CN106950440A - Transformer station's metering critical point quickly judges alarm method extremely - Google Patents

Transformer station's metering critical point quickly judges alarm method extremely Download PDF

Info

Publication number
CN106950440A
CN106950440A CN201710079450.8A CN201710079450A CN106950440A CN 106950440 A CN106950440 A CN 106950440A CN 201710079450 A CN201710079450 A CN 201710079450A CN 106950440 A CN106950440 A CN 106950440A
Authority
CN
China
Prior art keywords
power
metering
line
enter
loss
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710079450.8A
Other languages
Chinese (zh)
Other versions
CN106950440B (en
Inventor
李强
程方亮
石小帅
刘红丽
苏赞
刘兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yi Li Electric Co Of Guo Wang Xinjiang Power Co
State Grid Corp of China SGCC
Original Assignee
Yi Li Electric Co Of Guo Wang Xinjiang Power Co
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yi Li Electric Co Of Guo Wang Xinjiang Power Co, State Grid Corp of China SGCC filed Critical Yi Li Electric Co Of Guo Wang Xinjiang Power Co
Priority to CN201710079450.8A priority Critical patent/CN106950440B/en
Publication of CN106950440A publication Critical patent/CN106950440A/en
Application granted granted Critical
Publication of CN106950440B publication Critical patent/CN106950440B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/50Testing of electric apparatus, lines, cables or components for short-circuits, continuity, leakage current or incorrect line connections

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

It is that a kind of transformer station's metering critical point quickly judges alarm method extremely, it includes the first step the present invention relates to electric-power metering technical field, the electric quantity data in acquisition system database is extracted, second step formulates bus electric quantity balancing, line loss, the automatic calculation template of loss on transmission, 3rd step, target line metering critical point electric quantity data is calculated, the 4th step judges metering critical point with the presence or absence of abnormal, 5th step, alerted in time to keeper, the 6th step, the scene fortune timely defect elimination of inspection personnel.The present invention utilizes electricity report program system, day, which monitors, to be realized to transformer station's metering critical point of the whole network, abnormal metering critical point is searched in time and analysis advanced warning is carried out to abnormal critical point, be conducive to operation maintenance personnel on-call maintenance and realize accurate defect elimination, it is ensured that electric company's coulomb collection system gathers the accuracy of electric quantity data.

Description

变电站计量关口异常快速判断告警方法Method for quickly judging and alarming abnormalities of substation metering gates

技术领域technical field

本发明涉及电力计量技术领域,是一种变电站计量关口异常快速判断告警方法。The invention relates to the technical field of electric power metering, and relates to a method for quickly judging and alarming abnormality of a substation metering gate.

背景技术Background technique

目前,变电站计量关口电量数据正确与否关系到电量结算是否正确,关系到能否真实反映线损。现有的电能计量系统没有变电站计量关口异常告警功能,人工也没有足够的时间、精力去阅读分析其中的大量数据。目前变电站计量关口先出现故障或差错,再进行人工分析解决,延迟了问题的发现和处理,计量关口电能表计量差错将给供电双方造成巨大的经济损失。受到网内互感器设备检修或更换、二次设备改造等原因的影响,互感器及计量回路易发生变化,即电压、电流互感器接线端子至电镀屏表计端子之间容易出现变化,为确保计量关口的准确性,需要一种在计量关口出现异常后快速定位、判断及预警的方法。At present, whether the power data of the substation metering gateway is correct or not is related to whether the power settlement is correct or not, and whether it can truly reflect the line loss. The existing electric energy metering system does not have the abnormal alarm function of the substation metering gateway, and the manual labor does not have enough time and energy to read and analyze a large amount of data. At present, faults or errors occur at the metering gate of the substation first, and then manual analysis is carried out to solve the problem, which delays the discovery and treatment of the problem, and the measurement error of the electric energy meter at the metering gate will cause huge economic losses to both power supply parties. Affected by the maintenance or replacement of transformer equipment in the network, secondary equipment transformation, etc., transformers and metering circuits are prone to change, that is, changes are likely to occur between the terminals of voltage and current transformers and the meter terminals of the electroplating screen. To ensure The accuracy of the metering gate requires a method for quickly locating, judging and early warning when the metering gate is abnormal.

发明内容Contents of the invention

本发明提供了一种变电站计量关口异常快速判断告警的方法,克服了上述现有技术之不足,其能有效解决现有的变电站计量关口存在故障或差错时不能及时告警通知管理人员消缺的问题。The present invention provides a method for quickly judging and alarming the abnormality of the metering gate of the substation, which overcomes the above-mentioned deficiencies in the prior art, and can effectively solve the problem that the existing metering gate of the substation cannot timely alarm and notify the management personnel to eliminate the defect when there is a fault or error .

本发明的技术方案是通过以下措施来实现的:一种变电站计量关口异常快速判断告警方法,包括以下步骤:The technical solution of the present invention is achieved through the following measures: a method for quickly judging and alarming the abnormality of the substation metering gate, comprising the following steps:

第一步,提取电量采集系统数据库中的电量数据,在现有的计量报表数据库中查找得到目标线路的计量倍率、始码和底码,之后进入第二步;The first step is to extract the power data in the database of the power collection system, and find out the measurement magnification, initial code and bottom code of the target line in the existing metering report database, and then enter the second step;

第二步,按照“流入母线有功电量为反,流出母线有功电量为正”原则和计量装置本身“有功电量、无功电量正反四象限”计量特性,在电量报表程序系统中预先定义标记有功电量正反向,之后进入第三步;In the second step, according to the principle of "the active energy flowing into the bus is negative, and the active energy flowing out of the bus is positive" and the measurement characteristics of the metering device itself "positive and negative four quadrants of active energy and reactive energy", pre-define the marker active energy in the electricity report program system. The power is forward and reverse, and then enter the third step;

第三步,计算目标线路计量关口母线不平衡电量、线损、变损自动计算模板,The third step is to calculate the template for automatic calculation of unbalanced power, line loss, and variable loss of the target line metering gateway busbar,

(a)计量关口的有功电量数据,即有功电量=(底码-始码)×倍率,(2)以相邻两条电路的有功电量为基础计算得到变损及变损率,变损=(第一线路正向有功电量-第一线路反向有功电量)-(第二线路正向有功电量-第二线路反向有功电量),变损率=变损/第一线路正向有功电量×100%;(a) Active power data at the metering gate, that is, active power = (bottom code - initial code) × magnification, (2) Calculate the change loss and loss rate based on the active power of two adjacent circuits, and change loss = (Forward active energy of the first line - reverse active energy of the first line) - (Forward active energy of the second line - reverse active energy of the second line), change loss rate = change loss / forward active energy of the first line ×100%;

(b)以有功电量为基础计算得到母线不平衡电量及母线电量不平衡率;母线不平衡电量=∑(反向有功电量)-∑(正向有功电量),母线电量不平衡率=母线不平衡电量/∑(反向有功电量)×100%;(b) Calculate the unbalanced power of the bus and the unbalanced rate of the bus power based on the active power; Balance power/∑(reverse active power)×100%;

(c)以有功电量为基础计算得到线损电量及线损率,线损电量=(第一线路正向有功电量+第二线路反向有功电量)-(第一线路反向有功电量+第二线路反正向有功电量),线损率=线损电量/(第一线路正向有功电量+第二线路反向有功电量)×100%,之后进入第四步;(c) Calculate the line loss power and line loss rate based on the active power. Line loss power = (forward active power of the first line + reverse active power of the second line) - (reverse active power of the first line + second Line loss rate = line loss power / (forward active power of the first line + reverse active power of the second line) × 100%, and then enter the fourth step;

第四步,判断计量关口是否存在异常,根据第三步得到的电量数据,判定计量关口存在的异常情况,若存在异常,则执行(1)或/和(2)或/和(3)或/和(4):The fourth step is to determine whether there is an abnormality at the metering gate. According to the power data obtained in the third step, determine the abnormality of the metering gate. If there is an abnormality, perform (1) or/and (2) or/and (3) or // and (4):

(1)根据电流互感器倍率成倍的增加或减小,得出计量倍率错误,之后进入第五步;(1) According to the multiplied increase or decrease of the current transformer multiplier, it is obtained that the measurement multiplier is wrong, and then enter the fifth step;

(2)变电站表计具有正反四象限运行功能,每个相限对应不同计量工况,即有功正向、有功反向、无功正向、无功反向,若某一象限不是对应该象限的计量工况,则可以立即得出表计极性出现反向异常,之后进入第五步;(2) The substation meter has the function of positive and negative four-quadrant operation. Each phase corresponds to different metering conditions, that is, active power forward, active power reverse, reactive power forward, and reactive power reverse. If a quadrant does not correspond to In quadrant metering conditions, it can be immediately concluded that the polarity of the meter is reversed abnormally, and then enter the fifth step;

(3)利用母线电量不平衡判定计量关口异常,同时结合电能表中相电压、相电流的遥测量值,判断得出是回路接地或缺相、电压回路断线或电流回路短接,之后进入第五步;(3) Use the unbalanced power of the bus to determine the abnormality of the metering gate, and combine the remote measurement values of the phase voltage and phase current in the electric energy meter to determine whether the circuit is grounded or lack of phase, the voltage circuit is disconnected or the current circuit is shorted, and then enter the fifth step;

(4)若表计走码有数据但表计走慢,同时电压遥测量降低或为零,则判定回路接地或缺相;若表计走码无数据、断线电压遥测量为零且电流回路短接、电流遥测量为零,则判定为电压回路断线或电流回路短接,之后进入第五步;(4) If the meter running code has data but the meter runs slowly, and at the same time the voltage remote measurement is reduced or is zero, then it is determined that the circuit is grounded or a phase is missing; if the meter running code has no data, the disconnection voltage remote measurement is zero and the current If the circuit is short-circuited and the current remote measurement is zero, it is judged that the voltage circuit is disconnected or the current circuit is short-circuited, and then enter the fifth step;

若计量关口不存在异常情况,之后进入第七步;If there is no abnormal situation at the metering gate, then enter the seventh step;

第五步,向管理员及时告警,根据第四步判定计量关口存在的不同的异常情况通过网页提示告警的方式通知管理员或者发送告警短信通知现场运检人员,之后进入第六步;The fifth step is to alert the administrator in time, and according to the fourth step to determine the existence of different abnormal conditions at the metering gate, notify the administrator through the web page prompt alarm or send an alarm message to notify the on-site inspection personnel, and then enter the sixth step;

第六步,现场运检人员及时消缺,及时处理计量关口故障点,之后进入第七步;In the sixth step, the on-site inspection personnel eliminate the shortage in time, and deal with the fault points of the metering gate in time, and then enter the seventh step;

第七步,若计量关口还存在异常,则重复上述步骤;若计量关口正常,则结束。In the seventh step, if the metering gate is still abnormal, repeat the above steps; if the metering gate is normal, then end.

本发明利用电量报表程序系统,对全网的变电站计量关口实现日监测,及时查找异常计量关口并对异常关口进行分析提前告警,有利于运维人员及时维修并实现精确消缺,确保供电公司电量采集系统采集电量数据的准确性。The present invention utilizes the electricity report program system to realize daily monitoring of the metering gates of substations in the entire network, find abnormal metering gates in time and analyze the abnormal gates in advance and give an alarm in advance. Accuracy of power data collected by the collection system.

附图说明Description of drawings

附图1为本发明实施例1的方法流程图。Accompanying drawing 1 is the method flowchart of embodiment 1 of the present invention.

附图2为本发明实施例2的母线电量平衡示意图。Accompanying drawing 2 is the schematic diagram of the power balance of the busbar in Embodiment 2 of the present invention.

附图中的编号如下:D1为二西线计量关口,D2为西中线计量关口,D3为西坡线计量关口,D4为1号主变高侧计量关口,D5为2号主变高侧计量关口。The numbers in the attached drawings are as follows: D1 is the metering gate of the Second West Line, D2 is the metering gate of the West Middle Line, D3 is the metering gate of the West Slope Line, D4 is the high side metering gate of No. 1 main transformer, and D5 is the high side metering of No. 2 main transformer pass.

具体实施方式detailed description

本发明不受下述实施例的限制,可根据本发明的技术方案与实际情况来确定具体的实施方式。The present invention is not limited by the following examples, and specific implementation methods can be determined according to the technical solutions of the present invention and actual conditions.

在本发明中,为了便于描述,各部件的相对位置关系的描述均是根据说明书附图1的布图方式来进行描述的,如:前、后、上、下、左、右等的位置关系是依据说明书附图的布图方向来确定的。In the present invention, for the convenience of description, the description of the relative positional relationship of each component is described according to the layout of Figure 1 of the specification, such as: the positional relationship of front, rear, top, bottom, left, right, etc. It is determined according to the layout direction of the drawings in the description.

下面结合实施例及附图对本发明作进一步描述:Below in conjunction with embodiment and accompanying drawing, the present invention will be further described:

实施例1:如附图1所示,变电站计量关口异常快速判断告警方法包括以下步骤:Embodiment 1: As shown in the accompanying drawing 1, the abnormal rapid judgment and alarm method of the substation metering gate includes the following steps:

第一步,提取电量采集系统数据库中的电量数据,在现有的计量报表数据库中查找得到目标线路的计量倍率、始码和底码,之后进入第二步;The first step is to extract the power data in the database of the power collection system, and find out the measurement magnification, initial code and bottom code of the target line in the existing metering report database, and then enter the second step;

第二步,按照“流入母线有功电量为反,流出母线有功电量为正”原则和计量装置本身“有功电量、无功电量正反四象限”计量特性,在电量报表程序系统中预先定义标记有功电量正反向,之后进入第三步;In the second step, according to the principle of "the active energy flowing into the bus is negative, and the active energy flowing out of the bus is positive" and the measurement characteristics of the metering device itself "positive and negative four quadrants of active energy and reactive energy", pre-define the marker active energy in the electricity report program system. The power is forward and reverse, and then enter the third step;

第三步,计算目标线路计量关口母线不平衡电量、线损、变损自动计算模板,The third step is to calculate the template for automatic calculation of unbalanced power, line loss, and variable loss of the target line metering gateway busbar,

(a)计量关口的有功电量数据,即有功电量=(底码-始码)×倍率,(2)以相邻两条电路的有功电量为基础计算得到变损及变损率,变损=(第一线路正向有功电量-第一线路反向有功电量)-(第二线路正向有功电量-第二线路反向有功电量),变损率=变损/第一线路正向有功电量×100%;(a) Active power data at the metering gate, that is, active power = (bottom code - initial code) × magnification, (2) Calculate the change loss and loss rate based on the active power of two adjacent circuits, and change loss = (Forward active energy of the first line - reverse active energy of the first line) - (Forward active energy of the second line - reverse active energy of the second line), change loss rate = change loss / forward active energy of the first line ×100%;

(b)以有功电量为基础计算得到母线不平衡电量及母线电量不平衡率;母线不平衡电量=∑(反向有功电量)-∑(正向有功电量),母线电量不平衡率=母线不平衡电量/∑(反向有功电量)×100%;(b) Calculate the unbalanced power of the bus and the unbalanced rate of the bus power based on the active power; Balance power/∑(reverse active power)×100%;

(c)以有功电量为基础计算得到线损电量及线损率,线损电量=(第一线路正向有功电量+第二线路反向有功电量)-(第一线路反向有功电量+第二线路反正向有功电量),线损率=线损电量/(第一线路正向有功电量+第二线路反向有功电量)×100%,之后进入第四步;(c) Calculate the line loss power and line loss rate based on the active power. Line loss power = (forward active power of the first line + reverse active power of the second line) - (reverse active power of the first line + second Line loss rate = line loss power / (forward active power of the first line + reverse active power of the second line) × 100%, and then enter the fourth step;

第四步,判断计量关口是否存在异常,根据第三步得到的电量数据,判定计量关口存在的异常情况,若存在异常,则执行(1)或/和(2)或/和(3)或/和(4):The fourth step is to determine whether there is an abnormality at the metering gate. According to the power data obtained in the third step, determine the abnormality of the metering gate. If there is an abnormality, perform (1) or/and (2) or/and (3) or // and (4):

(1)根据电流互感器倍率成倍的增加或减小,得出计量倍率错误,之后进入第五步;(1) According to the multiplied increase or decrease of the current transformer multiplier, it is obtained that the measurement multiplier is wrong, and then enter the fifth step;

(2)变电站表计具有正反四象限运行功能,每个相限对应不同计量工况,即有功正向、有功反向、无功正向、无功反向,若某一象限不是对应该象限的计量工况,则可以立即得出表计极性出现反向异常,之后进入第五步;(2) The substation meter has the function of positive and negative four-quadrant operation. Each phase corresponds to different metering conditions, that is, active power forward, active power reverse, reactive power forward, and reactive power reverse. If a quadrant does not correspond to In quadrant metering conditions, it can be immediately concluded that the polarity of the meter is reversed abnormally, and then enter the fifth step;

(3)利用母线电量不平衡判定计量关口异常,同时结合电能表中相电压、相电流的遥测量值,判断得出是回路接地或缺相、电压回路断线或电流回路短接,之后进入第五步;(3) Use the unbalanced power of the bus to determine the abnormality of the metering gate, and combine the remote measurement values of the phase voltage and phase current in the electric energy meter to determine whether the circuit is grounded or lack of phase, the voltage circuit is disconnected or the current circuit is shorted, and then enter the fifth step;

(4)若表计走码有数据但表计走慢,同时电压遥测量降低或为零,则判定回路接地或缺相;若表计走码无数据、断线电压遥测量为零且电流回路短接、电流遥测量为零,则判定为电压回路断线或电流回路短接,之后进入第五步;(4) If the meter running code has data but the meter runs slowly, and at the same time the voltage remote measurement is reduced or is zero, then it is determined that the circuit is grounded or a phase is missing; if the meter running code has no data, the disconnection voltage remote measurement is zero and the current If the circuit is short-circuited and the current remote measurement is zero, it is judged that the voltage circuit is disconnected or the current circuit is short-circuited, and then enter the fifth step;

若计量关口不存在异常情况,之后进入第七步;If there is no abnormal situation at the metering gate, then enter the seventh step;

第五步,向管理员及时告警,根据第四步判定计量关口存在的不同的异常情况通过网页提示告警的方式通知管理员或者发送告警短信通知现场运检人员,之后进入第六步;The fifth step is to alert the administrator in time, and according to the fourth step to determine the existence of different abnormal conditions at the metering gate, notify the administrator through the web page prompt alarm or send an alarm message to notify the on-site inspection personnel, and then enter the sixth step;

第六步,现场运检人员及时消缺,及时处理计量关口故障点,之后进入第七步;In the sixth step, the on-site inspection personnel eliminate the shortage in time, and deal with the fault points of the metering gate in time, and then enter the seventh step;

第七步,若计量关口还存在异常,则重复上述步骤;若计量关口正常,则结束。In the seventh step, if the metering gate is still abnormal, repeat the above steps; if the metering gate is normal, then end.

第一步中的电量采集系统数据库和计量报表数据库均为现有公知技术,是现有的电网系统的数据库。这里便于提取目标线路的历史电量数据。Both the power collection system database and the metering report database in the first step are known technologies and are the databases of the existing power grid system. It is convenient to extract the historical power data of the target line here.

实施例2:如附图2、表1、表2、表3所示,计算110千伏西郊变和110千伏母线电量平衡,需要查询二西线计量关口D1、西中线计量关口D2、西坡线计量关口D3、1号主变高侧计量关口D4、2号主变高侧计量关口D5五个计量关口的始码、底码和倍率,按照“流入母线有功电量为反,流出母线有功电量为正”原则进行计算,即西郊变110千伏母线电量不平衡率:Example 2: As shown in Figure 2, Table 1, Table 2, and Table 3, to calculate the power balance of the 110 kV western suburban substation and the 110 kV busbar, it is necessary to query the metering gate D1 of the second west line, the metering gate D2 of the west middle line, The initial code, bottom code and multiplier of the five metering gates of West Slope Line Metering Gate D3, No. 1 main transformer high-side metering gate D4, and No. The calculation is based on the principle that the active power is positive, that is, the power imbalance rate of the 110 kV bus in the western suburbs:

M%=[(D1+D3)-(D2+D4+D5)]÷(D1+D3)×100%M%=[(D1+D3)-(D2+D4+D5)]÷(D1+D3)×100%

若M%>2%,则判定该条线路的母线电量存在不平衡,即为存在异常计量关口,利用相邻元件线损或变损来定位异常计量关口。If M%>2%, it is determined that the bus power of this line is unbalanced, that is, there is an abnormal metering gate, and the abnormal metering gate is located by using the line loss or change loss of adjacent components.

通过计算线路线损、主变变损是否异常推断该母线上异常计量关口,如果二西线计量关口D1、西中线计量关口D2、西坡线计量关口D3、1号主变高侧计量关口D4、2号主变高侧计量关口D5的5个计量关口中某一个元件损耗大于2%,则可以直接定位母线上D1至D5中异常计量关口;根据“流入母线有功电量为反,流出母线有功电量为正”的原则,若流入母线电量为正、流出母线电量为反,则可以确定现场表计反向。由于计量关口倍率与互感器接线变比是对应关系,若西坡线表计综合倍率为132000,则得出互感器计量变比为600:5。由于互感器变比为成倍增大或减小,可以从互感器接线变比确定正确计量关口倍率。若反推计算母平合格,则定位现场互感器计量变比接线错误。判断出计量关口异常原因后通过网页提示告警或者短信通知告警方式提醒运检人员,之后运检人员进行排查处理计量关口故障。Infer abnormal metering gates on the bus by calculating whether the line loss and main transformer loss are abnormal. 1. If the loss of one of the five metering gates of the high-side metering gate D5 of No. 2 main transformer is greater than 2%, the abnormal metering gates of D1 to D5 on the bus can be directly located; According to the principle of "positive power", if the power flowing into the bus is positive and the power flowing out of the bus is negative, then the on-site meter can be determined to be reversed. Due to the corresponding relationship between the metering gate magnification and the transformation ratio of the transformer connection, if the comprehensive magnification of the meter on the west slope line is 132000, then the metering transformation ratio of the transformer is 600:5. Since the transformation ratio of the transformer increases or decreases exponentially, the correct metering gate magnification can be determined from the transformation ratio of the transformer connection. If the reverse calculation of the bus level is qualified, then the measurement transformation ratio wiring of the localized field transformer is wrong. After judging the cause of the abnormality of the metering gate, the inspection personnel will be reminded through the webpage prompt alarm or SMS notification alarm, and then the inspection personnel will troubleshoot and deal with the fault of the metering gate.

以上技术特征构成了本发明的实施例,其具有较强的适应性和实施效果,可根据实际需要增减非必要的技术特征,来满足不同情况的需求。The above technical features constitute the embodiment of the present invention, which has strong adaptability and implementation effect, and non-essential technical features can be increased or decreased according to actual needs to meet the needs of different situations.

Claims (1)

1.一种变电站计量关口异常快速判断告警方法,其特征在于包括以下步骤:1. A kind of substation metering gateway abnormal fast judging alarm method, it is characterized in that comprising the following steps: 第一步,提取电量采集系统数据库中的电量数据,在现有的计量报表数据库中查找得到目标线路的计量倍率、始码和底码,之后进入第二步;The first step is to extract the power data in the database of the power collection system, and find out the measurement magnification, initial code and bottom code of the target line in the existing metering report database, and then enter the second step; 第二步,按照“流入母线有功电量为反,流出母线有功电量为正”原则和计量装置本身“有功电量、无功电量正反四象限”计量特性,在电量报表程序系统中预先定义标记有功电量正反向,之后进入第三步;In the second step, according to the principle of "the active energy flowing into the bus is negative, and the active energy flowing out of the bus is positive" and the measurement characteristics of the metering device itself "positive and negative four quadrants of active energy and reactive energy", pre-define the marker active energy in the electricity report program system. The power is forward and reverse, and then enter the third step; 第三步,计算目标线路计量关口母线不平衡电量、线损、变损自动计算模板,The third step is to calculate the template for automatic calculation of unbalanced power, line loss, and variable loss of the target line metering gateway busbar, (a)计量关口的有功电量数据,即有功电量=(底码-始码)×倍率,(2)以相邻两条电路的有功电量为基础计算得到变损及变损率,变损=(第一线路正向有功电量-第一线路反向有功电量)-(第二线路正向有功电量-第二线路反向有功电量),变损率=变损/第一线路正向有功电量×100%;(a) Active power data at the metering gate, that is, active power = (bottom code - initial code) × magnification, (2) Calculate the change loss and loss rate based on the active power of two adjacent circuits, and change loss = (Forward active energy of the first line - reverse active energy of the first line) - (Forward active energy of the second line - reverse active energy of the second line), change loss rate = change loss / forward active energy of the first line ×100%; (b)以有功电量为基础计算得到母线不平衡电量及母线电量不平衡率;母线不平衡电量=∑(反向有功电量)-∑(正向有功电量),母线电量不平衡率=母线不平衡电量/∑(反向有功电量)×100%;(b) Calculate the unbalanced power of the bus and the unbalanced rate of the bus power based on the active power; Balance power/∑(reverse active power)×100%; (c)以有功电量为基础计算得到线损电量及线损率,线损电量=(第一线路正向有功电量+第二线路反向有功电量)-(第一线路反向有功电量+第二线路反正向有功电量),线损率=线损电量/(第一线路正向有功电量+第二线路反向有功电量)×100%,之后进入第四步;(c) Calculate the line loss power and line loss rate based on the active power. Line loss power = (forward active power of the first line + reverse active power of the second line) - (reverse active power of the first line + second Line loss rate = line loss power / (forward active power of the first line + reverse active power of the second line) × 100%, and then enter the fourth step; 第四步,判断计量关口是否存在异常,根据第三步得到的电量数据,判定计量关口存在的异常情况,若存在异常,则执行(1)或/和(2)或/和(3)或/和(4):The fourth step is to determine whether there is an abnormality at the metering gate. According to the power data obtained in the third step, determine the abnormality of the metering gate. If there is an abnormality, perform (1) or/and (2) or/and (3) or // and (4): (1)根据电流互感器倍率成倍的增加或减小,得出计量倍率错误,之后进入第五步;(1) According to the multiplied increase or decrease of the current transformer multiplier, it is obtained that the measurement multiplier is wrong, and then enter the fifth step; (2)变电站表计具有正反四象限运行功能,每个相限对应不同计量工况,即有功正向、有功反向、无功正向、无功反向,若某一象限不是对应该象限的计量工况,则可以立即得出表计极性出现反向异常,之后进入第五步;(2) The substation meter has the function of positive and negative four-quadrant operation. Each phase corresponds to different metering conditions, that is, active power forward, active power reverse, reactive power forward, and reactive power reverse. If a quadrant does not correspond to In quadrant metering conditions, it can be immediately concluded that the polarity of the meter is reversed abnormally, and then enter the fifth step; (3)利用母线电量不平衡判定计量关口异常,同时结合电能表中相电压、相电流的遥测量值,判断得出是回路接地或缺相、电压回路断线或电流回路短接,之后进入第五步;(3) Use the unbalanced power of the bus to determine the abnormality of the metering gate, and combine the remote measurement values of the phase voltage and phase current in the electric energy meter to determine whether the circuit is grounded or lack of phase, the voltage circuit is disconnected or the current circuit is shorted, and then enter the fifth step; (4)若表计走码有数据但表计走慢,同时电压遥测量降低或为零,则判定回路接地或缺相;若表计走码无数据、断线电压遥测量为零且电流回路短接、电流遥测量为零,则判定为电压回路断线或电流回路短接,之后进入第五步;(4) If the meter running code has data but the meter runs slowly, and at the same time the voltage remote measurement is reduced or is zero, then it is determined that the circuit is grounded or a phase is missing; if the meter running code has no data, the disconnection voltage remote measurement is zero and the current If the circuit is short-circuited and the current remote measurement is zero, it is determined that the voltage circuit is disconnected or the current circuit is short-circuited, and then enter the fifth step; 若计量关口不存在异常情况,之后进入第七步;If there is no abnormal situation at the metering gate, then enter the seventh step; 第五步,向管理员及时告警,根据第四步判定计量关口存在的不同的异常情况通过网页提示告警的方式通知管理员或者发送告警短信通知现场运检人员,之后进入第六步;The fifth step is to alert the administrator in time, and according to the fourth step to determine the existence of different abnormal conditions at the metering gate, notify the administrator through the web page prompt alarm or send an alarm message to notify the on-site inspection personnel, and then enter the sixth step; 第六步,现场运检人员及时消缺,及时处理计量关口故障点,之后进入第七步;In the sixth step, the on-site inspection personnel eliminate the shortage in time, and deal with the fault points of the metering gate in time, and then enter the seventh step; 第七步,若计量关口还存在异常,则重复上述步骤;若计量关口正常,则结束。In the seventh step, if the metering gate is still abnormal, repeat the above steps; if the metering gate is normal, then end.
CN201710079450.8A 2017-02-14 2017-02-14 Substation's metering critical point is abnormal quickly to judge alarm method Active CN106950440B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710079450.8A CN106950440B (en) 2017-02-14 2017-02-14 Substation's metering critical point is abnormal quickly to judge alarm method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710079450.8A CN106950440B (en) 2017-02-14 2017-02-14 Substation's metering critical point is abnormal quickly to judge alarm method

Publications (2)

Publication Number Publication Date
CN106950440A true CN106950440A (en) 2017-07-14
CN106950440B CN106950440B (en) 2019-08-13

Family

ID=59466426

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710079450.8A Active CN106950440B (en) 2017-02-14 2017-02-14 Substation's metering critical point is abnormal quickly to judge alarm method

Country Status (1)

Country Link
CN (1) CN106950440B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107527114A (en) * 2017-08-09 2017-12-29 国网信通亿力科技有限责任公司 A kind of circuit taiwan area exception analysis method based on big data
CN107730114A (en) * 2017-10-17 2018-02-23 国网江苏省电力公司盐城供电公司 A kind of transformer station's uneven reason intelligent diagnostics platform
CN107748954A (en) * 2017-10-17 2018-03-02 国网江苏省电力公司盐城供电公司 A kind of transformer station's balancing monitor and control system
CN107944680A (en) * 2017-11-16 2018-04-20 国网江苏省电力有限公司 A kind of substation's electric energy balance monitoring method based on intelligent electric energy meter
CN110531305A (en) * 2019-08-12 2019-12-03 广西电网有限责任公司 A kind of electricity exception monitoring system and its platform and method
CN112230083A (en) * 2020-10-10 2021-01-15 国网四川省电力公司电力科学研究院 A method and system for identifying abnormal events of a gateway metering device
CN112785152A (en) * 2021-01-22 2021-05-11 国网山东省电力公司德州市陵城区供电公司 Distribution line loss analysis method based on integrated electric quantity and line loss management system
CN112986884A (en) * 2021-04-15 2021-06-18 国网山东省电力公司昌邑市供电公司 User metering multiplying power file checking method and system
CN114137300A (en) * 2021-11-22 2022-03-04 西安热工研究院有限公司 Metering system and method for offshore wind farm gateway of shared switching station
CN115219850A (en) * 2022-07-29 2022-10-21 国网北京市电力公司 Bus balance gateway fault diagnosis method and system based on electric energy acquisition system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101958544A (en) * 2010-08-11 2011-01-26 金华电业局 System and method for calculating loss rate of power distribution line
CN102116857A (en) * 2010-12-31 2011-07-06 江苏省电力公司 Method for checking electric quantity at power grid gate
CN202794330U (en) * 2012-09-10 2013-03-13 浙江晨泰科技股份有限公司 Three-phase four-wire charge intelligent electric energy meter
CN103743982A (en) * 2014-01-21 2014-04-23 国家电网公司 Method for measuring daily line loss of medium-voltage user equipment
CN203746069U (en) * 2013-11-30 2014-07-30 国家电网公司 A low-voltage line loss analysis system in public transformer station area
CN103995962A (en) * 2014-05-06 2014-08-20 国家电网公司 Online real-time calculation and analysis method of equipped wire loss

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101958544A (en) * 2010-08-11 2011-01-26 金华电业局 System and method for calculating loss rate of power distribution line
CN102116857A (en) * 2010-12-31 2011-07-06 江苏省电力公司 Method for checking electric quantity at power grid gate
CN202794330U (en) * 2012-09-10 2013-03-13 浙江晨泰科技股份有限公司 Three-phase four-wire charge intelligent electric energy meter
CN203746069U (en) * 2013-11-30 2014-07-30 国家电网公司 A low-voltage line loss analysis system in public transformer station area
CN103743982A (en) * 2014-01-21 2014-04-23 国家电网公司 Method for measuring daily line loss of medium-voltage user equipment
CN103995962A (en) * 2014-05-06 2014-08-20 国家电网公司 Online real-time calculation and analysis method of equipped wire loss

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107527114A (en) * 2017-08-09 2017-12-29 国网信通亿力科技有限责任公司 A kind of circuit taiwan area exception analysis method based on big data
CN107527114B (en) * 2017-08-09 2019-04-23 国网信通亿力科技有限责任公司 An abnormal analysis method of line station area based on big data
CN107730114A (en) * 2017-10-17 2018-02-23 国网江苏省电力公司盐城供电公司 A kind of transformer station's uneven reason intelligent diagnostics platform
CN107748954A (en) * 2017-10-17 2018-03-02 国网江苏省电力公司盐城供电公司 A kind of transformer station's balancing monitor and control system
CN107944680A (en) * 2017-11-16 2018-04-20 国网江苏省电力有限公司 A kind of substation's electric energy balance monitoring method based on intelligent electric energy meter
CN110531305A (en) * 2019-08-12 2019-12-03 广西电网有限责任公司 A kind of electricity exception monitoring system and its platform and method
CN112230083A (en) * 2020-10-10 2021-01-15 国网四川省电力公司电力科学研究院 A method and system for identifying abnormal events of a gateway metering device
CN112230083B (en) * 2020-10-10 2022-08-30 国网四川省电力公司电力科学研究院 Method and system for identifying abnormal events of gateway metering device
CN112785152A (en) * 2021-01-22 2021-05-11 国网山东省电力公司德州市陵城区供电公司 Distribution line loss analysis method based on integrated electric quantity and line loss management system
CN112785152B (en) * 2021-01-22 2022-04-12 国网山东省电力公司德州市陵城区供电公司 Analysis method of line loss of distribution line based on integrated power and line loss management system
CN112986884A (en) * 2021-04-15 2021-06-18 国网山东省电力公司昌邑市供电公司 User metering multiplying power file checking method and system
CN112986884B (en) * 2021-04-15 2021-08-13 国网山东省电力公司昌邑市供电公司 User metering magnification file verification method and system
CN114137300A (en) * 2021-11-22 2022-03-04 西安热工研究院有限公司 Metering system and method for offshore wind farm gateway of shared switching station
CN114137300B (en) * 2021-11-22 2024-01-19 西安热工研究院有限公司 System and method for metering gateway of offshore wind farm of shared switching station
CN115219850A (en) * 2022-07-29 2022-10-21 国网北京市电力公司 Bus balance gateway fault diagnosis method and system based on electric energy acquisition system

Also Published As

Publication number Publication date
CN106950440B (en) 2019-08-13

Similar Documents

Publication Publication Date Title
CN106950440A (en) Transformer station's metering critical point quickly judges alarm method extremely
CN102944817B (en) Locating method and device for one-phase earth fault of power distribution network based on transient state signal wavelet transformation
CN105811383B (en) A kind of new micro-capacitance sensor positive sequence impedance differential protecting method
CN102967800B (en) Method and device for positioning single-phase ground fault section of power distribution network based on transient signal prony algorithm
CN106291252B (en) A kind of 10kV line loss and low-voltage platform area line loss management analysis method
CN108120897A (en) A kind of distribution single-phase grounding selecting method based on three-phase current unbalance degree computation model
CN102707194A (en) Power distribution network broken line fault location method
CN103941079B (en) Power distribution network PT on-line monitoring and fault diagnosis system
CN106124935A (en) Middle and low voltage network Fault Locating Method
CN102798776B (en) Multi-parameter fused substation data integrity checking method
CN103995172B (en) Method for on-line monitoring of load current of GIS bus of substation
CN106443556A (en) Method for intelligently diagnosing electric energy meter
CN107543989B (en) Method for judging abnormal line loss based on voltage loss and phase failure of electric energy meter
CN106646130B (en) A fault location method and system for active distribution network based on current polarity comparison
CN105388396B (en) A method of tracing voltage sag source with the active increment current direction of sequence
CN101958544A (en) System and method for calculating loss rate of power distribution line
CN104215882B (en) Voltage sag source locating method based on active single-port network resistor polarity
CN106771448A (en) A kind of electric energy meter shunting anti-electricity-theft early warning analysis method of analysis
CN107015121A (en) A kind of distribution transforming stoppage in transit method for rapidly positioning
CN110488146B (en) Direct current distribution network insulation monitoring system and direct current insulation monitoring device
CN104834305A (en) Distribution network automated terminal telemetering abnormity analyzing system and method based on DMS system
CN104215879A (en) Method and system for locating short-circuit faults of power distribution networks
CN201717677U (en) Distribution transformer failure monitoring terminal
CN105391075B (en) Line loss reactive voltage integrated management approach
CN114971168A (en) An abnormal analysis method of cable line loss rate during the same period based on multi-system interaction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant