CN106972610A CN201710235871.5A CN201710235871A CN106972610A CN 106972610 A CN106972610 A CN 106972610A CN 201710235871 A CN201710235871 A CN 201710235871A CN 106972610 A CN106972610 A CN 106972610A
Authority
CN
China
Prior art keywords
power
energy
workover rig
unit
storage units
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710235871.5A
Other languages
Chinese (zh)
Other versions
CN106972610B (en
Inventor
黄继庆
史永庆
林文华
曲永哲
王建才
张庆军
聂永晋
苑成波
吴开磊
刘世峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Petroleum Corp
CNPC Bohai Equipment Manufacturing Co Ltd
Original Assignee
CNPC Bohai Equipment Manufacturing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CNPC Bohai Equipment Manufacturing Co Ltd filed Critical CNPC Bohai Equipment Manufacturing Co Ltd
Priority to CN201710235871.5A priority Critical patent/CN106972610B/en
Publication of CN106972610A publication Critical patent/CN106972610A/en
Application granted granted Critical
Publication of CN106972610B publication Critical patent/CN106972610B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J7/00Circuit arrangements for charging or depolarising batteries or for supplying loads from batteries
    • H02J7/34Parallel operation in networks using both storage and other dc sources, e.g. providing buffering
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B19/00Handling rods, casings, tubes or the like outside the borehole, e.g. in the derrick; Apparatus for feeding the rods or cables
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02E60/16Mechanical energy storage, e.g. flywheels or pressurised fluids

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Geology (AREA)
  • Fluid Mechanics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Mechanical Engineering (AREA)
  • Power Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Charge And Discharge Circuits For Batteries Or The Like (AREA)
  • Stand-By Power Supply Arrangements (AREA)

Abstract

A kind of net electric power workover rig energy storage control system and its control method.Well site power network of the present invention, well site transformer, dynamical system, work operations unit are sequentially connected;Dynamical system includes power control unit, energy-storage units, power unit, wherein:Power control unit is connected with well site transformer, and well site electric energy is accessed;Power control unit is used to control energy-storage units and power unit, power unit driving work operations cell operation, so as to complete workover treatment.In addition, present invention additionally comprises the control method of net electric power workover rig energy storage control system.Its advantage is to be that high-power workover rig is powered using existing power network, it is ensured that the high efficiency of the work of net electric power workover rig, reduce operating cost.

Description

Net electric power workover rig energy storage control system and its control method
Technical field
The present invention relates to petroleum well servicing rig technical field, and in particular to the electrodynamic workover rig energy storage control of one kind application net System and its control method.
Background technology
Vehicle carried well repairing machine is the mobile device for being widely used in workover treatment, for recovering oil-water well normally production or raising The construction operation of production capacity, main to include inspection pump, sand washing, well-flushing, change envelope, water blockoff etc., the operating type of workover rig is mainly Oil pipe, sucker rod are removed, and the course of work includes raising, three job steps of shackle and decentralization, the work of this loop cycle Feature needs workover rig to have corresponding power matching.
At present, conventional workover rig is using diesel engine as operation power source, due to the reason such as product oil price is high, energy consumption is big, Workover cost remains high, and fuels and energy well workover also has energy transformation ratio is low, discharge amount of pollution is high, operating noise is big etc. Environmental issue.Electric workover rig is compared with diesel powered workover rig with environmental protection, operating cost is low, noise is small, transmission efficiency It is high and the advantages of improve operating personnel's condition of work, progressively diesel oil substitute power workover rig.
Match somebody with somebody standby electricity by oil pumper more than oilfield electric net, used by main power network through the conveying of well site transformer for oil pumper.At present, Use " individual well is monotropic " power supply mode, i.e., one transformer is that an oil pumper is powered more;Some areas use " many wells are monotropic " Power supply mode, i.e., be that many mouthfuls of oil wells are powered with a high-power transformer, to improve transformer load rate, reduction loss." individual well It is monotropic " most of well site transformer capacity is 30 ~ 50kVA, and vehicle carried well repairing machine installed power will be far longer than and this be equipped with electricity Power, if the neighbouring well site transformer of access, can break power network because of electric workover rig work electricity consumption and power balance, the other oil pumping of influence The normal work of machine or electrical equipment.If matching electric workover rig input power according to well site transformer capacity, necessarily cause Electric workover rig operating efficiency is substantially reduced, and influences operation timeliness.If being powered according to petroleum well servicing rig power demand increase power network Ability, expands well site transformer capacity, not only invests huge, and under oil recovery operating mode, power network utilization rate is very low, causes power network A large amount of wastes of resource.
The content of the invention
In order to overcome the electricity needs of existing well site net electricity and electric workover rig to mismatch, workover treatment efficiency is low, cost High deficiency, the present invention provides a kind of net electric power workover rig energy storage control system and its control method.
The technical solution adopted for the present invention to solve the technical problems is:A kind of net electric power workover rig energy storage control system Including well site power network, well site transformer, the high-tension electricity of well site power network conveying accesses workover rig, the well after the transformer of well site Field power network, well site transformer, dynamical system, work operations unit are sequentially connected;
The dynamical system provides rotary power for net electric power workover rig, on workover rig voluntarily chassis;The operation The rotary power that dynamical system is exported is changed into straight line and removes power by working cell, for completing net electric power workover rig Rountrip, by workover rig, voluntarily chassis is carried, and is started working after in-site installation.
The dynamical system includes power control unit, energy-storage units, power unit, wherein:Power control unit and well Field transformer is connected, and well site electric energy is accessed;Power control unit is used to control energy-storage units and power unit, power list Member driving work operations cell operation, so as to complete workover treatment.
The energy-storage units are energy storage components, and specific form of energy includes electric energy or hydraulic pressure;When dynamical system is electricity During drive form, energy-storage units are battery and super capacitor;When dynamical system is hydraulic-driven form, energy-storage units are liquid Press accumulator.
A kind of control method of the net electric power workover rig energy storage control system, its step is:
Step A, sets the action setting value V of the DC voltage of net electric power workover rig energy storage control system0
Step B, the DC voltage value V that power control unit is monitored in real time1With action setting value V0It is compared, it is determined that dynamic Whether power unit is in running order;
Step C, when surveying DC voltage value >=action setting value, i.e.,:V1≥V0, power unit be in off working state, Power control unit would automatically turn on energy-storage units charge mode, and the energy for netting electric power supply is transferred in energy-storage units;In energy storage After unit is fully charged, power control unit closes energy-storage units charge function automatically;
Step D, when the magnitude of voltage < of DC side acts setting value, i.e.,:V1< V0, the power unit of dynamical system is in work State, under power control unit control, is powered unit, while monitoring the voltage of DC side by the energy of the electric power supply of net Value;Power control unit would automatically turn on energy-storage units discharge mode, be simultaneously power unit by the electric power supply of net and energy-storage units Electric energy is provided;
Step E, when surveying DC voltage value >=action setting value, i.e.,:V1≥V0, power unit be in off working state, Power control unit will automatically turn on energy-storage units charge mode again, and the energy for netting electric power supply is transferred in energy-storage units; After energy-storage units are fully charged, power control unit closes energy-storage units charge function automatically;
Step F, after charging complete, power control unit will turn off the charge function of energy-storage units, prepare next work Circulation;
According to the decentralization of well workover, lifting, shackle job requirements, step B- steps F moves in circles, until completing workover treatment, work Work terminates.
The action setting value V of DC voltage0Determined according to DC voltage, DC voltage is well site standard power electricity Pressure is multiplied by DC voltage coefficient.When the well site standard power voltage is 380V, DC voltage coefficient is
The power unit working condition refers to that workover rig is in lifting process;The power unit off working state refers to Workover rig is in decentralization either shackle process.
The step C is the decentralization operation process of workover rig;The step D is the lifting operation process of workover rig;It is described Shackles and/or decentralization operation process of the step E for workover rig.
The beneficial effects of the invention are as follows, it is reasonable in design, the well site transformer worked for oil pumper can be directly accessed nearby, It is that high-power workover rig is powered using existing power network, it is ensured that the high efficiency of net electric power workover rig work, and does not interfere with existing Power network normal power supply and the normal of other electrical equipments are used, so as to reduce well workover energy consumption, reduce operating cost, while environmental protection is high Effect, realizes " replacing oil by electricity " of workover treatment.
Brief description of the drawings
Fig. 1 is the schematic diagram of net electric power workover rig energy storage control system of the present invention.
Fig. 2 is the flow chart of the control method of net electric power workover rig energy storage control system of the present invention.
In figure:1. well site power network, 2. well site transformers, 3. dynamical systems, 4. work operations units, 5. dynamic Control lists Member, 6. energy-storage units, 7. power units.
Embodiment
The invention will be further described with reference to the accompanying drawings and examples.But, those skilled in the art should know , the invention is not restricted to listed embodiment, as long as meeting the spirit of the present invention, should all be included in the present invention Protection domain in.
Referring to accompanying drawing 1, the schematic diagram of net electric power workover rig energy storage control system of the present invention.A kind of net electric power of the present invention Workover rig energy storage control system, mainly includes well site power network 1, well site transformer 2, dynamical system 3, work operations unit 4, well site Power network 1, well site transformer 2, dynamical system 3, work operations unit 4 are sequentially connected;The high-tension electricity that well site power network 1 is conveyed is through well site After transformer 2, access workover rig dynamical system 3.The dynamical system 3 provides rotary power for net electric power workover rig, installs On workover rig voluntarily chassis;The work operations unit 4 is used for the rountrip for completing workover rig, can be by dynamical system institute The rotary power of output is changed into straight line and removes power, and by workover rig, voluntarily chassis is carried, by being started working after in-site installation.
The dynamical system 3 includes power control unit 5, energy-storage units 6, power unit 7, wherein:The dynamic Control Unit 5 is connected with well site transformer 2, and well site electric energy is accessed;The power control unit 5 be used for control energy-storage units 6 with And power unit 7, the driving work operations of power unit 7 unit 4 works, so as to complete workover treatment.
Specifically, the energy-storage units 6 are energy storage components, specific form of energy includes electric energy or hydraulic pressure or other energy Amount;When dynamical system 3 is electric drive form, energy-storage units 6 are battery and super capacitor;When dynamical system 3 is driven for hydraulic pressure During dynamic form, energy-storage units 6 are hydraulic accumulators.When using other energy modes, energy-storage units 6 are corresponding component.
The workover treatment process of workover rig is divided into two stages, i.e. raising and decentralization tubing string, and each stage includes some Rise and the decentralization course of work, workover rig is periodicity power demand in the course of work, and this course of work can be divided into three behaviour Make step, i.e. raising, shackle, decentralization, usual three steps take it is essentially identical, respectively account for a circulation total time-consuming three/ One.In three operating procedures, raising process workover rig power output is maximum(I.e. energy consumption is maximum), shackle, decentralization process are not required to Want power or only need to smaller power.Therefore, in the lifting operation process of workover rig, power unit 7 is in running order;Repairing The decentralization of well machine or shackle operation process, power unit 7 are in off working state.
Referring to accompanying drawing 2, the flow chart of the control method of net electric power workover rig energy storage control system of the present invention.Net of the present invention The control method of electric power workover rig energy storage control system, it is comprised the concrete steps that:
Step A, sets the action setting value V of the DC voltage of net electric power workover rig energy storage control system0
Step B, the DC voltage value V that power control unit 5 is monitored in real time1With action setting value V0It is compared, it is determined that Whether power unit 7 is in running order;
Step C, when surveying DC voltage value >=action setting value, i.e.,:V1≥V0, power unit 7 be in off working state, Power control unit 5 would automatically turn on the charge mode of energy-storage units 6, and the energy for netting electric power supply is transferred in energy-storage units 6;In storage After energy unit 6 is fully charged, power control unit 5 closes the charge function of energy-storage units 6 automatically;
Step D, when the magnitude of voltage < of DC side acts setting value, i.e.,:V1< V0, the power unit 7 of dynamical system 3 is in work Make state, under the control of power control unit 5, unit 7 is powered by the energy of the electric power supply of net, while monitoring the electricity of DC side Pressure value;Power control unit 5 would automatically turn on the discharge mode of energy-storage units 6, be simultaneously power by the electric power supply of net and energy-storage units 6 Unit 7 provides electric energy;
Step E, when surveying DC voltage value >=action setting value, i.e.,:V1≥V0, power unit 7 be in off working state, Power control unit 5 will automatically turn on the charge mode of energy-storage units 6 again, and the energy for netting electric power supply is transferred in energy-storage units 6; After energy-storage units 6 are fully charged, power control unit 5 closes the charge function of energy-storage units 6 automatically;
Step F, after charging complete, power control unit 5 will turn off the charge function of energy-storage units 6, prepare next work Circulate.
According to the decentralization of well workover, lifting, shackle job requirements, step B- steps F moves in circles, and makees until completing well workover Industry, end-of-job.
In above-mentioned control method, the action setting value V of the DC voltage0Determined generally according to DC voltage, DC voltage is that well site standard power voltage is multiplied by DC voltage coefficient, when well site standard power voltage is 380V, directly Flowing side voltage coefficient is
The action setting value V of DC voltage0It can also be determined according to threshold value, threshold value needs to set according to load state scene It is fixed.
In described control method, step C is the decentralization operation process of workover rig;Step D makees for the lifting of workover rig Industry process;Shackles and/or decentralization operation process of the step E for workover rig.
When workover rig is started working, power unit driving work operations unit carries out rountrip, power control unit DC voltage value is monitored in real time, and when detecting magnitude of voltage >=action setting value, well site transformer charges to energy-storage units, when dynamic When power unit is started working, power control unit stops charging to energy-storage units, and directly drives power by well site transformer Unit;When DC voltage < acts setting value, power control unit automatically discharges energy-storage units, is worked with adjunctive program Unit input power, it is ensured that power unit output is stable, and then completes complete raising, a decentralization process.
The present invention utilizes the circulation working characteristics of workover rig, in the non-activity duration of shackle and decentralization(Account for working cycles 2/3rds of cycle), it is ensured that there is time enough to supplement enough electric energy for energy-storage units;Within the activity duration of raising (Account for 1/3rd of a dust cycle), energy-storage units provide electric energy for power unit;Move in circles, meet whole Workover rig need for electricity during workover treatment.
The preferred embodiments of the present invention are these are only, are not intended to limit the invention, are come for those skilled in the art Say, the present invention there can be various modifications and variations.Any modification for being made within the spirit and principles of the invention, equally replace Generation, improvement etc., should be included in the scope of the protection.

Claims (7)

1. a kind of net electric power workover rig energy storage control system, including well site power network, well site transformer, the height of well site power network conveying Piezoelectricity accesses workover rig after the transformer of well site, it is characterized in that:
The well site power network(1), well site transformer(2), dynamical system(3), work operations unit(4)It is sequentially connected;
The dynamical system(3)Rotary power is provided for net electric power workover rig, on workover rig voluntarily chassis;
The work operations unit(4)The rotary power that dynamical system is exported is changed into straight line and removes power, for completing The rountrip of net electric power workover rig, by workover rig, voluntarily chassis is carried, and is started working after in-site installation;
The dynamical system(3)Including power control unit(5), energy-storage units(6), power unit(7), wherein:
The power control unit(5)With well site transformer(2)It is connected, well site electric energy is accessed;
The power control unit(5)For controlling energy-storage units(6)And power unit(7), power unit(7)Drive operation Working cell(4)Work, so as to complete workover treatment.
2. net electric power workover rig energy storage control system according to claim 1, it is characterized in that:The energy-storage units(6)For Energy storage components, specific form of energy includes electric energy or hydraulic pressure;Work as dynamical system(3)During for electric drive form, energy-storage units (6)It is battery and super capacitor;Work as dynamical system(3)During for hydraulic-driven form, energy-storage units(6)It is hydraulic accumulator.
3. the control method of net electric power workover rig energy storage control system described in a kind of claim 1, its step is:
Step A, sets the action setting value V of the DC voltage of net electric power workover rig energy storage control system0
Step B, by power control unit(5)The DC voltage value V monitored in real time1With action setting value V0It is compared, it is determined that Power unit(7)It is whether in running order;
Step C, when surveying DC voltage value >=action setting value, i.e.,:V1≥V0, power unit(7)In inoperative shape State, power control unit(5)It would automatically turn on energy-storage units(6)Charge mode, energy-storage units are transferred to by the energy for netting electric power supply (6)In;In energy-storage units(6)After fully charged, power control unit(5)It is automatic to close energy-storage units(6)Charge function;
Step D, when DC voltage value < acts setting value, i.e.,:V1< V0, dynamical system(3)Power unit(7)It is in Working condition, in power control unit(5)Under control, unit is powered by the energy of the electric power supply of net(7), while monitoring direct current The magnitude of voltage of side;Power control unit(5)It would automatically turn on energy-storage units(6)Discharge mode, by the electric power supply of net and energy-storage units (6)It is simultaneously power unit(7)Electric energy is provided;
Step E, when surveying DC voltage value >=action setting value, i.e.,:V1≥V0, power unit(7)In inoperative shape State, power control unit(5)Energy-storage units will be automatically turned on again(6)Charge mode, energy storage is transferred to by the energy for netting electric power supply Unit(6)In;In energy-storage units(6)After fully charged, power control unit(5)It is automatic to close energy-storage units(6)Charge function;
Step F, after charging complete, power control unit(5)It will turn off energy-storage units(6)Charge function, prepare it is next Individual working cycles;
According to the decentralization of well workover, lifting, shackle job requirements, step B- steps F moves in circles, until completing workover treatment, work Work terminates.
4. the control method of net electric power workover rig energy storage control system according to claim 3, it is characterized in that:The direct current The action setting value V of side voltage0Determined according to DC voltage, DC voltage is that well site standard power voltage is multiplied by DC side Voltage coefficient.
5. the control method of net electric power workover rig energy storage control system according to claim 4, it is characterized in that:When the well When field standard power voltage is 380V, DC voltage coefficient is
6. the control method of net electric power workover rig energy storage control system according to claim 5, it is characterized in that:The power Unit(7)Working condition refers to that workover rig is in lifting process;The power unit(7)Off working state refers to that workover rig is in Decentralization either shackle process.
7. the control method of net electric power workover rig energy storage control system according to claim 6, it is characterized in that:The step C is the decentralization operation process of workover rig;The step D is the lifting operation process of workover rig;The step E unloads for workover rig Button and/or decentralization operation process.
CN201710235871.5A 2017-04-12 2017-04-12 Energy storage control system and control method for net electric power workover rig Active CN106972610B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710235871.5A CN106972610B (en) 2017-04-12 2017-04-12 Energy storage control system and control method for net electric power workover rig

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710235871.5A CN106972610B (en) 2017-04-12 2017-04-12 Energy storage control system and control method for net electric power workover rig

Publications (2)

Publication Number Publication Date
CN106972610A true CN106972610A (en) 2017-07-21
CN106972610B CN106972610B (en) 2023-07-21

Family

ID=59332260

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710235871.5A Active CN106972610B (en) 2017-04-12 2017-04-12 Energy storage control system and control method for net electric power workover rig

Country Status (1)

Country Link
CN (1) CN106972610B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11955782B1 (en) 2022-11-01 2024-04-09 Typhon Technology Solutions (U.S.), Llc System and method for fracturing of underground formations using electric grid power

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201393176Y (en) * 2009-04-03 2010-01-27 中国石油集团渤海石油装备制造有限公司 Electric power system of electric workover rig
US20110297391A1 (en) * 2010-06-07 2011-12-08 Fielder Lance I Compact cable suspended pumping system for dewatering gas wells
CN205135462U (en) * 2015-12-02 2016-04-06 盘锦禹帝科技实业有限公司 Electronic workover rig of super capacitor energy storage formula
CN105525869A (en) * 2016-01-11 2016-04-27 中原特种车辆有限公司 Energy saving type power system and energy saving type sidetracking drilling machine
CN105811518A (en) * 2016-05-05 2016-07-27 湖南三石油科技有限公司 Lithium titanate battery energy storage and power supply system for workover rig and control method of lithium titanate battery energy storage and power supply system for workover rig
CN206673674U (en) * 2017-04-12 2017-11-24 中国石油集团渤海石油装备制造有限公司 Net electric power workover rig energy storage control system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201393176Y (en) * 2009-04-03 2010-01-27 中国石油集团渤海石油装备制造有限公司 Electric power system of electric workover rig
US20110297391A1 (en) * 2010-06-07 2011-12-08 Fielder Lance I Compact cable suspended pumping system for dewatering gas wells
CN205135462U (en) * 2015-12-02 2016-04-06 盘锦禹帝科技实业有限公司 Electronic workover rig of super capacitor energy storage formula
CN105525869A (en) * 2016-01-11 2016-04-27 中原特种车辆有限公司 Energy saving type power system and energy saving type sidetracking drilling machine
CN105811518A (en) * 2016-05-05 2016-07-27 湖南三石油科技有限公司 Lithium titanate battery energy storage and power supply system for workover rig and control method of lithium titanate battery energy storage and power supply system for workover rig
CN206673674U (en) * 2017-04-12 2017-11-24 中国石油集团渤海石油装备制造有限公司 Net electric power workover rig energy storage control system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11955782B1 (en) 2022-11-01 2024-04-09 Typhon Technology Solutions (U.S.), Llc System and method for fracturing of underground formations using electric grid power

Also Published As

Publication number Publication date
CN106972610B (en) 2023-07-21

Similar Documents

Publication Publication Date Title
CN105337397A (en) Drilling system and power supply method thereof
CN106761760A (en) The power shovel lifting system of electro-hydraulic combination drive
CN105811518B (en) Lithium titanate battery energy storage for power supply system and its control method for workover rig
CN108895017A (en) Multistage constant voltage compressed air energy memory
CN206673674U (en) Net electric power workover rig energy storage control system
CN104600759A (en) Cascade type electric field induction power supplying circuit
CN107013535A (en) A kind of pressure Self Matching energy utility system
CN111119757A (en) Energy storage workover rig
CN204646814U (en) A kind of energy recovery type hydraulic oil pumping machine hydraulic equipment
CN103114978A (en) Engineering machine and piezoelectric energy-absorbing power generation system for same
CN208634123U (en) It is directly driven using double pump and the hydraulic crawler excavator dynamical system of the automatic changing-over of differential F.F.
CN106972610A (en) Net electric power workover rig energy storage control system and its control method
CN212376607U (en) Energy storage workover rig
CN103326452A (en) Super-capacitor energy storage driving device of workover rig
CN205135462U (en) Electronic workover rig of super capacitor energy storage formula
CN107986196A (en) A kind of electri forklift potential energy regenerating unit
CN204465092U (en) Petroleum well servicing rig electric capacity energy storage type powersupply system
CN205283188U (en) Energy -conserving well electricity workover rig electrically controlled device
CN205296269U (en) Excavator swing arm potential energy regeneration system
CN207093298U (en) A kind of mining energy-saving emulsion power pack
CN203335537U (en) Energy recycling hydraulic system of working device
CN206533197U (en) A kind of workover rig energy-storage system based on super capacitor
CN204002625U (en) Energy storage type hybrid power well repairing machine
CN204851101U (en) Two atmospheric pressure driving system of electronic on -vehicle workover rig
CN205001262U (en) Hydraulic pressure generator auxiliary control ware

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20200929

Address after: 100120 Beijing Xicheng District six laying Kang

Applicant after: CHINA NATIONAL PETROLEUM Corp.

Applicant after: CNPC BOHAI EQUIPMENT MANUFACTURING Co.,Ltd.