CN106992520B - Power distribution network based on multi-source data stops monitoring method of sending a telegram in reply - Google Patents

Power distribution network based on multi-source data stops monitoring method of sending a telegram in reply Download PDF

Info

Publication number
CN106992520B
CN106992520B CN201710378905.6A CN201710378905A CN106992520B CN 106992520 B CN106992520 B CN 106992520B CN 201710378905 A CN201710378905 A CN 201710378905A CN 106992520 B CN106992520 B CN 106992520B
Authority
CN
China
Prior art keywords
data
telegram
reply
power
outage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710378905.6A
Other languages
Chinese (zh)
Other versions
CN106992520A (en
Inventor
陈宇星
殷自力
黄文英
朱宗毅
姚旭
徐积洲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Beijing Kedong Electric Power Control System Co Ltd
State Grid Fujian Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Beijing Kedong Electric Power Control System Co Ltd
State Grid Fujian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Beijing Kedong Electric Power Control System Co Ltd, State Grid Fujian Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710378905.6A priority Critical patent/CN106992520B/en
Publication of CN106992520A publication Critical patent/CN106992520A/en
Application granted granted Critical
Publication of CN106992520B publication Critical patent/CN106992520B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The present invention relates to a kind of power distribution networks based on multi-source data to stop monitoring method of sending a telegram in reply.The method of the present invention obtains multi-source power failure data by access power distribution network Dispatching Control System, production management system and application acquisition system, and then carries out according to multi-source power failure data that the differentiation of fault outage range and scheduled outage range, power-off event merges, data accuracy verifies and the amended record of missing data.The present invention adds the technologies such as fault outage and scheduled outage division, data accuracy verification, missing data amended record by fusion multi-source data, improves accuracy, real-time and integrality that power distribution network stops telegram in reply data statistics.

Description

Power distribution network based on multi-source data stops monitoring method of sending a telegram in reply
Technical field
The present invention relates to a kind of power distribution networks based on multi-source data to stop monitoring method of sending a telegram in reply.
Background technique
Stop the critical reliability index that telegram in reply statistics is power distribution network operation, power distribution network, which stops telegram in reply monitoring, to be intuitive to see The degree of reliability of operation of power networks is of great significance to distribution Analysis of Isolated Net Running.
Power distribution network, which mainly integrates power distribution network scheduling Dispatching Control System and automates, at present stops send a telegram in reply message, production management system Outage information data carry out stopping telegram in reply statistics.Since there are dispatchers to omit switch set, terminal frequency in generating operational process Numerous shake, have a power failure in short-term do not issue outage information, disaster during outage information publication not in time or do not issue and (big rule occur When mould power-off event, outage information can postpone to issue;Allow not issue outage information during disaster) phenomena such as, cause Stop telegram in reply and count generally existing deviation, can not ensure accuracy, real-time and the integrality of the data statistics that stops sending a telegram in reply.
System obtains power-off event data source at present, is broadly divided into two kinds:
(1) power distribution network Dispatching Control System pushes in real time power failure, telegram in reply message
Stop sending a telegram in reply message data comprising conjugating switch ID, switch changed position information (divide/close), switchtype (incoming switch/dry Wiretap/branch's wiretap), whether be that feeder line ID, switch changed position belonging to remote motion signal, displacement switch influence distribution transforming information etc..
(2) production management system timing updates outage information
Production management system can be by information such as newest Trouble ticket, plan list, power failure distribution transformings, and timing (frequency 5 minutes) is more Newly into ORACLE middle database, system can take out newest information, carry out data check work.
Based on power distribution network scheduling controlling need to provide push in real time stop sending a telegram in reply message, production management system outage information stop it is multiple Fault outage range and scheduled outage range in the message that stops sending a telegram in reply cannot be distinguished in electricity statistics, for automating scope of power outage accuracy Lack verification, and will appear information not in time, the problems such as failing to report, it is impossible to meet the requirements of power distribution network information security.
For existing power distribution network scope of power outage analysis there are deviation, fail to report, report the problems such as, the present invention fusion multi-source number According to the addition technologies such as fault outage and scheduled outage division, data accuracy verification, missing data amended record improve power distribution network and stop Accuracy, real-time and the integrality of telegram in reply data statistics.
Summary of the invention
The purpose of the present invention is to provide a kind of power distribution networks based on multi-source data to stop monitoring method of sending a telegram in reply, this method fusion Multi-source data, addition technologies, the raising such as fault outage and scheduled outage division, data accuracy verification, missing data amended record are matched Accuracy, real-time and the integrality of grid power failure telegram in reply data statistics.
To achieve the above object, the technical scheme is that a kind of power distribution network based on multi-source data stops telegram in reply monitoring Method includes the following steps,
S1, multi-source data obtain:
It accesses power distribution network Dispatching Control System, production management system and applies acquisition system, include stopping telegram in reply letter to obtain It ceases, study and judge outage information, production management system outage information, send a telegram in reply using acquisition system information, profile data information;
S2, fault outage range and scheduled outage range are distinguished:
Carry out failure based on power failure data and planning data, scheduled outage range divides, and determine scope of power outage ratio Matching rule, i.e. power failure message time of origin started in the single approval of plan and within the scope of the approval end times, and and scheduled outage Commensurate in scope >=70%;Meanwhile it identifying and being determined as scope of power outage and scheduled outage range mismatch portion in scheduled outage message Point, it distinguishes and is greater than scheduled outage range section and is less than scheduled outage range section;
S3, power-off event merge:
When handling multi-source data power-off event, multiple power failures influence distribution transforming is normalized, i.e., according to difference Multiple outage informations are integrated together by ID, the power off time of the identical distribution transforming of data source in conjunction with verification power failure duration algorithm, Guarantee only one power failure result set of same failure;
S4, data accuracy verification: it including wrong report data filtering, fails to report data amended record and reports data identification late;
(1) data filtering is reported by mistake
A, it for distribution transforming short time telegram in reply record, realizes and the shake for stopping telegram in reply record is filtered out;
B, being received based on every five minutes includes real-time section voltage, electric current, power data, continues 15 minutes checking prediction messages and stops Electric range stops telegram in reply state, and identification state inconsistency record is to report record by mistake, adds Data Identification;
(2) data amended record is failed to report
A, it does not send a telegram in reply record for a long time for distribution transforming, realizes correctness verifying function, integrate 98 profile datas of history, school Distribution transforming telegram in reply state correctness is tested, amended record distribution transforming is sent a telegram in reply the time;
B, comprehensive outage information data include, stop telegram in reply message not comprising record, are recognized as failing to report note to outage information Record is recorded using outage information and carries out data supplement;
(3) data identification is reported late
Telegram in reply message time is stopped for access and differs 1 hour record with telegram in reply event time interval is stopped, is recognized as reporting note late Report reason late is checked in record, analysis.
It in an embodiment of the present invention, can also be to power distribution network Dispatching Control System when handling multi-source data power-off event The message of transmission keeps a record, including shake message, merging message information.
Compared to the prior art, the invention has the following advantages: the method for the present invention merges multi-source data, failure is added Have a power failure and the technologies such as scheduled outage division, data accuracy verification, missing data amended record, improves power distribution network and stop data statistics of sending a telegram in reply Accuracy, real-time and integrality.
Detailed description of the invention
Fig. 1 is the system framework figure that the method for the present invention is based on.
Fig. 2 is data accuracy checking process figure of the present invention.
Specific embodiment
With reference to the accompanying drawing, technical solution of the present invention is specifically described.
As shown in Figure 1, 2, a kind of power distribution network based on multi-source data of the invention stops monitoring method of sending a telegram in reply, including walks as follows Suddenly,
S1, multi-source data obtain:
It accesses power distribution network Dispatching Control System, production management system and applies acquisition system, include stopping telegram in reply letter to obtain It ceases, study and judge outage information, production management system outage information, send a telegram in reply using acquisition system information, profile data information;
S2, fault outage range and scheduled outage range are distinguished:
Carry out failure based on power failure data and planning data, scheduled outage range divides, and determine scope of power outage ratio Matching rule, i.e. power failure message time of origin started in the single approval of plan and within the scope of the approval end times, and and scheduled outage Commensurate in scope >=70%;Meanwhile it identifying and being determined as scope of power outage and scheduled outage range mismatch portion in scheduled outage message Point, it distinguishes and is greater than scheduled outage range section and is less than scheduled outage range section;
S3, power-off event merge:
When handling multi-source data power-off event, multiple power failures influence distribution transforming is normalized, i.e., according to difference Multiple outage informations are integrated together by ID, the power off time of the identical distribution transforming of data source in conjunction with verification power failure duration algorithm, Guarantee only one power failure result set of same failure;
S4, data accuracy verification: it including wrong report data filtering, fails to report data amended record and reports data identification late;
(1) data filtering is reported by mistake
A, it for distribution transforming short time telegram in reply record, realizes and the shake for stopping telegram in reply record is filtered out;
B, being received based on every five minutes includes real-time section voltage, electric current, power data, continues 15 minutes checking prediction messages and stops Electric range stops telegram in reply state, and identification state inconsistency record is to report record by mistake, adds Data Identification;
(2) data amended record is failed to report
A, it does not send a telegram in reply record for a long time for distribution transforming, realizes correctness verifying function, integrate 98 profile datas of history, school Distribution transforming telegram in reply state correctness is tested, amended record distribution transforming is sent a telegram in reply the time;
B, comprehensive outage information data include, stop telegram in reply message not comprising record, are recognized as failing to report note to outage information Record is recorded using outage information and carries out data supplement;
(3) data identification is reported late
Telegram in reply message time is stopped for access and differs 1 hour record with telegram in reply event time interval is stopped, is recognized as reporting note late Report reason late is checked in record, analysis.
When handling multi-source data power-off event, the message that can also send to power distribution network Dispatching Control System keeps a record, and wraps It includes shake message, merge message information.
The following are specific implementation processes of the invention.
The system architecture of the method for the present invention, as shown in Figure 1, the method for the present invention is implemented as follows:
(1) multi-source data obtains
System access power distribution network Dispatching Control System stops telegram in reply information, studies and judges outage information, production management system power failure letter Breath, send a telegram in reply using acquisition system information, profile data etc., carry out multisource data fusion and data correctness verify.
(2) fault outage range and scheduled outage range are distinguished
It realizes based on power failure data and plans the failure of forms data, scheduled outage range partitioning technology, specify scope of power outage Ratio match rule, i.e. power failure message time of origin started in the single approval of plan and within the scope of the approval end times, and with plan Single scope of power outage matching >=70%.It identifies and is determined as scope of power outage in scheduled outage message and plans single scope of power outage mismatch Part is distinguished to be greater than and plans single scope of power outage part and be less than to plan single scope of power outage part, improves fault outage range and meter It draws scope of power outage and divides accuracy.
(3) power-off event merges
When handling multi-source data power-off event, it can take into account and multiple power failures influence distribution transforming is normalized, it is main Will ID, power off time according to the identical distribution transforming of different data sources, in conjunction with verification power failure duration scheduling algorithm, by multiple outage informations It is integrated together, guarantees only one power failure result set of same failure, improve the accuracy of power failure data.
(4) data accuracy verification (as shown in Figure 2)
1) data filtering is reported by mistake
It sends a telegram in reply and records for the distribution transforming short time, realize and the shake for stopping telegram in reply record is filtered out, access data correctness is provided.
The data such as real-time section voltage, electric current, power were received based on every five minutes, continue three points verification in (15 minutes) report Literary scope of power outage stops telegram in reply state, and identification state inconsistency record is to report record by mistake, adds Data Identification, improves access data Correctness
2) data amended record is failed to report
It does not send a telegram in reply record for a long time for distribution transforming, realizes that correctness verifying function, comprehensive 98 profile datas of history verify Distribution transforming telegram in reply state correctness, amended record distribution transforming are sent a telegram in reply the time, and telegram in reply state correctness is improved.
Comprehensive outage information data include, stop telegram in reply message not comprising record, are recognized as failing to report record to outage information, It is recorded using outage information and carries out data supplement, improve access data integrity.
3) data identification is reported late
Telegram in reply message time is stopped for access and differs 1 hour record with telegram in reply event time interval is stopped, is recognized as reporting note late Record, analysis check report reason late, improve data access real-time and stability.
(5) process management and control
When handling multi-source data, the message that can be sent to power distribution network Dispatching Control System keeps a record system, including It shakes message, merge the information such as message.
(6) dynamic configuration system parameter
System can modify parameters, including data check rule, Check-Out Time etc. when operation, modify Afterwards, it dynamically comes into force.
The above are preferred embodiments of the present invention, all any changes made according to the technical solution of the present invention, and generated function is made When with range without departing from technical solution of the present invention, all belong to the scope of protection of the present invention.

Claims (2)

1. a kind of power distribution network based on multi-source data stops monitoring method of sending a telegram in reply, it is characterised in that: include the following steps,
S1, multi-source data obtain:
It accesses power distribution network Dispatching Control System, production management system and applies acquisition system, to obtain including stopping telegram in reply information, grinding Sentence outage information, production management system outage information, send a telegram in reply using acquisition system information, profile data information;
S2, fault outage range and scheduled outage range are distinguished:
Carry out failure based on power failure data and planning data, scheduled outage range divides, and determine scope of power outage ratio match Rule, i.e. power failure message time of origin started in the single approval of plan and within the scope of the approval end times, and with scheduled outage range Matching >=70%;Meanwhile it identifying and being determined as scope of power outage and scheduled outage range non-matching part, area in scheduled outage message Divide and is greater than scheduled outage range section and is less than scheduled outage range section;
S3, power-off event merge:
When handling multi-source data power-off event, multiple power failures influence distribution transforming is normalized, i.e., according to different data Multiple outage informations are integrated together by ID, the power off time of the identical distribution transforming in source in conjunction with verification power failure duration algorithm, are guaranteed Only one power failure result set of same failure;
S4, data accuracy verification: it including wrong report data filtering, fails to report data amended record and reports data identification late;
(1) data filtering is reported by mistake
A, it for distribution transforming short time telegram in reply record, realizes and the shake for stopping telegram in reply record is filtered out;
B, being received based on every five minutes includes real-time section voltage, electric current, power data, continues verification in 15 minutes and stops message of sending a telegram in reply Middle scope of power outage stops telegram in reply state, and identification state inconsistency record is to report record by mistake, adds Data Identification;
(2) data amended record is failed to report
A, it does not send a telegram in reply record for a long time for distribution transforming, realizes correctness verifying function, integrate 98 profile datas of history, verification is matched Become telegram in reply state correctness, amended record distribution transforming is sent a telegram in reply the time;
B, comprehensive outage information data include, stop telegram in reply message not comprising record, are recognized as failing to report record, benefit to outage information Data supplement is carried out with outage information record;
(3) data identification is reported late
1 hour record is differed with the time interval for stopping telegram in reply event for access stop sending a telegram in reply time of message, is recognized as reporting late Report reason late is checked in record, analysis.
2. the power distribution network according to claim 1 based on multi-source data stops monitoring method of sending a telegram in reply, it is characterised in that: handling When multi-source data power-off event, the message that can also send to power distribution network Dispatching Control System keeps a record, including shake message, merging Message information.
CN201710378905.6A 2017-05-25 2017-05-25 Power distribution network based on multi-source data stops monitoring method of sending a telegram in reply Active CN106992520B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710378905.6A CN106992520B (en) 2017-05-25 2017-05-25 Power distribution network based on multi-source data stops monitoring method of sending a telegram in reply

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710378905.6A CN106992520B (en) 2017-05-25 2017-05-25 Power distribution network based on multi-source data stops monitoring method of sending a telegram in reply

Publications (2)

Publication Number Publication Date
CN106992520A CN106992520A (en) 2017-07-28
CN106992520B true CN106992520B (en) 2019-11-29

Family

ID=59419749

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710378905.6A Active CN106992520B (en) 2017-05-25 2017-05-25 Power distribution network based on multi-source data stops monitoring method of sending a telegram in reply

Country Status (1)

Country Link
CN (1) CN106992520B (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107666148B (en) * 2017-08-10 2021-03-05 国网浙江宁波市鄞州区供电公司 Line fault studying and judging method based on distribution transformer power failure signal
CN108647328B (en) * 2018-05-11 2022-04-01 国网安徽省电力有限公司淮南供电公司 Reliability power failure event acquisition integrity analysis and automatic completion method
CN110134053B (en) * 2019-06-19 2021-07-30 广东电网有限责任公司 Monitoring configuration method, device and equipment for distribution transformer fault power failure quick response
CN110516929A (en) * 2019-08-09 2019-11-29 国网浙江省电力有限公司 Power transmission and transformation closed-loop data processing method based on multi-source information
CN111813824B (en) * 2020-06-02 2022-09-02 国网江西省电力有限公司电力科学研究院 Method and system for automatically detecting missing report of power failure event of 10kV line outgoing line
CN112557802B (en) * 2021-02-24 2021-07-02 国网江西省电力有限公司电力科学研究院 Accurate analysis method and system for power outage of transformer area
CN113672647B (en) * 2021-08-02 2023-10-31 国电南瑞科技股份有限公司 Planned power outage specification verification method and device
CN114243682B (en) * 2021-11-19 2023-09-19 国电南京自动化股份有限公司 Intelligent power distribution network duplicate power research and judgment method and system based on multi-source information
CN115065587B (en) * 2022-06-20 2024-01-02 深圳供电局有限公司 Active power failure early warning method and device

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104143823A (en) * 2012-10-22 2014-11-12 国网山东省电力公司青岛供电公司 Blackout event information collecting method and system
CN104410067A (en) * 2014-11-28 2015-03-11 国家电网公司 Zone area power failure analyzing method based on common transformer and analysis of big data acquired by users

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104143823A (en) * 2012-10-22 2014-11-12 国网山东省电力公司青岛供电公司 Blackout event information collecting method and system
CN104143823B (en) * 2012-10-22 2016-02-10 国网山东省电力公司青岛供电公司 A kind of power-off event information collecting method and system
CN104410067A (en) * 2014-11-28 2015-03-11 国家电网公司 Zone area power failure analyzing method based on common transformer and analysis of big data acquired by users

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
一种基于BI的电网停复电事件分析方法;杨启京等;《电气应用》;20151231;第403-407页 *

Also Published As

Publication number Publication date
CN106992520A (en) 2017-07-28

Similar Documents

Publication Publication Date Title
CN106992520B (en) Power distribution network based on multi-source data stops monitoring method of sending a telegram in reply
JP6621808B2 (en) Method and apparatus for detecting the absence of voltage
CN105049223B (en) A kind of power telecom network defect troubleshooting decision assistant analysis method
CN108540483A (en) A kind of apparatus monitoring method and device based on block chain
CN108710099B (en) Monitoring and alarming method and system for capacitor voltage transformer
CN103514516B (en) Method for obtaining power grid device failure information based on calculation of multi-source redundant information
CN107959589A (en) A kind of power emergency repair dispatches system and method
US20200117151A1 (en) Outage and switch management for a power grid system
CN104908783A (en) System architecture of comprehensive monitoring and maintaining system for railway electricity
CN103324148A (en) Equipment cabinet safety integrated management system and equipment cabinet safety integrated management system control method
CN109842649A (en) A kind of urban rail transit equipment health control method and device
CN105095052A (en) Fault detection method and fault detection device in SOA (Service-Oriented Architecture) environment
CN109639477A (en) A kind of secondary device in-service monitoring and analysis system and method
CN102566531A (en) Monitoring and early warning system for service life of equipment
CN106506226B (en) A kind of starting method and device of fault detection
CN108107292B (en) Service data monitoring system and method of electric energy quality on-line monitoring system
CN110365534A (en) A kind of intelligent substation communication system is chopped off automatically and restoration methods
CN103986607A (en) Voice-sound-light alarm monitoring system for intelligent data center
CN105938153A (en) System for monitoring abnormal state of CT secondary loop and electricity stealing prevention method
CN104882964B (en) Substation information based on information redundancy verification error correction method
CN110781241A (en) Four-remote information acceptance method and system
CN106685759A (en) High-efficiency and zero-error updating and upgrading verification test method for scheduling main station
CN107896002A (en) 10kV feeder loads monitor active alarm system
CN112737863A (en) Intelligent measurement and control system capable of automatically correcting errors
CN109686070B (en) Terminal automatic debugging method of electricity consumption information acquisition system, medium and equipment thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant