- CN106996843A CN106996843A CN201710313794.0A CN201710313794A CN106996843A CN 106996843 A CN106996843 A CN 106996843A CN 201710313794 A CN201710313794 A CN 201710313794A CN 106996843 A CN106996843 A CN 106996843A
- Authority
- CN
- China
- Prior art keywords
- pipe clamp
- connecting tube
- vapor
- welding
- outlet connecting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01L—MEASURING FORCE, STRESS, TORQUE, WORK, MECHANICAL POWER, MECHANICAL EFFICIENCY, OR FLUID PRESSURE
- G01L5/00—Apparatus for, or methods of, measuring force, work, mechanical power, or torque, specially adapted for specific purposes
- G01L5/0061—Force sensors associated with industrial machines or actuators
- G01L5/0076—Force sensors associated with manufacturing machines
- G01L5/009—Force sensors associated with material gripping devices
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01L—MEASURING FORCE, STRESS, TORQUE, WORK, MECHANICAL POWER, MECHANICAL EFFICIENCY, OR FLUID PRESSURE
- G01L1/00—Measuring force or stress, in general
- G01L1/20—Measuring force or stress, in general by measuring variations in ohmic resistance of solid materials or of electrically-conductive fluids; by making use of electrokinetic cells, i.e. liquid-containing cells wherein an electrical potential is produced or varied upon the application of stress
- G01L1/22—Measuring force or stress, in general by measuring variations in ohmic resistance of solid materials or of electrically-conductive fluids; by making use of electrokinetic cells, i.e. liquid-containing cells wherein an electrical potential is produced or varied upon the application of stress using resistance strain gauges
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01L—MEASURING FORCE, STRESS, TORQUE, WORK, MECHANICAL POWER, MECHANICAL EFFICIENCY, OR FLUID PRESSURE
- G01L5/00—Apparatus for, or methods of, measuring force, work, mechanical power, or torque, specially adapted for specific purposes
- G01L5/0047—Apparatus for, or methods of, measuring force, work, mechanical power, or torque, specially adapted for specific purposes measuring forces due to residual stresses
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E30/00—Energy generation of nuclear origin
- Y02E30/30—Nuclear fission reactors
Abstract
The invention discloses a kind of HTGR steam (vapor) outlet connecting tube pipe clamp pretightening force measuring apparatus and corresponding measuring method, the device includes pipe clamp and two pipe clamp frocks, pipe clamp includes two blocks of L-type sheet materials for being assembled into rectangular frame, resistance strain gage is provided with the outer surface of the rectangular frame, the pipe clamp frock is used to tighten the connecting tube, pipe clamp frock is removed after the completion of pipe clamp welding, the strain value of pipe clamp is read by the electronics foil gauge on pipe clamp, and then knows the residual pre-tightening forces on pipe clamp;By changing welding parameter, experiment is repeated several times, multigroup welding condition and corresponding residual pre-tightening forces value information are resulted in, so as to filter out the welding parameter that can produce satisfactory residual pre-tightening forces as needed.
Description
Technical field
Field, more particularly to a kind of HTGR steam (vapor) outlet connecting tube pipe clamp are manufactured the present invention relates to nuclear power generating equipment
Pretightening force measuring apparatus and method.
Background technology
HTGR is the new nuclear reactor with advanced technology feature generally acknowledged in the world, high temperature gas-cooled core
Power station have inherent safety, generating efficiency it is high, it is widely used the features such as, widely paid attention in the world, be also to have
The nucleus reactor heap-type of the 4th generation of technology such as nuclear energy system principal character.Wherein, temperature gas cooled reactor steam generator is used as high temperature
The important component of HTGR, its significance level needn't elaborate any further, naturally, the difficulty faced in its Design and manufacturing process
It is also and its numerous and diverse with the problem of having to and solve;Specifically, temperature gas cooled reactor steam generator steam (vapor) outlet is connected
Tubular construction is exactly one of them and its crucial research project, and current China is to temperature gas cooled reactor steam generator steam (vapor) outlet
Connecting pipe structure has had more in-depth study, and obtains more great achievement in research, also right in the prior art
The achievement has done certain record;
Such as Chinese patent, Application No. 201020655609.X, entitled " temperature gas cooled reactor steam generator connecting pipe
Attachment structure ", Application No. 201610390319.9, it is entitled " temperature gas cooled reactor steam generator steam (vapor) outlet connect
Manage single poling attachment structure ", Application No. 201610392844.4, it is entitled that " temperature gas cooled reactor steam generator feedwater connects
Take over single poling attachment structure " etc. disclose temperature gas cooled reactor steam generator steam (vapor) outlet connecting tube knot in patent document
Structure, from the information described in above-mentioned document, has overcome attachment structure and has been only used for overall poling at present, it is impossible to real
The technical problem of existing single poling, and propose the concrete scheme of single poling;
But going deep into research, such scheme, which still needs, constantly to be improved and supplements;HTGR steam goes out
Mouth connecting tube is fixedly clamped by pipe clamp, is restrained by pipe clamp connecting tube is tightened to connecting tube more, and pipe clamp is in itself
It is that welding is formed, in real work, the pretightning force on pipe clamp is difficult to hold, and in general the pretightning force on pipe clamp may
Disturbed by several factors, if mishandling, residual pre-tightening forces are had on pipe clamp, and the residual pre-tightening forces can be to even
The normal operating efficiency and service life for taking over tube bank have undesirable effect, so, how to control the remaining pretension on pipe clamp
Power, how setting suitable pipe clamp welding procedure/parameter and just obtaining controllable/satisfactory pipe clamp of residual pre-tightening forces is mesh
The realistic problem of preceding urgent need to resolve;
Because the environment where HTGR steam (vapor) outlet connecting tube is more complicated, the operating space that can allow for is very
Small, the manufacturing cost of the connecting tube is very high, does not allow typically to damage or scratch connecting tube, so considering to solve above-mentioned technology
During problem, the problems such as also considering reduction process costs, meet actual production conditions and improve measuring and calculating efficiency.
For these reasons, the present inventor is to existing temperature gas cooled reactor steam generator steam (vapor) outlet connecting tube pipe clamp
Analyse in depth, with reference to above-mentioned technical problem and special working environment, go out to can solve the problem that above-mentioned technology is asked to be designed
Topic, meets the new technical scheme of use requirement.
The content of the invention
In order to overcome above mentioned problem, present inventor has performed studying with keen determination, a kind of HTGR steam (vapor) outlet is designed
Connecting tube pipe clamp pretightening force measuring apparatus and corresponding measuring method, the device include pipe clamp and two pipe clamp frocks, pipe clamp bag
Two blocks of L-type sheet materials for being assembled into rectangular frame are included, resistance strain gage is provided with the outer surface of the rectangular frame, it is described
Pipe clamp frock is used to tighten the connecting tube, removes pipe clamp frock after the completion of pipe clamp welding, passes through the electronics foil gauge on pipe clamp
The strain value of pipe clamp is read, and then knows the residual pre-tightening forces on pipe clamp;By changing welding parameter, experiment is repeated several times,
Multigroup welding condition and corresponding residual pre-tightening forces value information are resulted in, can so as to filter out as needed
The welding parameter of satisfactory residual pre-tightening forces is produced, so as to complete the present invention.
In particular it is object of the present invention to provide a kind of HTGR steam (vapor) outlet connecting tube pipe clamp pretightning force
Measurement apparatus, including pipe clamp 1 and two pipe clamp frocks 2;
Wherein, the pipe clamp 1 includes two blocks of L-type sheet materials 3 for being assembled into rectangular frame, in the appearance of the rectangular frame
Resistance strain gage 4 is provided with face;
The pipe clamp frock 2 is separately positioned on the both sides of pipe clamp 1, and clamping the HTGR by pipe clamp frock 2 steams
Vapor outlet connecting tube.
Wherein, the pipe clamp frock 2 includes two clamping plates 21 and two bolts 22,
Wherein, two clamping plates 21 are set in parallel in the connecting tube both sides, and two clamping plates 21 are fastened by two bolts 22
It is allowed to clamp the connecting tube.
Wherein, the orthogonal setting of clamping plate 21 in two pipe clamp frocks 2.
Wherein, the spacing between pipe clamp 1 and pipe clamp frock 2 is 50~150mm.
Wherein, the resistance strain gage 4 has four, is separately positioned on four away from the connecting tube on rectangular frame
On outer surface;
Preferably, the resistance strain gage 4 is high temperature resistance foil gauge.
Wherein, welding groove is offered on the L-type sheet material 3, bevel angle is 60 °~70 °.
Wherein, the welded gaps between two blocks of L-type sheet materials 3 are 1mm~2mm.
The present invention also provides a kind of HTGR steam (vapor) outlet connecting tube pipe clamp pretension force measuring method, and this method is
Realized by device described above.
Wherein, this method comprises the following steps:
Step 1:Arrangement HTGR steam (vapor) outlet connecting tube is arranged, pipe clamp frock 2 is placed in the connecting tube
On;
Step 2:Bolt 22 in two pipe clamp frocks 2 of synchronous fastening so that the clamping plate 21 in pipe clamp frock 2 clamps institute
State connecting tube;L-type sheet material is placed in the connecting tube;
Step 3:The welded gaps between two blocks of L-type sheet materials 3 are adjusted, and in the given time, according to predefined procedure by two
Individual L-type sheet material 3 is welded as a whole, and forms the pipe clamp 1 of the binding connecting tube;
Step 4:Dismantle two pipe clamp frocks 2;
Step 5:Strain value is read by resistance strain gage 4, and knows the residual pre-tightening forces on pipe clamp, wherein, the electricity
It is continuous firing to hinder foil gauge 4,;
Step 6:Repeat the above steps 1-5, and changes the welding parameter of any one in step 3;Preferably, the welding
Parameter includes welded gaps, weld interval and the welding sequence between two blocks of L-type sheet materials 3;
Step 7:According to the welding of the multigroup residual pre-tightening forces and corresponding welding parameter information sifting of acquisition suitably
Parameter.
Wherein, in step 6, the welded gaps between two blocks of L-type sheet material 3 are appointed in 1mm-2mm length ranges
2~10 length values of choosing;And/or
In step 6, the weld interval is optional 2~10 time values in the range of 1min-5min durations;With/
Or
In step 6, the welding sequence includes continuous welding and rotation welding;It is described to be continuously welded as completely one
Another groove is welded after groove again;The rotation is welded as completing after a welding bead in a groove, on another slope
One welding bead of intraoral completion, returns again to a groove and completes a welding bead, until two grooves are all full by weldering.
The present invention have the advantage that including:
(1) the HTGR steam (vapor) outlet connecting tube pipe clamp pretightening force measuring apparatus structure letter provided according to the present invention
It is single, experiment can be repeated several times, test efficiency is high, as a result accurately;
(2) pipe clamp of the HTGR steam (vapor) outlet connecting tube pipe clamp pretightening force measuring apparatus provided according to the present invention
Frock can clamp connecting tube, even if continuing to screw pipe clamp frock after connecting tube is clamped, the residual pre-tightening forces finally given
Significant change is not had, so pipe clamp frock need to only clamp connecting tube, pipe clamp frock will not be to the pretension that finally obtains
Power result is interfered;
(3) the HTGR steam (vapor) outlet connecting tube pipe clamp pretension force measuring method provided according to the present invention can be more
It is secondary progressively to adjust welding parameter, influence relation of each parameter to residual pre-tightening forces is obtained comprehensively, is eventually found and is resulted in
The welding parameter of optimal residual pre-tightening forces.
Brief description of the drawings
Fig. 1 is shown according to the HTGR steam (vapor) outlet connecting tube of preferred embodiment of the invention a kind of and thereon
Pipe clamp, pipe clamp frock overall structure diagram;
Fig. 2 shows section of the HTGR steam (vapor) outlet connecting tube pipe clamp according to a kind of preferred embodiment of the invention
Face figure;
Fig. 3 shows one in the HTGR steam (vapor) outlet connecting tube according to a kind of preferred embodiment of the invention
Pipe clamp tool structure schematic diagram;
Fig. 4 shows another in the HTGR steam (vapor) outlet connecting tube according to a kind of preferred embodiment of the invention
Individual pipe clamp tool structure schematic diagram;
Drawing reference numeral explanation:
1- pipe clamps
2- pipe clamp frocks
3-L based plates
4- resistance strain gages
21- clamping plates
22- bolts
Embodiment
Below by drawings and examples, the present invention is described in more detail.Illustrated by these, the features of the present invention
It will be become more apparent from clearly with advantage.
Special word " exemplary " is meant " being used as example, embodiment or illustrative " herein.Here as " exemplary "
Illustrated any embodiment should not necessarily be construed as preferred or advantageous over other embodiments.Although embodiment is shown in the drawings
Various aspects, but unless otherwise indicated, it is not necessary to accompanying drawing drawn to scale.
HTGR steam (vapor) outlet connecting tube one end is connected with steam (vapor) outlet tube sheet, the other end and spiral heat exchange tube phase
Even;The HTGR steam (vapor) outlet connecting tube has many with that in general, would generally be arranged in a HTGR
Thousand is up to ten thousand with the connecting tube, and usual several, more than ten or tens connecting tubes tie up into one group by pipe clamp is tired, turn into
One connection tube bank, and the pipe clamp is all the metal framework that welding is formed.It is an object of the invention to provide obtain optimal weldering
The measurement apparatus and correlation method of pipe connection clip technique/parameter, so-called optimal welding parameter refer to obtain by the welding parameter
Pipe clamp have residual pre-tightening forces the most rational.
The HTGR steam (vapor) outlet connecting tube pipe clamp pretightening force measuring apparatus provided according to the present invention, such as Fig. 1, figure
2nd, shown in Fig. 3 and Fig. 4, the device includes pipe clamp 1 and two pipe clamp frocks 2;
Wherein, the pipe clamp 1 includes two blocks of L-type sheet materials 3 for being assembled into rectangular frame, in the appearance of the rectangular frame
Resistance strain gage 4 is provided with face;I.e. described pipe clamp is to be welded to be formed by two blocks of L-type sheet materials 3, is had between two L-type sheet materials
Two points for being in contact, i.e., two welding positions;
The pipe clamp frock 2 is separately positioned on the both sides of pipe clamp 1, and clamping the HTGR by pipe clamp frock 2 steams
Vapor outlet connecting tube.
In one preferred embodiment, as shown in Figures 3 and 4, the pipe clamp frock 2 includes two clamping plates 21
With two bolts 22,
Wherein, two clamping plates 21 are set in parallel in the connecting tube both sides, and two clamping plates 21 are fastened by two bolts 22
So that two clamping plates 21 clamp the connecting tube.
In one preferred embodiment, as shown in Figures 3 and 4, the clamping plate 21 in two pipe clamp frocks 2 is mutual
It is vertically arranged, so that the connecting tube is clamped from both direction, so that it is guaranteed that clamping operation is firm.
In one preferred embodiment, the spacing between pipe clamp 1 and pipe clamp frock 2 is 50~150mm, it is preferable that
Two pipe clamp frocks are equal with the distance of pipe clamp.
In one preferred embodiment, the resistance strain gage 4 has four, is separately positioned on rectangular frame remote
From on four outer surfaces of the connecting tube;Preferably, the center in face where the resistance strain gage is located at it.
Preferably, the resistance strain gage 4 is high temperature resistance foil gauge, and the operating ambient temperature of resistance strain gage is 250
Degrees centigrade, the high temperature resistance foil gauge can bear more than 250 degrees Celsius of temperature.
In one preferred embodiment, welding groove is offered on the L-type sheet material 3, bevel angle is 60 °
~70 °, the angle of the welding groove can be adjusted according to actual conditions, preferably 64 °~68 °.
In one preferred embodiment, the welded gaps between two blocks of L-type sheet materials 3 are 1mm~2mm.
According to the HTGR steam (vapor) outlet connecting tube pipe clamp pretension force measuring method of the invention provided, this method is
Realized by device as described above.
Preferably, this method comprises the following steps:
Step 1:Arrangement HTGR steam (vapor) outlet connecting tube is arranged, L-type sheet material 3 and pipe clamp frock 2 are placed in institute
State in connecting tube;
Step 2:Bolt 22 in two pipe clamp frocks 2 of synchronous fastening so that the clamping plate 21 in pipe clamp frock 2 clamps institute
State connecting tube;
Step 3:The welded gaps between two blocks of L-type sheet materials 3 are adjusted, and in the given time, according to predefined procedure by two
Individual L-type sheet material 3 is welded as a whole, and forms the pipe clamp 1 of the binding connecting tube;
Step 4:Dismantle two pipe clamp frocks 2;
Step 5:Strain value is read by resistance strain gage 4, and knows the residual pre-tightening forces on pipe clamp;Wherein, the electricity
It is continuous firing to hinder foil gauge 4, and the resistance strain gage 4 begins to measure and record strain value before step 3 beginning, from
And know residual pre-tightening forces;
Step 6:Repeat the above steps 1-5, and changes the welding parameter of any one in step 3;Preferably, the welding
Parameter includes welded gaps, weld interval and the welding sequence between two blocks of L-type sheet materials 3;
Step 7:According to the welding of the multigroup residual pre-tightening forces and corresponding welding parameter information sifting of acquisition suitably
Parameter.
Preferably, in step 6, the welded gaps between two blocks of L-type sheet material 3 are in 1mm-2mm length ranges
2~10 optional length values;For example select during 5 length values, it is necessary to which that tests when progressively verifying each length value for five times is residual
Remaining pretightning force, it is preferable that five length values are respectively 1mm, 1.25mm, 1.5mm, 1.75mm and 2mm.
Preferably, in step 6, when the weld interval is optional in the range of 1min-5min durations 2~10
Between be worth;Preferably, 2~5 time values that the weld interval can be optional in the range of 1min-3min durations, for example, take 3
During individual time value, 3 time values are respectively 1min, 2min and 3min, that is, carry out three experiments, respectively with 1min, 2min and
3min completes weld job.
Preferably, in step 6, the welding sequence includes continuous welding and rotation welding;It is described to be continuously welded as
Another groove is welded again after a full groove;The rotation is welded as completing after a welding bead in a groove, another
A welding bead is completed in one groove, a groove is returned again to and completes a welding bead, until two grooves are all full by weldering.
Heretofore described resistance strain gage can directly spend the overstrain value for taking out pipe clamp, the overstrain value
It is multiplied with the modulus of elasticity of pipe clamp material and can obtain the residual stress of pipe clamp, and then obtains residual pre-tightening forces.
Experimental example:
One group of heretofore described heat exchanger tube is selected, totally 35, passes through the HTGR steam as shown in Fig. 1 to 4
Between the residual stress and welding parameter of the pipe clamp that the measurement of outlet connecting pipe pipe clamp pretightening force measuring apparatus is welded on heat exchanger tube
Relation, specifically using following steps;
Step 1:Arrangement HTGR steam (vapor) outlet connecting tube is arranged, pipe clamp frock 2 is placed in the connecting tube
On;
Step 2:Bolt 22 in two pipe clamp frocks 2 of synchronous fastening so that the clamping plate 21 in pipe clamp frock 2 clamps institute
State connecting tube;L-type sheet material is placed in the connecting tube;
Step 3:Adjust the welded gaps between two blocks of L-type sheet materials so that gap is 1mm, and in 1.5min, rotation
Welding, two L-type sheet materials are welded as a whole, and form the pipe clamp of the binding connecting tube;
Step 4:Dismantle two pipe clamp frocks;
Step 5:Strain value is read by resistance strain gage, and knows the residual pre-tightening forces on pipe clamp, the remaining pretension
Power is 6000N-9000N;
Step 6:Repeat the above steps 1-5, and changes the welding parameter of any one in step 3;
Step 7:According to the welding of the multigroup residual pre-tightening forces and corresponding welding parameter information sifting of acquisition suitably
Parameter.
Wherein, the relation of the welding parameter obtained and pipe clamp residual stress refers to following table;
It can be seen from the use requirement of the heat exchanger tube, its residual pre-tightening forces should in the range of 18000N-20000N, therefore
And select the welding parameter applied in the 6th Welding experiment to carry out the welding of pipe clamp in the connecting tube, finally give the company of being welded on
Pipe clamp in adapter;
It is 19500N to measure residual stress on the pipe clamp, meets design requirement, the year that the pipe clamp can be used is limited to 40
Year, and the actual life can illustrate that the residual stress on pipe clamp meets design requirement, and during because of operation, pipe clamp swell increment
More than tube bank swell increment, such as residual stress is too low, has the trend of fluffing, influence connection tube bank is fixed and insulating assembly is fixed,
If loosened, displacement can be produced in thermal stress situation lower tube clip, causes insulating assembly temperature compensation to meet requirement, shadow
The life-span is rung, when pipe clamp pretightning force is near required value, pipe clamp residual stress is not above pipe clamp allowable stress intensity, pipe clamp
Contact stress with tube bank ensures projected life also no more than tube bank and the allowable stress intensity of pipe clamp.Conversely, exceeding
The value, can make tube bank or pipe clamp stress level transfinite, influence tube bank and pipe clamp life-span.
Above in association with preferred embodiment the present invention is described, but these embodiments are only examples
Property, only play illustrative effect.On this basis, a variety of replacements and improvement can be carried out to the present invention, these each fall within
In protection scope of the present invention.
Claims (10)
1. a kind of HTGR steam (vapor) outlet connecting tube pipe clamp pretightening force measuring apparatus, it is characterised in that including pipe clamp (1) and
Two pipe clamp frocks (2);
Wherein, the pipe clamp (1) includes two pieces of L-type sheet materials (3) for being assembled into rectangular frame, in the outer surface of the rectangular frame
On be provided with resistance strain gage (4);
The pipe clamp frock (2) is separately positioned on the both sides of pipe clamp (1), and the HTGR is clamped by pipe clamp frock (2)
Steam (vapor) outlet connecting tube.
2. HTGR steam (vapor) outlet connecting tube pipe clamp pretightening force measuring apparatus according to claim 1, its feature exists
In,
The pipe clamp frock (2) includes two clamping plates (21) and two bolts (22),
Wherein, two clamping plates (21) are set in parallel in the connecting tube both sides, and two clamping plates are fastened by two bolts (22)
(21) it is allowed to clamp the connecting tube.
3. HTGR steam (vapor) outlet connecting tube pipe clamp pretightening force measuring apparatus according to claim 1, its feature exists
In,
The orthogonal setting of clamping plate (21) on two pipe clamp frocks (2).
4. HTGR steam (vapor) outlet connecting tube pipe clamp pretightening force measuring apparatus according to claim 1, its feature exists
In,
Spacing between pipe clamp (1) and pipe clamp frock (2) is 50~150mm.
5. HTGR steam (vapor) outlet connecting tube pipe clamp pretightening force measuring apparatus according to claim 1, its feature exists
In,
The resistance strain gage (4) has four, is separately positioned on rectangular frame on four outer surfaces away from the connecting tube;
Preferably, the resistance strain gage (4) is high temperature resistance foil gauge.
6. HTGR steam (vapor) outlet connecting tube pipe clamp pretightening force measuring apparatus according to claim 1, its feature exists
In,
Welding groove is offered on the L-type sheet material (3), bevel angle is 60 °~70 °.
7. HTGR steam (vapor) outlet connecting tube pipe clamp pretightening force measuring apparatus according to claim 1, its feature exists
In,
Welded gaps between two pieces of L-type sheet materials (3) are 1mm~2mm.
8. a kind of HTGR steam (vapor) outlet connecting tube pipe clamp pretension force measuring method, it is characterised in that this method is to pass through
As claim 1-7 described devices are realized.
9. HTGR steam (vapor) outlet connecting tube pipe clamp pretension force measuring method according to claim 8, its feature exists
In,
This method comprises the following steps:
Step 1:Arrangement HTGR steam (vapor) outlet connecting tube is arranged, pipe clamp frock (2) is placed in the connecting tube;
Step 2:Bolt (22) on two pipe clamp frocks (2) of synchronous fastening so that the clamping plate (21) in pipe clamp frock (2) is clamped
The connecting tube;L-type sheet material is placed in the connecting tube;
Step 3:The welded gaps between two pieces of L-type sheet materials (3) are adjusted, and in the given time, according to predefined procedure by two L
Based plate (3) is welded as a whole, and forms the pipe clamp (1) of the binding connecting tube;
Step 4:Dismantle two pipe clamp frocks (2);
Step 5:Strain value is read by resistance strain gage (4), and knows the residual pre-tightening forces on pipe clamp;Wherein, the resistance
Foil gauge (4) is continuous firing,
Step 6:Repeat the above steps 1-5, and changes the welding parameter of any one in step 3;Preferably, the welding parameter bag
Include welded gaps, weld interval and the welding sequence between two pieces of L-type sheet materials (3);
Step 7:According to multigroup residual pre-tightening forces of acquisition and the suitable welding parameter of corresponding welding parameter information sifting.
10. HTGR steam (vapor) outlet connecting tube pipe clamp pretension force measuring method according to claim 9, its feature exists
In,
In step 6, the welded gaps between two blocks of L-type sheet material (3) be optional 2 in 1mm-2mm length ranges~
10 length values;And/or
In step 6, the weld interval is optional 2~10 time values in the range of 1min-5min durations;And/or
In step 6, the welding sequence includes continuous welding and rotation welding;It is described to be continuously welded as after a full groove
Another groove is welded again;The rotation is welded as completing after a welding bead in a groove, complete in another groove
Into a welding bead, return again to a groove and complete a welding bead, until two grooves are all full by weldering.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710313794.0A CN106996843B (en) | 2017-05-05 | 2017-05-05 | High-temperature gas cooled reactor steam outlet connecting pipe clamp pretightening force measuring device and method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710313794.0A CN106996843B (en) | 2017-05-05 | 2017-05-05 | High-temperature gas cooled reactor steam outlet connecting pipe clamp pretightening force measuring device and method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106996843A true CN106996843A (en) | 2017-08-01 |
CN106996843B CN106996843B (en) | 2023-02-28 |
Family
ID=59435243
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710313794.0A Active CN106996843B (en) | 2017-05-05 | 2017-05-05 | High-temperature gas cooled reactor steam outlet connecting pipe clamp pretightening force measuring device and method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106996843B (en) |
Citations (24)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20050253351A1 (en) * | 2004-05-14 | 2005-11-17 | Jaw-Ping Pan | Preloaded suspension bracket assembly for axle housing |
US20070107529A1 (en) * | 2003-05-07 | 2007-05-17 | Maurin M L | Uniaxial thermal and/or mechanical deformation-measuring device system and method employing a bragg grating optical fibre |
JP2007218887A (en) * | 2006-02-14 | 2007-08-30 | Fabless:Kk | Built-in pretightening (preload) mechanism type load cell |
CN101418630A (en) * | 2008-11-03 | 2009-04-29 | 杨峰 | Pretensioned prestressing composite girder and method for producing the same |
CN202031322U (en) * | 2011-04-22 | 2011-11-09 | 任元根 | Lockset used for reinforcing post formwork |
CN102519652A (en) * | 2011-12-16 | 2012-06-27 | 天津大学 | Bolt pre-tightening force testing device and control method thereof |
CN202473267U (en) * | 2011-12-21 | 2012-10-03 | 哈电集团(秦皇岛)重型装备有限公司 | High temperature gas-cooled reactor steam generator heat exchange tube fixing structure |
US20130047715A1 (en) * | 2010-01-12 | 2013-02-28 | Continental Automotive Gmbh | Heater plug having a metal finger |
CN203050133U (en) * | 2013-02-07 | 2013-07-10 | 中冶建工集团有限公司 | Prestressed steel structure drag cable tensioning device capable of accurately measuring tension force |
CN103364124A (en) * | 2013-06-27 | 2013-10-23 | 天津大学 | Measuring device for soil resistance stressed on subsea oil and gas pipeline during horizontal movement |
CN203443727U (en) * | 2013-08-29 | 2014-02-19 | 南车株洲电力机车研究所有限公司 | Yaw clamping force testing system |
CN103698074A (en) * | 2013-12-27 | 2014-04-02 | 机械科学研究总院先进制造技术研究中心 | Online monitoring method for residual pretightening force of large-sized prestressed steel wire winding frame |
CN103900756A (en) * | 2014-04-16 | 2014-07-02 | 山东微感光电子有限公司 | Fiber bragg grating pressure sensor capable of achieving positive and negative pressure monitoring and testing method |
CN204108577U (en) * | 2014-09-30 | 2015-01-21 | 莱芜鲁能开源铁塔有限公司 | Hexagon steel tube tower weld jig |
CN204326533U (en) * | 2014-12-16 | 2015-05-13 | 许昌大成建设(集团)有限责任公司 | A kind of formwork reinforcement fixture |
CN204903361U (en) * | 2015-07-07 | 2015-12-23 | 青岛科技大学 | Take anchor clamps stress test platform |
CN105339771A (en) * | 2013-06-06 | 2016-02-17 | 高级传感设计工艺有限责任公司 | Apparatus and methods for measurement of pressure |
US9394950B1 (en) * | 2013-03-12 | 2016-07-19 | Hrl Laboratories, Llc | Short-beam negative stiffness elements |
CN105841854A (en) * | 2016-04-28 | 2016-08-10 | 西南石油大学 | Welding residual stress testing method |
CN205520930U (en) * | 2016-03-10 | 2016-08-31 | 广州声华科技有限公司 | Fixture used for grinding metallographic specimens |
CN105973517A (en) * | 2016-05-16 | 2016-09-28 | 河南科技大学 | Sunflower disc clamping device for impact test machine, and method for measuring impact force |
CN106193341A (en) * | 2016-08-31 | 2016-12-07 | 山东电力建设第工程公司 | A kind of rubber fastening band positioning attaching clamp device and using method |
CN106271157A (en) * | 2016-08-30 | 2017-01-04 | 苏州海陆重工股份有限公司 | Urceolus in lower heap core shell base and base plate welding method in HTGR |
CN106595914A (en) * | 2016-11-18 | 2017-04-26 | 常州普莱德新能源电池科技有限公司 | Method and device for determining cathode mix swelling degree by using strain gauges |
-
2017
- 2017-05-05 CN CN201710313794.0A patent/CN106996843B/en active Active
Patent Citations (24)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20070107529A1 (en) * | 2003-05-07 | 2007-05-17 | Maurin M L | Uniaxial thermal and/or mechanical deformation-measuring device system and method employing a bragg grating optical fibre |
US20050253351A1 (en) * | 2004-05-14 | 2005-11-17 | Jaw-Ping Pan | Preloaded suspension bracket assembly for axle housing |
JP2007218887A (en) * | 2006-02-14 | 2007-08-30 | Fabless:Kk | Built-in pretightening (preload) mechanism type load cell |
CN101418630A (en) * | 2008-11-03 | 2009-04-29 | 杨峰 | Pretensioned prestressing composite girder and method for producing the same |
US20130047715A1 (en) * | 2010-01-12 | 2013-02-28 | Continental Automotive Gmbh | Heater plug having a metal finger |
CN202031322U (en) * | 2011-04-22 | 2011-11-09 | 任元根 | Lockset used for reinforcing post formwork |
CN102519652A (en) * | 2011-12-16 | 2012-06-27 | 天津大学 | Bolt pre-tightening force testing device and control method thereof |
CN202473267U (en) * | 2011-12-21 | 2012-10-03 | 哈电集团(秦皇岛)重型装备有限公司 | High temperature gas-cooled reactor steam generator heat exchange tube fixing structure |
CN203050133U (en) * | 2013-02-07 | 2013-07-10 | 中冶建工集团有限公司 | Prestressed steel structure drag cable tensioning device capable of accurately measuring tension force |
US9394950B1 (en) * | 2013-03-12 | 2016-07-19 | Hrl Laboratories, Llc | Short-beam negative stiffness elements |
CN105339771A (en) * | 2013-06-06 | 2016-02-17 | 高级传感设计工艺有限责任公司 | Apparatus and methods for measurement of pressure |
CN103364124A (en) * | 2013-06-27 | 2013-10-23 | 天津大学 | Measuring device for soil resistance stressed on subsea oil and gas pipeline during horizontal movement |
CN203443727U (en) * | 2013-08-29 | 2014-02-19 | 南车株洲电力机车研究所有限公司 | Yaw clamping force testing system |
CN103698074A (en) * | 2013-12-27 | 2014-04-02 | 机械科学研究总院先进制造技术研究中心 | Online monitoring method for residual pretightening force of large-sized prestressed steel wire winding frame |
CN103900756A (en) * | 2014-04-16 | 2014-07-02 | 山东微感光电子有限公司 | Fiber bragg grating pressure sensor capable of achieving positive and negative pressure monitoring and testing method |
CN204108577U (en) * | 2014-09-30 | 2015-01-21 | 莱芜鲁能开源铁塔有限公司 | Hexagon steel tube tower weld jig |
CN204326533U (en) * | 2014-12-16 | 2015-05-13 | 许昌大成建设(集团)有限责任公司 | A kind of formwork reinforcement fixture |
CN204903361U (en) * | 2015-07-07 | 2015-12-23 | 青岛科技大学 | Take anchor clamps stress test platform |
CN205520930U (en) * | 2016-03-10 | 2016-08-31 | 广州声华科技有限公司 | Fixture used for grinding metallographic specimens |
CN105841854A (en) * | 2016-04-28 | 2016-08-10 | 西南石油大学 | Welding residual stress testing method |
CN105973517A (en) * | 2016-05-16 | 2016-09-28 | 河南科技大学 | Sunflower disc clamping device for impact test machine, and method for measuring impact force |
CN106271157A (en) * | 2016-08-30 | 2017-01-04 | 苏州海陆重工股份有限公司 | Urceolus in lower heap core shell base and base plate welding method in HTGR |
CN106193341A (en) * | 2016-08-31 | 2016-12-07 | 山东电力建设第工程公司 | A kind of rubber fastening band positioning attaching clamp device and using method |
CN106595914A (en) * | 2016-11-18 | 2017-04-26 | 常州普莱德新能源电池科技有限公司 | Method and device for determining cathode mix swelling degree by using strain gauges |
Non-Patent Citations (1)
Title |
---|
盛世伟: "《管路支撑参数对液压管路系统振动特性影响研究》", 《中国优秀硕士学位论文全文数据库(电子期刊)》 * |
Also Published As
Publication number | Publication date |
---|---|
CN106996843B (en) | 2023-02-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Coffin Jr et al. | Apparatus for study of effects of cyclic thermal stresses on ductile metals | |
CN109142202B (en) | High-flux evaluation device and method for stress corrosion sensitivity of slit environment | |
CN104181052A (en) | Method for testing mechanical property of braze welding connector | |
CN101013105A (en) | Device for measuring change of material residual stress | |
CN104101532A (en) | Fixture for axial push-pull fatigue testing of metal thin-walled tube sample in high-temperature and high-pressure water | |
CN110853778B (en) | Irradiation device for realizing real-time measurement of axial length change of fuel element | |
CN106996843A (en) | HTGR steam (vapor) outlet connecting tube pipe clamp pretightening force measuring apparatus and method | |
CN206787746U (en) | HTGR steam (vapor) outlet connecting tube pipe clamp pretightening force measuring apparatus | |
KR100909118B1 (en) | Apparatus for forming a stress corrosion crack | |
Aakre et al. | Nuclear code case development of printed-circuit heat exchangers with thermal and mechanical performance testing | |
CN201514289U (en) | Demountable multipoint measurement thermocouple device | |
Ru et al. | Historical Experience Providing Bases for Predicting Corrosion and Stress Corrosion in Emerging Supercritical Water Nuclear Technology: Part 3 | |
CN207866182U (en) | A kind of tube sheet built-up welding deformation measuring device | |
CN202661256U (en) | Pulling-out force testing device | |
CN210451529U (en) | Angle fixing tool for section steel connecting plate | |
CN211227232U (en) | Complex structure induction heating coil position degree adjusting device | |
CN108154940A (en) | PWR nuclear power plant steel plate concrete structure module forming frock and its moulding process | |
CN209919140U (en) | Dynamic stress testing device for welding seam of steam guide pipe of steam turbine of supercritical unit | |
CN206435914U (en) | It is a kind of to be used for the positioner that vibrationproof bar is welded in steam generator | |
CN204203141U (en) | A kind of device measuring Plate Welding thermal cycling temperature curve | |
Chang et al. | Preliminary Computational Study on Conduction Thermal Resistance for a Printed Circuit Heat Exchanger with Monitoring Channels | |
Davis et al. | Status of Research Activities on LVDTs: Modeling and Simulation Development and Performance Characterization of Commercial LVDTs | |
CN209103828U (en) | A kind of measurement suitable for neutron flux pipe elongate rod, protective device | |
Gorka et al. | Edge-cooled, high-current septum magnet | |
Chrzanowski et al. | Manufacturing development of the NCSX modular coil windings |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |