CN107023950A CN201710214523.XA CN201710214523A CN107023950A CN 107023950 A CN107023950 A CN 107023950A CN 201710214523 A CN201710214523 A CN 201710214523A CN 107023950 A CN107023950 A CN 107023950A
Authority
CN
China
Prior art keywords
heat exchanger
control valve
outdoor heat
outdoor
control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710214523.XA
Other languages
Chinese (zh)
Other versions
CN107023950B (en
Inventor
许文明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Haier Air Conditioner Gen Corp Ltd
Haier Smart Home Co Ltd
Qingdao Haier Jiaozhou Air Conditioner Co Ltd
Original Assignee
Qingdao Haier Air Conditioner Gen Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Haier Air Conditioner Gen Corp Ltd filed Critical Qingdao Haier Air Conditioner Gen Corp Ltd
Priority to CN201710214523.XA priority Critical patent/CN107023950B/en
Publication of CN107023950A publication Critical patent/CN107023950A/en
Application granted granted Critical
Publication of CN107023950B publication Critical patent/CN107023950B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/30Control or safety arrangements for purposes related to the operation of the system, e.g. for safety or monitoring
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F2110/00Control inputs relating to air properties
    • F24F2110/10Temperature
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B47/00Arrangements for preventing or removing deposits or corrosion, not provided for in another subclass
    • F25B47/02Defrosting cycles
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/30Control or safety arrangements for purposes related to the operation of the system, e.g. for safety or monitoring
    • F24F11/41Defrosting; Preventing freezing
    • F24F11/42Defrosting; Preventing freezing of outdoor units
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/70Control systems characterised by their outputs; Constructional details thereof
    • F24F11/80Control systems characterised by their outputs; Constructional details thereof for controlling the temperature of the supplied air
    • F24F11/83Control systems characterised by their outputs; Constructional details thereof for controlling the temperature of the supplied air by controlling the supply of heat-exchange fluids to heat-exchangers
    • F24F11/84Control systems characterised by their outputs; Constructional details thereof for controlling the temperature of the supplied air by controlling the supply of heat-exchange fluids to heat-exchangers using valves

Abstract

The invention discloses a kind of air conditioner without shutting Defrost operation method.The air conditioner without shutting runs Defrost method, including:Control air-conditioning heating operation;Detect outdoor environment temperature;The working condition of outdoor heat exchanger is adjusted according to outdoor environment temperature;When outdoor heat exchanger is adjusted to preparatory condition, outdoor coil temperature is detected;The working condition of outdoor heat exchanger is adjusted according to outdoor coil temperature so that the operation heat absorption of one of the first outdoor heat exchanger and the second outdoor heat exchanger, another operation heat release defrost.According to above-mentioned technical proposal, suitable control mode can be selected during operation of air conditioner, the operational energy efficiency of air-conditioning is improved, defrosting is not shut down in realization.

Description

Air conditioner without shutting Defrost operation method
Technical field
The present invention relates to air-conditioning technique field, in particular to a kind of air conditioner without shutting Defrost operation method.
Background technology
Existing air-conditioning is possible to the situation for frosting occur during heating operation, and frosting is reached after certain degree just Need carry out defrost, otherwise heating effect worse and worse, but existing air-conditioning during defrosting indoor heating stop, even Indoor temperature can be declined, i.e., it is uncomfortable also not save.
The content of the invention
The purpose of the present invention is to propose to a kind of air conditioner without shutting Defrost operation method, air conditioner without shutting can be made to defrost Operation, improves comfort of air conditioner.
According to an aspect of the invention, there is provided a kind of air conditioner without shutting operation Defrost method, including:Control air-conditioning Heating operation;Detect outdoor environment temperature;The working condition of outdoor heat exchanger is adjusted according to outdoor environment temperature;Work as room When external heat exchanger is adjusted to preparatory condition, outdoor coil temperature is detected;Work according to outdoor coil temperature to outdoor heat exchanger State is adjusted so that the operation heat absorption of one of the first outdoor heat exchanger and the second outdoor heat exchanger, another operation Heat release defrost.
Preferably, the step of working condition of outdoor heat exchanger being adjusted according to outdoor environment temperature includes:Work as room When external environment temperature is more than T1, the first control valve of control, the 4th control valve, the 5th control valve, the 7th control valve are opened, control the Two control valves, the 3rd control valve and the 6th control valve are closed, control the first outdoor heat exchanger heat absorption, the second outdoor heat exchanger heat release Defrost.
Preferably, preparatory condition includes:The coil temperature of second outdoor heat exchanger is more than T2 and is continued above time t1.
Preferably, the step of working condition of outdoor heat exchanger being adjusted according to outdoor coil temperature includes:When When the coil temperature of one outdoor heat exchanger is less than or equal to T3, the second control valve of control, the 3rd control valve, the 5th control valve and the Seven control valves are opened, and the first control valve of control, the 4th control valve, the 6th control valve are closed, and control the first outdoor heat exchanger heat release Defrost, the heat absorption of the second outdoor heat exchanger.
Preferably, the step of working condition of outdoor heat exchanger being adjusted according to outdoor coil temperature also includes:When When the coil temperature of first outdoor heat exchanger is more than T3, the second outdoor heat exchanger stops defrost operation, controls the first outdoor heat exchange Device and the second outdoor heat exchanger absorb heat simultaneously and continue the t2 times;
The second control valve, the 3rd control valve, the 5th control valve and the 7th control valve is controlled to open, the first control valve of control, 4th control valve, the 6th control valve are closed, and control the first outdoor heat exchanger heat release defrost, the heat absorption of the second outdoor heat exchanger.
Preferably, the step of working condition of outdoor heat exchanger being adjusted according to outdoor coil temperature also includes:Inspection Survey the coil temperature of the first outdoor heat exchanger;When the coil temperature of the first outdoor heat exchanger is more than T4 and duration more than t3 When, the 3rd control valve of control, the 5th control valve and the 6th control valve are opened, the first control valve of control, the second control valve, the 4th control Valve processed and the 7th control valve are closed, the first outdoor heat exchanger of control and the heat absorption of the second outdoor heat exchanger.
Preferably, the step of working condition of outdoor heat exchanger being adjusted according to outdoor environment temperature includes:Work as room When external environment temperature is less than or equal to T1, the second control valve of control, the 3rd control valve, the 5th control valve and the 7th control valve are beaten Open, the first control valve of control, the 4th control valve, the 6th control valve are closed, and control the first outdoor heat exchanger heat release defrost, second Room External heat exchanger absorbs heat.
Preferably, preparatory condition includes:The coil temperature of first outdoor heat exchanger is more than T5 and is continued above time t4.
Preferably, the step of working condition of outdoor heat exchanger being adjusted according to outdoor coil temperature also includes:When The coil temperature of second outdoor heat exchanger be less than or equal to T6 when, control the first control valve, the 4th control valve, the 5th control valve, 7th control valve is opened, and the second control valve of control, the 3rd control valve and the 6th control valve are closed, and the first outdoor heat exchanger of control is inhaled Heat, the second outdoor heat exchanger heat release defrost.
Preferably, the step of working condition of outdoor heat exchanger being adjusted according to outdoor coil temperature also includes:When When the coil temperature of second outdoor heat exchanger is more than T6, the first outdoor heat exchanger stops defrost operation, controls the first outdoor heat exchange Device and the second outdoor heat exchanger absorb heat simultaneously and continue the t5 times;Control the first control valve, the 4th control valve, the 5th control valve, 7th control valve is opened, and the second control valve of control, the 3rd control valve and the 6th control valve are closed, and the first outdoor heat exchanger of control is inhaled Heat, the second outdoor heat exchanger heat release defrost.
Preferably, the step of working condition of outdoor heat exchanger being adjusted according to outdoor coil temperature also includes:Inspection Survey the coil temperature of the second outdoor heat exchanger;When the coil temperature of the second outdoor heat exchanger is more than T7 and duration more than t6 When, the 3rd control valve of control, the 5th control valve and the 6th control valve are opened, the first control valve of control, the second control valve, the 4th control Valve processed and the 7th control valve are closed, the first outdoor heat exchanger of control and the heat absorption of the second outdoor heat exchanger.
According to the above-mentioned technical proposal of the present invention, during operation of air conditioner, outdoor environment temperature is detected first, When outdoor environment temperature is more than preset value, illustrate that the heat exchange amount between outdoor environment temperature and outdoor heat exchanger disclosure satisfy that The demand of indoor heating, therefore the operational mode of outdoor heat exchanger can be now adjusted according to outdoor environment temperature so that first Outdoor heat exchanger and the alternating defrost of the second outdoor heat exchanger, it is ensured that while indoor temperature is maintained in OK range, air-conditioning Power consumption is relatively low, and defrosting is not shut down while realizing;When outdoor heat exchanger is adjusted to preparatory condition, it is possible to outdoor heat exchanger Coil temperature is detected, and operation of air conditioner is further adjusted according to testing result so that air-conditioning can kept On the basis of higher operational energy efficiency, quick regulation is carried out to indoor temperature so that indoor temperature can be rapidly achieved user's requirement, The operational energy efficiency of air-conditioning is improved, operating cost is reduced.
It should be appreciated that the general description of the above and detailed description hereinafter are only exemplary and explanatory, not Can the limitation present invention.
Brief description of the drawings
Accompanying drawing herein is merged in specification and constitutes the part of this specification, shows the implementation for meeting the present invention Example, and for explaining principle of the invention together with specification.
Fig. 1 is the structured flowchart of the air conditioner of one embodiment of the invention;
Fig. 2 is that the air conditioner without shutting of one embodiment of the invention runs the flow chart of Defrost method;
Fig. 3 is that the air conditioner without shutting of one embodiment of the invention runs the flow chart of Defrost method.
Description of reference numerals:110th, compressor;120th, four-way valve;130th, indoor heat exchanger;140th, first throttle device; 150th, the first outdoor heat exchanger;160th, the second outdoor heat exchanger;170th, second throttling device;181st, the first control valve;182nd, Two control valves;183rd, the 3rd control valve;184th, the 4th control valve;185th, the 5th control valve;186th, the 6th control valve;187th, the 7th Control valve.
Embodiment
The following description and drawings fully show specific embodiments of the present invention, to enable those skilled in the art to Put into practice them.Other embodiments can include structure, logic, electric, process and other changes.Embodiment Only represent possible change.Unless explicitly requested, otherwise single components and functionality is optional, and the order operated can be with Change.The part of some embodiments and feature can be included in or replace part and the feature of other embodiments.This hair The scope of bright embodiment includes the gamut of claims, and claims is all obtainable equivalent Thing.Herein, each embodiment individually or can be represented generally with term " invention ", and it is convenient that this is used for the purpose of, And if in fact disclosing the invention more than one, the scope for being not meant to automatically limit the application is any single invention Or inventive concept.Herein, such as first and second or the like relational terms be used only for by an entity or operation with Another entity or operation make a distinction, without requiring or implying between these entities or operation there is any actual relation Or order.Moreover, term " comprising ", "comprising" or any other variant thereof is intended to cover non-exclusive inclusion, so that So that process, method or equipment including a series of key elements not only include those key elements, but also including being not expressly set out Other key elements, or also include for this process, method or the intrinsic key element of equipment.In the feelings of not more limitations Under condition, the key element limited by sentence "including a ...", it is not excluded that in the process including the key element, method or equipment In also there is other identical element.Each embodiment herein is described by the way of progressive, and each embodiment is stressed Be all between difference with other embodiment, each embodiment identical similar portion mutually referring to.For implementing For example disclosed method, product etc., because it is corresponding with method part disclosed in embodiment, so the comparison of description is simple Single, related part is referring to method part illustration.
With reference to shown in Figure 1, the embodiments of the invention provide a kind of air conditioner, including compressor 110, four-way valve 120, Indoor heat exchanger 130, outdoor heat exchanger and first throttle device 140, first throttle device 140 are disposed in the interior heat exchanger Between 130 and outdoor heat exchanger, outdoor heat exchanger includes the first outdoor heat exchanger 150 and the second outdoor heat exchanger 160, air conditioner During heating operation, there is the first outdoor heat exchanger 150 to absorb heat and for the first outdoor heat exchanger 150 and the second outdoor heat exchanger 160 The first working condition, the heat release of the first outdoor heat exchanger 150 and the second outdoor heat exchanger 160 of the heat release of two outdoor heat exchanger 160 are inhaled The 3rd work shape that the second working condition and the first outdoor heat exchanger 150 and the second outdoor heat exchanger 160 of heat are absorbed heat State, wherein the heat exchange area of the first outdoor heat exchanger 150 is S1, the heat exchange area of the second outdoor heat exchanger 160 is S2, wherein S1 >S2。
When needing to defrost to the second outdoor heat exchanger 160, air-conditioning can be controlled to be in the first working condition, now compressed The HTHP refrigerant that machine 110 compresses first passes through the second outdoor heat exchanger 160 and the heat release of indoor heat exchanger 130, for indoor system Heat and the defrost of the second outdoor heat exchanger 160, the refrigerant of exchanged heat return to compressor after being absorbed heat through the first outdoor heat exchanger 150 110;When needing to defrost to the first outdoor heat exchanger 150, air-conditioning can be controlled to be in the second working condition, now compressor The HTHP refrigerant of 110 compressions first passes through the first outdoor heat exchanger 150 and the heat release of indoor heat exchanger 130, for indoor heating With the defrost of the first outdoor heat exchanger 150, the refrigerant of exchanged heat returns to compressor after being absorbed heat through the second outdoor heat exchanger 160 110;When air-conditioner outdoor unit need not defrost, air-conditioning can be controlled to be in the 3rd working condition, now compressor 110 compresses HTHP refrigerant first passes through the heat release of indoor heat exchanger 130, for indoor heating, and the refrigerant of exchanged heat is changed through the first outdoor Compressor 110 is returned to after the hot outdoor heat exchanger 160 of device 150 and second heat absorption.
Wherein the heat exchange area of the first outdoor heat exchanger 150 is S1, and the heat exchange area of the second outdoor heat exchanger 160 is S2, The heat exchange area S=S1+S2, optional S1=70%S, S2=30%S of outdoor heat exchanger.Those skilled in the art can be with root S1 and S2 size are set according to being actually needed, and S1 and S2 can also be identical, and the heat exchange area of two outdoor heat exchangers is arranged to Different value, air-conditioning is adjusted so as to the heat exchange amount difference according to indoor demand can both meet indoor heating amount demand, can also protect Demonstrate,prove outdoor heat exchanger alternately to defrost, to improve the comfort level of air-conditioning.
,, can be first to second when needing to defrost to outdoor heat exchange when air conditioner heat-production is run according to above-mentioned technical proposal Outdoor heat exchanger 160 is defrosted, i.e., air-conditioning is in the first working condition, first the first outdoor heat exchanger 150 can also be carried out Defrosting, i.e. air-conditioning are in the second working condition, after the outdoor heat exchanger defrosting defrosted in the ban is finished, then to another outdoor heat exchange Device defrosts, and when so ensuring that air-conditioner defrosting, indoor heating does not stop, and indoor heat exchanger 130 is constantly in heat release work State, improves the comfort level of air-conditioning.
As shown in figure 1, the embodiments of the invention provide a kind of air conditioner, the first end C of the first outdoor heat exchanger 150 passes through The first interface A connections of first pipeline and four-way reversing valve, by the second interface B connections of the second pipeline and four-way reversing valve, The first end E of second outdoor heat exchanger 160 passes through the 4th pipe by the first interface A connections of the 3rd pipeline and four-way reversing valve Road and the second interface B connections of four-way reversing valve, include the 5th pipeline, between indoor heat exchanger 130 and outdoor heat exchanger Six pipelines and the 7th pipeline, the first end G of the 5th pipeline are connected in the first end of indoor heat exchanger 130, the 6th pipeline and The first end of seven pipelines is commonly connected to the second end H of the 5th pipeline, and the second end of the 6th pipeline is connected to the first outdoor heat exchange The first end C of device 150, the second end of the 7th pipeline is connected to tie point and the second branch road, and tie point is connected to Second end D of one outdoor heat exchanger 150, the second branch road is connected on the second end F of the second outdoor heat exchanger 160, the first pipeline It is provided with the first control valve 181, the second pipeline and is provided with the second control valve 182, the 3rd control valve is provided with the 3rd pipeline 183, it is provided with the 4th control valve 184, the 5th pipeline on the 4th pipeline and is provided with the 5th control valve 185 and first throttle device 140, it is provided with the 6th control valve 186, the 7th pipeline on the 6th pipeline and is provided with the 7th control valve 187, is set on the second branch road It is equipped with second throttling device 170.
Wherein, the 5th control valve 185 is used for the path for cutting off indoor heat exchanger 130 and outdoor heat exchanger, so that the later stage is empty When tune is safeguarded, outdoor heat exchanger refrigerant is flowed back to after compressor, and there is no the inflow of new refrigerant.
When air-conditioning heating is run, the refrigerant of HTHP flows out from the second interface B of four-way valve 120, the first outdoor heat exchange The first end C of device 150 is connected by the second pipeline with the second interface B of four-way valve 120, and the second control valve 182 is used to control height The refrigerant of warm high pressure flows through the heat release of the first outdoor heat exchanger 150, for the defrost of the first outdoor heat exchanger 150, while first is outdoor The first end C of heat exchanger 150 is connected by the first pipeline with the first interface A of four-way valve 120, and the first control valve 181 is used to control Make the refrigerant absorbed heat through the first outdoor heat exchanger 150 and flow back to compressor 110, during the first 150 normal work of outdoor heat exchanger, the Two control valves 182 are closed, and the first control valve 181 is opened, when the first outdoor heat exchanger 150 needs defrost, control the second control valve 182 are opened, and the first control valve 181 is closed.The first end E of second outdoor heat exchanger 160 passes through the 4th pipeline and four-way valve 120 Second interface B connections, the 4th control valve 184 is used to control the refrigerant of HTHP to flow through the heat release of the second outdoor heat exchanger 160, uses In the defrost of the second outdoor heat exchanger 160, while the first end E of the second outdoor heat exchanger 160 passes through the 3rd pipeline and four-way valve 120 First interface A connections, the 3rd control valve 183 is used to control the refrigerant that absorbed heat through the second outdoor heat exchanger 160 to flow back to compression Machine 110, during the second 160 normal work of outdoor heat exchanger, the 4th control valve 184 is closed, and the 3rd control valve 183 is opened, second Room When external heat exchanger 160 needs defrost, the 4th control valve 184 of control is opened, and the 3rd control valve 183 is closed.
In the empty hot heating and defrosting course of work, when air-conditioning is in the first working condition, the control of the first control valve the 181, the 4th Valve 184 processed, the 5th control valve 185 and the 7th control valve 187 are opened, the second control valve 182, the 3rd control valve 183 and the 6th control Valve 186 processed is closed, second interface B outflow of the refrigerant that compressor 110 compresses through four-way valve 120, and it is outdoor that a part flows into second The heat release of heat exchanger 160 a, part flows into the heat release of indoor heat exchanger 130, flows through the refrigerant of the second outdoor heat exchanger 160 through second section The first outdoor heat exchanger 150 is returned to after stream device 170 to absorb heat, and flows through the HTHP refrigerant of indoor heat exchanger 130 through first segment The first outdoor heat exchanger 150 is also returned to after stream device 140 to absorb heat, refrigerant is after the heat absorption of the first outdoor heat exchanger 150 through four-way valve 120 first interface A flow back into compressor 110;When air-conditioning is in the second working condition, the control of the second control valve the 182, the 3rd Valve 183, the 5th control valve 185 and the 7th control valve 187 are opened, the first control valve 181, the 4th control valve 184 and the 6th control Valve 186 is closed, and second interface B outflow of the refrigerant that compressor 110 compresses through four-way valve 120 a, part flows into the first outdoor and changed The hot heat release of device 150 a, part flows into the heat release of indoor heat exchanger 130, flows through the refrigerant of the first outdoor heat exchanger 150 through the second throttling The first outdoor heat exchanger 150 is returned to after device 170 to absorb heat, and flows through the refrigerant of indoor heat exchanger 130 after first throttle device 140 The second outdoor heat exchanger 160 can be returned to through second throttling device 170 again to absorb heat, refrigerant absorbs heat from the second outdoor heat exchanger 160 Compressor 110 is flow back into by the first interface A of four-way valve 120.
Air-conditioning heating does not defrost in the course of work, when air-conditioning may be at three working conditions, when air-conditioning is in the 3rd work When making state, the 3rd control valve 183, the 5th control valve 185 and the 6th control valve 186 are opened, the control of the first control valve 181, second Valve 182 processed, the 4th control valve 184 and the 7th control valve 187 are closed, compressor 110 compress refrigerant through four-way valve 120 second Interface B flows out, and all flows into the heat release of indoor heat exchanger 130, and the refrigerant from the outflow of indoor heat exchanger 130 is through first throttle device The first outdoor heat exchanger 150 is first passed through after 140 to absorb heat, then passes through after second throttling device 170 second outdoor heat exchanger 160 Heat absorption, whole refrigerants gasify more thorough all by throttling twice;Air-conditioning heating does not defrost and is also in the course of work Four working conditions, when air-conditioning is in four working conditions, the first control valve 181, the 3rd control valve 183, the 5th control valve 185 Opened with the 7th control valve 187, the second control valve 182, the 4th control valve 184 and the 6th control valve 186 are closed, compressor 110 Second interface B outflow of the refrigerant of compression through four-way valve 120, all flows into the heat release of indoor heat exchanger 130, from indoor heat exchanger The refrigerant of 130 outflows first passes through the heat release of indoor heat exchanger 130, and the first Room is passed through through the rear portion refrigerant of first throttle device 140 External heat exchanger 150 absorbs heat directly returns to compressor 110 through the first interface A of four-way valve 120, and another part refrigerant is by the second throttling Absorbed heat after device 170 by the second outdoor heat exchanger 160 and return to compressor 110 through the first interface A of four-way valve 120 again, by The refrigerant of two outdoor parallel operations gasifies more thorough by throttling twice.
As shown in Fig. 2 the embodiment of the present invention additionally provides a kind of air conditioner without shutting operation Defrost method, including:Control Air-conditioning heating is run;Detect outdoor environment temperature;The working condition of outdoor heat exchanger is adjusted according to outdoor environment temperature; When outdoor heat exchanger is adjusted to preparatory condition, outdoor coil temperature is detected;According to outdoor coil temperature to outdoor heat exchanger Working condition is adjusted so that the operation heat absorption of one of the first outdoor heat exchanger and the second outdoor heat exchanger, another Run heat release defrost.
During operation of air conditioner, outdoor environment temperature is detected first, when outdoor environment temperature is more than preset value When, illustrate that the heat exchange amount between outdoor environment temperature and outdoor heat exchanger disclosure satisfy that the demand of indoor heating, therefore now The operational mode of outdoor heat exchanger can be adjusted according to outdoor environment temperature so that the first outdoor heat exchanger and the second outdoor heat exchange Device replaces defrost, it is ensured that while indoor temperature is maintained in OK range, the power consumption of air-conditioning is relatively low, is removed while realizing not shut down Frost;When outdoor heat exchanger is adjusted to preparatory condition, it is possible to which the coil temperature of outdoor heat exchanger is detected, and according to inspection Survey result further to adjust operation of air conditioner so that air-conditioning can be on the basis of higher operational energy efficiency be kept, to room Interior temperature carries out quick regulation so that indoor temperature can be rapidly achieved user's requirement, improves the operational energy efficiency of air-conditioning, reduction fortune Row cost.
The step of working condition of outdoor heat exchanger is adjusted according to outdoor environment temperature includes:When outdoor environment temperature When degree is less than or equal to T1, the first control valve 181 of control, the 4th control valve 184, the 5th control valve 185, the 7th control valve 187 Open, the second control valve 182 of control, the 3rd control valve 183 and the 6th control valve 186 are closed, and control the first outdoor heat exchanger 150 Heat absorption, the heat release defrost of the second outdoor heat exchanger 160.When outdoor environment temperature is less than or equal to T1, illustrate outdoor environment temperature There is the larger temperature difference between outdoor heat exchanger, abundance can be provided for indoor heat exchanger heats institute's calorific requirement, therefore now The first outdoor heat exchanger 150 with larger heat exchange amount can be made to absorb heat, the second outdoor heat exchanger 160 with smaller heat exchange amount Heat release defrost, because the defrost time of the first outdoor heat exchanger 150 is more than the defrost time of the second outdoor heat exchanger 160, therefore Control the second outdoor heat exchanger 160 earlier than the defrost of the first outdoor heat exchanger 150, also ensure that the trouble-free operation of indoor heating, Reduce the defrost time of outdoor heat exchanger, while ensureing interior by the first outdoor heat exchanger 150 with larger heat exchange amount It is stable to heat, the defrost to the second outdoor heat exchanger 160 can be synchronously completed on the basis of air conditioning high efficiency energy-saving run is realized Processing, that realizes the second outdoor heat exchanger 160 does not shut down defrosting operation.
Preparatory condition includes:The coil temperature of second outdoor heat exchanger 160 is more than T2 and is continued above time t1.When second The coil temperature of outdoor heat exchanger 160 is more than T2 and is continued above time t1, then illustrates the defrost temperature of the second outdoor heat exchanger 160 Degree and defrost time have been enough to provide enough defrost heats, meet the heat of the abundant defrost of the second outdoor heat exchanger 160 Amount demand, therefore now it is considered that the second outdoor heat exchanger 160 has completed defrost.
After the second outdoor heat exchanger 160 completes defrost, according to work shape of the outdoor coil temperature to outdoor heat exchanger The step of state is adjusted includes:When the coil temperature of the first outdoor heat exchanger is more than T3, the second control valve 182 of control, the Three control valves 183, the 5th control valve 185 and the 7th control valve 187 are opened, control the first control valve 181, the 4th control valve 184, 6th control valve 186 is closed, and controls the heat release defrost of the first outdoor heat exchanger 150, and the second outdoor heat exchanger 160 absorbs heat.When second Outdoor heat exchanger 160 is completed after defrost, if the coil temperature of the first outdoor heat exchanger 150 is less than or equal to T3, is illustrated The coil temperature of first outdoor heat exchanger 150 is relatively low, it is easy to coagulate frost on the surface of the first outdoor heat exchanger 150, therefore now, Determine the second outdoor heat exchanger 160 complete defrost after, it is possible to control the first outdoor heat exchanger 150 carry out heat release defrost, together When control second Room external heat exchanger 160 absorb heat and heated to indoor, it is ensured that the normal operation of indoor heating, while realizing outdoor The defrosting of not shutting down of heat exchanger is operated.
The step of working condition of outdoor heat exchanger is adjusted according to outdoor coil temperature also includes:When the first outdoor When the coil temperature of heat exchanger is more than T3, the second outdoor heat exchanger 160 stops defrost operation, controls the first outdoor heat exchanger 150 Absorbed heat simultaneously with the second outdoor heat exchanger 160 and continue the t2 times;Control the second control valve 182, the 3rd control valve the 183, the 5th The control valve 187 of control valve 185 and the 7th is opened, and the first control valve 181 of control, the 4th control valve 184, the 6th control valve 186 are closed Close, control the heat release defrost of the first outdoor heat exchanger 150, the second outdoor heat exchanger 160 absorbs heat.
If the coil temperature of the first outdoor heat exchanger 150 is more than T3, illustrate the coil pipe temperature of the first outdoor heat exchanger 150 Degree is higher, and frost is not yet coagulated in the outer surface of the first outdoor heat exchanger 150, without carrying out defrost processing, therefore now can be in second Room External heat exchanger 160 is completed after defrost, just stops the defrost heat release of the second outdoor heat exchanger 160, while temporarily not controlling the first Room External heat exchanger 150 carries out heat release defrost so that the first outdoor heat exchanger 150 and the second outdoor heat exchanger 160 absorb heat simultaneously, it is ensured that Indoor heating needs, and after two outdoor heat exchangers, which absorb heat, to be continued for some time simultaneously, now indoor temperature deviation reduces, can Heat exchange heat is provided for interior to only rely on the second outdoor heat exchanger 160, therefore the first outdoor heat exchanger 150 can now be entered Row heat release defrost, can also reduce the influence caused by being adjusted when taking such a working condition to indoor temperature, and reducing user makes The uncomfortable row of used time, improves the use feeling of user.
The step of working condition of outdoor heat exchanger is adjusted according to outdoor environment temperature also includes:Detect the first Room The coil temperature of external heat exchanger 150;When the coil temperature of the first outdoor heat exchanger 150 is more than T4 and the duration is more than t3, The 3rd control valve 183, the 5th control valve 185 and the 6th control valve 186 is controlled to open, control the first control valve 181, second control Valve 182, the 4th control valve 184 and the 7th control valve 187 are closed, the first outdoor heat exchanger 150 of control and the second outdoor heat exchanger 160 heat absorptions.When the coil temperature of the first outdoor heat exchanger 150 is more than T4 and the duration is more than t3, then illustrate that first is outdoor The defrost of heat exchanger 150 continue for time enough, it is ensured that the first outdoor heat exchanger 150 completes defrost, now, and first is outdoor The outdoor heat exchanger 160 of heat exchanger 150 and second completes defrost circulation, can control the first outdoor heat exchanger 150 and the Two outdoor heat exchangers 160 are absorbed heat, and the governing speed of indoor temperature are improved with this so that indoor temperature can be as soon as possible Meet the requirement of user.
The step of working condition of outdoor heat exchanger is adjusted according to outdoor environment temperature includes:When outdoor environment temperature When degree is more than T1, the second control valve 182 of control, the 3rd control valve 183, the 5th control valve 185 and the 7th control valve 187 are opened, Control the first control valve 181, the 4th control valve 184, the 6th control valve 186 to close, control the heat release of the first outdoor heat exchanger 150 Frost, the second outdoor heat exchanger 160 absorbs heat.When outdoor environment temperature is more than T1, illustrate outdoor heat exchanger and outdoor environment temperature Between there is the larger temperature difference, it is only necessary to compared with low capacity heat exchanger be just able to maintain that interior heating needs, therefore now with change Frost is main purpose, and the first outdoor heat exchanger 150 that can be first longer to the defrost time carries out defrost.Due to only needing to second Room External heat exchanger 160 can just provide the heating needs of interior with outdoor exchanged heat, therefore can control the first outdoor heat exchanger 150 heat release defrosts, the second outdoor heat exchanger 160 absorbs heat so that the first outdoor heat exchanger 150 and the second outdoor heat exchanger 160 its One of defrost, another provides indoor heating institute calorific requirement, and that realizes air-conditioning does not shut down defrosting operation, while avoiding to room Interior temperature adjustment is affected greatly so that indoor temperature can be remained in OK range, meets the comfortable of human body Degree is required.
When carrying out defrost to the first outdoor heat exchanger 150 first, preparatory condition includes:First outdoor heat exchanger 150 Coil temperature is more than T5 and is continued above time t4.T5 is more than with the coil temperature of outdoor heat exchanger and it is continued above the time when the T4, the then defrost temperature and defrost time for illustrating the first outdoor heat exchanger 150 has been enough to provide enough defrost heats, full The heat demand of the abundant defrost of the first outdoor heat exchanger 150 of foot, therefore now can consider the first outdoor heat exchanger 150 Complete defrost.
The step of working condition of outdoor heat exchanger is adjusted according to outdoor coil temperature also includes:When the second outdoor The coil temperature of heat exchanger be less than or equal to T6 when, control the first control valve 181, the 4th control valve 184, the 5th control valve 185, 7th control valve 187 is opened, and the second control valve 182 of control, the 3rd control valve 183 and the 6th control valve 186 are closed, control first Outdoor heat exchanger 150 absorbs heat, the heat release defrost of the second outdoor heat exchanger 160.After the first outdoor heat exchanger 150 completes defrost, If the coil temperature of the second outdoor heat exchanger is less than or equal to T6, the outer surface of the second outdoor heat exchanger 160 reaches solidifying frost temperature Spend, need to carry out defrost processing in the outer surface of the second outdoor heat exchanger 160, to avoid the second outdoor heat exchanger 160 The heat exchange efficiency of the second outdoor heat exchanger 160 of the solidifying frost influence in outer surface.Therefore now, it is determined that the first outdoor heat exchanger 150 is complete Into after defrost, it is possible to control the second outdoor heat exchanger 160 to carry out heat release defrost, while controlling the first outdoor heat exchanger 150 Heat absorption is heated to indoor, it is ensured that the normal operation of indoor heating, while realizing that the defrosting of not shutting down of outdoor heat exchanger is operated.
The step of working condition of outdoor heat exchanger is adjusted according to outdoor coil temperature also includes:When the second outdoor When the coil temperature of heat exchanger is more than T6, the first outdoor heat exchanger 150 stops defrost operation, controls the first outdoor heat exchanger 150 Absorbed heat simultaneously with the second outdoor heat exchanger 160 and continue the t5 times;Control the first control valve 181, the 4th control valve the 184, the 5th Control valve 185, the 7th control valve 187 are opened, and the second control valve 182 of control, the 3rd control valve 183 and the 6th control valve 186 are closed Close, the first outdoor heat exchanger 150 of control absorbs heat, the heat release defrost of the second outdoor heat exchanger 160.
If the coil temperature of the second outdoor heat exchanger is more than T6, illustrate the coil temperature of the second outdoor heat exchanger 160 Higher, the outer surface of the second outdoor heat exchanger 160 not yet reaches solidifying ice-lolly part, without carrying out defrost processing, therefore now can be First outdoor heat exchanger 150 is completed after defrost, just stops the defrost heat release of the first outdoor heat exchanger 150, while not controlling temporarily Second outdoor heat exchanger 160 carries out heat release defrost so that the first outdoor heat exchanger 150 and the second outdoor heat exchanger 160 are inhaled simultaneously Heat, it is ensured that indoor heating needs, after two outdoor heat exchangers, which absorb heat, to be continued for some time simultaneously, now indoor temperature deviation Reduce, the first outdoor heat exchanger 150 can be only relied on and provide heat exchange heat for interior, therefore now can be to the second outdoor heat exchange Device 160 carries out heat release defrost, can also reduce the influence caused by being adjusted when taking such a working condition to indoor temperature, reduces Uncomfortable row when user uses, improves the use feeling of user.
The step of working condition of outdoor heat exchanger is adjusted according to outdoor environment temperature also includes:Detect second Room The coil temperature of external heat exchanger 160;When the coil temperature of the second outdoor heat exchanger 160 is more than T7 and the duration is more than t6, The 3rd control valve 183, the 5th control valve 185 and the 6th control valve 186 is controlled to open, control the first control valve 181, second control Valve 182, the 4th control valve 184 and the 7th control valve 187 are closed, the first outdoor heat exchanger 150 of control and the second outdoor heat exchanger 160 heat absorptions.When the coil temperature of the second outdoor heat exchanger 160 is more than T7 and the duration is more than t6, then illustrate that second is outdoor The defrost of heat exchanger 160 continue for time enough, it is ensured that the second outdoor heat exchanger 160 completes defrost, now, and first is outdoor The outdoor heat exchanger 160 of heat exchanger 150 and second completes defrost circulation, can control the first outdoor heat exchanger 150 and the Two outdoor heat exchangers 160 are absorbed heat, and the governing speed of indoor temperature are improved with this so that indoor temperature can be as soon as possible Meet the requirement of user.
In above-mentioned each parameter, T1 is, for example, 2 DEG C, and T2 is, for example, 6 DEG C, and T3 is, for example, -5 DEG C, and T4 is, for example, 6 DEG C, T5 It it is such as 6 DEG C, T6 is, for example, -5 DEG C, and T7 is, for example, 6 DEG C, and t1 is, for example, 1min, and t2 is, for example, 10min, and t3 is, for example, 1min, t4 It is such as 1min, t5 is, for example, 15min, and t6 is, for example, 1min.
It should be appreciated that the invention is not limited in the flow and structure for being described above and being shown in the drawings, And various modifications and changes can be being carried out without departing from the scope.The scope of the present invention is only limited by appended claim System.

Claims (11)

1. a kind of air conditioner without shutting runs Defrost method, it is characterised in that including:
Control air-conditioning heating operation;
Detect outdoor environment temperature;
The working condition of outdoor heat exchanger is adjusted according to outdoor environment temperature;
When outdoor heat exchanger is adjusted to preparatory condition, outdoor coil temperature is detected;
The working condition of outdoor heat exchanger is adjusted according to outdoor coil temperature so that the first outdoor heat exchanger and second Room The operation heat absorption of one of external heat exchanger, another operation heat release defrost.
2. air conditioner without shutting according to claim 1 runs Defrost method, it is characterised in that described according to outdoor environment The step of working condition of outdoor heat exchanger is adjusted temperature includes:
When outdoor environment temperature is more than T1, the first control valve of control, the 4th control valve, the 5th control valve, the 7th control valve are beaten Open, the second control valve of control, the 3rd control valve and the 6th control valve are closed, control the first outdoor heat exchanger heat absorption, second is outdoor Heat exchanger heat release defrost.
3. air conditioner without shutting according to claim 2 runs Defrost method, it is characterised in that the preparatory condition bag Include:
The coil temperature of second outdoor heat exchanger is more than T2 and is continued above time t1.
4. air conditioner without shutting according to claim 3 runs Defrost method, it is characterised in that described according to outdoor coil pipe used The step of working condition of outdoor heat exchanger is adjusted temperature includes:
When the coil temperature of the first outdoor heat exchanger is less than or equal to T3, the second control valve of control, the 3rd control valve, the 5th control Valve processed and the 7th control valve are opened, and the first control valve of control, the 4th control valve, the 6th control valve are closed, and the first outdoor of control is changed Hot device heat release defrost, the heat absorption of the second outdoor heat exchanger.
5. air conditioner without shutting according to claim 3 runs Defrost method, it is characterised in that described according to outdoor coil pipe used The step of working condition of outdoor heat exchanger is adjusted temperature also includes:
When the coil temperature of the first outdoor heat exchanger is more than T3, the second outdoor heat exchanger stops defrost operation, controls the first Room External heat exchanger and the second outdoor heat exchanger absorb heat simultaneously and continue the t2 times;
The second control valve, the 3rd control valve, the 5th control valve and the 7th control valve is controlled to open, the first control valve of control, the 4th Control valve, the 6th control valve are closed, and control the first outdoor heat exchanger heat release defrost, the heat absorption of the second outdoor heat exchanger.
6. the air conditioner without shutting operation Defrost method according to claim 4 or 5, it is characterised in that described according to outdoor The step of working condition of outdoor heat exchanger is adjusted coil temperature also includes:
Detect the coil temperature of the first outdoor heat exchanger;
When the coil temperature of the first outdoor heat exchanger is more than T4 and the duration is more than t3, the 3rd control valve of control, the 5th control Valve processed and the 6th control valve are opened, and the first control valve of control, the second control valve, the 4th control valve and the 7th control valve are closed, control Make the first outdoor heat exchanger and the heat absorption of the second outdoor heat exchanger.
7. air conditioner without shutting according to claim 1 runs Defrost method, it is characterised in that described according to outdoor environment The step of working condition of outdoor heat exchanger is adjusted temperature includes:
When outdoor environment temperature is less than or equal to T1, the second control valve of control, the 3rd control valve, the 5th control valve and the 7th control Valve processed is opened, and the first control valve of control, the 4th control valve, the 6th control valve are closed, and control the first outdoor heat exchanger heat release defrost, Second outdoor heat exchanger absorbs heat.
8. air conditioner without shutting according to claim 7 runs Defrost method, it is characterised in that the preparatory condition bag Include:
The coil temperature of first outdoor heat exchanger is more than T5 and is continued above time t4.
9. air conditioner without shutting according to claim 8 runs Defrost method, it is characterised in that described according to outdoor coil pipe used The step of working condition of outdoor heat exchanger is adjusted temperature also includes:
When the coil temperature of the second outdoor heat exchanger is less than or equal to T6, the first control valve of control, the 4th control valve, the 5th control Valve processed, the 7th control valve are opened, and the second control valve of control, the 3rd control valve and the 6th control valve are closed, and the first outdoor of control is changed Hot device heat absorption, the second outdoor heat exchanger heat release defrost.
10. air conditioner without shutting according to claim 3 runs Defrost method, it is characterised in that described according to outdoor disk The step of working condition of outdoor heat exchanger is adjusted pipe temperature also includes:
When the coil temperature of the second outdoor heat exchanger is more than T6, the first outdoor heat exchanger stops defrost operation, controls the first Room External heat exchanger and the second outdoor heat exchanger absorb heat simultaneously and continue the t5 times;
The first control valve, the 4th control valve, the 5th control valve, the 7th control valve is controlled to open, the second control valve of control, the 3rd control Valve processed and the 6th control valve are closed, control the first outdoor heat exchanger heat absorption, the second outdoor heat exchanger heat release defrost.
11. the air conditioner without shutting operation Defrost method according to claim 9 or 10, it is characterised in that described according to room The step of working condition of outdoor heat exchanger is adjusted outer coil temperature also includes:Detect the coil pipe of the second outdoor heat exchanger Temperature;
When the coil temperature of the second outdoor heat exchanger is more than T7 and the duration is more than t6, the 3rd control valve of control, the 5th control Valve processed and the 6th control valve are opened, and the first control valve of control, the second control valve, the 4th control valve and the 7th control valve are closed, control Make the first outdoor heat exchanger and the heat absorption of the second outdoor heat exchanger.
CN201710214523.XA 2017-04-01 2017-04-01 Defrosting operation method for air conditioner without stopping Active CN107023950B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710214523.XA CN107023950B (en) 2017-04-01 2017-04-01 Defrosting operation method for air conditioner without stopping

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710214523.XA CN107023950B (en) 2017-04-01 2017-04-01 Defrosting operation method for air conditioner without stopping

Publications (2)

Publication Number Publication Date
CN107023950A true CN107023950A (en) 2017-08-08
CN107023950B CN107023950B (en) 2020-07-31

Family

ID=59527919

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710214523.XA Active CN107023950B (en) 2017-04-01 2017-04-01 Defrosting operation method for air conditioner without stopping

Country Status (1)

Country Link
CN (1) CN107023950B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108800436A (en) * 2018-04-25 2018-11-13 广东美的制冷设备有限公司 Air conditioner, Defrost method and computer readable storage medium
CN108954676A (en) * 2018-07-17 2018-12-07 苏州韵之秋智能科技有限公司 A kind of intelligent air condition does not shut down defrosting method
CN113944987A (en) * 2021-11-24 2022-01-18 广东美的制冷设备有限公司 Control method, device and equipment of air conditioning system and storage medium
WO2023071151A1 (en) * 2021-10-28 2023-05-04 青岛海尔空调器有限总公司 Air conditioning defrost control method, control device and air conditioner

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1983277A2 (en) * 2007-04-19 2008-10-22 Matsushita Electric Industrial Co., Ltd. Refrigeration cycle apparatus
JP2014081174A (en) * 2012-10-18 2014-05-08 Fujitsu General Ltd Air conditioner
CN104089427A (en) * 2014-06-24 2014-10-08 珠海格力电器股份有限公司 Air conditioner system and control method thereof
CN105258408A (en) * 2015-10-08 2016-01-20 Tcl空调器(中山)有限公司 Air conditioner and defrosting method for air conditioner
JP2016031182A (en) * 2014-07-29 2016-03-07 日立アプライアンス株式会社 Air conditioner
CN105387560A (en) * 2015-10-30 2016-03-09 株洲麦格米特电气有限责任公司 Intelligent defrosting method for direct current frequency conversion air conditioner
CN105723168A (en) * 2013-10-24 2016-06-29 三菱电机株式会社 Air conditioner
CN105928272A (en) * 2016-04-20 2016-09-07 广东美的暖通设备有限公司 Air conditioning system and defrosting method thereof

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1983277A2 (en) * 2007-04-19 2008-10-22 Matsushita Electric Industrial Co., Ltd. Refrigeration cycle apparatus
JP2014081174A (en) * 2012-10-18 2014-05-08 Fujitsu General Ltd Air conditioner
CN105723168A (en) * 2013-10-24 2016-06-29 三菱电机株式会社 Air conditioner
CN104089427A (en) * 2014-06-24 2014-10-08 珠海格力电器股份有限公司 Air conditioner system and control method thereof
JP2016031182A (en) * 2014-07-29 2016-03-07 日立アプライアンス株式会社 Air conditioner
CN105258408A (en) * 2015-10-08 2016-01-20 Tcl空调器(中山)有限公司 Air conditioner and defrosting method for air conditioner
CN105387560A (en) * 2015-10-30 2016-03-09 株洲麦格米特电气有限责任公司 Intelligent defrosting method for direct current frequency conversion air conditioner
CN105928272A (en) * 2016-04-20 2016-09-07 广东美的暖通设备有限公司 Air conditioning system and defrosting method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108800436A (en) * 2018-04-25 2018-11-13 广东美的制冷设备有限公司 Air conditioner, Defrost method and computer readable storage medium
CN108954676A (en) * 2018-07-17 2018-12-07 苏州韵之秋智能科技有限公司 A kind of intelligent air condition does not shut down defrosting method
WO2023071151A1 (en) * 2021-10-28 2023-05-04 青岛海尔空调器有限总公司 Air conditioning defrost control method, control device and air conditioner
CN113944987A (en) * 2021-11-24 2022-01-18 广东美的制冷设备有限公司 Control method, device and equipment of air conditioning system and storage medium

Also Published As

Publication number Publication date
CN107023950B (en) 2020-07-31

Similar Documents

Publication Publication Date Title
CN106918122A (en) Air conditioner without shutting Defrost operation method
CN106871381A (en) Air conditioner without shutting Defrost operation method
CN107023950A (en) Air conditioner without shutting Defrost operation method
CN106382701A (en) Multiple-on-line air conditioner as well as outdoor unit thereof, control method thereof and control device thereof
WO2018223927A1 (en) Air conditioning apparatus and control method therefor
CN104101127B (en) Multi-online air-conditioning system and defrosting control method thereof
CN104422072B (en) The control method of multi-gang air-conditioner and the control system of multi-gang air-conditioner
CN104748426B (en) multiple on-line system
CN104110776B (en) Air conditioning system and control method thereof
CN102734885B (en) Serial air conditioner and temperature regulating box all-in-one machine and operation control method thereof
CN106940071A (en) Air-conditioning device and its control method
CN206207630U (en) Multi-gang air-conditioner and its outdoor unit
CN104344466B (en) Air regulator
CN106679089A (en) Control method and device for air conditioner
CN107023946A (en) Air conditioner without shutting Defrost operation method
US20100206000A1 (en) Air conditioner and method of controlling the same
CN110836417A (en) Air conditioner and air conditioner control method
CN107023944A (en) Air conditioner without shutting Defrost operation method
CN106839346A (en) A kind of air-conditioner and control method
CN103363707A (en) Heat pump type air conditioning device
CN107023948A (en) Air conditioner and its do not shut down Defrost operation method
CN202546973U (en) Heat pump type air conditioning device
CN211551798U (en) Air conditioner
CN106871382A (en) Air conditioner without shutting Defrost operation method
CN107023963A (en) A kind of air conditioner and control method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Li Xiwu

Inventor after: Xu Wenming

Inventor after: Zhang Long

Inventor after: Wang Fei

Inventor before: Xu Wenming

CB03 Change of inventor or designer information
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20200916

Address after: 266101 Haier Industrial Park, Haier Road, Laoshan District, Shandong, Qingdao, China

Co-patentee after: QINGDAO HAIER (JIAOZHOU) AIR CONDITIONER Co.,Ltd.

Patentee after: QINGDAO HAIER AIR CONDITIONER GENERAL Corp.,Ltd.

Address before: 266101 Haier Industrial Park, Haier Road, Laoshan District, Shandong, Qingdao, China

Patentee before: QINGDAO HAIER AIR CONDITIONER GENERAL Corp.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201103

Address after: 266101 Haier Industrial Park, Haier Road, Laoshan District, Shandong, Qingdao, China

Patentee after: QINGDAO HAIER AIR CONDITIONER GENERAL Corp.,Ltd.

Patentee after: QINGDAO HAIER (JIAOZHOU) AIR CONDITIONER Co.,Ltd.

Patentee after: Haier Zhijia Co.,Ltd.

Address before: 266101 Haier Industrial Park, Haier Road, Laoshan District, Shandong, Qingdao, China

Patentee before: QINGDAO HAIER AIR CONDITIONER GENERAL Corp.,Ltd.

Patentee before: QINGDAO HAIER (JIAOZHOU) AIR CONDITIONER Co.,Ltd.

TR01 Transfer of patent right