CN106930539A - Purlin localization method - Google Patents
Purlin localization method Download PDFInfo
- Publication number
- CN106930539A CN106930539A CN201710153631.0A CN201710153631A CN106930539A CN 106930539 A CN106930539 A CN 106930539A CN 201710153631 A CN201710153631 A CN 201710153631A CN 106930539 A CN106930539 A CN 106930539A
- Authority
- CN
- China
- Prior art keywords
- purlin
- roller
- section steel
- guiding channel
- roofing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The present invention provides a kind of purlin localization method, comprises the following steps:S1:Purlin end is installed, and the end of many purlins is weldingly fixed on the steel construction longeron of roofing, and multiple purlins are equally spaced;S2:The whole body positioning of purlin, using positioning action platform carry out auxiliary install installation process in, promote positioning action platform, purlin is pressed on roofing first roller height when ensureing that purlin is positioned, second roller of both sides is used to correct the spacing between purlin, after positioning action platform moves a segment distance, adjacent purlin is fixed by pull bar by operating personnel's profit, roofing covering is carried out on purlin after fixation, install in proper order until whole roofing is carried out into covering completion successively, location and installation purlin is easy to operate on roofing, without being positioned manually using scaffold.
Description
Technical field
Installed the present invention relates to purlin, more particularly to a kind of purlin localization method.
Background technology
All it is all the time have variable edge pull bar with manpower consumption to adjust and between amendment during the purlin on general installation roof
Away from, such as use scaffold(Door cabinet frame)The mode for taking the height of purlin to construct is done, above-mentioned installation method, not only operates
Inconvenience, and position not accurate enough.
The content of the invention
It is an object of the invention to overcome defect present in prior art, there is provided a kind of purlin localization method, in roofing
Upper location and installation purlin is easy to operate, without being positioned manually using scaffold.
To achieve the above object, the technical scheme is that providing a kind of purlin localization method, comprise the following steps:
S1:Purlin end is installed, and the end of many purlins is fixed on the steel construction longeron of roofing, and multiple purlins equidistantly divide
Cloth;
S2:The whole body positioning of purlin, many purlins are adjusted and are repaired in installation process using positioning action platform
Two support frames including Longitudinal extending away from, the positioning action platform and be arranged in parallel, laterally it is fixedly installed on described in two
The multiple of support frame bottom are oriented to channel-section steels, and the guiding channel-section steel is corresponded with the purlin, the opening of the guiding channel-section steel to
Under, running fix structure is provided with the guiding channel-section steel, the running fix structure includes being fixedly installed on the gathering sill
First bolt axle parallel with support frame as described above on steel, two be fixedly installed on the guiding channel-section steel and support frame as described above phase
The second parallel bolt axle, rotates in first bolt axle and is arranged with the first roller, is rotated respectively in second bolt axle
Be arranged with the second roller, the first roller pressure located at the upper surface of the purlin, two second rollers respectively with it is described
The two sides of the upper end of purlin are inconsistent, in installation process, promote positioning action platform, the first roller that purlin is pressed in into room
Height when ensureing that purlin is positioned on face, the second roller of both sides is used to correct the spacing between purlin, and positioning action platform is moved
After a dynamic segment distance, adjacent purlin is fixed by pull bar by operating personnel's profit, roofing covering is carried out on purlin after fixation,
Install in proper order until whole roofing is carried out into covering completion successively.
It is further improved to be:Multigroup running fix structure is evenly equipped with the guiding channel-section steel along its length.
It is further improved to be:One end of first bolt axle has the first limiting section, and its other end has the first spiral shell
Line section, first limiting section is inconsistent with the side of the guiding channel-section steel, and first thread segment passes through the first locking nut
First bolt axle is fixed on the guiding channel-section steel.
It is further improved to be:One end of second bolt axle has the second limiting section, and its other end has the second spiral shell
Line section, described the and limiting section is inconsistent with the lower surface of the guiding channel-section steel, second thread segment passes through the second locking screw
Be fixed on support frame as described above for second bolt axle and the guiding channel-section steel by mother.
It is further improved to be:Two spacing catch are provided with the inside of the guiding channel-section steel, first roller has
Two, two first rollers are located between two spacing catch.
It is further improved to be:First roller and second roller are bearing.
It is further improved to be:Support frame as described above is made up of square tube.
It is further improved to be:It is solid by welding or bolt between the end of the purlin and the steel construction longeron
It is fixed.
It is further improved to be:In step s 2, operating personnel by pull bar fix purlin while, by L-type
Be fixed on the purlin on roofing by purlin support.
The advantages of the present invention are:On roofing during mounting purlines, positioning action platform is directly used, by
It is equally spaced in channel-section steel is oriented to, and the first roller is rolled along the upper surface of purlin, and the roller of both sides second is respectively along purlin
Two sides roll, so as to the purlin that ensure that installation can reach installation standard in upper and lower, left and right directions, operate in addition
When, need to only promote positioning action platform to be capable of achieving precise positioning, and it is easy to operate.
Brief description of the drawings
Fig. 1 is positioning action platform schematic diagram;
Fig. 2 is the partial enlarged drawing of Fig. 1;
Fig. 3 is roofing scheme of installation.
Wherein:1st, support frame;2nd, it is oriented to channel-section steel;3rd, the first bolt axle;4th, the second bolt axle;5th, the first roller;6th, second
Roller;7th, spacing catch;8th, purlin;9th, purlin support;10th, pull bar;11st, longeron.
Specific embodiment
With reference to the accompanying drawings and examples, specific embodiment of the invention is further described.Following examples are only
For clearly illustrating technical scheme, and can not be limited the scope of the invention with this.
As shown in Figure 1-Figure 3, a kind of localization method of purlin 8, comprises the following steps:
S1:Purlin end is installed, and many ends of purlin 8 are fixed on the steel construction of roofing by way of welding or bolting
On longeron 11, multiple purlins 8 are equally spaced;
S2:The whole body positioning of purlin, many purlins 8 are adjusted and are repaired in installation process using positioning action platform
Two support frames 1 including Longitudinal extending away from, the positioning action platform and be arranged in parallel, laterally it is fixedly installed on described in two
The multiple of the bottom of support frame 1 are oriented to channel-section steel 2, and the guiding channel-section steel 2 is corresponded with the purlin 8, described to be oriented to opening for channel-section steel 2
Mouth downwards, is provided with running fix structure on the guiding channel-section steel 2, the running fix structure includes being fixedly installed on described leading
To the first bolt axle 3, two parallel with support frame as described above 1 on channel-section steel 2 be fixedly installed on it is described guiding channel-section steel 2 on it is described
The second parallel bolt axle 4 of support frame 1, rotates in first bolt axle 3 and is arranged with the first roller 5, second bolt
Rotated respectively on axle 4 and be arranged with the second roller 6, the pressure of the first roller 5 located at the upper surface of the purlin 8, two described the
Two sides of the second wheel 6 respectively with the upper end of the purlin 8 are inconsistent, in installation process, promote positioning action platform, first
Purlin 8 is pressed on roofing roller 5 height when ensureing that purlin 8 is installed, the second roller 6 of both sides be used to correcting purlin 8 it
Between spacing, positioning action platform move a segment distance after, by operating personnel profit adjacent purlin 8 is fixed by pull bar 10, with
Be fixed on the purlin 8 on roofing by the purlin support 9 of L-type simultaneously by this, and roofing covering is carried out on purlin 8 after fixation, according to
It is secondary to install in proper order until whole roofing is carried out into covering completion.
If only with one group of running fix structure, tilting phenomenon can occur in positioning action platform moving process, therefore
In order to ensure the stability of positioning action platform, increase it and greatly improve locating effect with the contact area of purlin 1, it is described
It is oriented on channel-section steel 2 and is evenly equipped with multigroup running fix structure along its length.
The first bolt axle 3 is fixed on guiding channel-section steel 2 for convenience, one end of first bolt axle 3 has first
Limiting section, its other end has the first thread segment, and first limiting section is inconsistent with the side of the guiding channel-section steel 2, described
Be fixed on first bolt axle 3 on the guiding channel-section steel 2 by the first locking nut by the first thread segment.
The second bolt axle 4, guiding channel-section steel 2 and support frame 1 are fixedly connected for convenience, second bolt axle
4 one end has the second limiting section, and its other end has the second thread segment, described the and limiting section and the channel-section steel 2 that is oriented to
Lower surface is inconsistent, and second thread segment passes through the second locking nut by second bolt axle 4 and the guiding channel-section steel 2
Be fixed on support frame as described above 1, the second bolt axle 4 not only acts as the effect of wheel shaft, and play be directed to channel-section steel 2 and support
The effect that frame 1 is fixed.
In order to carry out axially position to the second roller 6, prevent it from off-set phenomenon, the gathering sill occurring in moving process
The inner side of steel 2 is provided with two spacing catch 7, and first roller 5 has two, and two first rollers 5 are located at two
Between the spacing catch 7.
It is preferred embodiment that first roller 5 and second roller 6 are bearing in the present embodiment.
It is preferred embodiment that support frame as described above 1 is made up of square tube in the present embodiment.
General principle of the invention and principal character and its advantage has been shown and described above, the technical staff of the industry should
The understanding, the present invention is not limited to the above embodiments, and simply original of the invention is illustrated described in above-described embodiment and explanation
Reason, without departing from the spirit and scope of the present invention, various changes and modifications of the present invention are possible, these changes and improvements
All fall within the protetion scope of the claimed invention, the claimed scope of the invention is by appending claims and its equivalent circle.
It is fixed.
Claims (9)
1. a kind of purlin localization method, it is characterised in that:Comprise the following steps:
S1:Purlin end is installed, and the end of many purlins is fixed on the steel construction longeron of roofing, and multiple purlins equidistantly divide
Cloth;
S2:The whole body positioning of purlin, many purlins are adjusted and are repaired in installation process using positioning action platform
Two support frames including Longitudinal extending away from, the positioning action platform and be arranged in parallel, laterally it is fixedly installed on described in two
The multiple of support frame bottom are oriented to channel-section steels, and the guiding channel-section steel is corresponded with the purlin, the opening of the guiding channel-section steel to
Under, running fix structure is provided with the guiding channel-section steel, the running fix structure includes being fixedly installed on the gathering sill
First bolt axle parallel with support frame as described above on steel, two be fixedly installed on the guiding channel-section steel and support frame as described above phase
The second parallel bolt axle, rotates in first bolt axle and is arranged with the first roller, is rotated respectively in second bolt axle
Be arranged with the second roller, the first roller pressure located at the upper surface of the purlin, two second rollers respectively with it is described
The two sides of the upper end of purlin are inconsistent, in installation process, promote positioning action platform, the first roller that purlin is pressed in into room
Height when ensureing that purlin is positioned on face, the second roller of both sides is used to correct the spacing between purlin, and positioning action platform is moved
After a dynamic segment distance, adjacent purlin is fixed by pull bar by operating personnel's profit, roofing covering is carried out on purlin after fixation,
Install in proper order until whole roofing is carried out into covering completion successively.
2. purlin localization method as claimed in claim 1, it is characterised in that:It is uniform along its length on the guiding channel-section steel
There is multigroup running fix structure.
3. purlin localization method as claimed in claim 1, it is characterised in that:One end of first bolt axle has the first limit
Position portion, its other end has the first thread segment, and first limiting section is inconsistent with the side of the guiding channel-section steel, and described first
Be fixed on first bolt axle on the guiding channel-section steel by the first locking nut by thread segment.
4. purlin localization method as claimed in claim 1, it is characterised in that:One end of second bolt axle has the second limit
Position portion, its other end has the second thread segment, described the and limiting section is inconsistent with the lower surface of the guiding channel-section steel, and described the
Be fixed on support frame as described above for second bolt axle and the guiding channel-section steel by the second locking nut by two thread segments.
5. purlin localization method as claimed in claim 1, it is characterised in that:Two limits are provided with the inside of the guiding channel-section steel
Position catch, first roller has two, and two first rollers are located between two spacing catch.
6. purlin localization method as claimed in claim 1, it is characterised in that:First roller and second roller are equal
It is bearing.
7. purlin localization method as claimed in claim 1, it is characterised in that:Support frame as described above is made up of square tube.
8. purlin localization method as claimed in claim 1, it is characterised in that:The end of the purlin and the steel construction longeron
Between by welding or bolt fix.
9. purlin localization method as claimed in claim 1, it is characterised in that:In step s 2, operating personnel are by pull bar
While fixed purlin, the purlin is fixed on roofing by the purlin support of L-type.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710153631.0A CN106930539B (en) | 2017-03-15 | 2017-03-15 | Purlin localization method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710153631.0A CN106930539B (en) | 2017-03-15 | 2017-03-15 | Purlin localization method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106930539A true CN106930539A (en) | 2017-07-07 |
CN106930539B CN106930539B (en) | 2019-01-29 |
Family
ID=59433276
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710153631.0A Active CN106930539B (en) | 2017-03-15 | 2017-03-15 | Purlin localization method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106930539B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115874799A (en) * | 2022-11-30 | 2023-03-31 | 江西中煤建设集团有限公司 | Steel structure factory building Z-shaped steel brace mounting platform and construction method |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005016135A (en) * | 2003-06-25 | 2005-01-20 | Daiwa House Ind Co Ltd | Fire-resistant roof structure |
WO2005056435A2 (en) * | 2003-11-28 | 2005-06-23 | Harv Lillegard | Method and apparatus for truss rollout |
CN201835454U (en) * | 2010-11-01 | 2011-05-18 | 广州市恒盛建设工程有限公司 | Horizontal transport vehicle for super-long roof panels |
CN204081088U (en) * | 2014-09-12 | 2015-01-07 | 中旭建筑设计有限责任公司 | Z-shaped purline is in the syndeton at bearing place |
CN104818857A (en) * | 2015-04-21 | 2015-08-05 | 中国十七冶集团有限公司 | Installation method of multiple uniform-distributed thin praline pull rods on large-span roof |
CN205276725U (en) * | 2015-12-31 | 2016-06-01 | 沈阳三新实业有限公司 | Translation dolly in various steel room panel construction technology of overlength |
-
2017
- 2017-03-15 CN CN201710153631.0A patent/CN106930539B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005016135A (en) * | 2003-06-25 | 2005-01-20 | Daiwa House Ind Co Ltd | Fire-resistant roof structure |
WO2005056435A2 (en) * | 2003-11-28 | 2005-06-23 | Harv Lillegard | Method and apparatus for truss rollout |
CN201835454U (en) * | 2010-11-01 | 2011-05-18 | 广州市恒盛建设工程有限公司 | Horizontal transport vehicle for super-long roof panels |
CN204081088U (en) * | 2014-09-12 | 2015-01-07 | 中旭建筑设计有限责任公司 | Z-shaped purline is in the syndeton at bearing place |
CN104818857A (en) * | 2015-04-21 | 2015-08-05 | 中国十七冶集团有限公司 | Installation method of multiple uniform-distributed thin praline pull rods on large-span roof |
CN205276725U (en) * | 2015-12-31 | 2016-06-01 | 沈阳三新实业有限公司 | Translation dolly in various steel room panel construction technology of overlength |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115874799A (en) * | 2022-11-30 | 2023-03-31 | 江西中煤建设集团有限公司 | Steel structure factory building Z-shaped steel brace mounting platform and construction method |
Also Published As
Publication number | Publication date |
---|---|
CN106930539B (en) | 2019-01-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2022033502A1 (en) | Assembling trolley for lower assembly section of assembly-type station pile-anchor system | |
CN106930539A (en) | Purlin localization method | |
AT518613B1 (en) | Swiveling photovoltaic carport | |
CN206445347U (en) | The outer longitudinal seam welding frame of wind power tower | |
CN206495380U (en) | Aluminum plate curtain wall system | |
CN105239700A (en) | Novel portal-frame steel-structural building exterior wall structure and mounting method of wall purlins | |
CN111219020A (en) | Transport trolley for roof panel of large-span steel structure workshop and installation method | |
CN110056218B (en) | Single-storey factory building column-drawing steel frame structure | |
CN207222639U (en) | A kind of novel wind power tower drum flange ovality corrects frock | |
CN204919883U (en) | Novel gate -type frame steel construction building external wall structure | |
CN206502952U (en) | A kind of New-type computer quilter stretched frame | |
CN111075018B (en) | Cylindrical steel structure support | |
CN201458414U (en) | Bearing steel strip stretch-draw rectifying machine | |
CN215669060U (en) | Low-position tunnel-crossing bridge girder erection machine tunnel-crossing first-hole beam via-hole wheel group walking-shape deviation correcting device | |
CN205949547U (en) | Weld a H -beam pollution discharge amount | |
CN214577047U (en) | Steel structure trolley supporting system for station rail top air duct construction | |
CN206455350U (en) | Can be walked out-seam weld holder | |
CN207001447U (en) | A kind of tube laying rack | |
CN206529707U (en) | A kind of Hanging Basket for building | |
CN206983991U (en) | A kind of rail vehicles skirtboard | |
CN206685866U (en) | Cable unwinding device | |
CN206128480U (en) | Roof boarding mounting platform | |
CN205330264U (en) | Steel construction tent | |
CN211775221U (en) | Travelling bogie of large-span steel structure factory building roof boarding | |
WO2019149867A1 (en) | Device and method for continuously driving a tunnel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |