CN106979004A - A kind of boring observation instrument and its installation method - Google Patents

A kind of boring observation instrument and its installation method Download PDF

Info

Publication number
CN106979004A
CN106979004A CN201710344271.2A CN201710344271A CN106979004A CN 106979004 A CN106979004 A CN 106979004A CN 201710344271 A CN201710344271 A CN 201710344271A CN 106979004 A CN106979004 A CN 106979004A
Authority
CN
China
Prior art keywords
binding agent
observation instrument
boring observation
data
controlling organization
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710344271.2A
Other languages
Chinese (zh)
Inventor
姜景捷
彭华
李振
马秀敏
彭立国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
INSTITUTE OF GEOMECHANICS CHINESE ACADEMY OF GEOLOGICAL SCIENCES
Original Assignee
INSTITUTE OF GEOMECHANICS CHINESE ACADEMY OF GEOLOGICAL SCIENCES
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by INSTITUTE OF GEOMECHANICS CHINESE ACADEMY OF GEOLOGICAL SCIENCES filed Critical INSTITUTE OF GEOMECHANICS CHINESE ACADEMY OF GEOLOGICAL SCIENCES
Priority to CN201710344271.2A priority Critical patent/CN106979004A/en
Publication of CN106979004A publication Critical patent/CN106979004A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B23/00Apparatus for displacing, setting, locking, releasing, or removing tools, packers or the like in the boreholes or wells

Abstract

The invention provides a kind of boring observation instrument and its installation method, including:Binding agent storage portion, data monitoring portion and the controlling organization being fixedly connected from top to bottom successively;The first cavity volume is provided with binding agent storage portion;The centre in data monitoring portion is provided with the second cavity volume;First cavity volume and the second cavity volume are sequentially communicated;Lower end of the data monitoring portion away from binding agent storage portion is provided with the controlling organization for controlling binding agent to flow out;When controlling organization is opened, the binding agent stored in the first cavity volume and the second cavity volume is discharged into drilling by controlling organization, data monitoring portion is pasted on the palisades of drilling;It integrates binding agent storage portion, data monitoring portion and controlling organization, the installation of whole boring observation instrument and release operation implementation in process of once going into the well of adhesive can be made, realize the integral installation of adhesive and boring observation instrument, reduce the time of instrument installation process, efficiency of construction and the degree of reliability of installation are improved, work risk is reduced.

Description

A kind of boring observation instrument and its installation method
Technical field
The present invention relates to drilling monitoring technical field, in particular to a kind of boring observation instrument and its installation method.
Background technology
Be intended in geological drilling, hydrology and water well drilling, geothermal drilling, engineering investigation probing and the engineering such as oil drilling into Boring observation instrument, is then positioned in drilling by row drilling, for gathering various Monitoring Datas, such as low interference geophysics, change Hygienic monitoring on hands of childhood data, to provide important foundation for the research of geological sciences.
, it is necessary to boring observation instrument is arranged in corresponding drilling, specifically before using boring observation instrument Monitoring Data Installation method includes two kinds:The first, delivers cement (or other binding agents) to drilling bottom first by cement release Portion, then, lifts cement release, equipment to be installed (i.e. boring observation instrument) is attached into foot of hole;Second, first cloth If pumping line, cement (or other binding agents) is pumped into by foot of hole by above-mentioned pumping line using slush pump, so After remove above-mentioned pumping line, equipment to be installed (i.e. boring observation instrument) is attached to foot of hole.
But, in the mounting means of above two boring observation instrument, equipment adhesive is installed step by step with equipment so that whole Individual installation procedure elapsed time is longer, and the longer set-up time can influence the installation effect of binding agent, particularly deep in drilling In the case of spending relatively depth, installation risk can be greatly improved, success rate is installed in reduction;Binding agent hardening time limits whole operation The time of process, it also limit the most deep fitting depth of instrument.
The content of the invention
In view of this, the purpose of the embodiment of the present invention is to provide a kind of boring observation instrument and its installation method, and it is realized The integral installation of adhesive and boring observation instrument, reduces the time of instrument installation process, improves efficiency of construction and peace The degree of reliability of dress, reduces work risk.
In a first aspect, the embodiments of the invention provide a kind of boring observation instrument, including:It is fixedly connected from top to bottom successively Binding agent storage portion, data monitoring portion and controlling organization;
The first cavity volume for accommodating binding agent is provided with the binding agent storage portion;The centre in the data monitoring portion It is provided with the second cavity volume for accommodating binding agent;First cavity volume and second cavity volume are sequentially communicated;
Lower end of the data monitoring portion away from the binding agent storage portion is provided with for controlling the binding agent to flow out The controlling organization;
When the controlling organization is opened, first cavity volume of the binding agent storage portion and the data monitoring portion The binding agent of storage is discharged into the drilling by the controlling organization in second cavity volume, to by the data monitoring Portion is pasted on the palisades of the drilling.
With reference in a first aspect, the embodiments of the invention provide the possible embodiment of the first of first aspect, wherein, institute Stating controlling organization includes:Mechanical trigger mechanism and valve;The mechanical trigger mechanism includes:Frizzen is latched with triggering;It is described Frizzen is fixedly connected by the triggering lock with the data monitoring portion, and the valve is connected with the frizzen;
When the frizzen is triggered to the palisades of the foot of hole, the frizzen triggering control valve is beaten Open.
With reference to the first possible embodiment of first aspect, the embodiments of the invention provide second of first aspect Possible embodiment, wherein, the controlling organization also includes the first detector;
First detector, for detecting the current location data where the boring observation instrument in real time, and will be described Current location data is sent to control terminal.
With reference in a first aspect, the embodiments of the invention provide the possible embodiment of the third of first aspect, wherein, institute Stating controlling organization includes:Controller, the second detector, electronics release control switch and valve, the electronics release control switch Electrically connected respectively with the controller with second detector;The electronics release control switch is fixed with the valve to be connected Connect;The controller is interacted by cable with ground control terminal, is presented to operating personnel;
Second detector, for detecting the current location data where the boring observation instrument in real time, described will work as Front position data are sent to the controller;The controller, for receiving the current location data, by the current location Data are sent to the control terminal on ground by the cable;And, ground handling operator is received according to the control terminal The control signal of the current location data triggering of display, the control signal is sent to the electronics release control and opened Close;The electronics release control switch, for receiving the control signal, the valve that it is connected is controlled according to the control signal Open.
With reference to the first possible embodiment of first aspect, the embodiments of the invention provide the 4th of first aspect kind Possible embodiment, wherein, the data monitoring portion is multiple, and multiple data monitoring portions are fixed from top to bottom successively to be connected Connect, and be interconnected;The data monitoring portion of multiple connections is consolidated by head end data monitoring portion and the binding agent storage portion Fixed connection, the bottom in the data monitoring portion of multiple connections is provided with the control for controlling the binding agent outflow Mechanism.
With reference in a first aspect, first aspect the first possible embodiment to first aspect the 5th kind of possible reality The possible embodiment of any one in mode is applied, the embodiments of the invention provide the possible embodiment party of the 5th of first aspect kind Formula, wherein, described boring observation instrument, in addition to connection cable;The connection cable includes:Cable and it is arranged on the cable On can load receiving part;
The connection cable runs through the binding agent storage portion, the data monitoring portion and the control by the cable Mechanism, the data transfer to realize the data monitoring portion and the controlling organization and ground control terminal, and, pass through institute State can load receiving part be fixedly connected with the binding agent storage portion, for when installing the boring observation instrument into drilling, bearing The active force of the boring observation instrument and the binding agent.
With reference to the third possible embodiment of second possible embodiment or first aspect of first aspect, The embodiments of the invention provide the possible embodiment of the 6th of first aspect kind, wherein, described boring observation instrument, in addition to 3rd detector;
3rd detector, the opening data for detecting the controlling organization in real time, by the opening Data are sent to control terminal.
Second aspect, the embodiment of the present invention additionally provides a kind of installation method of boring observation instrument, and the installation method should For the boring observation instrument described in above-mentioned any one of first aspect, methods described includes:
The all parts of boring observation instrument are assembled, and check the integrality of all parts after assembling;Wherein, institute Stating all parts of boring observation instrument at least includes:Binding agent storage portion and controlling organization;
The good binding agent of pre-coordination, the deployed binding agent is positioned over the binding agent of the boring observation instrument In storage portion;
The boring observation instrument for being placed with the binding agent is transferred into drilling, and monitors the drilling monitoring in real time The current lowered position of instrument;
When monitoring that the lowered position reaches default installation site, the boring observation instrument releasing adhesive is controlled, The boring observation instrument is arranged in the default installation site of the drilling.
With reference to second aspect, the embodiments of the invention provide the possible embodiment of the first of second aspect, wherein, institute The installation method for the boring observation instrument stated, in addition to:
During the boring observation instrument discharges the binding agent, the release conditions of the binding agent are monitored in real time;
The release conditions data for monitoring the obtained binding agent are real-time transmitted to control terminal, so as to the control eventually The end display release conditions data.
With reference to second aspect, the embodiments of the invention provide the possible embodiment of second of second aspect, wherein, institute Stating method also includes:
After the binding agent tentatively consolidation of the binding agent release completion and release is monitored, delivered into drilling The grains of sand, the top in the fixed data monitoring portion and the palisades of drilling are aided in so as to the grains of sand.
A kind of boring observation instrument and its installation method provided in an embodiment of the present invention, including:It is fixed from top to bottom successively to connect Binding agent storage portion, data monitoring portion and the controlling organization connect;Be provided with binding agent storage portion for accommodate binding agent One cavity volume;The centre in data monitoring portion is provided with the second cavity volume for accommodating binding agent;First cavity volume and the second cavity volume are successively Connection;Lower end of the data monitoring portion away from binding agent storage portion is provided with the controlling organization for controlling binding agent to flow out;In control During mechanism opening processed, the binding agent of the first cavity volume and the second cavity volume storage is discharged into drilling by controlling organization, to by number Pasted according to monitoring portion on the palisades of drilling, and in the mounting means of boring observation instrument of the prior art, equipment adhesive with Equipment is installed step by step so that whole installation procedure elapsed time is longer, and installation risk can be greatly improved, and success rate is installed in reduction Compare, it integrates binding agent storage portion, data monitoring portion and binding agent release portion, can make the peace of whole boring observation instrument The release of dress and adhesive is carried out simultaneously, is realized the integral installation of adhesive and boring observation instrument, is reduced instrument and installed The time of journey, efficiency of construction and the degree of reliability of installation are improved, work risk is reduced.
Also, due to time restriction of the reliable fitting depth by binding agent reliable bond, provided by the embodiment of the present invention A kind of boring observation instrument and its installation method, time demand is reduced in process, instrument can be arranged on to deeper drilling In.
Further, a kind of boring observation instrument and its installation method provided in an embodiment of the present invention, its controlling organization included Can be electronic control mechanism, the electronic control mechanism is by the second detector and controller control release valve, to release Binding agent is put, the reliability of releasing adhesive operation can be improved.
To enable the above objects, features and advantages of the present invention to become apparent, preferred embodiment cited below particularly, and coordinate Appended accompanying drawing, is described in detail below.
Brief description of the drawings
In order to illustrate the technical solution of the embodiments of the present invention more clearly, below will be attached to what is used required in embodiment Figure is briefly described, it will be appreciated that the following drawings illustrate only certain embodiments of the present invention, therefore is not construed as pair The restriction of scope, for those of ordinary skill in the art, on the premise of not paying creative work, can also be according to this A little accompanying drawings obtain other related accompanying drawings.
Fig. 1 shows a kind of structural representation for boring observation instrument that the embodiment of the present invention is provided;
Fig. 2 shows a kind of flow chart of the installation method for boring observation instrument that the embodiment of the present invention is provided;
Fig. 3 shows the flow chart of the installation method for another boring observation instrument that the embodiment of the present invention is provided;
Fig. 4 shows the flow chart of the installation method for another boring observation instrument that the embodiment of the present invention is provided.
Major Symbol explanation:
10th, binding agent storage portion;20th, data monitoring portion;30th, controlling organization;301st, valve;302nd, frizzen;40th, connect Cable;401st, cable;402nd, can load receiving part.
Embodiment
To make the purpose, technical scheme and advantage of the embodiment of the present invention clearer, below in conjunction with the embodiment of the present invention Middle accompanying drawing, the technical scheme in the embodiment of the present invention is clearly and completely described, it is clear that described embodiment is only It is a part of embodiment of the invention, rather than whole embodiments.The present invention being generally described and illustrated herein in the accompanying drawings is real Applying the component of example can be arranged and be designed with a variety of configurations.Therefore, it is of the invention to what is provided in the accompanying drawings below The detailed description of embodiment is not intended to limit the scope of claimed invention, but is merely representative of the selected reality of the present invention Apply example.Based on embodiments of the invention, the institute that those skilled in the art are obtained on the premise of creative work is not made There is other embodiment, belong to the scope of protection of the invention.
In view of in the mounting means of existing boring observation instrument, equipment adhesive is installed step by step with equipment so that whole Individual installation procedure elapsed time is longer, and the longer set-up time can influence the installation effect of binding agent, particularly deep in drilling In the case of spending relatively depth, installation risk can be greatly improved, success rate is installed in reduction.Based on this, the embodiments of the invention provide one Boring observation instrument and its installation method are planted, is described below by embodiment.
With reference to Fig. 1, the embodiments of the invention provide a kind of boring observation instrument, including:It is fixedly connected from top to bottom successively Binding agent storage portion 10, data monitoring portion 20 and controlling organization 30;
The first cavity volume for accommodating binding agent is provided with binding agent storage portion 10;Setting in the middle of data monitoring portion 20 There is the second cavity volume for accommodating binding agent;First cavity volume and the second cavity volume are sequentially communicated;
Lower end of the data monitoring portion 20 away from binding agent storage portion 10 is provided with the control machine for controlling binding agent to flow out Structure 30;When controlling organization 30 is opened, the first cavity volume of binding agent storage portion 10 and the second cavity volume storage of data monitoring portion 20 Binding agent by controlling organization 30 be discharged into drilling in, data monitoring portion 20 is pasted on the palisades of drilling.
Based on the shortcoming of the mounting means of boring observation instrument in currently associated technology, one kind is devised in the embodiment of the present invention Boring observation instrument, the boring observation instrument, including three parts, be respectively from up to down:The binding agent storage portion being fixedly connected sequentially 10th, data monitoring portion 20 and controlling organization 30;
Above-mentioned binding agent storage portion 10 includes the first cavity volume for being used to store binding agent, and its top and bottom is set respectively There are the first openend and the second openend;The centre in above-mentioned data monitoring portion 20 is provided with the second appearance for accommodating binding agent Chamber, and its top and bottom is respectively arranged with the 3rd openend and the 4th openend, first openend, described first are held Chamber, second openend, the 3rd openend, second cavity volume and the 4th openend are sequentially communicated;Described One openend is used to be provided with controlling organization 30 on the binding agent for receiving injection, the 4th openend.
Specifically, binding agent is filled in binding agent storage portion 10 by user by the first openend, binding agent passes through viscous Second openend of knot agent storage portion 10 and the 3rd openend of data monitoring portion 20 are discharged into the second of data monitoring portion 20 and held In chamber, two cavity volumes are finally filled;Binding agent is released by the openend of data monitoring portion 20 the 4th when controlling organization 30 is triggered It is put into drilling.
Controlling organization 30 is provided with the 4th openend in data monitoring portion 20, the controlling organization 30 is used to control to bond The binding agent outflow stored in agent release portion.
A kind of boring observation instrument provided in an embodiment of the present invention, the mounting means with boring observation instrument of the prior art In, equipment adhesive is installed step by step with equipment so that whole installation procedure elapsed time is longer, and installation wind can be greatly improved Danger, reduction is installed success rate and compared, and it integrates binding agent storage portion 10, data monitoring portion 20 and binding agent release portion, energy The installation of whole boring observation instrument and the release of adhesive is carried out simultaneously, realize the entirety of adhesive and boring observation instrument Install, reduce the time of instrument installation process, improve efficiency of construction and the degree of reliability of installation, reduce work wind Danger;
Also, due to time restriction of the reliable fitting depth by binding agent reliable bond, provided by the embodiment of the present invention A kind of boring observation instrument and its installation method, time demand is reduced in process, instrument can be arranged on to deeper drilling In.
In the embodiment of the present invention, above-mentioned controlling organization 30 can be mechanical control mechanism 30, can also be electronic conductivity control controller Structure 30, mechanical control mechanism 30 and electronic control mechanism 30 can also be included simultaneously, separately below to the He of mechanical control mechanism 30 Electronic control mechanism 30 is illustrated.
When above-mentioned controlling organization 30 is mechanical control mechanism 30, above-mentioned controlling organization 30 includes:Mechanical trigger mechanism and Valve 301;Mechanical trigger mechanism includes:Frizzen 302 is latched with triggering;Frizzen 302 is by triggering lock and data monitoring Portion 20 is fixedly connected, and valve 301 is connected with frizzen 302;
When frizzen 302 is triggered to the palisades of foot of hole, the triggering of frizzen 302 control valve 301 is opened.
Specifically, the set location of above-mentioned frizzen 302 is the installation site based on boring observation instrument to determine, when whole When individual boring observation instrument is arranged on the bottommost of drilling, above-mentioned frizzen 302 is set towards the bottom direction of drilling, now, when When whole boring observation instrument is slowly delivered foot of hole by staff, frizzen 302 can be triggered to foot of hole first, when When frizzen 302 is triggered to the palisades of foot of hole, its control valve 301 is opened, so that being stored in data monitoring portion 20 Binding agent release.
In addition, above-mentioned controlling organization 30 also includes the first detector, the first detector, for detecting boring observation instrument in real time The current location data at place, and current location data is sent into the control terminal to ground by cable.
Specifically, above-mentioned control terminal can be the control terminal for resting on the ground drilling site, interior can also be located at Docking remote server control terminal;When control terminal for the former when, above-mentioned second detector is preferably whole with above-mentioned control End electrical connection;When control terminal is the latter, above-mentioned second detector is preferably connected with above-mentioned control terminal telecommunication.
Above-mentioned first detector is used to the current location data where above-mentioned boring observation instrument being sent to control in real time eventually End, so that control terminal is shown, is checked for operating personnel.
When above-mentioned controlling organization 30 is electronic control mechanism 30, above-mentioned controlling organization 30 includes:Controller, electronics release Controlling switch, the second detector and valve 301, electronics release control switch are electrically connected with controller respectively with the second detector respectively Connect;Electronics release control switch is fixedly connected with valve 301;Controller is interacted by cable with ground control terminal, To be shown to ground handling operator;
Second detector, for the current location data where detection boring observation instrument in real time, current location data is sent out Deliver to controller;Controller, for receiving current location data, current location data is sent to the control on ground by cable Terminal processed;And, the control signal for the current location data triggering that ground handling operator shows according to control terminal is received, will be controlled Signal processed is sent to electronics release control switch;Electronics release control is switched, for receiving control signal, according to control signal control The valve 301 for making its connection is opened.
Specifically, when controlling organization 30 is electronic control mechanism 30, by the second detector, detection is whole in real time first The current location data of boring observation instrument, and current location data is sent to, then current location data is sent out by controller The control terminal on ground is delivered to, so that operating personnel are checked;The current location number that operating personnel show according to control terminal According to, judge whether to controller send control valve 301 open control signal, when operating personnel judge boring observation instrument ought When front position data reach default installation site, control signal is sent to controller, then controller is sent control signals to Electronics release control is switched, so that electronics release control switch controls its valve 301 connected to open according to control signal.
In the embodiment of the present invention, it is operating personnel's artificial judgment Trig control signal, is opened with control valve 301, it is actual In, boring observation instrument can also be automatically controlled electronics release-push by controller and open valve 301, specifically, in the second inspection Survey device to send the current location data of detection to controller, controller is pre- by current location data and the boring observation instrument If installation site is compared, when detecting current location data and default installation site matches, control signal is generated, and The control signal is sent to electronics release control switch;The electronics release control is switched under control of the control signal, control Its valve 301 connected is opened, so that the binding agent for storing data monitoring portion 20 is discharged into the boring observation instrument in drilling In default installation site, so as to which boring observation instrument is fixed on into above-mentioned default installation site.
Above-mentioned second detector is used to the current location data where above-mentioned boring observation instrument being sent to control in real time eventually End, so that control terminal is shown, is checked for operating personnel.Discharge viscous by electronic control mechanism 30 in the embodiment of the present invention Agent is tied, the reliability of releasing adhesive operation can be improved.
Further, in boring observation instrument provided in an embodiment of the present invention, data monitoring portion 20 is multiple, multiple data prisons Survey portion 20 is fixedly connected from top to bottom successively, and is interconnected;The data monitoring portion 20 of multiple connections is monitored by head end data Portion 20 is fixedly connected with binding agent storage portion 10, and the bottom in the data monitoring portion 20 of multiple connections is provided with for controlling to bond The controlling organization 30 of agent outflow.
Specifically, can effectively improve the utilization ratio of monitoring drilling using multiple data monitoring portions 20;Wherein, it is multiple Data monitoring portion 20 is fixedly connected from top to bottom successively, and multiple data monitoring portions 20 are interconnected.
In multiple interconnected boring observation instruments, head end data monitoring portion 20 is fixed with binding agent storage portion 10 to be connected Connect, the controlling organization 30 for controlling the binding agent outflow is only provided with the lower end of endian data monitoring portion 20.
Further, with reference to Fig. 1, boring observation instrument provided in an embodiment of the present invention, in addition to:Connection cable 40;Connection Cable 40 includes:Cable 401 and be arranged on cable 401 can load receiving part 402;
Connection cable 40 runs through binding agent storage portion 10, data monitoring portion 20 and controlling organization 30 by cable 401, is used to Realize the data transfer of data monitoring portion 20 and controlling organization 30 and ground control terminal, and, by can load receiving part 402 with it is viscous Knot agent storage portion 10 is fixedly connected, for when discharging boring observation instrument into drilling, bearing boring observation instrument and binding agent Active force.
Specifically, user can by connection cable 40 can load receiving part 402 by whole boring observation instrument deliver into drilling, And by the boring observation instrument slowly to the movement of drilling bottom, the connection cable 40 can bear binding agent storage portion 10, data prison The active force of survey portion 20 and controlling organization 30 and the binding agent of storage.
Further, boring observation instrument provided in an embodiment of the present invention, in addition to the 3rd detector;
3rd detector, for the opening data of real-time measure and control mechanism 30, by opening data send to Control terminal and/or controller;
Controller is additionally operable to, and adjustment signal is generated according to opening data;Electronics release control is switched, for according to tune Control the opening of its valve 301 connected of signals-modulating.
Above-mentioned 3rd detector can be jaw opening sensor, and it is used for the unlatching shape for detecting valve 301 in controlling organization 30 Whether state data, such as detection valve 301 is opened, the angle that valve 301 is opened, current location that valve 301 is opened etc., then The opening data of detection are sent to control terminal, so that control terminal is shown, so that user checks.
Or, the opening data of detection are sent to controller, so that the controller is according to the opening data Adjustment signal is regenerated, so that electronics release control switchs the opening for the valve 301 for regulating and controlling its connection again.
Or, data that the 3rd detector is gathered the opening data of detection are sent to control terminal simultaneously and Controller, so that control terminal is shown, and controller controls electronics release control to switch according to the opening data Again the opening of the valve 301 of its connection is regulated and controled.
A kind of boring observation instrument provided in an embodiment of the present invention, the mounting means with boring observation instrument of the prior art In, equipment adhesive is installed step by step with equipment so that whole installation procedure elapsed time is longer, and installation wind can be greatly improved Danger, reduction is installed success rate and compared, and it integrates binding agent storage portion 10, data monitoring portion 20 and binding agent release portion, energy The installation of whole boring observation instrument and the release of adhesive is carried out simultaneously, realize the entirety of adhesive and boring observation instrument Install, reduce the time of instrument installation process, improve efficiency of construction and the degree of reliability of installation, reduce work wind Danger;
Also, due to time restriction of the reliable fitting depth by binding agent reliable bond, provided by the embodiment of the present invention A kind of boring observation instrument, time demand is reduced in process, instrument can be arranged in deeper drilling.
With reference to Fig. 1, boring observation instrument structure provided in an embodiment of the present invention is divided into 3 parts, and bottom-up is respectively to discharge Valve portion (i.e. above-mentioned controlling organization 30), monitoring instrument bay section (i.e. above-mentioned data monitoring portion 20), binding agent bay section are (i.e. above-mentioned viscous Tie agent storage portion 10).
Discharging valve portion includes release valve 301, mechanical trigger switch, electronics release-push and the 3rd detector, release The function of valve portion is, in foot of hole or other installation site Open valves 301, the binding agent in binding agent bay section to be released It is put into drilling, monitoring instrument bay section is reliably bonded with drilling palisades.Above-mentioned release valve portion includes:Both mechanically and electrically two sets Triggering system, the optional configuration wherein at least of two sets of triggering systems is a set of, and above-mentioned 3rd detector can check control structure The unlatching effect of valve 301 and the position of current instrument, judge for installation effect.
Monitoring instrument bay section, the centre of above-mentioned monitoring instrument bay section different from commonly using monitoring instrument design in correlation technique For hollow design, i.e., the centre of above-mentioned monitoring instrument bay section is provided with the second cavity volume for accommodating binding agent, second cavity volume The passage discharged downwards for binding agent, wherein, can be with the protective housing of mounting portion electronic instrument, still in above-mentioned second cavity volume UNICOM above and below instrument bay section is ensured, inside point collectively forms binding agent parking space with binding agent bay section space.
Above-mentioned binding agent bay section is the bay section of special storage binding agent, and its length can be according to dividing into monitoring instrument bay section Length is planned.
Boring observation instrument provided in an embodiment of the present invention, mount scheme reduces the time of instrument installation process, improves Efficiency of construction, reduces work risk;The effect that binding agent discharges can be checked by sensor, the reliable journey of installation is improved Degree;Because time restriction of the reliable fitting depth by binding agent reliable bond, reducing the time in process using this method need to Ask, therefore instrument can be arranged in deeper drilling.
Drilling is realized in binding agent storage nacelle of the present invention and monitoring instrument nacelle global design, integral installation, once decentralization The installment work of monitoring instrument;Binding agent release valve 301 can be improved releasing adhesive by sensor and electronic circuit control The reliability of operation.
The embodiment of the present invention additionally provides a kind of installation method of boring observation instrument, with reference to Fig. 2, the installation method application In above-mentioned boring observation instrument, methods described includes:
S101, all parts of boring observation instrument are assembled, and check the integrality of all parts after assembling;Its In, all parts of the boring observation instrument at least include:Binding agent storage portion and controlling organization.
Specifically, boring observation instrument is scattered all parts in production, therefore, when in use, first by its each Part is assembled, and then checks the integrality of all parts after assembling, such as checks whether the valve of controlling organization is normal.
The good binding agent of S102, pre-coordination, the deployed binding agent is positioned over described in the boring observation instrument In binding agent storage portion.
In this step, all parts of instrument are assembled and check it is errorless after, good binding agent (such as water of pre-coordination Mud, resin engineering glue etc.), then deployed binding agent is positioned in the binding agent storage portion of boring observation instrument.
S103, the boring observation instrument for being placed with the binding agent transferred into drilling, and monitor the brill in real time The current lowered position of hole monitor.
Specifically, the connection cable that Engineering operation personnel are included by boring observation instrument can load receiving part will be placed with bonding The boring observation instrument of agent is discharged into drilling, and the boring observation instrument is slowly moved down, meanwhile, detect that the drilling is examined in real time The lowered position of instrument is surveyed, when the boring observation instrument reaches default installation site, the boring observation instrument to be bonded in above-mentioned Default installation site.
S104, when monitoring that the lowered position reaches default installation site, control boring observation instrument release viscous Agent is tied, the boring observation instrument is arranged in the default installation site of the drilling.
Specifically, when monitoring that the boring observation instrument reaches default installation site, controlling organization is opened, now, drilling The binding agent storage portion of monitor starts releasing adhesive, and the binding agent is by data monitoring portion, and eventually through control structure It is discharged on the palisades of drilling, data monitoring portion reliably to be bonded with drilling palisades, the boring observation instrument to be pacified In the default installation site of the drilling.
Further, with reference to Fig. 3, the embodiment of the present invention additionally provides the installation method of boring observation instrument, in addition to:
S105, during the boring observation instrument discharges the binding agent, the release of the binding agent is monitored in real time State.
S106, the release conditions data for the binding agent for obtaining monitoring are real-time transmitted to control terminal, so as to described Control terminal shows the release conditions data.
S107, monitoring that binding agent release completes and after the binding agent tentatively consolidation of release, to drilling The middle dispensing grains of sand, the top in the fixed data monitoring portion and the palisades of drilling are aided in so as to the grains of sand.
With reference to Fig. 4, the embodiment of the present invention additionally provides a kind of entire flow figure of the installation method of boring observation instrument, bag Include:
S201, all parts of boring observation instrument are assembled, and check the integrality of all parts after assembling;Its In, all parts of the boring observation instrument at least include:Binding agent storage portion and controlling organization.
Specifically, boring observation instrument is scattered all parts in production, therefore, when in use, first by its each Part is assembled, and then checks the integrality of all parts after assembling, such as checks whether the valve of controlling organization is normal.
The good binding agent of S202, pre-coordination, the deployed binding agent is positioned over described in the boring observation instrument In binding agent storage portion.
In this step, all parts of instrument are assembled and check it is errorless after, good binding agent (such as water of pre-coordination Mud, resin engineering glue etc.), then deployed binding agent is positioned in the binding agent storage portion of boring observation instrument.
S203, the boring observation instrument for being placed with the binding agent transferred into drilling, and monitor the brill in real time The current lowered position of hole monitor.
Then, the boring observation instrument for being placed with binding agent is transferred in drilling, so as to when the boring observation instrument reach it is pre- If during installation site, the boring observation instrument is bonded in into above-mentioned default installation site.
S204, when monitoring that the lowered position reaches default installation site, control boring observation instrument release viscous Agent is tied, the boring observation instrument is arranged in the default installation site of the drilling.
S205, during the boring observation instrument discharges the binding agent, the release of the binding agent is monitored in real time State.
S206, the release conditions data for the binding agent for obtaining monitoring are real-time transmitted to control terminal, so as to described Control terminal shows the release conditions data.
S207, monitoring that binding agent release completes and after the binding agent tentatively consolidation of release, to drilling The middle dispensing grains of sand, the top in the fixed data monitoring portion and the palisades of drilling are aided in so as to the grains of sand, it is possible to reduce and bore Influence of the water level to instrument in hole.
S208, the installation for completing the boring observation instrument.
With reference to above-mentioned steps 204 to step 208, engineering staff by boring observation instrument include can bearing cable will drill Monitor is discharged into drilling, and the boring observation instrument is slowly moved down, and the monitor is bored when the boring observation instrument is reached Default installation site when, controlling organization open, now, the binding agent storage portion of boring observation instrument starts releasing adhesive, should Binding agent is discharged into drilling by data monitoring portion and binding agent release portion eventually through the controlling organization in binding agent release portion On palisades, data monitoring portion reliably to be bonded with drilling palisades, completed and the binding agent when the binding agent discharges After primary solidification, the grains of sand are delivered into drilling, the installation of boring observation instrument is completed.
The installation method of a kind of boring observation instrument provided in an embodiment of the present invention, with boring observation instrument of the prior art In mounting means, equipment adhesive is installed step by step with equipment so that whole installation procedure elapsed time is longer, can be greatly improved Installation risk, reduction is installed success rate and compared, and it integrates binding agent storage portion, data monitoring portion and binding agent release portion, The installation of whole boring observation instrument and the release of adhesive can be made to carry out simultaneously, the whole of adhesive and boring observation instrument is realized Body is installed, and is reduced the time of instrument installation process, is improved efficiency of construction and the degree of reliability of installation, reduce work wind Danger;
Also, due to time restriction of the reliable fitting depth by binding agent reliable bond, provided by the embodiment of the present invention A kind of boring observation instrument and its installation method, time demand is reduced in process, instrument can be arranged on to deeper drilling In.
It should be noted that:Similar label and letter represents similar terms in following accompanying drawing, therefore, once a certain Xiang Yi It is defined in individual accompanying drawing, then it further need not be defined and explained in subsequent accompanying drawing, in addition, term " the One ", " second ", " the 3rd " etc. are only used for distinguishing description, and it is not intended that indicating or implying relative importance.
Finally it should be noted that:Embodiment described above, is only the embodiment of the present invention, to illustrate the present invention Technical scheme, rather than its limitations, protection scope of the present invention is not limited thereto, although with reference to the foregoing embodiments to this hair It is bright to be described in detail, it will be understood by those within the art that:Any one skilled in the art The invention discloses technical scope in, it can still modify to the technical scheme described in previous embodiment or can be light Change is readily conceivable that, or equivalent substitution is carried out to which part technical characteristic;And these modifications, change or replacement, do not make The essence of appropriate technical solution departs from the spirit and scope of technical scheme of the embodiment of the present invention.The protection in the present invention should all be covered Within the scope of.Therefore, protection scope of the present invention should be based on the protection scope of the described claims.

Claims (10)

1. a kind of boring observation instrument, it is characterised in that including:Binding agent storage portion, the data being fixedly connected from top to bottom successively Monitoring portion and controlling organization;
The first cavity volume for accommodating binding agent is provided with the binding agent storage portion;Setting in the middle of the data monitoring portion There is the second cavity volume for accommodating binding agent;First cavity volume and second cavity volume are sequentially communicated;
Lower end of the data monitoring portion away from the binding agent storage portion is provided with the institute for controlling the binding agent outflow State controlling organization;
When the controlling organization is opened, first cavity volume of the binding agent storage portion and the second of the data monitoring portion The binding agent of cavity volume storage is discharged into the drilling by the controlling organization, the data monitoring portion to be pasted Onto the palisades of the drilling.
2. boring observation instrument according to claim 1, it is characterised in that the controlling organization includes:Mechanical trigger mechanism And valve;The mechanical trigger mechanism includes:Frizzen is latched with triggering;The frizzen by it is described triggering lock with it is described Data monitoring portion is fixedly connected, and the valve is connected with the frizzen;
When the frizzen is triggered to the palisades of the foot of hole, the frizzen triggering control valve is opened.
3. boring observation instrument according to claim 2, it is characterised in that the controlling organization also includes the first detector;
First detector, for detecting the current location data where the boring observation instrument in real time, and will be described current Position data is sent to control terminal.
4. boring observation instrument according to claim 1, it is characterised in that the controlling organization includes:Controller, the second inspection Survey device, electronics release control switch and valve, electronics release control switch and second detector respectively with the control Device electrical connection processed;The electronics release control switch is fixedly connected with the valve;The controller passes through cable and ground Control terminal is interacted;
Second detector, for detecting the current location data where the boring observation instrument in real time, by the present bit Data are put to send to the controller;The controller, for receiving the current location data, by the current location data Sent by the cable to the control terminal on ground;And, receive ground handling operator and shown according to the control terminal The current location data triggering control signal, by the control signal send to the electronics release control switch;Institute Electronics release control switch is stated, for receiving the control signal, controls its valve connected to open according to the control signal.
5. boring observation instrument according to claim 2, it is characterised in that the data monitoring portion be it is multiple, it is multiple described Data monitoring portion is fixedly connected from top to bottom successively, and is interconnected;The data monitoring portion of multiple connections passes through head end number It is fixedly connected according to monitoring portion with the binding agent storage portion, the bottom in the data monitoring portion of multiple connections, which is provided with, to be used for Control the controlling organization of the binding agent outflow.
6. the boring observation instrument according to claim any one of 1-5, it is characterised in that also including connection cable;The company Connecing cable includes:Cable and be arranged on the cable can load receiving part;
The connection cable runs through the binding agent storage portion, the data monitoring portion and the control machine by the cable Structure, the data transfer to realize the data monitoring portion and the controlling organization and ground control terminal, and, by described Can load receiving part be fixedly connected with the binding agent storage portion, for when installing the boring observation instrument into drilling, bearing institute State the active force of boring observation instrument and the binding agent.
7. the boring observation instrument according to claim 3 or 4, it is characterised in that also including the 3rd detector;
3rd detector, the opening data for detecting the controlling organization in real time, by the opening data Send to control terminal.
8. a kind of installation method of boring observation instrument, it is characterised in that the installation method is applied to any one of claim 1-7 Described boring observation instrument, methods described includes:
The all parts of boring observation instrument are assembled, and check the integrality of all parts after assembling;Wherein, it is described to bore The all parts of hole monitor at least include:Binding agent storage portion and controlling organization;
The good binding agent of pre-coordination, the binding agent that the deployed binding agent is positioned over into the boring observation instrument is stored In portion;
The boring observation instrument for being placed with the binding agent is transferred into drilling, and monitors the boring observation instrument in real time and is worked as Preceding lowered position;
When monitoring that the lowered position reaches default installation site, the boring observation instrument releasing adhesive is controlled, is used to In the default installation site that the boring observation instrument is arranged on to the drilling.
9. the installation method of boring observation instrument according to claim 8, it is characterised in that methods described also includes:
During the boring observation instrument discharges the binding agent, the release conditions of the binding agent are monitored in real time;
The release conditions data for monitoring the obtained binding agent are real-time transmitted to control terminal, so that the control terminal is aobvious Show the release conditions data.
10. the installation method of boring observation instrument according to claim 8, it is characterised in that methods described also includes:
After the binding agent tentatively consolidation of the binding agent release completion and release is monitored, sand is delivered into drilling Grain, the top in the fixed data monitoring portion and the palisades of drilling are aided in so as to the grains of sand.
CN201710344271.2A 2017-05-16 2017-05-16 A kind of boring observation instrument and its installation method Pending CN106979004A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710344271.2A CN106979004A (en) 2017-05-16 2017-05-16 A kind of boring observation instrument and its installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710344271.2A CN106979004A (en) 2017-05-16 2017-05-16 A kind of boring observation instrument and its installation method

Publications (1)

Publication Number Publication Date
CN106979004A true CN106979004A (en) 2017-07-25

Family

ID=59342868

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710344271.2A Pending CN106979004A (en) 2017-05-16 2017-05-16 A kind of boring observation instrument and its installation method

Country Status (1)

Country Link
CN (1) CN106979004A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109025870A (en) * 2018-08-06 2018-12-18 广州博昊信息科技有限公司 Boring observation instrument installs equipment

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102748005A (en) * 2012-07-13 2012-10-24 中煤矿山建设集团有限责任公司 System for monitoring temperature, stress and deformation of frozen wall of shaft in real time and laying method thereof
CN202676334U (en) * 2012-03-26 2013-01-16 安徽理工大学 Ground stress meter installation device
CN103196610A (en) * 2013-03-14 2013-07-10 付志亮 Hollow inclusion crustal stress telemetry system and method
CN203534737U (en) * 2013-07-05 2014-04-09 河南理工大学 Temperature sensor-based testing device for hollow inclusion stress gauges
CN104390734A (en) * 2014-12-02 2015-03-04 安徽恒源煤电股份有限公司 Hollow inclusion stressometer
CN104452726A (en) * 2014-12-04 2015-03-25 浙江广川工程咨询有限公司 Deep water region soil mass layered settlement monitoring device and method
CN104807563A (en) * 2015-05-04 2015-07-29 中国矿业大学 Non-contact ground stress testing device and method based on drilling microscopy digital photography
CN206957687U (en) * 2017-05-16 2018-02-02 中国地质科学院地质力学研究所 A kind of boring observation instrument and drilling monitoring system

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202676334U (en) * 2012-03-26 2013-01-16 安徽理工大学 Ground stress meter installation device
CN102748005A (en) * 2012-07-13 2012-10-24 中煤矿山建设集团有限责任公司 System for monitoring temperature, stress and deformation of frozen wall of shaft in real time and laying method thereof
CN103196610A (en) * 2013-03-14 2013-07-10 付志亮 Hollow inclusion crustal stress telemetry system and method
CN203534737U (en) * 2013-07-05 2014-04-09 河南理工大学 Temperature sensor-based testing device for hollow inclusion stress gauges
CN104390734A (en) * 2014-12-02 2015-03-04 安徽恒源煤电股份有限公司 Hollow inclusion stressometer
CN104452726A (en) * 2014-12-04 2015-03-25 浙江广川工程咨询有限公司 Deep water region soil mass layered settlement monitoring device and method
CN104807563A (en) * 2015-05-04 2015-07-29 中国矿业大学 Non-contact ground stress testing device and method based on drilling microscopy digital photography
CN206957687U (en) * 2017-05-16 2018-02-02 中国地质科学院地质力学研究所 A kind of boring observation instrument and drilling monitoring system

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘允芳;肖本职;: "西部地区地震活动与地应力研究" *
李黎龙;: "钻孔套心应力解除法在米仓山隧道中的应用" *
白金朋;彭华;马秀敏;姜景捷;李振;: "深孔空心包体法地应力测量仪及其应用实例" *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109025870A (en) * 2018-08-06 2018-12-18 广州博昊信息科技有限公司 Boring observation instrument installs equipment

Similar Documents

Publication Publication Date Title
US9909376B2 (en) Latching assembly for wellbore logging tools and method of use
US9759037B2 (en) Method for monitoring cement plugs
EP0918919B1 (en) Logging method
BR112018074158B1 (en) METHOD FOR MANIPULATING A WELL AND METHOD FOR MANIPULATING A WELL
US9752431B2 (en) Apparatus and method for obtaining formation fluid samples utilizing a sample clean-up device
NO335588B1 (en) Method and apparatus for communicating with downhole devices in a wellbore
US20070007016A1 (en) Apparatus and methods for activating a downhole tool
GB2365894A (en) Well with a self-contained intervention system
BRPI0508407B1 (en) formation sampling system, formation sampler for penetrating a formation and retrieving a formation sample and a sampling method of a formation
US9404338B2 (en) Methods and apparatus for improved cement plug placement
CN110410021A (en) A kind of well completing test tubing string and method for gas well
NO20130389A1 (en) Improved cushioning device for resistivity imaging wells with oil-based drilling fluid
CN104088620B (en) Intelligent pneumatic supporting leg type vibrating anchor drilling rig capable of recognizing looseness range of surrounding rock
CN106979004A (en) A kind of boring observation instrument and its installation method
CN207332872U (en) Blocking type dual probe pressure gauge and eccentric injection mandrel
US20090033332A1 (en) Telemetry subsystem to communicate with plural downhole modules
WO2010046021A1 (en) Methods and apparatus for improved cement plug placement
CN107567532A (en) Lifted by nitrogen, production logging and recovery test extend the method for carrying out well testing operation with single coiled tubing
CN205805470U (en) Conveying-type side-wall coring system
CN206957687U (en) A kind of boring observation instrument and drilling monitoring system
CN111502643B (en) Downhole positioning tool and method
CN104343439A (en) Electric direct reading and examining seal system for dispersing pipe column and application method of system
CN104912543A (en) Deviational survey while drilling device
US7151465B2 (en) Method and apparatus for transmitting information between a salt-cavern and the surface of the ground
CN211505606U (en) Tracer agent feeding device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination