The electric bus battery change method of night operation
Technical field
The present invention relates to the electric bus batteries that electric bus charging technique field more particularly to a kind of night are run
Replacing options.
Background technique
Existing electric bus in the process of running, generally will change electricity until the electricity of battery exhausts Shi Caihui entrance fastly
Station carries out the operation of replacement battery.When electric bus goes out vehicle in the morning, the battery of institute's band is generally full power state, when the electricity
For the not enough power supply in pond to meet in the daylong situation of bus running, electric bus needs carry out one in its run the period
The operation of secondary or multiple replacement battery.In order to guarantee have sufficient battery for replacing, the battery changed from bus is general
It can be immediately placed in charging unit and charge, not take into account that the influence of electricity price, since there are two kinds of valences of peak valley for the electricity price of power grid
Lattice undoubtedly will increase the operation cost of bus operator if charging when peak electricity.
Summary of the invention
The purpose of the present invention is overcoming defect at high cost of the existing technology, a kind of Electric Transit of night operation is provided
Vehicle battery change method can reduce the operation cost of electric bus.
The technical solution adopted by the present invention to solve the technical problems is: a kind of electric bus battery of night operation is more
Change method, comprising the following steps:
(A) electrical changing station is set in the turn-round of bus, charging unit is set in electrical changing station, is gone out every time in bus
Computer is detected, counted and is inputted to bus battery capacity respectively when standing, entering the station, bus one is calculated in computer
Amount of battery consumption in a driving process back and forth, remaining operation shift n and road on the day of the bus is inputted into computer
The unobstructed state parameter in road starts the time of valuation further according to daily paddy electricity valence, finally show that the bus running to paddy electricity valence is opened
The actual travel time T at moment beginning;
If T≤0, show that paddy electricity valence has been already expired now starts the moment of valuating, then replaces the battery of bus, more immediately
The battery changed, which is put into charging unit, to charge, and the battery just replaced on bus band is outbound;
If T > 0, at the time of showing that not arriving paddy electricity valence also now starts valuation, then according to the coast is clear parameter and one way row
Average power consumption is sailed, electricity U required in actual travel time T is calculated by computer;
(B) battery dump energy X is compared with institute electricity demand U;
If X >=U, make the bus outbound in the case where being changed without battery;
If X < U, show battery dump energy be insufficient to allow bus travel to paddy electricity valence start valuation at the time of, then
The consumption in each shift driving process is calculated according to the road is clear state parameter and one way traveling average power consumption in computer
Electricity p;
(C) the shift Y that battery dump energy is able to maintain that the bus reruns is calculated according to power consumption p in computer
(i.e. remaining battery operation shift);
If Y >=1, illustrate that the bus enough of the remaining capacity in battery at least travels a shift, at this time public transport again
Vehicle is outbound in the case where being changed without battery;
If Y < 1, illustrates that the remaining capacity in battery is not enough to that the bus is supported to travel a shift again, at this time should
Battery altering on bus gets off and will be placed on locker room, etc. paddy electricities valence start that the battery is put into charging again at the time of valuation
Device charges, and reserve battery is changed to bus at the same time, then allows bus outbound.
The utility model has the advantages that the electric bus that night can either be made to run saves the cost of charging using method of the invention,
The operation cost of electric bus is reduced, and the replacement frequency of battery can be increased after entering paddy electricity valence charging point, is improved public
The utilization rate for handing over vehicle battery makes the electricity in battery keep within the set range, preventing battery over-discharge, being conducive to extend battery
Service life.
Detailed description of the invention
Fig. 1 is flow chart of the invention.
Specific embodiment
Below with reference to Fig. 1, the invention will be further described.
A kind of electric bus battery change method of night operation, comprising the following steps:
(A) electrical changing station is set in the turn-round of bus, charging unit is set in electrical changing station, is gone out every time in bus
Computer is detected, counted and is inputted to bus battery capacity respectively when standing, entering the station, bus one is calculated in computer
Amount of battery consumption in a driving process back and forth, remaining operation shift n and road on the day of the bus is inputted into computer
The unobstructed state parameter in road starts the time of valuation further according to daily paddy electricity valence, finally show that the bus running to paddy electricity valence is opened
The actual travel time T at moment beginning;
If T≤0, show that paddy electricity valence has been already expired now starts the moment of valuating, then replaces the battery of bus, more immediately
The battery changed, which is put into charging unit, to charge, and the battery just replaced on bus band is outbound;
If T > 0, at the time of showing that not arriving paddy electricity valence also now starts valuation, then according to the coast is clear parameter and one way row
Average power consumption is sailed, electricity U required in actual travel time T is calculated by computer;
(B) battery dump energy X is compared with institute electricity demand U;
If X >=U, make the bus outbound in the case where being changed without battery;
If X < U, show battery dump energy be insufficient to allow bus travel to paddy electricity valence start valuation at the time of, then
The consumption in each shift driving process is calculated according to the road is clear state parameter and one way traveling average power consumption in computer
Electricity p;
(C) the shift Y that battery dump energy is able to maintain that the bus reruns is calculated according to power consumption p in computer
(i.e. remaining battery operation shift);
If Y >=1, illustrate that the bus enough of the remaining capacity in battery at least travels a shift, at this time public transport again
Vehicle is outbound in the case where being changed without battery;
If Y < 1, illustrates that the remaining capacity in battery is not enough to that the bus is supported to travel a shift again, at this time should
Battery altering on bus gets off and will be placed on locker room, etc. paddy electricities valence start that the battery is put into charging again at the time of valuation
Device charges, and reserve battery is changed to bus at the same time, then allows bus outbound.
Using method of the invention, the electric bus that night can either be made to run saves the cost of charging, reduces electronic
The operation cost of bus, and the replacement frequency of battery can be increased after entering paddy electricity valence charging point, improve bus battery
Utilization rate, make electricity in battery keep within the set range, preventing battery over-discharge, be conducive to extend battery uses the longevity
Life.
It is further, described that the road is clear that state parameter is according to bus running road in the run the period in nearly one month
Section congestion in road situation come count obtain have regularity parameter.
Further, the charging unit is two or more, is charged simultaneously convenient for multiple batteries.
It should be appreciated that described above, the specific embodiments are only for explaining the present invention, is not intended to limit the present invention.By
The obvious changes or variations that spirit of the invention is extended out are still in the protection scope of this invention.