CN107020287A - hanger - Google Patents

hanger Download PDF

Info

Publication number
CN107020287A
CN107020287A CN201710307721.0A CN201710307721A CN107020287A CN 107020287 A CN107020287 A CN 107020287A CN 201710307721 A CN201710307721 A CN 201710307721A CN 107020287 A CN107020287 A CN 107020287A
Authority
CN
China
Prior art keywords
holder
peg
workpiece
hanger
support bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710307721.0A
Other languages
Chinese (zh)
Inventor
周作坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Evenwin Precision Technology Co Ltd
Original Assignee
Guangdong Evenwin Precision Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Evenwin Precision Technology Co Ltd filed Critical Guangdong Evenwin Precision Technology Co Ltd
Priority to CN201710307721.0A priority Critical patent/CN107020287A/en
Publication of CN107020287A publication Critical patent/CN107020287A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B08CLEANING
    • B08BCLEANING IN GENERAL; PREVENTION OF FOULING IN GENERAL
    • B08B13/00Accessories or details of general applicability for machines or apparatus for cleaning

Landscapes

  • Supports Or Holders For Household Use (AREA)

Abstract

The present invention relates to a kind of hanger.The hanger includes hanging frame, peg and holder, and the two ends of peg are arranged on extension frame, and holder is arranged on peg.Holder is flexible, and the two ends of holder form clamping part.During holder clamping workpiece, holder is compressed, holder is located between the locating dowel of workpiece, releasable clamps, clamping part is caught in the neck of the locating dowel, workpiece is by clamping tightly, and workpiece is difficult to come off from hanger.When being cleaned using the hanger to workpiece such as mobile phone shells, each workpiece is tightly held on hanger, and play will not occur for workpiece during cleaning, and the surface of workpiece will not be scratched will not be overlapping between scratch, workpiece, and workpiece is cleaned up.

Description

Hanger
Technical field
The present invention relates to machinery manufacturing technology field, more particularly to a kind of hanger.
Background technology
The surface of the handwares such as mobile phone shell is after polishing, and mobile phone shell surface has dust and greasy dirt, it is necessary to opponent Casing is cleaned.When being cleaned to workpiece such as mobile phone shells, it usually needs use hanger.Cleaned using traditional hanger When, it is typically that mobile phone shell is directly introduced in hanger, play easily occurs for mobile phone shell during cleaning, the easy quilt in the surface of mobile phone shell Scratch is scratched, and it is easily overlapping between mobile phone shell, and greasy dirt and dust are not washed clean clearly.
The content of the invention
Based on this, it is necessary in view of the above-mentioned problems, offer is a kind of can effectively to clean the hanger of the workpiece such as mobile phone shell.
A kind of hanger, including:
Hang frame;
Peg, its two ends are arranged on the extension frame;And
Holder, is arranged on the peg, and the holder is flexible, and the two ends of the holder form clamping Portion, during the holder clamping workpiece, compresses the holder, the holder is located between the locating dowel of the workpiece, The holder is unclamped, the clamping part is caught in the neck of the locating dowel.
In one of the embodiments, the holder is shell fragment, forms raised after the holder bending, the projection It is fixed on the peg.
In one of the embodiments, bracing piece is provided with the peg, the projection is fixed on the peg and institute State on bracing piece.
In one of the embodiments, the neck formed on the clamping part in arc bayonet socket, the locating dowel of the workpiece For deep-slotted chip breaker.
In one of the embodiments, the extension frame includes framework, and the opposite sides of the framework is respectively arranged with support Bar, the two ends of the peg are connected with the support bar of opposite sides respectively.
In one of the embodiments, the peg is multiple, and multiple pegs are arranged at intervals on the support bar.
In one of the embodiments, the opposite sides of the framework is respectively arranged with multiple support bars, Duo Gesuo The holder stated on support bar interval setting, the two neighboring peg is staggered, and the two neighboring peg point Wei Yu not be on the two neighboring support bar.
In one of the embodiments, the holder is multiple, and multiple holders are arranged at intervals at the peg On.
In one of the embodiments, the opposite sides of the framework is respectively arranged with auxiliary rod, and the auxiliary rod with The support bar is connected.
In one of the embodiments, the extension frame is provided with handle.
Above-mentioned hanger at least has advantages below:
During hanger clamping workpiece, holder is compressed, holder is located between the locating dowel of workpiece, releasable clamps, In the presence of elastic force, clamping part is caught in the neck of locating dowel, and workpiece is by clamping tightly, and workpiece is difficult to come off from hanger. When being cleaned using the hanger to workpiece such as mobile phone shells, each workpiece is tightly held on hanger, and workpiece is not during cleaning Can occur play, the surface of workpiece will not be scratched will not be overlapping between scratch, workpiece, and workpiece is cleaned up.
Brief description of the drawings
Fig. 1 is the structural representation of hanger in an embodiment;
Fig. 2 is the partial enlarged drawing at A in Fig. 1;
Fig. 3 is the top view of hanger shown in Fig. 1;
Fig. 4 is that hanger shown in Fig. 1 clamps the structural representation after a workpiece;
Fig. 5 is the partial enlarged drawing at B in Fig. 4;
Fig. 6 is that hanger shown in Fig. 1 clamps the structural representation after three workpiece;
Fig. 7 is that hanger shown in Fig. 6 clamps the rearview after three workpiece.
Embodiment
In order to facilitate the understanding of the purposes, features and advantages of the present invention, below in conjunction with the accompanying drawings to the present invention Embodiment be described in detail.Many details are elaborated in the following description to fully understand this hair It is bright.But the invention can be embodied in many other ways as described herein, those skilled in the art can be not Similar improvement is done in the case of running counter to intension of the present invention, therefore the present invention is not limited to the specific embodiments disclosed below.
It should be noted that when element is referred to as " being fixed on " another element, it can be directly on another element Or can also have element placed in the middle.When an element is considered as " connection " another element, it can be directly connected to To another element or it may be simultaneously present centering elements.Term as used herein " vertical ", " level ", " left side ", For illustrative purposes only, it is unique embodiment to be not offered as " right side " and similar statement.
Unless otherwise defined, all of technologies and scientific terms used here by the article is with belonging to technical field of the invention The implication that technical staff is generally understood that is identical.Term used in the description of the invention herein is intended merely to description tool The purpose of the embodiment of body, it is not intended that in the limitation present invention.Each technical characteristic of embodiment described above can be carried out arbitrarily Combination, to make description succinct, combination not all possible to each technical characteristic in above-described embodiment is all described, so And, as long as contradiction is not present in the combination of these technical characteristics, all it is considered to be the scope of this specification record.
The hanger 10 in Fig. 1 and Fig. 4, an embodiment is referred to, for clamping the workpiece such as mobile phone shell 20, is then carried out clear Wash, be adapted to cleaning and require workpiece appearance higher and more greasy dirt product, the mount volume of hanger 10 is big, uses simple side Just.The hanger 10 includes hanging frame 100, peg 200, holder 300 and handle 400.
Hanging frame 100 includes framework 110, support bar 120 and auxiliary rod 130.In present embodiment, framework 110 is cuboid, Framework 110 includes head rod 112, the second connecting rod 114 and the 3rd connecting rod 116, wherein, head rod 112, second The connecting rod 116 of connecting rod 114 and the 3rd is four.Two head rods 112 are oppositely arranged, two second connecting rods 114 It is oppositely arranged, two head rods 112 and two second connecting rods 114 join end to end and surround rectangular shaped rim, therefore four first Connecting rod 112 and four second connecting rods 114 can surround two frames.The two ends of four the 3rd connecting rods 116 are respectively with two Four angles of individual frame are connected, so as to constitute cuboid framework 110.It is understood that in other embodiments, framework 100 can also be made of other shapes and other modes.
The opposite sides of framework 110 is respectively arranged with support bar 120, and support bar 120 is used to carry hanging strip 200.Framework 110 Relative both sides are respectively arranged with multiple support bars 120, and multiple support bars 120 are arranged at intervals.Specific in present embodiment, frame The relative both sides of frame 110 are respectively arranged with two support bars 120, and two support bars 120 are arranged at intervals.The two ends of support bar 120 It is connected respectively with two head rods being oppositely arranged 112.
The opposite sides of framework 110 is respectively arranged with auxiliary rod 130, and auxiliary rod 130 is connected with support bar 120, uses In the stability for strengthening support bar 120, support bar 120 is prevented to be bent.In present embodiment, the two ends difference of auxiliary rod 130 It is connected with the second connecting rod 114 that two are oppositely arranged, support bar 120 is connected with the body of rod of auxiliary rod 130.Framework 110 Opposite sides be respectively arranged with two auxiliary rods 130, two auxiliary rods 130 are arranged at intervals, and further strengthen support bar 120 Stability.
Peg 200 is arranged on extension frame 100, and peg 200 is used to carry holder 300.Specific in present embodiment, hang The two ends of bar 200 are connected with the support bar 120 of opposite sides respectively.Peg 200 is multiple, and multiple pegs 200 are arranged at intervals In on support bar 120.In present embodiment, the opposite sides of framework 110 is respectively arranged with two support bars 120, therefore peg 200 are provided with two rows, and a row is arranged at intervals with seven pegs 200.
Also referring to Fig. 2, holder 300 is arranged on peg 200, and holder 300 is used for clamping workpiece 20.This implementation In mode, bracing piece 210 is provided with peg 200, one end of bracing piece 210 is connected with peg 200, bracing piece 210 it is another One end is connected with holder 300.Bracing piece 210 is used to strengthen the connection between peg 200 and holder 300, prevents clamping Part 300 is separated with peg 200.Holder 300 can be fixed on by way of welding on peg 200 and bracing piece 210.
Holder 300 is multiple, and multiple holders 300 are arranged at intervals in hanging strip 200.It is each to hang in present embodiment 4 holders 300 are provided with bar 200.Also referring to Fig. 3, in present embodiment, peg 200 is provided with two rows, first row Holder 300 on peg 200 is staggered with the holder 300 on second row peg 200.Specifically, first row peg 200 On holder 300 be dorsad staggered with the holder 300 on second row peg 200.
Holder 300 is flexible, and the two ends of holder 300 form clamping part 320, and clamping part 320 offers bayonet socket 310.Specific in present embodiment, holder 300 is shell fragment, and holder 300 has projection 330 after bending, projection 330 is fixed In on peg 200 and bracing piece 210.By pressing the both sides of projection 330, holder 300 can be conveniently compressed.
Also referring to Fig. 4 and Fig. 5, the surface of workpiece 20 is provided with locating dowel 22, and locating dowel 22 at least two, two The distance between individual locating dowel 22 is less than the length of holder 300.The side wall of locating dowel 22 offers neck 24.Present embodiment In, locating dowel 22 is two, and the line between two locating dowels 22 is with the horizontal predetermined angle, holder 300 and peg 200 Between be in predetermined angle so that after the clamping workpiece 20 of holder 300, workpiece 20 and plane-parallel.Locating dowel 22 is cylinder, Neck 24 is deep-slotted chip breaker, and bayonet socket 310 is arc, it is ensured that the stabilization clamped after the clamping workpiece 20 of holder 300.
During above-mentioned 300 clamping workpiece 20 of holder, two side walls of lug boss 330 are pressed, holder 300 is compressed, will Holder 300 is arranged between locating dowel 22.The bayonet socket 310 of holder 300 is directed at locating dowel 22, releasable clamps 300, folder Gripping member 300 is extended in the presence of elastic force, and locating dowel 200 is caught in bayonet socket 310, and clamping part 320 is caught in neck 24, workpiece 20 Tightly clamped.It is understood that in other embodiments, clamping part 320 can not also open up bayonet socket 310, clamping part 320 are directly caught in neck 24.
Also referring to Fig. 6 and Fig. 7, after the clamping workpiece 20 of holder 300, due to the holder on first row peg 200 300 are staggered with the holder 300 on second row peg 200, therefore, after workpiece 20 is clamped, and two row's workpiece 20 are mutually handed over Mistake, can effectively reduce the volume of whole hanger 10, save space and material.
Handle 400 is arranged on extension frame 100, can conveniently be lifted hanger 10 and is put into rinse bath and taken out of rinse bath Go out.In present embodiment, the opposite sides for hanging frame 100 is respectively arranged with handle 400, specifically, and two handles 400 are respectively with two Individual head rod 112 is connected.
Above-mentioned hanger 10 at least has advantages below:
During 10 clamping workpiece 20 of hanger, holder 300 is compressed, holder 300 is located between the locating dowel 22 of workpiece 20. Releasable clamps 300, in the presence of elastic force, locating dowel 200 is caught in bayonet socket 310, and clamping part 320 is caught in neck 24, work Part 20 is tightly clamped, and workpiece 20 is difficult to come off from hanger 10, and the clamping of workpiece 20 is stable.Also, holder 300 clamps difference During the workpiece 20 of specification, holder 300 degree different by compressing is met, and hanger 10 can clamp the workpiece of different size 20, expand the use scope of hanger 10.
When being cleaned using the hanger 10 to the workpiece such as mobile phone shell 20, each workpiece 20 is tightly held in hanger 10 On, play will not occur for workpiece 20 during cleaning, and the surface of workpiece 20 will not be scratched will not be overlapping between scratch, workpiece 20, work Part 20 is cleaned up.The mount volume of hanger 10 is big, can once clamp 56 workpiece 20, greatly increase production efficiency.
Embodiment described above only expresses the several embodiments of the present invention, and it describes more specific and detailed, but simultaneously Can not therefore it be construed as limiting the scope of the patent.It should be pointed out that coming for one of ordinary skill in the art Say, without departing from the inventive concept of the premise, various modifications and improvements can be made, these belong to the protection of the present invention Scope.Therefore, the protection domain of patent of the present invention should be determined by the appended claims.

Claims (10)

1. a kind of hanger, it is characterised in that including:
Hang frame;
Peg, its two ends are arranged on the extension frame;And
Holder, is arranged on the peg, and the holder is flexible, and the two ends of the holder form clamping part, institute When stating holder clamping workpiece, the holder is compressed, the holder is located between the locating dowel of the workpiece, institute is unclamped Holder is stated, the clamping part is caught in the neck of the locating dowel.
2. hanger according to claim 1, it is characterised in that the holder is shell fragment, shape after the holder bending Into projection, the projection is fixed on the peg.
3. hanger according to claim 2, it is characterised in that bracing piece is provided with the peg, described raised fixed In on the peg and the bracing piece.
4. hanger according to claim 1, it is characterised in that arc bayonet socket is formed on the clamping part, the workpiece Neck in locating dowel is deep-slotted chip breaker.
5. hanger according to claim 1, it is characterised in that the extension frame includes framework, the opposite sides of the framework Support bar is respectively arranged with, the two ends of the peg are connected with the support bar of opposite sides respectively.
6. hanger according to claim 5, it is characterised in that the peg is multiple, and multiple pegs are arranged at intervals In on the support bar.
7. hanger according to claim 6, it is characterised in that the opposite sides of the framework is respectively arranged with multiple described Support bar, multiple support bars are arranged at intervals, and the holder on the two neighboring peg is staggered, and adjacent two The individual peg is located on the two neighboring support bar respectively.
8. hanger according to claim 6, it is characterised in that the holder is multiple, multiple holder intervals It is arranged on the peg.
9. hanger according to claim 5, it is characterised in that the opposite sides of the framework is respectively arranged with auxiliary rod, And the auxiliary rod is connected with the support bar.
10. hanger according to claim 1, it is characterised in that the extension frame is provided with handle.
CN201710307721.0A 2017-05-04 2017-05-04 hanger Pending CN107020287A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710307721.0A CN107020287A (en) 2017-05-04 2017-05-04 hanger

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710307721.0A CN107020287A (en) 2017-05-04 2017-05-04 hanger

Publications (1)

Publication Number Publication Date
CN107020287A true CN107020287A (en) 2017-08-08

Family

ID=59528362

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710307721.0A Pending CN107020287A (en) 2017-05-04 2017-05-04 hanger

Country Status (1)

Country Link
CN (1) CN107020287A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW200827492A (en) * 2006-12-26 2008-07-01 Sutech Trading Ltd Rack structure
CN201500633U (en) * 2009-08-04 2010-06-09 晋江福兴拉链有限公司 Varnish baking rack for zipper head
TW201226634A (en) * 2010-12-31 2012-07-01 Hon Hai Prec Ind Co Ltd Rack device
CN202530189U (en) * 2012-03-13 2012-11-14 宁波四维尔工业股份有限公司 Electroplating hanger
CN203683709U (en) * 2014-01-06 2014-07-02 苏州道蒙恩电子科技有限公司 Key hanging tool
CN204779895U (en) * 2015-07-09 2015-11-18 佛山市高明高盛铝业有限公司 A set oxidation treatment hanger generates heat
CN205474048U (en) * 2016-03-18 2016-08-17 绍兴市新弘包装有限公司 Anodic oxidation hanger of aluminium system of placing bottle lid

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW200827492A (en) * 2006-12-26 2008-07-01 Sutech Trading Ltd Rack structure
CN201500633U (en) * 2009-08-04 2010-06-09 晋江福兴拉链有限公司 Varnish baking rack for zipper head
TW201226634A (en) * 2010-12-31 2012-07-01 Hon Hai Prec Ind Co Ltd Rack device
CN202530189U (en) * 2012-03-13 2012-11-14 宁波四维尔工业股份有限公司 Electroplating hanger
CN203683709U (en) * 2014-01-06 2014-07-02 苏州道蒙恩电子科技有限公司 Key hanging tool
CN204779895U (en) * 2015-07-09 2015-11-18 佛山市高明高盛铝业有限公司 A set oxidation treatment hanger generates heat
CN205474048U (en) * 2016-03-18 2016-08-17 绍兴市新弘包装有限公司 Anodic oxidation hanger of aluminium system of placing bottle lid

Similar Documents

Publication Publication Date Title
CN207272793U (en) A kind of thin wall type fixture
CN104586339A (en) Dish-washing machine shelf and dish-washing machine
CN107020287A (en) hanger
CN107815737B (en) Cotton pocket forming machine with water spray nozzle
KR910008085Y1 (en) Ultrasonic cleaning device
CN209032265U (en) Knife and fork basket, bowl and basket assembly and dish-washing machine
CN211802935U (en) Cleaning hanger
US5611441A (en) Device for housing throw pillows during washing
CN210300531U (en) Cup holder and cup holder set
CN215429727U (en) Hanger assembly
CN205869021U (en) Wash hanger with quick compact structure
CN107054833B (en) Brick pallets
CN210546850U (en) Cleaning brush for cleaning test tube
CN208758289U (en) A kind of high efficiency coating cleaning basket
CN210358355U (en) Ultrasonic cleaning machine
CN207738216U (en) A kind of bobbin-winding machine of convenient clamping
CN202322980U (en) Hanging frame with inclined hanging rods
CN104438188A (en) Cleaning basket for small workpieces
CN211283442U (en) Hook for oil immersion of automobile engine connecting rod
CN204769667U (en) Wash crystal with putting utensil
CN213332206U (en) Vibration damping base for ultrasonic cleaning machine
CN209744031U (en) novel grid structure
CN211420616U (en) Textile fabric defeathering device for textile production
CN212980274U (en) A place handcart for fabrics drying process
CN211009440U (en) Square steel pipe connecting piece capable of resisting torsion

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170808

RJ01 Rejection of invention patent application after publication