CN106958281A - Blowdown tubular construction - Google Patents

Blowdown tubular construction Download PDF

Info

Publication number
CN106958281A
CN106958281A CN201710271786.4A CN201710271786A CN106958281A CN 106958281 A CN106958281 A CN 106958281A CN 201710271786 A CN201710271786 A CN 201710271786A CN 106958281 A CN106958281 A CN 106958281A
Authority
CN
China
Prior art keywords
purification
infiltration
storage tank
tubular construction
liquid storage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710271786.4A
Other languages
Chinese (zh)
Other versions
CN106958281B (en
Inventor
温月强
黄尧舜
黄丕勇
谭将
陈小锋
饶伟忠
黄丕和
雷明河
罗远良
李振良
李光明
黄子奇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Hengda Hose Product Co Ltd
Original Assignee
Guangdong Hengda Hose Product Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Hengda Hose Product Co Ltd filed Critical Guangdong Hengda Hose Product Co Ltd
Priority to CN201710271786.4A priority Critical patent/CN106958281B/en
Publication of CN106958281A publication Critical patent/CN106958281A/en
Application granted granted Critical
Publication of CN106958281B publication Critical patent/CN106958281B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • CCHEMISTRY; METALLURGY
    • C02TREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02FTREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02F3/00Biological treatment of water, waste water, or sewage
    • C02F3/32Biological treatment of water, waste water, or sewage characterised by the animals or plants used, e.g. algae
    • CCHEMISTRY; METALLURGY
    • C02TREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02FTREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02F2101/00Nature of the contaminant
    • C02F2101/10Inorganic compounds
    • C02F2101/20Heavy metals or heavy metal compounds
    • CCHEMISTRY; METALLURGY
    • C02TREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02FTREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02F2103/00Nature of the water, waste water, sewage or sludge to be treated
    • C02F2103/06Contaminated groundwater or leachate
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W10/00Technologies for wastewater treatment
    • Y02W10/10Biological treatment of water, waste water, or sewage

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Water Supply & Treatment (AREA)
  • Hydrology & Water Resources (AREA)
  • Biotechnology (AREA)
  • Public Health (AREA)
  • Health & Medical Sciences (AREA)
  • Botany (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Microbiology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Organic Chemistry (AREA)
  • Filtration Of Liquid (AREA)
  • Sewage (AREA)

Abstract

A kind of blowdown tubular construction, including accommodating component, drain assembly and purification assembly.Accommodating component includes liquid storage tank and accumulation pond, and accumulation pond is arranged in liquid storage tank, and accumulation pond is used for heap garbage, and accumulation pond offers multiple infiltration outlets, and each infiltration outlet is connected with liquid storage tank respectively.Drain assembly includes multiple drainpipes, and each drainpipe spread configuration is connected with corresponding two infiltration outlets respectively in the bottom in accumulation pond, the two ends of each drainpipe.Purification assembly includes multiple purification plantation cylinders, each purification plantation cylinder is arranged at intervals at the bottom of liquid storage tank, in a purification plantation cylinder, purification growing area is provided with purification plantation cylinder, the side wall of purification plantation cylinder offers multiple infiltration entrance holes, and each infiltration entrance hole is connected with liquid storage tank and purification growing area respectively.Above-mentioned blowdown tubular construction can mitigate the pollution problem of content of beary metal is higher and moisture is higher rubbish to environment, be extremely applicable to use in family, community and small business.

Description

Blowdown tubular construction
Technical field
The present invention relates to pipelaying techniques field, more particularly to a kind of blowdown tubular construction.
Background technology
At present, for the rubbish that some content of beary metal are higher and moisture is higher, if directly abandoning out of doors, External environment condition is directly seated in, is easy to cause the heavy metal contained in these rubbish to leak into soil and rivers, so that The problem of causing environmental pollution.Especially the ring of bulky refuse processing system is laid in the so inconvenience of family, community and small business Border, above mentioned problem is particularly acute.
The content of the invention
Based on this, it is necessary to which providing a kind of can mitigate content of beary metal is higher and moisture is higher rubbish to ring The pollution problem in border, and the blowdown tubular construction used suitable for family, community and small business.
A kind of blowdown tubular construction, including:
Accommodating component, the accommodating component includes liquid storage tank and accumulation pond, and the accumulation pond is arranged in the liquid storage tank, The accumulation pond is used for heap garbage, and the accumulation pond offers multiple infiltration outlets, each infiltration outlet respectively with The liquid storage tank connection;
Drain assembly, the drain assembly includes multiple drainpipes, and each drainpipe spread configuration is in the accumulation pond Bottom, the two ends of each drainpipe respectively with the corresponding two infiltration outlets connections;And
Purification assembly, the purification assembly includes multiple purification plantation cylinders, and each purification plantation cylinder is arranged at intervals at institute The bottom of liquid storage tank is stated, in a purification plantation cylinder, purification growing area is provided with the purification plantation cylinder, it is described net The side wall for changing plantation cylinder offers multiple infiltration entrance holes, each infiltration entrance hole respectively with the liquid storage tank and described net Change growing area connection.
In wherein one embodiment, the accumulation pond is located at the medium position of the liquid storage tank.
In wherein one embodiment, the height of the liquid storage tank is less than the height in the accumulation pond.
It is equal per the distance between the two neighboring infiltration outlet in wherein one embodiment.
In wherein one embodiment, the accumulation pond has hollow rectangular structure, the length of the drainpipe and institute The width for stating accumulation pond is identical.
In wherein one embodiment, the accumulation pond had and set at garbage inlet, the garbage inlet position There is cover plate.
In wherein one embodiment, each drainpipe is arranged in parallel.
In wherein one embodiment, the purification plantation cylinder has hollow round tubular structure, and position is planted in the purification Inside the purification plantation cylinder.
In wherein one embodiment, the purification plantation cylinder is internally provided with support frame, and support frame as described above has spiral Shape structure.
In wherein one embodiment, the surface of support frame as described above, which is additionally provided with, multiple has twist structured support bar.
Above-mentioned blowdown tubular construction is included by setting accommodating component, drain assembly and purification assembly, when content of beary metal compared with When the high and higher dumping of moisture is in accommodating component, the most of heavy metal contained in these rubbish can be with Infiltration outflow, afterwards, then is assembled by drain assembly, is discharged again by drain assembly afterwards, purification assembly is used for plantation pair The water plant of plantation is used to absorb and arranged out of drain assembly in the preferable water plant of Metal uptake effect, i.e. purification assembly The infiltration containing heavy metal gone out, i.e., the heavy metal contained in infiltration is enriched with water plant, so as to mitigate weight Pollution problem of the rubbish that tenor is higher and moisture is higher to environment.Also need to it is emphasized that above-mentioned row Dirty tubular construction is simply compact, the applied environment of bulky refuse processing system is laid for some inconvenience, above-mentioned blowdown tubular construction is all It can be competent at, for example, above-mentioned blowdown tubular construction is extremely applicable to use in family, community and small business.
Brief description of the drawings
Fig. 1 is the structural representation of the blowdown tubular construction of an embodiment of the present invention;
Fig. 2 is the structural representation of the novel pipeline shown in Fig. 1;
Fig. 3 is enlarged drawing of the novel pipeline at A shown in Fig. 2.
Embodiment
For the ease of understanding the present invention, the present invention is described more fully below with reference to relevant drawings.In accompanying drawing Give the better embodiment of the present invention.But, the present invention can be realized in many different forms, however it is not limited to herein Described embodiment.On the contrary, the purpose for providing these embodiments is to make to understand more the disclosure Plus it is thorough comprehensive.
It should be noted that when element is referred to as " being fixed on " another element, it can be directly on another element Or can also have element placed in the middle.When an element is considered as " connection " another element, it can be directly connected to To another element or it may be simultaneously present centering elements.Term as used herein " vertical ", " level ", " left side ", For illustrative purposes only, it is unique embodiment to be not offered as " right side " and similar statement.
Unless otherwise defined, all of technologies and scientific terms used here by the article is with belonging to technical field of the invention The implication that technical staff is generally understood that is identical.Used term is intended merely to describe specific reality in the description of the invention Apply the purpose of mode, it is not intended that in the limitation present invention.Term as used herein " and/or " including one or more related The arbitrary and all combination of Listed Items.
Referring to Fig. 1, blowdown tubular construction 10 includes:Accommodating component 100, drain assembly 200 and purification assembly 300, draining Component 200 and purification assembly 300 are respectively arranged on accommodating component 100, and accommodating component 100 is higher for stacking content of beary metal And the higher rubbish of moisture, when content of beary metal is higher and the higher dumping of moisture is in accommodating component When in 100, contained most of heavy metal can flow out with infiltration in these rubbish, afterwards, then be carried out by drain assembly 200 Aggregation, is discharged by drain assembly 200 again afterwards, and purification assembly 300 is used to plant the preferably aquatic plant of heavy metal assimilation effect The water plant of plantation is used to absorb from drain assembly in thing, the water plant such as duckweed and water hyacinth, i.e. purification assembly 300 The infiltration containing heavy metal of discharge in 200, i.e., the heavy metal contained in infiltration is enriched with water plant, so as to Pollution problem of the mitigation rubbish that content of beary metal is higher and moisture is higher to environment.Also need to it is emphasized that Above-mentioned blowdown tubular construction 10 is simple and compact for structure, and the applied environment of bulky refuse processing system is laid for some inconvenience, above-mentioned Blowdown tubular construction 10 can be competent at, for example, above-mentioned blowdown tubular construction 10 is extremely applicable to make in family, community and small business With.
Referring to Fig. 1, accommodating component 100 includes liquid storage tank 110 and accumulation pond 120, the accumulation pond 120 is arranged at described In liquid storage tank 110, also it is understood that the accumulation pond 120 is arranged in the liquid storage tank 110 or the accumulation pond 120 is set On the bottom for being placed in the liquid storage tank 110, the accumulation pond 120 is used for heap garbage, and be particularly suitable for use in stacking content of beary metal The higher rubbish of higher and moisture, for example, these rubbish come from family, community and small business.It is deposited in accumulation pond The infiltration that rubbish in 120 oozes out is flowed out in liquid storage tank 110 by accumulating pond 120 again, then by being stored in liquid storage tank 110, So as to which purification assembly 300 of being more convenient for carries out follow-up heavy metal treatment and purification operation.
Referring to Fig. 1, accumulation pond 120 offer it is multiple infiltration outlets 121, it is each it is described infiltration outlet 121 respectively with The liquid storage tank 110 is connected, so, and liquid storage tank 110 is expelled to by the outlet 121 that seeps water by accumulating aggregation infiltration in pond 120 It is interior.
In one embodiment, the accumulation pond is located at the medium position of the liquid storage tank;And for example, the height of the liquid storage tank Height of the degree less than the accumulation pond;And for example, it is equal per the distance between the two neighboring infiltration outlet;And for example, it is described Accumulation pond has hollow rectangular structure, and the length of the drainpipe is identical with the width in the accumulation pond, so, is more conducive to ooze The discharging operation of water and the storage of infiltration;And for example, the accumulation pond has at garbage inlet, the garbage inlet position Cover plate is provided with, so, is more beneficial for covering the accumulation pond.
Referring to Fig. 1, drain assembly 200 includes multiple drainpipes 210, each spread configuration of drainpipe 210 is in described The bottom in pond 120 is accumulated, the two ends of each drainpipe 210 are connected with the corresponding two infiltration outlets 121 respectively, So, the infiltration that the rubbish of accumulation oozes out in accumulation pond 120 can flow to bottom, and separately flow into each drainpipe 210, these Infiltration is assembled in each drainpipe 210, finally, is expelled to by infiltration outlet 121 in liquid storage tank 110, so as to be more convenient for Purification assembly 300 carries out follow-up heavy metal treatment and purification operation.
For example, the body offers multiple infiltration access aperture;The support component is placed on outside the body, each described Infiltration access aperture is connected with the support component respectively;The barrier component is arranged in the support component, the barrier group Part includes multiple grille strips, and each grille strip is connected with the support component respectively, and the body has hollow round tubular knot Structure, each grille strip is radially distributed with the central axis of the body, is set between every two neighboring grille strip There is infiltration area, each infiltration area is connected with the support component respectively;And for example, referring to Fig. 3, in a drainpipe In 210, drainpipe 210 includes:Body 211, support component 212 and barrier component 213, support component 212 are arranged at body 211 On, barrier component 213 is arranged in support component 212, support component 212 and barrier component 213 be used to reducing rubbish directly with Body 210 is contacted, but can cause the infiltration that rubbish oozes out by support component 212 and barrier component 213, and flows into body Inside 211.Also referring to Fig. 1, the two ends of body 211 are connected with the corresponding two infiltration outlets 121 respectively, described Body 211 offers multiple infiltration access aperture 211a, and the infiltration that rubbish oozes out flows into body by each infiltration access aperture 211a In 211, and assembled by body 211.The support component 212 is placed on outside the body, each infiltration access aperture 211a is connected with the support component 212 respectively, and the barrier component 213 is arranged in the support component 212, the support Component 212 includes multiple support twisted piece 212a, each support twisted piece 212a and is set in turn in the lateral wall of the body 211 On, each support twisted piece 212a is linked in sequence the helical structure to be formed and be placed on outside the body 211, per two neighboring institute State support twisted piece 212a correspondences and surround the antifouling area 212b of a rubbish, each infiltration access aperture 211a correspondences and rubbish described in one The antifouling area 212b connections of rubbish, so, in the antifouling area 212b of a rubbish, two adjacent support twisted piece 212a can prop up rubbish Rubbish, is directly entered to the antifouling area 212b of rubbish so as to reduce rubbish, meanwhile, the infiltration that rubbish oozes out can flow into rubbish again In antifouling area 212b, and then flowed into from infiltration access aperture 211a in body 211, so that infiltration access aperture 211a It is difficult to be blocked by rubbish.The barrier component 213 include multiple grille strip 213a, each grille strip 213a respectively with each institute Support twisted piece 212a connections are stated, the body has hollow round tubular structure, also referring to Fig. 2, each grille strip 213a Radially distributed with the central axis of the body 211, infiltration area is provided between every two neighboring grille strip 213a 213b, each infiltration area 213b are connected with each antifouling area 213a of rubbish respectively, so, by setting barrier component 213 can further reduce the problem of infiltration access aperture 211a is blocked by rubbish.
It is important to note that the support component for being designed and being made up of each support twisted piece 212a by helical structure 212, which not only overcome conventional discharge pipe, directly sets filter screen in infiltration access aperture or barrier cylinder is directly nested with outside and is led The free space that the infiltration access aperture of cause is neighbouring is smaller, and the easily accumulation of the tiny granulated garbage of particle diameter is full of infiltration access aperture free zone Domain, is unfavorable for the problem of infiltration enters, and the rubbish that respectively support twisted piece 212a can also be tiny to particle diameter aqueous in flowing Particle plays guiding function, it is flowed out to outside drainpipe 210, and respectively support twisted piece 212a can play obstruction work to rubbish With, and guiding function is played to infiltration, it is more conducive to flow into the infiltration access aperture.
In one embodiment, each drainpipe is arranged in parallel;And for example, per it is two neighboring it is described infiltration access aperture it Between distance it is equal;And for example, infiltration access aperture has borehole structure or square hole structure;And for example, per the two neighboring grille strip Between spacing it is equal;And for example, the grille strip has arcuate structure;And for example, the diameter of the body is distinguished with the body Equal to the distance between each grille strip, so, more conducively infiltration enters and played the problem of mitigation rubbish is blocked;Again Such as, the novel pipeline also includes micro pump, and the micro pump is connected with the body, in such manner, it is possible to be more conducive to extract out Infiltration in the body;And for example, the length of the grille strip is identical with the length of the body;And for example, the grille strip bag Barrier body and inner core are included, the inner core is placed in the barrier body;And for example, reinforcement is provided with the grille strip, The bearing of trend of the reinforcement is identical with the bearing of trend of the grille strip, and the grille strip is strengthened in such manner, it is possible to play Structural strength.
Referring to Fig. 1, purification assembly described in purification assembly 300 includes multiple purification plantation cylinders 310, each purification plantation Cylinder is arranged at intervals at the bottom of the liquid storage tank, in a purification plantation cylinder, is provided with the purification plantation cylinder net Change growing area, the side wall of purification plantation cylinder offers multiple infiltration entrance holes, each infiltration entrance hole respectively with institute Liquid storage tank and purification growing area connection are stated, so, by by the preferable water plant of heavy metal assimilation effect, for example, By the way that duckweed and water hyacinth etc. are planted in purification plantation cylinder 310, flowed into from infiltration entrance hole in purification plantation cylinder 310 Infiltration containing heavy metal carries out absorption cleaning by these water plants, i.e., the heavy metal contained in infiltration is obtained in water plant To enrichment, so as to mitigate the pollution problem of content of beary metal is higher and moisture is higher rubbish to environment.
For example, the purification plantation cylinder has hollow round tubular structure, the purification growing area is located at the purification plantation Cylinder is internal;And for example, the purification plantation cylinder is internally provided with support frame, and support frame as described above has helical structure;And for example, it is described The surface of support frame be additionally provided with it is multiple have twist structured support bar, in such manner, it is possible to preferably be propped up water plant Support.
Above-mentioned blowdown tubular construction 10 is included by setting accommodating component 100, drain assembly 200 and purification assembly 300, when weight When the dumping that tenor is higher and moisture is higher is in accommodating component 100, in these rubbish contain it is big Part heavy metal can flow out with infiltration, afterwards, then be assembled by drain assembly 200, afterwards again by the row of drain assembly 200 Go out, purification assembly 300 is used for the water for planting plantation in the preferable water plant of heavy metal assimilation effect, i.e. purification assembly 300 Plant is used for the infiltration containing heavy metal for absorbing the discharge out of drain assembly 200, i.e., the heavy metal contained in infiltration is in water It is enriched with plant, so as to mitigate the pollution of content of beary metal is higher and moisture is higher rubbish to environment Problem.Also need to it is emphasized that above-mentioned blowdown tubular construction 10 is simple and compact for structure, for some inconvenience laying bulky refuses The applied environment of processing system, above-mentioned blowdown tubular construction 10 can be competent at, for example, above-mentioned blowdown tubular construction 10 is extremely applicable to Used in family, community and small business.
For example, the barrier component also includes multiple connection straps, each connection strap distinguish described in adjacent two every Grizzly bar is connected, and the barrier component is formed in one structure, and the body and the support component being capable of relatively described barrier groups Part is rotated, and when the support component inner product has rubbish, then can pass through institute by rotating the body and the support component State support component helical structure, i.e., can be by the rubbish of these accumulation when the support component of described helical structure is rotated Rubbish is expelled to outside the barrier component.
Each technical characteristic of embodiment described above can be combined arbitrarily, to make description succinct, not to above-mentioned reality Apply all possible combination of each technical characteristic in example to be all described, as long as however, the combination of these technical characteristics is not deposited In contradiction, the scope of this specification record is all considered to be.
The above embodiment only expresses the several embodiments of the present invention, and it describes more specific and detailed, but Therefore the limitation to the scope of the claims of the present invention can not be interpreted as.It should be pointed out that for the ordinary skill people of this area For member, without departing from the inventive concept of the premise, various modifications and improvements can be made, these belong to the present invention's Protection domain.Therefore, the protection domain of patent of the present invention should be determined by the appended claims.

Claims (10)

1. a kind of blowdown tubular construction, it is characterised in that including:
Accommodating component, the accommodating component includes liquid storage tank and accumulation pond, and the accumulation pond is arranged in the liquid storage tank, described Accumulating pond is used for heap garbage, and the accumulation pond offers multiple infiltration outlets, each infiltration outlet respectively with it is described Liquid storage tank is connected;
Drain assembly, the drain assembly includes multiple drainpipes, and each drainpipe spread configuration is in the bottom in the accumulation pond Portion, the two ends of each drainpipe are connected with the corresponding two infiltration outlets respectively;And
Purification assembly, the purification assembly includes multiple purification plantation cylinders, and each purification plantation cylinder is arranged at intervals at the storage The bottom of liquid pool, in a purification plantation cylinder, purification growing area, the purification kind are provided with the purification plantation cylinder The side wall for planting cylinder offers multiple infiltration entrance holes, each infiltration entrance hole respectively with the liquid storage tank and the purification kind Growing area is connected.
2. blowdown tubular construction according to claim 1, it is characterised in that the accumulation pond is located at the middle part of the liquid storage tank At position.
3. blowdown tubular construction according to claim 2, it is characterised in that the height of the liquid storage tank is less than the accumulation pond Height.
4. blowdown tubular construction according to claim 1, it is characterised in that per between the two neighboring infiltration outlet Apart from equal.
5. blowdown tubular construction according to claim 1, it is characterised in that the accumulation pond has hollow rectangular structure, The length of the drainpipe is identical with the width in the accumulation pond.
6. blowdown tubular construction according to claim 1, it is characterised in that the accumulation pond has garbage inlet, described Garbage inlet is provided with cover plate at position.
7. blowdown tubular construction according to claim 1, it is characterised in that each drainpipe is arranged in parallel.
8. blowdown tubular construction according to claim 1, it is characterised in that the purification plantation cylinder has hollow round tubular knot Structure, the purification growing area is located inside the purification plantation cylinder.
9. blowdown tubular construction according to claim 1, it is characterised in that the purification plantation cylinder is internally provided with support Frame, support frame as described above has helical structure.
10. blowdown tubular construction according to claim 9, it is characterised in that the surface of support frame as described above is additionally provided with multiple With twist structured support bar.
CN201710271786.4A 2017-04-24 2017-04-24 Sewage pipe structure Active CN106958281B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710271786.4A CN106958281B (en) 2017-04-24 2017-04-24 Sewage pipe structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710271786.4A CN106958281B (en) 2017-04-24 2017-04-24 Sewage pipe structure

Publications (2)

Publication Number Publication Date
CN106958281A true CN106958281A (en) 2017-07-18
CN106958281B CN106958281B (en) 2019-09-03

Family

ID=59484267

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710271786.4A Active CN106958281B (en) 2017-04-24 2017-04-24 Sewage pipe structure

Country Status (1)

Country Link
CN (1) CN106958281B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1673122A (en) * 2005-04-14 2005-09-28 北京大学 Efficient ecological waste water treating apparatus and method
CN101143756A (en) * 2007-09-07 2008-03-19 崔玉波 In situ collection and ecological processing method and device for residential area domestic garbage station percolate
CN201978931U (en) * 2010-11-21 2011-09-21 周万松 Ecologically-utilizing system of garbage decomposing liquid
RU2014123764A (en) * 2014-06-10 2015-12-20 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Южно-Уральский государственный университет" (национальный исследовательский университет) (ФГБОУ ВПО "ЮУрГУ" (НИУ)) SEWAGE TREATMENT SYSTEM (OPTIONS)
CN105461073A (en) * 2015-11-23 2016-04-06 江苏省农业科学院 Eutrophication sewage purification simulation system
CN205436599U (en) * 2016-03-24 2016-08-10 轻工业环境保护研究所 Plant purification stock rubbish soil ooze filtrate collecting device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1673122A (en) * 2005-04-14 2005-09-28 北京大学 Efficient ecological waste water treating apparatus and method
CN101143756A (en) * 2007-09-07 2008-03-19 崔玉波 In situ collection and ecological processing method and device for residential area domestic garbage station percolate
CN201978931U (en) * 2010-11-21 2011-09-21 周万松 Ecologically-utilizing system of garbage decomposing liquid
RU2014123764A (en) * 2014-06-10 2015-12-20 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Южно-Уральский государственный университет" (национальный исследовательский университет) (ФГБОУ ВПО "ЮУрГУ" (НИУ)) SEWAGE TREATMENT SYSTEM (OPTIONS)
CN105461073A (en) * 2015-11-23 2016-04-06 江苏省农业科学院 Eutrophication sewage purification simulation system
CN205436599U (en) * 2016-03-24 2016-08-10 轻工业环境保护研究所 Plant purification stock rubbish soil ooze filtrate collecting device

Also Published As

Publication number Publication date
CN106958281B (en) 2019-09-03

Similar Documents

Publication Publication Date Title
US20100025312A1 (en) Debris cage
US8940170B2 (en) Triple-chambered wetland biofilter treatment system
CN105000672B (en) Drop radial-flow surface flow artificial marshland
CN209797618U (en) Rural sewage treatment plant
CA2747590C (en) Riser assembly for water storage chambers
CN1785857A (en) Mineralization ecological systen of sludge biological treatment
CN106958281B (en) Sewage pipe structure
US9328499B2 (en) Device for settlement of particles from a liquid
CN206706963U (en) It is a kind of can the anti-blocking multi-sealed deodorization of multilayer drain structure
US11459255B2 (en) Two-sided horizontal flow bioretention stormwater system
CN107166134B (en) Novel pipeline
DE102012011816A1 (en) Filters for aquariums, fish ponds, swimming pools, swimming ponds or the like
KR102106915B1 (en) A perforated-pipe
US9884780B2 (en) Wetland roof technology for treating domestic wastewater
CN208545896U (en) It is a kind of for storing the landscape flower box of rain water on roof
CN207553074U (en) Permeable PE pipes
CN203008063U (en) Straight tube type odor-resistant floor drain
CN208802907U (en) Rainwater buffers drop level purification system
CN110526409A (en) A kind of vertical multi-stage constructed wetland device
CN201165702Y (en) Drainage net ditch pipe
CN206467038U (en) A kind of landscape overflow channel of two-way purification
CN202850123U (en) Novel filter type outdoor impounding reservoir
KR102485815B1 (en) Non-powered rainwater filtration system
CN110521438A (en) Strengthen the assembled rainwater flower bed being detained
CN211816598U (en) Novel paddy field is irrigated with retaining device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant