CN107035377A - A kind of construction method of tailwater tunnel excavation supporting - Google Patents

A kind of construction method of tailwater tunnel excavation supporting Download PDF

Info

Publication number
CN107035377A
CN107035377A CN201710489258.6A CN201710489258A CN107035377A CN 107035377 A CN107035377 A CN 107035377A CN 201710489258 A CN201710489258 A CN 201710489258A CN 107035377 A CN107035377 A CN 107035377A
Authority
CN
China
Prior art keywords
hole
layer
excavation
drilling
tailwater tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710489258.6A
Other languages
Chinese (zh)
Other versions
CN107035377B (en
Inventor
张洪宝
林平
朱宿雨
卢星星
叶云洲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang East China Engineering Consulting Co Ltd
Original Assignee
Zhejiang East China Engineering Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang East China Engineering Consulting Co Ltd filed Critical Zhejiang East China Engineering Consulting Co Ltd
Priority to CN201710489258.6A priority Critical patent/CN107035377B/en
Publication of CN107035377A publication Critical patent/CN107035377A/en
Application granted granted Critical
Publication of CN107035377B publication Critical patent/CN107035377B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/003Machines for drilling anchor holes and setting anchor bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/021Grouting with inorganic components, e.g. cement
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/006Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/10Making by using boring or cutting machines
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings

Abstract

The invention discloses a kind of construction method of tailwater tunnel excavation supporting, tailwater tunnel is from vault to bottom plate is divided into I layer, II layer with III layer and being constructed from top to bottom successively, it is quick-fried by way of preceding excavate in rear supporting follow-up boring, while improving excavation effect, it is ensured that the stability of country rock.

Description

A kind of construction method of tailwater tunnel excavation supporting
Technical field
The present invention relates to a kind of construction technology of underground ground drilling, a kind of more particularly to tailwater tunnel excavation supporting is applied Work method.
Background technology
At present, in coastal thermal power plant or nuclear power plant project, circulation typically uses direct-flow water supply system, i.e., In marine site water intaking, after the cold and hot energy exchange circulation of power plant, then marine site is drained back into.Due to the spy of factory site topographic and geologic condition Point, and consider the factor such as technology and economic condition, the drainage channel of the recirculated water of many power plant engineerings, which needs to use, passes through mountain Internal tailwater tunnel is realized.
Generally, in order to tunnel mouthful structure safety and convenient carry out hole support reinforcement, it is desirable to canal axes with Tunnel mouthful hillside is domatic substantially vertical.In order to reduce tunnel mouthful temperature pier investment, tunnel openings position is all selected in geology as far as possible Condition is preferably local.The existing construction usual way for tunnel is excavating load, and such a method excavates skill for soft soil zone There can be the safety problem of massif slope failure after art is simple, and need not adjust tunnel route, but the weak soil soil body is excavated simultaneously. And be to avoid safety problem appearance and the increase of supporting expense, soft soil zone can be typically avoided, selection geological conditions is preferable Position, but in the country rock grade construction of I class, II class or III class, due to rock property preferably, common excavating load is difficult Degree is larger, and efficiency of construction is relatively low.
The content of the invention
It is an object of the invention to provide a kind of construction method of tailwater tunnel excavation supporting, opened using drilling and blasting method combination layering Dig and supporting follow-up mode, reduction excavates difficulty and improves efficiency of construction.
The present invention above-mentioned technical purpose technical scheme is that:
A kind of construction method of tailwater tunnel excavation supporting, comprises the following steps:
1)The height of tailwater tunnel is designed according to construction road distribution situation, and tailwater tunnel is divided into I from vault to bottom plate Layer, II layer and III layer, wherein III layer is used as base plate protection layer;
2)I layer of excavation:Using drill-blast tunnelling method, photoface exploision, the control of artillery salvo drilling depth bores quick-fried rear arch top spray steel fine in 3.1 ~ 3.5m Tie up concrete, abutment wall shotcrete with mesh and suspension roof support;
3)II layer of excavation:Carry out carrying out abutment wall presplitting first, and disposable presplitting is completed after presplitting to II layer of middle part to bottom plate Excavated using drill-blast tunnelling method in region;
4)III layer of excavation:Using drill-blast tunnelling method, artillery salvo drilling depth control follow-up spray anchor after the completion of 3.05 ~ 3.5m, excavation is excavated Supporting.
By using above-mentioned technical proposal, layering staged construction is carried out to tunnel and improves the stability of country rock, and is utilized Quick-fried mode is bored first to I layer, II layer and III layer progress explosion open circuit, facilitates follow-up excavation construction and improves efficiency of construction, Secondly the drilling depth of controlled blasting reduces rock burst, and the profile quality side that photoface exploision mode improves excavation section at first is used for I layer Just II layer and III layer of ensuing blast excavation, carry out presplitting to abutment wall first in II layer of construction, and the stress of II layer of country rock of adjustment is carried The effect of high follow-up country rock explosion;In addition every layer of Blasting Excavation simultaneously follow up supporting avoid excavation section cave in situation raising Security in work progress.
Preferably, the drill-blast tunnelling method includes following operating procedure:
1)Preparation of construction:Wind in hole, water, electricity are ready, and workmen, equipment prepare in place, periphery presplitting excavate before according to setting Count blasting parameter and carry out experimental explosion, according to demolition effect to determine suitable blasting parameter;
2)Surveying setting-out:Measurement is before professional's unwrapping wire, periphery pre-splitting hole, and measurement need to release peripheral profile line or explosion Hole hole position, must be designed gauge wire measuring, the delayed 10~15m of excavation face of section survey is pressed during section excavation after every artillery salvo Mono- section of 5m, meanwhile, with cavern excavation, supporting progress, a pile No. mark is set in both sides Dong Bi and hole top every 20m;
3)Bore operation:The excavation contour line that drilling hole position should be made according to measurement determines that drilling hole depth is according to layering, point sequence etc. Arrangement and method for construction is strictly controlled;When upstream and downstream abutment wall and headwall hand air drill make presplitting or light blast hole, using steel pipe locating rack spitting drill Hole, periphery hole perforate on range line profile is not preferably greater than 5cm along the scope hole position deviation that contour line is adjusted;
4)Charge explosion:Using platform truck is made by oneself by hole blasting design parameter powder charge, aperture blocks tight with clay, and powder charge is completed Afterwards, by technician and professional big gun work point area subdivision planning, it is coupled blasting network, withdraws from working face equipment, material to home, Non-electric ms detonator is ignited;
5)Ventilation dissipates cigarette:Blown during construction by ventilation hole side, cross the side air draft of factory building temporary traffic hole, accelerated ventilation and dissipate cigarette speed Degree;
6)Safe handling:After explosion, the danger stone and fragment remained on face and abutment wall is first checked, and used by safe handling personnel Crowbar is handled, it is ensured that backhoe carries out face safe handling after the safety of slag-tapping device, muck removal;
7)Muck removal and clear bottom:Transported using loading machine or backhoe car with dump truck to spoil disposal area, after muck removal is finished, use backhoe Into working face, and the residual quarrel in face bottom is removed, be that the excavation of subsequent cycle creates conditions.
By using above-mentioned technical proposal, endless form is used to every layer of blast working, passes through city's roads and brill Hole hole position deviation calculates the guarantee for improving surrounding rock stability after demolition effect and explosion, secondly before muck removal and clear bottom first Scattered cigarette and safe handling are aerated, the security in work progress is improved.
Preferably, I layer is sequentially arranged from inside to outside according to existing drilling and data of explosive filled on face is excavated Keyhole, around multiple rows of main blast hole of keyhole and the periphery hole at outer rim;II layer according to existing drilling and powder charge Parameter is excavating middle part horizontally disposed multiple rows of main blast hole, and being arranged vertically respectively in the both sides of main blast hole from top to bottom of face One row's cushion hole;III layer according to existing drilling and data of explosive filled on face vertical direction is excavated from top to bottom level successively Arrange row's breaking hole and row's bottom outlet.
By using above-mentioned technical proposal, I layer, II layer and III layer according to the elastic strain energy density point on face Cloth, using the rate of release and intensity for changing blasthole blasting circuit control elastic strain energy, can substantially reduce elastic strain energy fast Quick-release puts caused country rock energetic disturbance, and then preferably improves security in work progress.
Preferably, quantity increases the main blast hole in I layer successively from inside to outside;Main blast hole in II layer includes locating respectively In the main blast hole of the superiors and undermost upper strata, the main blast hole of lower floor and between the main blast hole of the main blast hole in upper strata and lower floor The main blast hole in portion, its at the middle and upper levels main blast hole quantity be less than the main blast hole in middle part quantity be less than the main blast hole of lower floor quantity;In III layer The quantity of breaking hole is less than the quantity of bottom outlet.
By using above-mentioned technical proposal, it is ensured that the uniform release of each Regional strain energy in blasting process, reach good Crushing effect.
Preferably, in step 2)It is preceding that quick-fried area's fence operation is carried out to the intake-outlet of tailwater tunnel first, with bag Include following steps:
1)Tile multiple sping mattresses above blast area, and stacks on sping mattress bamboo raft;
2)Soft protecting net is covered on bamboo raft, and is fixed soft protecting net with reinforcing bar earth anchor, it is preliminary by soft protecting net Bamboo raft and sping mattress are compressed;
3)Multiple sand bags are placed on the net in flexible protective, and are mutually connected to each other multiple sands bag with steel wire, pass through sand Earth bag is further fixed to sping mattress and bamboo raft.
By using above-mentioned technical proposal, the initial speed of Rolling Stone and slungshot can be reduced to the fence operation that tunnel is imported and exported Degree, reduces stone fling distance, it is to avoid chattering, and protection effect is improved using three-layer protection structure;First layer uses sping mattress The top for being layed in quick-fried area is played to the effect of the float support of two floor, three-layer protection part first, produced during its separate explosion The elastic potential energy that impulsive force can be partially converted to mattress absorbs partial capability, reduces impulsive force;Second layer laying bamboo raft utilizes bamboo Sping mattress is carried out pre-pressing by the toughness of row, further reduces impulsive force produced during explosion, plays preferably anti- Shield is acted on;Last third layer, which is first coated the protecting component of first layer and the second layer by soft protecting net, to be compressed, and soft Property protection network above place sand bag and more preferably play compression protective action, multiple sands bags are attached using steel wire, improve pressure Tight effect.
Preferably, watering is carried out to bamboo raft and soft protecting net before explosion and drenches operation.
By using above-mentioned technical proposal, are drenched by operation and can be reduced after explosion for bamboo raft and soft protecting net progress watering Sand and dust, and quick-fried area's temperature can be reduced.
Preferably, step 2)Middle suspension roof support comprises the following steps:
1)Setting-out is measured to anchor pole hole position using total powerstation, and mark is carried out with paint or steelframe;
2)Equidistantly drilled using three arm rock drilling jumbos, borehole cleaning operation is carried out after drilling;
3)Supporting is carried out using small one and large one long anchor pole of diameter and Short bolt, the slip casting and by long anchor pole and short anchor into bolthole Bar is alternately inserted in bolthole.
By using above-mentioned technical proposal, carrying out drilling operation using three arm rock drilling jumbos reduces the constructor of the scope of operation Member, it is to avoid because rock burst causes casualties;Secondly the arrangement mode of anchor pole alternating supporting causes anchor pole to be inserted into behind rock stratum, rock stratum Loose, raising supporting effect is less likely to occur.
Preferably, step 2)Middle linked network coordinates artificial extension bar-mat reinforcement using platform truck, is fixed using anchor pole head spot welding, Middle encrypted with expansion bolt is fixed, and makes bar-mat reinforcement be close between wall, net be fastened with galvanized wire, spray normal concrete and spray steel fibre Concrete sprays car operation using concrete.
By using above-mentioned technical proposal, bar-mat reinforcement is tentatively fixed using spot welding, is realized with reference to expansion bolt and is reinforced operation, Fastened using galvanized wire between net and facilitate follow-up pneumatically placed concrete, increase spray area, improve uniformity during concrete spray, and then Improve supporting effect.
In summary, the invention has the advantages that:
1st, by being layered drill-blast tunnelling mode, it is adaptable to the good geology of rock property, and with certain on every layer of face Arrangement mode combines designed the number of the boring hole and ensures that strain energy uniformly discharges, and reduces country rock energetic disturbance, is followed up after explosion Excavate and then supporting follow-up, while improving excavation effect, it is ensured that the stability of country rock;
2nd, by the impulsive force produced when tunnel import and export uses three-layer protection structure, effectively reduction explosion, tunnel is reduced Country rock is influenceed and crushed by explosion in the middle part of hole, is easy to subsequent construction to operate.
Brief description of the drawings
Fig. 1 is layered schematic diagram for the section excavation of tailwater tunnel;
The protection schematic diagram in Tu2Wei Bao areas;
Fig. 3 is the layout drawing of excavation blasthole in I layer;
Fig. 4 is the enlarged diagram of keyhole in Fig. 3;
Fig. 5 is the layout drawing of excavation blasthole in II layer, III layer;
Fig. 6 is the construction schematic diagram of excavation drilling supporting in I layer;
Fig. 7 is the section supporting schematic diagram of tailwater tunnel;
Fig. 8 is the construction schematic diagram slagged tap in I layer;
Fig. 9 is the construction schematic diagram of pneumatically placed concrete in I layer;
Figure 10 is the construction schematic diagram of excavation drilling supporting in II layer;
Figure 11 is the construction schematic diagram slagged tap in II layer.
In figure:1a, vault;1b, abutment wall;1c, bottom plate;2a, long anchor pole;2b, Short bolt;2c, concrete layer;3rd, platform Car;31st, bar-mat reinforcement;4th, three arm rock drilling jumbo;5th, drilling cramp chassis;6a, load wagon;6b, backhoe car;7th, dumper;8th, concrete Spray car;9a, sping mattress;9b, bamboo raft;9c, soft protecting net;9d, sand bag;9e, steel wire;9f, reinforcing bar earth anchor.
Embodiment
The present invention is described in further detail below in conjunction with accompanying drawing.
Embodiment one
A kind of construction method of tailwater tunnel excavation supporting, including following operating procedure:
1st, stratified construction
Referring to Fig. 1, the height of tailwater tunnel is designed according to construction road distribution situation, and by tailwater tunnel from vault 1a the bottoms of to 1c points of plate is I layer, II layer and III layer, wherein III layer is used as bottom plate 1c protective layers.
2nd, blasting safety protection is set up
Referring to Fig. 2, progress blasting safety protection is set up at the intake-outlet of tailwater tunnel, and security protection is set up in quick-fried area Top, be respectively from the bottom to top:
First layer:Spring sheet is used to cover quick-fried area top with tile mode;
The second layer:The bamboo raft 9b of at least two rows is used to be laid on sping mattress 9a top with transverse and longitudinal;
Third layer:Bamboo raft 9b and sping mattress 9a is covered using soft protecting net 9c, and placed on soft protecting net 9c Multiple sand bag 9d, and be mutually connected to each other multiple sands bag 9d with steel wire 9e, soft protecting net 9c reinforcing bar earth anchor 9f It is fixed on above quick-fried area.
3rd, I layer of blasthole is opened up
1)Preparation of construction:Wind in hole, water, electricity are ready, and workmen, equipment prepare in place, periphery presplitting excavate before according to setting Count blasting parameter and carry out experimental explosion, according to demolition effect to determine suitable blasting parameter.
2)Surveying setting-out:Measurement before professional's unwrapping wire, periphery presplitting pore-creating, measurement need to release peripheral profile line or Blast hole hole position, per must be designed gauge wire measuring after the artillery salvo during section excavation, the delayed excavation face 10 of section survey~ 15m, by mono- section of 5m, meanwhile, with cavern excavation, supporting progress, a pile No. mark is set in both sides Dong Bi and hole top every 20m Will.
3)I layer of bore operation:It is in face according to design requirement using the people of drilling cramp chassis 5 referring to Fig. 3, Fig. 4 and Fig. 6 Upper carry out drilling operation, slotting is sequentially arranged according to I layer of existing drilling and data of explosive filled from inside to outside on face is excavated Hole, around multiple rows of main blast hole of keyhole and the periphery hole at outer rim, wherein quantity increases main blast hole successively from inside to outside Plus, keyhole is that hexagonal inner has two emptying apertures, and I layer of specific explosion design parameter is as shown in table 1.
1 I layers of explosion design parameter table of table
4th, I layer of Blasting Excavation
1)Charge explosion:Using platform truck 3 is made by oneself by hole blasting design parameter powder charge, aperture blocks tight with clay, and powder charge is completed Afterwards, by technician and professional big gun work point area subdivision planning, it is coupled blasting network, withdraws from working face equipment, material to home, Non-electric ms detonator is ignited;
2)Ventilation dissipates cigarette:Blown during construction by ventilation hole side, cross the side air draft of factory building temporary traffic hole, accelerated ventilation and dissipate cigarette speed Degree;
3)Safe handling:After explosion, the danger stone and fragment remained on face and abutment wall 1b is first checked, and by safe handling personnel Handled with crowbar, it is ensured that backhoe carries out face safe handling after the safety of slag-tapping device, muck removal;
4)Muck removal and clear bottom:Transported referring to Fig. 8 using loading machine with dump truck to spoil disposal area, after muck removal is finished, and remove the palm The sub- residual quarrel in face bottom, is that the excavation of subsequent cycle creates conditions.
5)Suspension roof support:Referring to Fig. 6 and Fig. 7, setting-out is measured to anchor pole hole position using total powerstation first, and with oily Paint or steelframe carry out mark;Equidistantly bored using three arm rock drilling jumbos 4, borehole cleaning operation is carried out after drilling;Using long anchor pole 2a with Short bolt 2b carries out supporting, slip casting and is alternately inserted in long anchor pole 2a and Short bolt 2b in bolthole into bolthole, its Middle long anchor pole 2a diameter is greater than the diameter of end anchor pole.
6)Shotcrete with mesh:Artificial extension bar-mat reinforcement 31 is coordinated using platform truck 3, fixed using anchor pole head spot welding, it is middle Encrypted and fixed with expansion bolt, make bar-mat reinforcement 31 be close between wall, net be fastened with galvanized wire, spray normal concrete is mixed with spray steel fibre Solidifying soil sprays the operation of car 8 using concrete.
Other I layer of artillery salvo drilling depth is 3.1m.
5th, II layer of blasthole is opened up
Referring to Fig. 5, the difference for opening up construction with I layer of blasthole is that II layer is being excavated area according to existing drilling and data of explosive filled The middle part in face horizontally disposed multiple rows of main blast hole, and row's cushion hole, II are arranged vertically respectively in the both sides of main blast hole from top to bottom Main blast hole in layer includes being respectively at the superiors and the main blast hole in undermost upper strata, the main blast hole of lower floor and quick-fried positioned at upper strata master The main blast hole in middle part between the main blast hole in hole and lower floor, the quantity of the main blast hole in upper strata is less than the quantity of the main blast hole in middle part less than lower floor master The quantity of blast hole, II layer of specific explosion design parameter is as shown in table 2
2 II layers of explosion design parameter table of table
It is the main blast hole in upper strata to define the blasthole for being Ms1 equipped with detonator rank, and the blasthole for being Ms11 equipped with detonator rank is lower floor master Blast hole, is the main blast hole in middle level equipped with the blasthole that detonator rank is Ms3, Ms5, Ms7, Ms9.
6th, II layer of Blasting Excavation
Difference with I layer of Blasting Excavation is to carry out presplitting to abutment wall 1b first, using the light-duty hidden hole drilling disposable presplitting bottom of to Plate 1c as shown in figure 1, carry out Blasting Excavation again.
As shown in Figure 10 and Figure 11, II layer of Excavation Blasting process is identical with I layer of Excavation Blasting process, wherein going out After quarrel is finished, enter working face using backhoe car 6b and remove the residual quarrel in face bottom, be that the excavation of subsequent cycle creates conditions.
7th, III layer of blasthole is opened up
As shown in figure 4, III layer according to existing drilling and data of explosive filled on face vertical direction is excavated successively from top to bottom Horizontally disposed row breaking hole and row's bottom outlet, the quantity of breaking hole are less than the quantity of bottom outlet, III layer of specific explosion design Parameter is as shown in table 3.
3 III layers of explosion design parameter table of table
8th, III layer of Blasting Excavation
Identical with II layer of Blasting Excavation supporting construction mode, wherein artillery salvo drilling depth control is 3.1m.
9th, repeat step 3-8 is got through until whole tailwater tunnel.
Embodiment two
A kind of construction method of tailwater tunnel excavation supporting, the difference with embodiment one is that I layer of artillery salvo drilling depth is 3.5m, III layer The control of artillery salvo drilling depth is 3.5m.
This specific embodiment is only explanation of the invention, and it is not limitation of the present invention, people in the art Member can make the modification without creative contribution to the present embodiment as needed after this specification is read, but as long as at this All protected in the right of invention by Patent Law.

Claims (8)

1. a kind of construction method of tailwater tunnel excavation supporting, it is characterised in that comprise the following steps:
1)Design the height of tailwater tunnel according to construction road distribution situation, and by tailwater tunnel from vault(1a)To bottom plate (1c)It is divided into I layer, II layer and III layer, wherein III layer is used as bottom plate(1c)Protective layer;
2)I layer of excavation:Using drill-blast tunnelling method, photoface exploision, the control of artillery salvo drilling depth bores quick-fried rear vault in 3.1 ~ 3.5m(1a)Spray Steel fiber reinforced concrete, abutment wall(1b)Shotcrete with mesh and suspension roof support;
3)II layer of excavation:Carry out first to abutment wall(1b)Carry out presplitting, and disposable presplitting is to bottom plate(1c), complete right after presplitting II layer of central region is excavated using drill-blast tunnelling method;
4)III layer of excavation:Using drill-blast tunnelling method, artillery salvo drilling depth control follow-up spray anchor after the completion of 3.05 ~ 3.5m, excavation is excavated Supporting.
2. the construction method of a kind of tailwater tunnel excavation supporting according to claim 1, it is characterised in that the brill pops Digging method includes following operating procedure:
1)Preparation of construction:Wind in hole, water, electricity are ready, and workmen, equipment prepare in place, periphery presplitting excavate before according to setting Count blasting parameter and carry out experimental explosion, according to demolition effect to determine suitable blasting parameter;
2)Surveying setting-out:Measurement is before professional's unwrapping wire, periphery pre-splitting hole, and measurement need to release peripheral profile line or explosion Hole hole position, must be designed gauge wire measuring, the delayed 10~15m of excavation face of section survey is pressed during section excavation after every artillery salvo Mono- section of 5m, meanwhile, with cavern excavation, supporting progress, a pile No. mark is set in both sides Dong Bi and hole top every 20m;
3)Bore operation:The excavation contour line that drilling hole position should be made according to measurement determines that drilling hole depth is according to layering, point sequence etc. Arrangement and method for construction is strictly controlled;Upstream and downstream abutment wall(1b)It is fixed using steel pipe locating rack and headwall hand air drill is when making presplitting or light blast hole Position drilling, periphery hole perforate on range line profile is not preferably greater than 5cm along the scope hole position deviation that contour line is adjusted;
4)Charge explosion:Using making platform truck by oneself(3)By hole blasting design parameter powder charge, aperture blocks tight with clay, and powder charge is complete Cheng Hou, by technician and professional big gun work point area subdivision planning, is coupled blasting network, withdraws from working face equipment, material to security bit Put, non-electric ms detonator is ignited;
5)Ventilation dissipates cigarette:Blown during construction by ventilation hole side, cross the side air draft of factory building temporary traffic hole, accelerated ventilation and dissipate cigarette speed Degree;
6)Safe handling:After explosion, face and abutment wall are first checked(1b)The danger stone and fragment of upper residual, and by safe handling people Member is handled with crowbar, it is ensured that backhoe carries out face safe handling after the safety of slag-tapping device, muck removal;
7)Muck removal and clear bottom:Using loading machine or backhoe car(6b)Transport to spoil disposal area, after muck removal is finished, use with dump truck Backhoe enters working face, and removes the residual quarrel in face bottom, is that the excavation of subsequent cycle creates conditions.
3. the construction method of a kind of tailwater tunnel excavation supporting according to claim 2, it is characterised in that I layer according to Some drilling and data of explosive filled are sequentially arranged keyhole, multiple rows of main blast hole around keyhole from inside to outside on face is excavated And the periphery hole at outer rim;II layer is being excavated the middle part of face from top to bottom according to existing drilling and data of explosive filled Horizontally disposed multiple rows of main blast hole, and arrange row's cushion hole vertically respectively in the both sides of main blast hole;III layer according to existing drilling With data of explosive filled on face vertical direction is excavated from top to bottom horizontally disposed row breaking hole and row's bottom outlet successively.
4. a kind of construction method of tailwater tunnel excavation supporting according to claim 3, it is characterised in that the master in I layer Quantity increases blast hole successively from inside to outside;Main blast hole in II layer includes being respectively at the superiors and undermost upper strata master is quick-fried Hole, the main blast hole of lower floor and the main blast hole in middle part between the main blast hole of the main blast hole in upper strata and lower floor, its main blast hole at the middle and upper levels Quantity is less than quantity of the quantity less than the main blast hole of lower floor of the main blast hole in middle part;The quantity of breaking hole is less than the number of bottom outlet in III layer Amount.
5. the construction method of a kind of tailwater tunnel excavation supporting according to claim 1, it is characterised in that in step 2)Before Quick-fried area's fence operation is carried out to the intake-outlet of tailwater tunnel first, with comprising the following steps:
1)Tile multiple sping mattresses above blast area(9a), and in sping mattress(9a)On stack bamboo raft(9b);
2)In bamboo raft(9b)Upper covering soft protecting net(9c), and use reinforcing bar earth anchor(9f)By soft protecting net(9c)It is fixed, lead to Cross soft protecting net(9c)It is preliminary by bamboo raft(9b)And sping mattress(9a)Compressed;
3)In soft protecting net(9c)It is upper to place multiple sand bags(9d), and use steel wire(9e)By multiple sands bag(9d)Mutually it is connected It is connected together, passes through sand bag(9d)To sping mattress(9a)And bamboo raft(9b)Further it is fixed.
6. the construction method of a kind of tailwater tunnel excavation supporting according to claim 5, it is characterised in that to bamboo before explosion Row(9b)And soft protecting net(9c)Carry out watering and drench operation.
7. a kind of construction method of tailwater tunnel excavation supporting according to claim 1, it is characterised in that step 2)Middle anchor Bar supporting comprises the following steps:
1)Setting-out is measured to anchor pole hole position using total powerstation, and mark is carried out with paint or steelframe;
2)Using three arm rock drilling jumbos(4)Equidistant drilling, carries out borehole cleaning operation after drilling;
3)Using small one and large one long anchor pole of diameter(2a)With Short bolt(2b)Supporting is carried out, the slip casting and by long anchor into bolthole Bar(2a)With Short bolt(2b)Alternately it is inserted in bolthole.
8. a kind of construction method of tailwater tunnel excavation supporting according to claim 1, it is characterised in that step 2)It is middle to hang Net uses platform truck(3)Coordinate artificial extension bar-mat reinforcement(31), fixed using anchor pole head spot welding, it is middle to be encrypted admittedly with expansion bolt It is fixed, make bar-mat reinforcement(31)It is close between wall, net be fastened with galvanized wire, spray normal concrete uses coagulation with stir cement and soft soil in deep ground Soil spray car(8)Operation.
CN201710489258.6A 2017-06-24 2017-06-24 A kind of construction method of tailwater tunnel excavation supporting Active CN107035377B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710489258.6A CN107035377B (en) 2017-06-24 2017-06-24 A kind of construction method of tailwater tunnel excavation supporting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710489258.6A CN107035377B (en) 2017-06-24 2017-06-24 A kind of construction method of tailwater tunnel excavation supporting

Publications (2)

Publication Number Publication Date
CN107035377A true CN107035377A (en) 2017-08-11
CN107035377B CN107035377B (en) 2018-12-21

Family

ID=59541256

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710489258.6A Active CN107035377B (en) 2017-06-24 2017-06-24 A kind of construction method of tailwater tunnel excavation supporting

Country Status (1)

Country Link
CN (1) CN107035377B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108999613A (en) * 2018-08-07 2018-12-14 中国水利水电第七工程局有限公司 A kind of high-ground stress region underground chamber middle and lower part excavation method
CN109026019A (en) * 2018-08-03 2018-12-18 中水电第十工程局(郑州)有限公司 The method that water mill bores non-blasting rock move hole excavation construction
CN109488309A (en) * 2018-10-22 2019-03-19 中国水利水电第七工程局有限公司 High-ground stress, basalt underground power house cavern con struction method
CN109854265A (en) * 2019-02-26 2019-06-07 重庆交通建设(集团)有限责任公司 Three arm rock drilling jumbos stablize construction method and stablize rack
CN110195597A (en) * 2019-06-14 2019-09-03 中国水利水电建设工程咨询西北有限公司 A kind of water-storage chamber and construction method suitable for TBM construction
CN110307761A (en) * 2019-06-25 2019-10-08 中国水利水电第四工程局有限公司 One kind being used for the one-time formed method of diversion tunnel middle layer full face tunneling
CN111795621A (en) * 2020-07-22 2020-10-20 中电建路桥集团有限公司 Blasting excavation method for densely populated area
CN112709605A (en) * 2020-12-29 2021-04-27 中国电建集团中南勘测设计研究院有限公司 Seepage control construction method for underground water seal cave depot
CN114320315A (en) * 2022-01-11 2022-04-12 湖南省通盛工程有限公司 Pre-splitting method for tunnel driving construction
CN114622918A (en) * 2022-03-17 2022-06-14 西南交通大学 Control method for stability of two-layer primary support arch springing of large-span structure by using soft and weak stratum arch cover method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236948B (en) * 2020-01-13 2021-09-28 中国水利水电第七工程局有限公司 High-pressure branch pipe excavation method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102607352A (en) * 2012-02-27 2012-07-25 薛世忠 Tunnel full-section excavation blasting method
CN102937398A (en) * 2012-11-20 2013-02-20 武汉大学 Rockburst active control method based on blasting excavation disturbance control
CN104482817A (en) * 2014-12-15 2015-04-01 武汉大学 Deep-buried tunnel stress relieving pre-splitting blasting method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102607352A (en) * 2012-02-27 2012-07-25 薛世忠 Tunnel full-section excavation blasting method
CN102607352B (en) * 2012-02-27 2015-05-20 薛世忠 Tunnel full-section excavation blasting method
CN102937398A (en) * 2012-11-20 2013-02-20 武汉大学 Rockburst active control method based on blasting excavation disturbance control
CN104482817A (en) * 2014-12-15 2015-04-01 武汉大学 Deep-buried tunnel stress relieving pre-splitting blasting method
CN104482817B (en) * 2014-12-15 2015-10-21 武汉大学 A kind of deep-lying tunnel stress relieving presplit blasting method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
易泽荣: "黄金坪水电站尾水隧洞特大断面爆破开挖施工技术", 《铁道建筑技术》 *
李树迎: "糯扎渡水电站尾水系统五岔口快速开挖施工技术", 《水力发电》 *
杨庆喜等: "瑞丽江一级水电站引水隧洞锚喷段开挖质量控制", 《云南水力发电》 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109026019A (en) * 2018-08-03 2018-12-18 中水电第十工程局(郑州)有限公司 The method that water mill bores non-blasting rock move hole excavation construction
CN108999613A (en) * 2018-08-07 2018-12-14 中国水利水电第七工程局有限公司 A kind of high-ground stress region underground chamber middle and lower part excavation method
CN109488309A (en) * 2018-10-22 2019-03-19 中国水利水电第七工程局有限公司 High-ground stress, basalt underground power house cavern con struction method
CN109854265A (en) * 2019-02-26 2019-06-07 重庆交通建设(集团)有限责任公司 Three arm rock drilling jumbos stablize construction method and stablize rack
CN110195597A (en) * 2019-06-14 2019-09-03 中国水利水电建设工程咨询西北有限公司 A kind of water-storage chamber and construction method suitable for TBM construction
CN110195597B (en) * 2019-06-14 2024-04-09 中国水利水电建设工程咨询西北有限公司 Pumped storage chamber suitable for TBM construction and construction method
CN110307761A (en) * 2019-06-25 2019-10-08 中国水利水电第四工程局有限公司 One kind being used for the one-time formed method of diversion tunnel middle layer full face tunneling
CN111795621A (en) * 2020-07-22 2020-10-20 中电建路桥集团有限公司 Blasting excavation method for densely populated area
CN112709605A (en) * 2020-12-29 2021-04-27 中国电建集团中南勘测设计研究院有限公司 Seepage control construction method for underground water seal cave depot
CN114320315A (en) * 2022-01-11 2022-04-12 湖南省通盛工程有限公司 Pre-splitting method for tunnel driving construction
CN114622918A (en) * 2022-03-17 2022-06-14 西南交通大学 Control method for stability of two-layer primary support arch springing of large-span structure by using soft and weak stratum arch cover method

Also Published As

Publication number Publication date
CN107035377B (en) 2018-12-21

Similar Documents

Publication Publication Date Title
CN107035377B (en) A kind of construction method of tailwater tunnel excavation supporting
CN108286920B (en) Implementation method for tunnel blasting and excavation
CN103629980B (en) Near existing line steep massif Loose Control Blasting construction method
CN103470267B (en) The one Rapid Construction of Tunnels technique of growing up
CN102230769B (en) Multi-row micro-differential roadbed deep hole blasting construction method
CN107478114A (en) A kind of parallel slope buffered hole depth hole side slope pre split blasting construction method
CN106643361A (en) Construction method for excavating upper drift heading and lower drift heading in two side walls of ultra-large subsurface tunnel
CN110132084A (en) A kind of Tunnel Overbreak & Underbreak control method
CN107063014A (en) Slope method is cut in the step controlled blasting of cutting shallow bore hole under complex environment
CN103244133B (en) The milling of coal measure strata tunnel is dug and is combined construction with explosion
CN110454172B (en) Tunnel cross tunnel and main tunnel intersection construction method and bench blasting method
CN102251777A (en) Large-scale karst cavity treatment method for karst tunnel
CN107201913B (en) A kind of fine vibration-reducing blasting construction method of cross-over tunnel
CN108868814B (en) Air shaft of underground excavation air duct shield tunnel of collapsible loess combined pebble soil stratum
CN112066830A (en) Method for constructing sandy slate tunnel
CN109668487A (en) Micro-vibration rock and soil blasting controls construction method
CN115182737A (en) Vertical orthogonal ejection type air duct structure of deep-buried subway station and construction method
CN112177635A (en) Construction method of step multiple advanced small guide pipe and construction method of overlapped tunnel
CN105065004B (en) A kind of Shallow Large Span rock tunnel Portal Section weak blast excavation construction method
CN111677530B (en) Safe construction method for three-step temporary inverted arch at tunnel through section
CN112432566A (en) Full-section rapid excavation method for large-section tunnel
CN209263807U (en) Micro-vibration rock and soil blasting structure
CN111457804A (en) Method for blasting IV-grade massive crushed rock with disordered development and wide fracture surface
CN114483054A (en) Non-explosive excavation construction method for pilot tunnel in upper soft and lower hard stratum
CN108086981A (en) With the construction method of more than the 100m high slopes of national highway zero distance

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant