the judgement that data-signal is sequentially completed data area:
1. the height limit range ability of every kind of data-signal is set in real time data processing module;
2. every kind of data-signal real time data processing module received is compared with height limit range ability respectively, If in range ability, judging that data rationally can use, if not in range ability, judging that data are unreasonable, going forward side by side Row alarm;
3. for the data using dual or multiple measuring point, after the judgement of data reasonability is completed, to all measuring point numbers According to carry out arithmetic average, and using average value as the measuring point end value.
Moreover, the circular of ice-storage air-conditioning power consumption totle drilling cost is in the step (5):
1. by ice-storage air-conditioning peak period power consumption Pf, calculate ice-storage air-conditioning peak period power consumption cost Mf=Pf×Af, its Middle AfIt is a constant for area power grid peak period electricity price;
2. by ice-storage air-conditioning usually section power consumption Pp, calculate ice-storage air-conditioning usually section power consumption cost Mp=Pp×Ap, its Middle ApIt is a constant for area power grid usually section electricity price;
3. by ice-storage air-conditioning peak period power consumption Pg, calculate ice-storage air-conditioning peak period power consumption cost Mg=Pg×Ag, its Middle AgIt is a constant for area power grid paddy period electricity price;
4. ice-storage air-conditioning power consumption totle drilling cost Mx=Mf+Mp+Mg
User is with the circular of cold conversion totle drilling cost in the step (5):
1. cold Q is used by the user peak periodf, user's peak period is calculated with cold conversion cost MfQ=(Qf/s)×Af, wherein S is the cold conversion coefficient of ice-storage air-conditioning electricity, is a constant;
2. by user usually section cold Qp, calculating user, usually section converts cost M with coldpQ=(Qp/s)×Ap
3. cold Q is used the paddy period by userg, user's paddy period is calculated with cold conversion cost MgQ=(Qg/s)×Ag
4. user converts totle drilling cost M with coldy=MfQ+MpQ+MgQ
The circular of ice-storage air-conditioning economic benefit is in the step (5):
Ice-storage air-conditioning economic benefit M=My-Mx
Moreover, the specific sorting technique that data are classified in the step (6) is:Data are divided into ice-storage air-conditioning real time execution Data and calculation result data,
1. wherein ice-storage air-conditioning real-time running data includes:Ice-storage air-conditioning peak period power consumption Pf, usually section power consumption Measure Pp, paddy period power consumption Pg;The user peak period uses cold Qf, usually section cold Qp, the paddy period use cold Qg
2. wherein calculation result data storage synchronous with time data bag.
Moreover, form specifically includes ice-storage air-conditioning peak period power consumption P in the step (7)f, usually section power consumption Pp、 Paddy period power consumption Pg;The user peak period uses cold Qf, usually section cold Qp, the paddy period use cold Qg;The curve is specifically wrapped Include the curve that ice-storage air-conditioning economic benefit is changed over time.
Advantages and positive effects of the present invention are:
The present invention by ice-storage air-conditioning real-time running data acquisition module, ice-storage air-conditioning real-time data acquisition net, in real time Data processing module, ice-storage air-conditioning economic benefit calculation module, data storage server, ice-storage air-conditioning economic benefit are online Monitoring system key frame links together, and constitutes ice-storage air-conditioning economic benefit on-line monitoring system.The system by counting in real time Calculation can reflect the economic benefit of ice-storage air-conditioning, and be presented to operations staff in the form of chart and history curve, help to transport Administrative staff grasps ice-storage air-conditioning economic benefit, and reference is provided for the economical operation of ice-chilling air conditioning system.
Brief description of the drawings
Fig. 1 is the system logic graph of a relation of the present invention.
Embodiment
The embodiment of the present invention is further described below in conjunction with accompanying drawing:It is emphasized that of the present invention implement Example is illustrative, rather than limited, therefore the present invention is not limited to the embodiment described in embodiment, every The other embodiment drawn by those skilled in the art's technique according to the invention scheme, also belongs to the model that the present invention is protected Enclose.
A kind of ice-storage air-conditioning economic benefit on-line monitoring method, including step are as follows:
(1) system is constituted
The system include ice-storage air-conditioning service data acquisition module, real-time data acquisition net, real time data processing module, Economic benefit calculation module, data storage server and on-line monitoring main display;
(2) ice needed for ice-storage air-conditioning service data acquisition module from ice-storage air-conditioning operation control system collection of server Cold accumulation air-conditioner real-time running data, and real-time running data is sent to real-time data acquisition net;
Wherein, ice-storage air-conditioning real-time running data is specifically included:Ice-storage air-conditioning peak period power consumption Pf, usually section consume Electricity Pp, paddy period power consumption Pg;The user peak period uses cold Qf, usually section cold Qp, the paddy period use cold Qg
(3) ice-storage air-conditioning real-time data acquisition net is recompiled to the transmission data of reception, isolation with it is outside its The contact of its data transmission network, and result will be recompiled send to real time data processing module and data storage server;
Wherein, it is by the ice-storage air-conditioning peak period power consumption P of reception the transmission data of reception recompilef、 Usually section power consumption Pp, paddy period power consumption Pg;The user peak period uses cold Qf, usually section cold Qp, the paddy period use cold Qg Transmission data are combined II binary datas coding with time data bag again.
(4) real time data processing module ice-storage air-conditioning raw operational data judge by the data that receive and Processing, is sequentially completed the judgement of data area for data-signal and averages, and result is sent to economic benefit Computing module;
Wherein, comprised the concrete steps that in the step (4) for the judgement that data-signal is sequentially completed data area:
1. the height limit range ability of every kind of data-signal is set in real time data processing module;
2. every kind of data-signal real time data processing module received is compared with height limit range ability respectively, If in range ability, judging that data rationally can use, if not in range ability, judging that data are unreasonable, going forward side by side Row alarm;
3. for the data using dual or multiple measuring point, after the judgement of data reasonability is completed, to all measuring point numbers According to carry out arithmetic average, and using average value as the measuring point end value.
(5) economic benefit calculation module to receive data calculate under current operating condition ice-storage air-conditioning power consumption totle drilling cost and User converts totle drilling cost with cold, and then calculates ice-storage air-conditioning economic benefit, and result of calculation is sent to on-line monitoring System main display and data storage server;
Wherein, the circular of ice-storage air-conditioning power consumption totle drilling cost is in the step (5):
1. by ice-storage air-conditioning peak period power consumption Pf, calculate ice-storage air-conditioning peak period power consumption cost Mf=Pf×Af, its Middle AfIt is a constant for area power grid peak period electricity price;
2. by ice-storage air-conditioning usually section power consumption Pp, calculate ice-storage air-conditioning usually section power consumption cost Mp=Pp×Ap, its Middle ApIt is a constant for area power grid usually section electricity price;
3. by ice-storage air-conditioning peak period power consumption Pg, calculate ice-storage air-conditioning peak period power consumption cost Mg=Pg×Ag, its Middle AgIt is a constant for area power grid paddy period electricity price;
4. ice-storage air-conditioning power consumption totle drilling cost Mx=Mf+Mp+Mg
Wherein, user is with the circular of cold conversion totle drilling cost in the step (5):
1. cold Q is used by the user peak periodf, user's peak period is calculated with cold conversion cost MfQ=(Qf/s)×Af, wherein S is the cold conversion coefficient of ice-storage air-conditioning electricity, is a constant;
2. by user usually section cold Qp, calculating user, usually section converts cost M with coldpQ=(Qp/s)×Ap
3. cold Q is used the paddy period by userg, user's paddy period is calculated with cold conversion cost MgQ=(Qg/s)×Ag
4. user converts totle drilling cost M with coldy=MfQ+MpQ+MgQ
Wherein, the circular of ice-storage air-conditioning economic benefit is in the step (5):
Ice-storage air-conditioning economic benefit M=My-Mx
(6) data storage server receives the number for coming from real-time data acquisition net and economic benefit calculation module simultaneously According to, and the classification and storage of data are completed, for user of service's transferring and subsequent treatment to historical data;
Wherein, the specific sorting technique of data classification is in the step (6):
1. data are divided into ice-storage air-conditioning real-time running data and calculation result data, wherein ice-storage air-conditioning real time execution Data include:Ice-storage air-conditioning peak period power consumption Pf, usually section power consumption Pp, paddy period power consumption Pg;The user peak period is with cold Measure Qf, usually section cold Qp, the paddy period use cold Qg
2. because the collection of ice-storage air-conditioning real-time running data is from ice-storage air-conditioning operation control system server, in this number No longer preserved according in storage server, wherein calculation result data storage synchronous with time data bag.
(7) ice-storage air-conditioning economic benefit reality is presented in on-line monitoring system main display simultaneously in the form of form and curve When data and history data.
Wherein, form specifically includes ice-storage air-conditioning peak period power consumption P in the step (7)f, usually section power consumption Pp、 Paddy period power consumption Pg;The user peak period uses cold Qf, usually section cold Qp, the paddy period use cold Qg
Wherein, the curve is specifically included:The curve that ice-storage air-conditioning economic benefit is changed over time.

Claims (7)

1. a kind of ice-storage air-conditioning economic benefit on-line monitoring method, it is characterised in that as follows including step:
(1) system is constituted
The system includes ice-storage air-conditioning service data acquisition module, real-time data acquisition net, real time data processing module, economy Benefit calculation module, data storage server and on-line monitoring main display;
(2) ice cold-storage needed for ice-storage air-conditioning service data acquisition module from ice-storage air-conditioning operation control system collection of server Air-conditioning real-time running data, and real-time running data is sent to real-time data acquisition net;
(3) ice-storage air-conditioning real-time data acquisition net is recompiled to the transmission data of reception, isolation and outside other numbers According to the contact of transmission network, and result will be recompiled send to real time data processing module and data storage server;
(4) real time data processing module is judged and located to ice-storage air-conditioning raw operational data by the data received Reason, is sequentially completed the judgement of data area for data-signal and averages, and result is sent to economic benefit meter Calculate module;
(5) economic benefit calculation module calculates ice-storage air-conditioning power consumption totle drilling cost and user under current operating condition to receiving data Totle drilling cost is converted with cold, and then calculates ice-storage air-conditioning economic benefit, and result of calculation is sent to on-line monitoring system Main display and data storage server;
(6) data storage server receives the data for coming from real-time data acquisition net and economic benefit calculation module simultaneously, and The classification and storage of data are completed, for user of service's transferring and subsequent treatment to historical data;
(7) on-line monitoring system main display is presented ice-storage air-conditioning economic benefit and counted in real time simultaneously in the form of form and curve According to this and history data.
2. ice-storage air-conditioning economic benefit on-line monitoring method according to claim 1, it is characterised in that:
Ice-storage air-conditioning real-time running data is specifically included in the step (2):Ice-storage air-conditioning peak period power consumption Pf, usually Section power consumption Pp, paddy period power consumption Pg;The user peak period uses cold Qf, usually section cold Qp, the paddy period use cold Qg
3. ice-storage air-conditioning economic benefit on-line monitoring method according to claim 1, it is characterised in that:The step (3) it is by the ice-storage air-conditioning peak period power consumption P of reception that the transmission data of reception, which recompile, inf, usually section consume Electricity Pp, paddy period power consumption Pg;The user peak period uses cold Qf, usually section cold Qp, the paddy period use cold QgTransmit data Again II binary datas coding is combined with time data bag.
4. ice-storage air-conditioning economic benefit on-line monitoring method according to claim 1, it is characterised in that:The step (4) comprised the concrete steps that in for the judgement that data-signal is sequentially completed data area:
1. the height limit range ability of every kind of data-signal is set in real time data processing module;
2. every kind of data-signal real time data processing module received is compared with height limit range ability respectively, if In range ability, then judge that data rationally can use, if not in range ability, judging that data are unreasonable, and reported Alert prompting;
3. for the data using dual or multiple measuring point, after the judgement of data reasonability is completed, all measuring point datas are entered Row arithmetic average, and using average value as the measuring point end value.
5. ice-storage air-conditioning economic benefit on-line monitoring method according to claim 1, it is characterised in that:The step (5) circular of ice-storage air-conditioning power consumption totle drilling cost is in:
1. by ice-storage air-conditioning peak period power consumption Pf, calculate ice-storage air-conditioning peak period power consumption cost Mf=Pf×Af, wherein Af It is a constant for area power grid peak period electricity price;
2. by ice-storage air-conditioning usually section power consumption Pp, calculate ice-storage air-conditioning usually section power consumption cost Mp=Pp×Ap, wherein Ap It is a constant for area power grid usually section electricity price;
3. by ice-storage air-conditioning peak period power consumption Pg, calculate ice-storage air-conditioning peak period power consumption cost Mg=Pg×Ag, wherein Ag It is a constant for area power grid paddy period electricity price;
4. ice-storage air-conditioning power consumption totle drilling cost Mx=Mf+Mp+Mg
User is with the circular of cold conversion totle drilling cost in the step (5):
1. cold Q is used by the user peak periodf, user's peak period is calculated with cold conversion cost MfQ=(Qf/s)×Af, wherein s is The cold conversion coefficient of ice-storage air-conditioning electricity, is a constant;
2. by user usually section cold Qp, calculating user, usually section converts cost M with coldpQ=(Qp/s)×Ap
3. cold Q is used the paddy period by userg, user's paddy period is calculated with cold conversion cost MgQ=(Qg/s)×Ag
4. user converts totle drilling cost M with coldy=MfQ+MpQ+MgQ
The circular of ice-storage air-conditioning economic benefit is in the step (5):
Ice-storage air-conditioning economic benefit M=My-Mx
6. ice-storage air-conditioning economic benefit on-line monitoring method according to claim 1, it is characterised in that:The step (6) the specific sorting technique of data classification is in:Data are divided into ice-storage air-conditioning real-time running data and calculation result data,
1. wherein ice-storage air-conditioning real-time running data includes:Ice-storage air-conditioning peak period power consumption Pf, usually section power consumption Pp、 Paddy period power consumption Pg;The user peak period uses cold Qf, usually section cold Qp, the paddy period use cold Qg
2. wherein calculation result data storage synchronous with time data bag.
7. ice-storage air-conditioning economic benefit on-line monitoring method according to claim 1, it is characterised in that:
Form specifically includes ice-storage air-conditioning peak period power consumption P in the step (7)f, usually section power consumption Pp, the paddy period consumption Electricity Pg;The user peak period uses cold Qf, usually section cold Qp, the paddy period use cold Qg;The curve specifically includes ice cold-storage The curve that air-conditioning economic benefit is changed over time.
CN201710187732.XA 2017-03-27 2017-03-27 A kind of ice-storage air-conditioning economic benefit on-line monitoring method Pending CN107062475A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710187732.XA CN107062475A (en) 2017-03-27 2017-03-27 A kind of ice-storage air-conditioning economic benefit on-line monitoring method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710187732.XA CN107062475A (en) 2017-03-27 2017-03-27 A kind of ice-storage air-conditioning economic benefit on-line monitoring method

Publications (1)

Publication Number Publication Date
CN107062475A true CN107062475A (en) 2017-08-18

Family

ID=59621162

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710187732.XA Pending CN107062475A (en) 2017-03-27 2017-03-27 A kind of ice-storage air-conditioning economic benefit on-line monitoring method

Country Status (1)

Country Link
CN (1) CN107062475A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108361885A (en) * 2018-01-30 2018-08-03 深圳市奥宇节能技术股份有限公司 A kind of ice-chilling air conditioning system dynamic programming method
CN108596458A (en) * 2018-04-12 2018-09-28 国网天津市电力公司电力科学研究院 A kind of earth source heat pump winter economic benefit on-line monitoring method
CN110657512A (en) * 2018-06-29 2020-01-07 清华大学 Ice storage air conditioner economic analysis method and device based on thermoelectric combined scheduling
CN111174376A (en) * 2019-09-18 2020-05-19 同方泰德国际科技(北京)有限公司 Calculation method for energy efficiency evaluation of cold storage air-conditioning system based on measured value

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101464475A (en) * 2009-01-23 2009-06-24 北京佩尔优科技有限公司 Energy accumulation income measuring system and method thereof
JP2010242990A (en) * 2009-04-01 2010-10-28 Tokyo Toshi Service Kk Air conditioning system
CN103499136A (en) * 2013-09-26 2014-01-08 中铁建设集团有限公司 Ice storage control system with next-day energy consumption simulating function
CN204534977U (en) * 2015-01-12 2015-08-05 上禾谷能源科技(北京)有限公司 A kind of ice conserve cold amount of energy saving monitoring system
CN104864648A (en) * 2015-04-30 2015-08-26 国家电网公司 Method for online monitoring of overall performance coefficient of recycled circulation water waste heat of absorption heat pump
CN105020773A (en) * 2015-07-01 2015-11-04 国网天津市电力公司 Online monitoring method for performance coefficients of warming type heat pump for recycling residual heat of circulating water

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101464475A (en) * 2009-01-23 2009-06-24 北京佩尔优科技有限公司 Energy accumulation income measuring system and method thereof
JP2010242990A (en) * 2009-04-01 2010-10-28 Tokyo Toshi Service Kk Air conditioning system
CN103499136A (en) * 2013-09-26 2014-01-08 中铁建设集团有限公司 Ice storage control system with next-day energy consumption simulating function
CN204534977U (en) * 2015-01-12 2015-08-05 上禾谷能源科技(北京)有限公司 A kind of ice conserve cold amount of energy saving monitoring system
CN104864648A (en) * 2015-04-30 2015-08-26 国家电网公司 Method for online monitoring of overall performance coefficient of recycled circulation water waste heat of absorption heat pump
CN105020773A (en) * 2015-07-01 2015-11-04 国网天津市电力公司 Online monitoring method for performance coefficients of warming type heat pump for recycling residual heat of circulating water

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108361885A (en) * 2018-01-30 2018-08-03 深圳市奥宇节能技术股份有限公司 A kind of ice-chilling air conditioning system dynamic programming method
CN108596458A (en) * 2018-04-12 2018-09-28 国网天津市电力公司电力科学研究院 A kind of earth source heat pump winter economic benefit on-line monitoring method
CN110657512A (en) * 2018-06-29 2020-01-07 清华大学 Ice storage air conditioner economic analysis method and device based on thermoelectric combined scheduling
CN111174376A (en) * 2019-09-18 2020-05-19 同方泰德国际科技(北京)有限公司 Calculation method for energy efficiency evaluation of cold storage air-conditioning system based on measured value

Similar Documents

Publication Publication Date Title
CN107062475A (en) A kind of ice-storage air-conditioning economic benefit on-line monitoring method
CN107038527A (en) A kind of heat storage electric boiler economic benefit on-line monitoring method
US11513480B2 (en) Method and device for automatically diagnosing and controlling apparatus in intelligent building
CN104534617B (en) Cold source centralized digital control method based on energy consumption monitoring
CN105204449B (en) Aluminum section extruder real time energy consumption monitors and energy consumption abnormality detection system
CN103335537B (en) Condenser real time execution cleanliness factor on-line monitoring method
CN104863841A (en) Method for online efficiency monitoring of circulating water pump in thermal power plant
CN105890819A (en) Back-pressure steam turbine heat consumption rate on-line monitoring method
CN106899431A (en) The crucial environmental surveillance of intelligent task and EMS
CN105003427A (en) Online efficiency monitoring method of condensate pump of thermal power generating unit
CN105046595B (en) Energy efficiency assessment and diagnosis cloud system and method based on Internet of things technology
TW200902920A (en) Remote capability monitoring device and method
CN104864648B (en) Absorption heat pump reclaims circulating water afterheat overall coefficient of performance on-line monitoring method
CN109829592B (en) Loss prediction method, device, equipment and storage medium for express cabinet users
CN105976588A (en) Comprehensive bridge distribution type monitoring processing system
CN114446037A (en) Carbon emission monitoring system and method based on Internet of things technology
CN202614339U (en) Monitoring system for flow state data of gas gauge flow meters
CN103914965A (en) Urban heat supply data acquisition system based on internet of things technology
CN108830440A (en) A kind of earth source heat pump summer economic benefit on-line monitoring method
CN108596458A (en) A kind of earth source heat pump winter economic benefit on-line monitoring method
CN201896733U (en) Energy-saving diagnosis instrument for air compressor
CN106292408A (en) A kind of multiple-energy-sources based on RSMC's data comprehensive utilization control system
CN202331187U (en) Remote PLC (programmable logic controller) state monitoring and fault alarm system supporting WEB view
CN108302327A (en) A kind of gas pipeline remote monitoring system
CN103955748A (en) Single-load decision optimization method based on data communication reliability

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170818