CN106996097B - A kind of safe evaluation method of Arch Dam Structure - Google Patents

A kind of safe evaluation method of Arch Dam Structure Download PDF

Info

Publication number
CN106996097B
CN106996097B CN201710374587.6A CN201710374587A CN106996097B CN 106996097 B CN106996097 B CN 106996097B CN 201710374587 A CN201710374587 A CN 201710374587A CN 106996097 B CN106996097 B CN 106996097B
Authority
CN
China
Prior art keywords
arch
dam
arch ring
ring
evaluation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710374587.6A
Other languages
Chinese (zh)
Other versions
CN106996097A (en
Inventor
张敬
潘燕芳
祝海霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Chengdu Engineering Co Ltd
Original Assignee
PowerChina Chengdu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Chengdu Engineering Co Ltd filed Critical PowerChina Chengdu Engineering Co Ltd
Priority to CN201710374587.6A priority Critical patent/CN106996097B/en
Publication of CN106996097A publication Critical patent/CN106996097A/en
Application granted granted Critical
Publication of CN106996097B publication Critical patent/CN106996097B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages
    • E02B7/04Dams across valleys
    • E02B7/08Wall dams
    • E02B7/12Arch dams

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to a kind of safe evaluation methods of Arch Dam Structure, belong to arch dam field of engineering technology, comprising the following steps: the arch ring of arch dam is divided into several sequentially connected point of arch ring by a, along height of dam direction from top to bottom;B, using arch dam center line as boundary line, each point of arch ring is divided into left and right two parts;C, choosing each left side divides arch ring, the right side to divide arch ring arc length s, arch abutment thickness T corresponding to arch ring, dam foundation foundation deformation modulus R and the strong p of hydraulic pressure born for evaluation parameter;D, aforementioned four corresponding evaluation parameter group is combined into single macroscopic evaluation parameter;E, evaluation criterion N, f, structure evaluation are formulated, if left divide arch ring or the right value for dividing F corresponding to arch ring to be greater than the value of corresponding N, the structure is dangerous;If arch ring is divided on a left side or the right value for dividing F corresponding to arch ring is less than the value of corresponding N, structure safety.The present invention provides a kind of safe evaluation methods of the higher Arch Dam Structure of accuracy.

Description

A kind of safe evaluation method of Arch Dam Structure
Technical field
The present invention relates to a kind of safe evaluation methods of Arch Dam Structure, belong to arch dam field of engineering technology.
Background technique
It is safe and economically theme and pursuit eternal in hydroelectric development using hydraulic power potentials, arch dam is safety and warp The advantageous dam type of Ji property, while being extremely complex dam type again, Arch Dam Structure safety how is quickly evaluated, Yi Ji Economic Arch Dam is designed under the premise of safety, is that dam worker person makes great efforts to solve the problems, such as.
How in design early period, the reasonability and safety of Fast Evaluation layout of arch dam, dam worker are come from the data of macroscopic view Member establishes some macro-indicators.The famous dam working platform man Lombardi proposition softness factor of Switzerland makees arch dam thickness empirical Judgement, softness factor C=A2/ VH, wherein A --- the area of section in arch dam, V --- arch dam volume, H --- maximum height of dam. The famous dam working platform person Zhu Baifang academician in China proposes with stress level coefficient and arch dam safety horizontal coefficients come preresearch estimates arch dam Level of security.Stress level coefficient D=CH=A2/ V, level of security coefficient J=100R/D=100RV/A2, wherein R --- dam The intensity of body and basis.There are also the ratios that expert proposes total hydraulic thrust and dam concrete side's amount, i.e. equivalent concrete comes anti- Reflect the safe condition of arch dam.
The evaluation parameter that the safe evaluation method of existing arch dam is chosen has the following problems:
(1) in evaluation parameter in A, that is, arch dam section area, in the case of identical area, the shape in river valley may be U-shaped Or V-arrangement, due to terrain differences, the load acted on arch dam is different, and not can reflect topographic features, obtained macroscopic view Index directiveness is not strong;
(2) safe evaluation method of existing arch dam all incorporates dam concrete side amount V, and identical cubic amount of concrete V can By taking vault subsidence section as an example, triangular cross-section can be used, trapezoidal cross-section can be used there are many in a manner of shape and configuration, Rectangular section can be used, under different sections, with regard to different, corresponding strcture safety is different for the distribution of concrete;
(3) evaluation parameter chosen cannot reflect the architectural characteristic of controlling position, for specific elevation arch ring, effect The size of load, the soft or hard degree on basis, cross dimensions of structure etc. are very important, and the evaluation parameter of selection fails specifically Reflect these structure attributes.
In view of existing obtained macro-indicators there are the above limitation, be suitable only for doing some very rough statistical analysis and Estimation, in design inconvenient grasp and operation not strong to the directiveness of layout of arch dam design.
Summary of the invention
Technical problem to be solved by the invention is to provide a kind of safe evaluation methods of the higher Arch Dam Structure of accuracy.
The technical solution adopted by the present invention to solve the technical problems is: a kind of safe evaluation method of Arch Dam Structure, packet Include following steps:
A, along height of dam direction, the arch ring of arch dam is divided into several sequentially connected point of arch ring from top to bottom;
B, using arch dam center line as boundary line, each point of arch ring is divided into left and right two parts, being connected with the left bank dam foundation is Arch ring is divided on a left side, and being connected with the right bank dam foundation is connected in the right side and divides arch ring;
C, choosing each left side divides arch ring, the right side to divide arch ring arc length s, arch abutment thickness T corresponding to arch ring, dam foundation foundation deformation mould The amount R and strong p of hydraulic pressure born is evaluation parameter;
D, aforementioned four corresponding evaluation parameter group is combined into single macroscopic evaluation parameter according to formula F=sp/TR;
E, evaluation criterion N, N=- (M-0.5) are formulated2+ 0.5, M=E/H, wherein M is opposite height of dam, and E is to divide arch ring elevation For plane to the distance of dam crest top surface, H is maximum height of dam;
F, structure evaluation, if left divide arch ring or the right value for dividing F corresponding to arch ring to be greater than the value of corresponding N, the structure It is dangerous;If arch ring is divided on a left side or the right value for dividing F corresponding to arch ring is less than the value of corresponding N, structure safety.
The beneficial effects of the present invention are: main structure of the arch ring as arch dam, plays water blocking, it is proposed by the invention The safe evaluation method of Arch Dam Structure, especially suitable for the layout design of new arch dam, using arch ring as the basis of assay, Arch ring is divided into several sequentially connected point of arch ring from top to bottom first, arch ring is refined, then divides arch ring again to refinement The secondary left side that is refined as divides arch ring, the right side to divide arch ring, chooses a left side and arch ring, the right side is divided to divide arch ring arc length s, arch abutment thickness T, institute corresponding to arch ring The strong p of the hydraulic pressure of receiving and corresponding dam foundation foundation deformation modulus R, will be upper according still further to formula F=sp/TR as evaluation parameter It states four corresponding evaluation parameter groups and is combined into single macroscopic evaluation parameter, make the parameter of arch ring and the parameter knot of the two sides dam foundation It closes, obtains a comprehensive macroscopic evaluation parameter F, be then foundation according to the data to a large amount of built arch dams, formulate evaluation mark Quasi- N, finally carries out structure evaluation according to the value of corresponding macroscopic evaluation parameter F and evaluation criterion N, and obtained arch dam safety is commented The accuracy of valence is high.Especially when new layout of arch dam designs, divide arch ring in specific elevation, the strong p of the hydraulic pressure born, arch Enclose arc length s be it is fixed, this divides the arrangement of arch ring to be then adjusted cloth between arch abutment thickness T and dam foundation foundation deformation modulus R Meter is installed, specifies the direction of design adjustment, there is accurately directiveness to the design of new layout of arch dam.
Detailed description of the invention
Fig. 1 is the overlooking structure diagram of point arch ring;
Fig. 2 is the side structure schematic view of point arch ring;
Components, position and number in figure: a left side divides arch ring 1, the right side to divide arch ring 2, arch dam center line 3, the left bank dam foundation 4, right bank The dam foundation 5, dam bottom 6.
Specific embodiment
The present invention will be further explained below with reference to the attached drawings.
A kind of safe evaluation method of Arch Dam Structure of the present invention, comprising the following steps:
A, along height of dam direction, the arch ring of arch dam is divided into several sequentially connected point of arch ring from top to bottom, arch ring is thin Change, then to the evaluation for dividing arch ring successively to carry out safety of refinement, it is accurately high to obtain evaluation index.According to the height of dam of arch dam Fixed, preferably each dividing the height of arch ring is 40m.Main structure of the arch ring as arch dam, plays water blocking, whether is Arch Dam Structure Securely and reliably that is to say whether arch ring is safe and reliable.
B, as shown in Figure 1 and Figure 2, it is boundary line with arch dam center line 3, each point of arch ring is divided into left and right two parts, with a left side It is that arch ring 1 is divided on a left side that the bank dam foundation 4, which is connected, and being connected with the right bank dam foundation 5 is connected in the right side and divides arch ring 2, each point of arch ring is divided into left and right Two parts further refine arch ring.Since the structure of the left bank dam foundation 4 of arch dam, the basement rock of the right bank dam foundation 5 is different, arch Circle is also different with the contact situation of the left bank dam foundation 4, the right bank dam foundation 5, divides arch ring 1, the right side to divide arch ring so arch ring is refined as a left side 2。
C, choosing each left side divides arch ring 1, the right side to divide arch ring arc length s, arch abutment thickness T, dam foundation foundation deformation corresponding to arch ring 2 The modulus R and strong p of the hydraulic pressure born is evaluation parameter.The strong p of hydraulic pressure is the main external load that arch dam is born, and arch dam passes through arch The strong p of hydraulic pressure is passed to the left bank dam foundation 4, the right bank dam foundation 5 by circle.In the case where landform determines, the arch ring arc length s of arch dam, held In the case that the strong p of the hydraulic pressure received is certain, the safety of arch dam by the left bank dam foundation 4, the right bank dam foundation 5 arch abutment range basement rock Non-deformability determine that and the product of arch abutment thickness T and dam foundation foundation deformation modulus R exactly reflects the base of arch abutment range The non-deformability of plinth rock.Arch ring 1, the right side is divided to divide arch ring arc length s, arch abutment thickness corresponding to arch ring 2 so choosing each left side T, the dam foundation foundation deformation modulus R and strong p of the hydraulic pressure born is evaluation parameter, can accurately show out the safety of arch dam. Further, arch ring arc length s, arch abutment thickness T, dam foundation foundation deformation modulus R and the strong p of hydraulic pressure these data born are All know in shape design of arch dams arrangement, the accuracy for obtaining data is high.
D, make the parameter of arch ring in conjunction with the parameter of the two sides dam foundation, it will be aforementioned four corresponding according to formula F=sp/TR Evaluation parameter group is combined into single macroscopic evaluation parameter, is by structure stress and 4 parameter combinations of arch abutment basis non-deformability Dimensionless group.
E, it is foundation according to the data of a large amount of built arch dams, formulates evaluation criterion N, N=- (M-0.5)2+ 0.5, M=E/H, Wherein M is opposite height of dam, and E is distance of point arch ring elevation plane to dam crest top surface, and H is maximum height of dam.The value of evaluation criterion N with The value of opposite height of dam M has relationship, and the dam crest of arch dam is by traffic requirement and detailing requiments, and thickness is higher than structure stress requirement, top The strong p of the hydraulic pressure born in portion is lower, the bottom of arch dam close to basis, beam to effect it is very strong, the effect of arch is not obvious, edge Height of dam direction is the strongest place of effect of arch in the middle part of arch dam, using the middle part of arch dam as basic point, upwardly or downwardly, arch Effect successively weakens, and evaluation criterion N is consistent with the actual conditions of arch dam.
F, structure evaluation, if left divide arch ring 1 or the right value for dividing F corresponding to arch ring 2 to be less than the value of corresponding N, the knot Structure safety;If a left side divides arch ring 1 or the right value for dividing F corresponding to arch ring 2 to be greater than the value of corresponding N, the structure is dangerous.To knot Unsafe point of arch ring of structure should reinforce dam foundation foundation deformation modulus R, to place arch ring position by increasing its arch abutment thickness T Soft rock mass or Geological Defects increase the range of processing, make the value that treated divides the value of F corresponding to arch ring to be less than corresponding N.
Main structure of the arch ring as arch dam plays water blocking, the safety evaluation of Arch Dam Structure proposed by the invention Method, especially suitable for the layout design of new arch dam, using arch ring as the basis of assay, first from top to bottom by arch ring It is divided into several sequentially connected point of arch ring, arch ring is refined, then refinement is divided arch ring to be refined as a left side again to divide arch ring, the right side Divide arch ring, chooses a left side and arch ring, the right side is divided to divide arch ring arc length s, arch abutment thickness T corresponding to arch ring, the strong p of hydraulic pressure born and institute Corresponding dam foundation foundation deformation modulus R is as evaluation parameter, according still further to formula F=sp/TR by aforementioned four corresponding evaluation Parameter combination is single macroscopic evaluation parameter, makes the parameter of arch ring in conjunction with the parameter of the two sides dam foundation, obtain one it is comprehensive macro Evaluation parameter F is seen, is then foundation according to the data to a large amount of built arch dams, evaluation criterion N is formulated, finally according to corresponding macro The value for seeing evaluation parameter F and evaluation criterion N carries out structure evaluation, and the accuracy of obtained arch dam safety evaluation is high.Especially New layout of arch dam design when, divide arch ring in specific elevation, the strong p of the hydraulic pressure born, arch ring arc length s be it is fixed, should Divide the arrangement of arch ring to be then adjusted layout design between arch abutment thickness T and dam foundation foundation deformation modulus R, specifies that design is adjusted Whole direction has accurately directiveness to the design of new layout of arch dam.
Embodiment 1
The arch ring of arch dam is divided into several from top to bottom and is sequentially connected by certain engineering maximum height of dam 240m along height of dam direction Divide arch ring, each left side divide arch ring, it is right divide arch ring arc length s, arch abutment thickness T corresponding to arch ring, dam foundation foundation deformation modulus R with And the parameter of the strong p of hydraulic pressure born is as shown in Table 1:
Table one
Aforementioned four corresponding evaluation parameter group is combined into single macroscopic evaluation parameter according to formula F=sp/TR, is formulated Evaluation criterion N, N=- (M-0.5)2+ 0.5, M=E/H, as shown in Table 2:
Table two
From two kinds of table as can be seen that in addition to the right side of right bank elevation 1090m divides the value of the corresponding F of arch ring to be less than corresponding N Value, structure is dangerous outer, and the value of the correspondence F of remaining elevation is less than the value of corresponding N, illustrates structure safety.Right bank elevation The right side of 1090m divides arch ring to increase arch abutment thickness T, reinforces dam foundation foundation deformation modulus R, so that the value of corresponding F be made to be less than corresponding N Value, make the structure reach safety.

Claims (1)

1. a kind of safe evaluation method of Arch Dam Structure, it is characterised in that: the following steps are included:
A, along height of dam direction, the arch ring of arch dam is divided into several sequentially connected point of arch ring from top to bottom;
B, each point of arch ring is divided into left and right two parts, is connected with the left bank dam foundation (4) for boundary line with arch dam center line (3) Divide arch ring (1) for a left side, being connected with the right bank dam foundation (5) is connected in the right side and divides arch ring (2);
C, choosing each left side divides arch ring (1), the right side to divide arch ring arc length s, arch abutment thickness T, dam foundation foundation deformation corresponding to arch ring (2) The modulus R and strong p of the hydraulic pressure born is evaluation parameter;
D, aforementioned four corresponding evaluation parameter group is combined into single macroscopic evaluation parameter according to formula F=sp/TR;
E, evaluation criterion N, N=- (M-0.5) are formulated2+ 0.5, M=E/H, wherein M is opposite height of dam, and E is to divide arch ring elevation plane To the distance of dam crest top surface, H is maximum height of dam;
F, structure evaluation, if the value that a left side divides arch ring (1) or the right side that the value of F corresponding to arch ring (2) is divided to be greater than corresponding N, the knot Structure is dangerous;If the value that a left side divides arch ring (1) or the right side that the value of F corresponding to arch ring (2) is divided to be less than corresponding N, structure safety.
CN201710374587.6A 2017-05-24 2017-05-24 A kind of safe evaluation method of Arch Dam Structure Active CN106996097B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710374587.6A CN106996097B (en) 2017-05-24 2017-05-24 A kind of safe evaluation method of Arch Dam Structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710374587.6A CN106996097B (en) 2017-05-24 2017-05-24 A kind of safe evaluation method of Arch Dam Structure

Publications (2)

Publication Number Publication Date
CN106996097A CN106996097A (en) 2017-08-01
CN106996097B true CN106996097B (en) 2019-01-01

Family

ID=59435853

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710374587.6A Active CN106996097B (en) 2017-05-24 2017-05-24 A kind of safe evaluation method of Arch Dam Structure

Country Status (1)

Country Link
CN (1) CN106996097B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110135107B (en) * 2019-05-29 2022-08-05 中国电建集团成都勘测设计研究院有限公司 Method for evaluating topographic and geological conditions of pseudo-built arch dam site
CN110263450B (en) * 2019-06-25 2022-10-04 中国电建集团成都勘测设计研究院有限公司 General arch dam body expression method
CN110438948A (en) * 2019-08-19 2019-11-12 北京航空航天大学 A kind of new method for evaluating arch dam slope monolith parting effect
CN110532694B (en) * 2019-08-29 2023-02-28 四川大学 Arch dam safety evaluation method based on geomechanical model comprehensive method test
CN111832918B (en) * 2020-06-30 2024-01-09 中国电建集团西北勘测设计研究院有限公司 M method for evaluating safety and economical efficiency of arch dam
CN112395799B (en) * 2020-11-30 2023-03-10 中国电建集团成都勘测设计研究院有限公司 Method for evaluating reasonability of arch dam body design and working state in operation period

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1076515A1 (en) * 1981-12-09 1984-02-29 Natorkhin Boris A Method of modelling a hydraulic structure
CN103791882A (en) * 2014-02-28 2014-05-14 中国水电顾问集团昆明勘测设计研究院有限公司 Arch dam complete-deformation monitoring method
CN105890537A (en) * 2016-06-29 2016-08-24 四川大学 Distributed fiber optic sensing technology and system for monitoring of deformation of high arch dam
CN105976104A (en) * 2016-05-03 2016-09-28 中国电建集团昆明勘测设计研究院有限公司 Dam safety evaluation method based on monitoring data
CN106407525A (en) * 2016-09-05 2017-02-15 中国电建集团成都勘测设计研究院有限公司 Simple algorithm of security of high arc dam three-axis force structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1076515A1 (en) * 1981-12-09 1984-02-29 Natorkhin Boris A Method of modelling a hydraulic structure
CN103791882A (en) * 2014-02-28 2014-05-14 中国水电顾问集团昆明勘测设计研究院有限公司 Arch dam complete-deformation monitoring method
CN105976104A (en) * 2016-05-03 2016-09-28 中国电建集团昆明勘测设计研究院有限公司 Dam safety evaluation method based on monitoring data
CN105890537A (en) * 2016-06-29 2016-08-24 四川大学 Distributed fiber optic sensing technology and system for monitoring of deformation of high arch dam
CN106407525A (en) * 2016-09-05 2017-02-15 中国电建集团成都勘测设计研究院有限公司 Simple algorithm of security of high arc dam three-axis force structure

Also Published As

Publication number Publication date
CN106996097A (en) 2017-08-01

Similar Documents

Publication Publication Date Title
CN106996097B (en) A kind of safe evaluation method of Arch Dam Structure
CN106996096B (en) A kind of analysis and processing method of Arch Dam Structure safety
CN106096203B (en) A kind of substrate construction method of hinge dam
CN104047256B (en) The water level response appraisal procedure of zones of different river bed change under hydrodynamism
Ribeiro et al. Rehabilitation of St-Marc dam. Experimental optimization of a piano key weir
CN108643246B (en) The prediction technique that artesian water precipitation influences surrounding enviroment in foundation pit construction
CN108797631A (en) A kind of more negative well bore pressure bucket anemometer tower foundation scour protection methods of jacket
CN106193076A (en) Deep basal pit is combined the Groundwater Control method of water-bearing structure
CN202416338U (en) Foundation for novel grating dam
EP1865112A1 (en) Mound breakwater having a geometry that provides maximum stability
Qie et al. Research on partial coefficients for design of quarter-circular caisson breakwater
RU2736193C2 (en) Ground dam with clay-cement-concrete diaphragm
Fraser Ski-jump energy dissipation: design of a ski-jump to maximise energy dissipation and aeration.
Crispino et al. Junction chamber at vortex drop shaft: case study of Cossonay
Jiang et al. The influence of soil surrounding the caisson cutting edge to excavation and sinking
Alabas et al. Investigation of flow regimes and energy dissipation in gabion stepped weirs
CN104912025B (en) A kind of determination method of straight river course low Water Ecological Recovery engineering layout
CN201087337Y (en) Convex flat plate shutter gate groove
Maatooq et al. Evaluation the hydraulic aspects of stepped labyrinth spillway
Sarhan Stepped Submerged Offshore Breakwaters for Wave Energy Dissipation
CN116464005B (en) Fish guiding weir system
Hur et al. Experimental study on reduction of water level behind a caisson-type submerged breakwater
Prevot et al. Stability of rubble mound breakwaters in shallow water and surf zone: An experimental study
CN116644499B (en) Determination method suitable for action range of canal wave bank slope impact area and ship traveling wave model test device
CN215165306U (en) Asphalt concrete core rock-fill dam arrangement structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant