CN106968432A - Super large cantilever balcony structure form bracing system and its construction method - Google Patents

Super large cantilever balcony structure form bracing system and its construction method Download PDF

Info

Publication number
CN106968432A
CN106968432A CN201710249528.6A CN201710249528A CN106968432A CN 106968432 A CN106968432 A CN 106968432A CN 201710249528 A CN201710249528 A CN 201710249528A CN 106968432 A CN106968432 A CN 106968432A
Authority
CN
China
Prior art keywords
steel slab
embedded steel
platform
fixedly connected
lumps
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710249528.6A
Other languages
Chinese (zh)
Inventor
杜俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201710249528.6A priority Critical patent/CN106968432A/en
Publication of CN106968432A publication Critical patent/CN106968432A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/06Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for stairs, steps, cornices, balconies, or other parts corbelled out of the wall
    • E04G13/066Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for stairs, steps, cornices, balconies, or other parts corbelled out of the wall for overhangs

Abstract

The invention discloses super large cantilever balcony structure form bracing system and its construction method, the bottom of cast-in-place concrete floor plates can be located at ground in the present invention, can also be located in the air, and the program, which overcomes traditional structure and method, cannot face the empty defect set up;Template in the present invention, the secondary beam lumps of wood, the girder lumps of wood, vertical rod, horizon bar, horizontal girder steel platform, bearing diagonal, the first pre-embedded steel slab, the second pre-embedded steel slab, the 3rd pre-embedded steel slab, the scheme of the horizontal girder steel platform of corner and corner support frame save material, while the construction period is shorter, firmness is higher.

Description

Super large cantilever balcony structure form bracing system and its construction method
Technical field
The invention belongs to the realm of building construction, more particularly to super large cantilever balcony structure form bracing system and its construction party Method.
Background technology
With the progress in epoch, the requirement more and more higher to quality of the life now, people are to houses such as lake scape or seascapes Interest is more and more denseer, present invention relates particularly to super large cantilever balcony monolithic reinforced concrete structure, and traditional solution is applied Work structures and methods need to set up upwards in layer, so there is that the construction period is longer, firmness is not high enough and cost is high Defect, traditional structure and method cannot more face sky and set up.
The content of the invention
The technical problems to be solved by the invention are:The constructing structure and method of traditional solution need in layer to On set up, so there is the defect that the construction period is longer, firmness is not high enough and cost is high.
In order to solve the above-mentioned technical problem, the invention discloses super large cantilever balcony structure form bracing system, including it is existing Pouring concrete floor plates, the cast-in-place concrete floor plates include upper strata, middle level, bottom and corner vertical level, and the bottom is long Degree less than upper strata or middle level length, in addition to template, the secondary beam lumps of wood, the girder lumps of wood, vertical rod, horizon bar, horizontal girder steel platform, Bearing diagonal, the first pre-embedded steel slab, the second pre-embedded steel slab, the 3rd pre-embedded steel slab, the horizontal girder steel platform of corner and corner support frame;Institute Template is stated below upper strata, the secondary beam lumps of wood is uniformly distributed in below template, the girder lumps of wood is located under the secondary beam lumps of wood Side;First pre-embedded steel slab is located at bottom front end, and the 3rd pre-embedded steel slab is horizontally placed on middle level rear end, and described second is pre- Steel plate is buried to be fixed on vertically on the 3rd pre-embedded steel slab;The horizontal girder steel platform is arranged at middle level upper surface, and its one end, which is fixed, to be connected The second pre-embedded steel slab is connected to, it is free end that the other end, which stretches out middle level,;By vertical rod between the girder lumps of wood and horizontal girder steel platform It is fixedly connected, horizon bar is fixedly connected with the vertical rod, the vertical rod root is connected with bar of sweeping the floor;The bearing diagonal is I-shaped Girder steel, its one end is fixedly connected on the first pre-embedded steel slab, and the other end is fixedly connected on the bottom of horizontal girder steel platform free end front end Portion;The bearing diagonal includes two in rotation angle position, and one root is in the identical setting in common position, and another one end is fixedly connected on First pre-embedded steel slab, the other end is fixedly connected on lower section in the middle part of middle level, and the corner support frame includes 1~5 channel-section steel, and it is fixed It is connected between two bearing diagonals of rotation angle position.
It is preferred that, be additionally provided with provisional protection frame above the horizontal girder steel platform free end, the provisional protection frame in Horizon bar is fixedly connected.
It is preferred that, it is fixedly connected between the vertical rod, horizon bar and provisional protection frame by fastener.
The invention also discloses the construction method of super large cantilever balcony structure form bracing system, comprise the following steps:
Step one:First pre-embedded steel slab, the second pre-embedded steel slab and the 3rd pre-embedded steel slab are installed;
Step 2:Set up horizontal steel I-beam platform and bearing diagonal;Set up the horizontal girder steel platform of corner and corner support frame;
Step 3:The vertical rod of the balcony support system is erected on horizontal steel I-beam platform;
Step 4:Balcony support system is built, vertical rod, horizon bar, bar of sweeping the floor are installed and connect integral.With prior art Compare, the present invention can obtain following technique effect:
(1) bottom of cast-in-place concrete floor plates can be located at ground in the present invention, can also be located at aerial, the program gram The empty defect set up cannot be faced by having taken traditional structure and method.
(2) template, the secondary beam lumps of wood, the girder lumps of wood, vertical rod, horizon bar, horizontal girder steel platform, bearing diagonal, the in the present invention One pre-embedded steel slab, the second pre-embedded steel slab, the 3rd pre-embedded steel slab, the horizontal girder steel platform of corner and corner support frame scheme need not Concrete building surface intensity is waited to come up can construct completely, so as to significantly shorten the duration, it is ensured that the stabilization of support body, while top Load is delivered to horizontal steel I-beam platform, in order to ensure indeformable horizontal girder steel platform and horizontal girder steel external end head and I-steel Diagonal brace is welded, and I-steel diagonal brace bottom and pre-embedded steel slab are welded, make whole stress be smoothly delivered to it is non-encorbelment on balcony, both protected Demonstrate,prove cast-in-place concrete floor not to be destroyed, in turn ensure that the stabilization of support muscle power;Conventional construction method be from lower floor toward upper strata, Steel pipe supporting system is set up layer by layer, increases material cost, while cause the duration longer, and because discontinuity may cause Intensity is not reaching to the Cracks On Concrete Floors of code requirement, causes later stage infiltration maintenance to spend, this programme saves material, simultaneously Construction period is shorter, firmness is higher.
(3) scheme of provisional protection frame plays a protective role, while further increasing entire firmness.
(4) construction method of the invention rationally, first sets up horizontal I-steel needing to set up on the floor face of support system Liang Pingtai, the scheme that balcony support system is then set up again reduces the duration, while having ensured firmness.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing There is the accompanying drawing used required in technology description to be briefly described, it should be apparent that, come for those of ordinary skill in the art Say, on the premise of not paying creative work, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is the common position schematic diagram of super large cantilever balcony structure form bracing system.
Fig. 2 is super large cantilever balcony structure form bracing system rotation angle position schematic diagram.
Wherein:1. template, the 2. secondary beam lumps of wood, the 3. girder lumps of wood, 4. vertical rods, 5. fasteners, 6. horizon bars, 7. sweep the floor bar, 8. Horizontal girder steel platform, 9. bearing diagonals, 10. first pre-embedded steel slabs, 11. second pre-embedded steel slabs, 12. the 3rd pre-embedded steel slabs, 13. corners Horizontal girder steel platform, 14. corner support framves, 15. cast-in-place concrete floor plates, 151. upper stratas, 152. middle levels, 153. bottoms, 16. Provisional protection frame.
Embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, with reference to embodiments, to the present invention It is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not used to Limit the present invention.
Below in conjunction with the accompanying drawings and specific embodiment to the present invention application principle be further described.
Embodiment one
As depicted in figs. 1 and 2, super large cantilever balcony structure form bracing system, including cast-in-place concrete floor plates 15, institute Stating cast-in-place concrete floor plates 15 includes upper strata 151, middle level 152, bottom 153 and corner vertical level 154, and the bottom 153 is grown Degree is less than the length in upper strata 151 or middle level 152, in addition to template 1, the secondary beam lumps of wood 2, the girder lumps of wood 3, vertical rod 4, horizon bar 6, water Flat girder steel platform 8, bearing diagonal 9, the first pre-embedded steel slab 10, the second pre-embedded steel slab 11, the 3rd pre-embedded steel slab 12, the horizontal girder steel of corner Platform 13 and corner support frame 14;The template 1 is located at the lower section of upper strata 151, and the secondary beam lumps of wood 2 is uniformly distributed under template 1 Side, the girder lumps of wood 3 is located at the lower section of the secondary beam lumps of wood 2;First pre-embedded steel slab 10 is located at the front end of bottom 153, the described 3rd Pre-embedded steel slab 12 is horizontally placed on the rear end of middle level 152, and second pre-embedded steel slab 11 is fixed on the 3rd pre-embedded steel slab 12 vertically; The horizontal girder steel platform 8 is arranged at the upper surface of middle level 152, and its one end is fixedly connected on the second pre-embedded steel slab 11, and the other end is stretched Go out middle level 152 for free end;It is fixedly connected between the girder lumps of wood 3 and horizontal girder steel platform 8 by vertical rod 4, in the vertical rod 4 Horizon bar 6 is fixedly connected with, the root of vertical rod 4 is connected with bar 7 of sweeping the floor;The bearing diagonal 9 is steel I-beam, and its one end is fixed The first pre-embedded steel slab 10 is connected to, the other end is fixedly connected on the bottom of the horizontal free end front end of girder steel platform 8;The bearing diagonal 9 include two in rotation angle position, and one root is in the identical setting in common position, and another one end is fixedly connected on the first pre-embedded steel slab 10, the other end is fixedly connected on the middle part of middle level 152 lower section, and the corner support frame 14 includes 3 channel-section steels, and it, which is fixedly connected on, turns Between two bearing diagonals 9 of angular position.
Wherein:Provisional protection frame 16, the provisional protection frame 16 are additionally provided with above the horizontal free end of girder steel platform 8 It is fixedly connected in horizon bar 6;It is fixedly connected between the vertical rod 4, horizon bar 6 and provisional protection frame 16 by fastener 5.
The horizontal girder steel platform 8 is No. 18 I-steel;Bearing diagonal 9 is No. 16 I-steel.
As the deformation originally implemented, integer root channel-section steel during the corner support frame 14 includes 1 to 5.
Embodiment two
According to the construction method of the super large cantilever balcony structure form bracing system of the structure of embodiment one, including following step Suddenly:
Step one:First pre-embedded steel slab 10, the second pre-embedded steel slab 11 and the 3rd pre-embedded steel slab 12 are installed;
Step 2:Set up horizontal steel I-beam platform 8 and bearing diagonal 9;Set up the horizontal girder steel platform 13 of corner and corner branch Support 14;
Step 3:The vertical rod 4 of the balcony support system is erected on horizontal steel I-beam platform 8;
Step 4:Balcony support system is built, it is integral that vertical rod 4, horizon bar 6, bar 7 of sweeping the floor are installed into connection.
The foregoing is only a preferred embodiment of the present invention, but protection scope of the present invention be not limited thereto, Any one skilled in the art the invention discloses technical scope in, technique according to the invention scheme and its Inventive concept is subject to equivalent substitution or change, should all be included within the scope of the present invention.

Claims (4)

1. super large cantilever balcony structure form bracing system, including cast-in-place concrete floor plates (15), the cast-in-place concrete building Laminate (15) includes upper strata (151), middle level (152), bottom (153) and corner vertical level (154), bottom (153) length Less than the length of upper strata (151) or middle level (152), it is characterised in that:Also include template (1), the secondary beam lumps of wood (2), the girder lumps of wood (3), vertical rod (4), horizon bar (6), horizontal girder steel platform (8), bearing diagonal (9), the first pre-embedded steel slab (10), the second pre-embedded steel slab (11), the horizontal girder steel platform (13) of the 3rd pre-embedded steel slab (12), corner and corner support frame (14);The template (1) is located at upper Below layer (151), the secondary beam lumps of wood (2) is uniformly distributed in below template (1), and the girder lumps of wood (3) is located at the secondary beam lumps of wood (2) lower section;First pre-embedded steel slab (10) is located at bottom (153) front end, and the 3rd pre-embedded steel slab (12) is horizontally placed on Middle level (152) rear end, second pre-embedded steel slab (11) is fixed on the 3rd pre-embedded steel slab (12) vertically;The horizontal girder steel is put down Platform (8) is arranged at middle level (152) upper surface, and its one end is fixedly connected on the second pre-embedded steel slab (11), and the other end stretches out middle level (152) it is free end;It is fixedly connected between the girder lumps of wood (3) and horizontal girder steel platform (8) by vertical rod (4), the vertical rod (4) horizon bar (6) is fixedly connected with, vertical rod (4) root is connected with bar of sweeping the floor (7);The bearing diagonal (9) is I-steel Beam, its one end is fixedly connected on the first pre-embedded steel slab (10), and the other end is fixedly connected on horizontal girder steel platform (8) free end front end Bottom;The bearing diagonal (9) includes two in rotation angle position, and one root is consolidated in the identical setting in common position, another one end Surely the first pre-embedded steel slab (10) is connected to, the other end is fixedly connected on lower section, the corner support frame (14) in the middle part of middle level (152) Including 1~5 channel-section steel, it is fixedly connected between two bearing diagonals (9) of rotation angle position.
2. super large cantilever balcony structure form bracing system according to claim 1, it is characterised in that:The horizontal girder steel Provisional protection frame (16) is additionally provided with above platform (8) free end, the provisional protection frame (16) is in the fixed company of horizon bar (6) Connect.
3. super large cantilever balcony structure form bracing system according to claim 2, it is characterised in that:The vertical rod (4), It is fixedly connected between horizon bar (6) and provisional protection frame (16) by fastener (5).
4. the construction method of the super large cantilever balcony structure form bracing system as described in claims 1 to 3, it is characterised in that Comprise the following steps:
Step one:First pre-embedded steel slab (10), the second pre-embedded steel slab (11) and the 3rd pre-embedded steel slab (12) are installed;
Step 2:Set up horizontal steel I-beam platform (8) and bearing diagonal (9);Set up the horizontal girder steel platform (13) of corner and corner Support frame (14);
Step 3:The vertical rod (4) of the balcony support system is erected on horizontal steel I-beam platform (8);
Step 4:Balcony support system is built, vertical rod (4), horizon bar (6), bar of sweeping the floor (7) are installed and connect integral.
CN201710249528.6A 2017-04-17 2017-04-17 Super large cantilever balcony structure form bracing system and its construction method Pending CN106968432A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710249528.6A CN106968432A (en) 2017-04-17 2017-04-17 Super large cantilever balcony structure form bracing system and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710249528.6A CN106968432A (en) 2017-04-17 2017-04-17 Super large cantilever balcony structure form bracing system and its construction method

Publications (1)

Publication Number Publication Date
CN106968432A true CN106968432A (en) 2017-07-21

Family

ID=59332969

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710249528.6A Pending CN106968432A (en) 2017-04-17 2017-04-17 Super large cantilever balcony structure form bracing system and its construction method

Country Status (1)

Country Link
CN (1) CN106968432A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108678144A (en) * 2018-07-18 2018-10-19 广州机施建设集团有限公司 Support system and its installation method for prefabricated balcony
CN115075530A (en) * 2022-07-01 2022-09-20 中亿丰建设集团股份有限公司 Cantilever structure and construction method thereof
CN108678144B (en) * 2018-07-18 2024-04-30 广州机施建设集团有限公司 Support system for prefabricated balcony and installation method thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103993735A (en) * 2014-06-06 2014-08-20 山东义泰建设工程有限公司 Support system of roof inclined beam and slab cantilever structure and construction method of support system
CN105442839A (en) * 2015-09-06 2016-03-30 上海建工七建集团有限公司 Erecting method of cantilever structure formwork bent
CN106150088A (en) * 2016-08-11 2016-11-23 上海嘉实(集团)有限公司 Large cantilever beam slab combined type formwork system and construction method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103993735A (en) * 2014-06-06 2014-08-20 山东义泰建设工程有限公司 Support system of roof inclined beam and slab cantilever structure and construction method of support system
CN105442839A (en) * 2015-09-06 2016-03-30 上海建工七建集团有限公司 Erecting method of cantilever structure formwork bent
CN106150088A (en) * 2016-08-11 2016-11-23 上海嘉实(集团)有限公司 Large cantilever beam slab combined type formwork system and construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
吴少平: "超高大悬臂阳台结构模板支撑体系施工技术", 《建筑技术》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108678144A (en) * 2018-07-18 2018-10-19 广州机施建设集团有限公司 Support system and its installation method for prefabricated balcony
CN108678144B (en) * 2018-07-18 2024-04-30 广州机施建设集团有限公司 Support system for prefabricated balcony and installation method thereof
CN115075530A (en) * 2022-07-01 2022-09-20 中亿丰建设集团股份有限公司 Cantilever structure and construction method thereof
CN115075530B (en) * 2022-07-01 2024-03-22 中亿丰建设集团股份有限公司 Cantilever structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN107090975B (en) Formwork erecting construction method for ultrahigh large-span concrete cast-in-place beam bailey truss
CN102839678B (en) Structure for improving rigidity and stability of foundation pit steel support
CN107419824A (en) The full precast shear wall structural system of regenerative steel skeleton and construction method
CN104480922B (en) Space truss formwork system and construction method thereof
CN104790681B (en) A kind of prevent unstability outside body of wall face from causing the device that masonry structure building earthquake is collapsed
CN107989447A (en) A kind of large-scale earthing concrete tank dome steel support structure and installation method
CN203441073U (en) Hoop-type high-altitude guard platform suitable for super high-rise building outline boarder structural column
CN103352428A (en) Suspension bridge cable bent tower beam non-support construction method
CN205775852U (en) A kind of active force conversion support for steel structure support moulding bed top
CN107435335A (en) Brick retaining wall steel bar girder hardened system and method on foundation pit enclosure top beam
CN103321155B (en) Viaduct pier operation platform system and build this system and pour into a mould the method for bridge pier
CN206438529U (en) Beam and slab type raft foundation formwork support structure
CN203213021U (en) Large-span non-ground type cast-in-place beam falsework
CN207017483U (en) The full precast shear wall structural system of regenerative steel skeleton
CN106032704A (en) Construction method for using concrete columns to support structures on both sides of post-pouring strip
CN212507296U (en) High formwork system
CN103147573B (en) Natatorium roof beam slab high formwork construction method
CN106968432A (en) Super large cantilever balcony structure form bracing system and its construction method
CN207847150U (en) A kind of temporary facility for being used for structural demolition and rebuilding
CN205369229U (en) But walking hoisting frame suitable for manual hole digging pile steel reinforcement cage is laid
CN209603163U (en) A kind of tower crane bearing platform ruggedized construction
CN111236632A (en) Construction method of heavy bracket and profile steel combined supporting system for super-thick top plate
CN207244633U (en) Brick retaining wall steel bar girder hardened system on foundation pit enclosure top beam
CN108104506A (en) It is a kind of to be used for structural demolition and the temporary facility rebuilded and its construction method
CN108755701A (en) The construction method of the support construction of deep basal pit

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170721