CN106930337A - A kind of technique administered to underground Tipple Bottom plate seepage based on XYPEX materials - Google Patents

A kind of technique administered to underground Tipple Bottom plate seepage based on XYPEX materials Download PDF

Info

Publication number
CN106930337A
CN106930337A CN201511008597.5A CN201511008597A CN106930337A CN 106930337 A CN106930337 A CN 106930337A CN 201511008597 A CN201511008597 A CN 201511008597A CN 106930337 A CN106930337 A CN 106930337A
Authority
CN
China
Prior art keywords
xypex
mortar
concentrating agents
water
type groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201511008597.5A
Other languages
Chinese (zh)
Inventor
唐嘉莺
费庆伟
张兰军
祝周旺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Sheng Sheng Building Decoration Materials Co Ltd
Original Assignee
Shanghai Sheng Sheng Building Decoration Materials Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Sheng Sheng Building Decoration Materials Co Ltd filed Critical Shanghai Sheng Sheng Building Decoration Materials Co Ltd
Priority to CN201511008597.5A priority Critical patent/CN106930337A/en
Publication of CN106930337A publication Critical patent/CN106930337A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D37/00Repair of damaged foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • E02D31/04Watertight packings for use under hydraulic pressure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0045Composites

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses it is a kind of efficiently, persistently, can turn into concrete entirety solution F3/B3 base plate leakage technique.The use that the present invention passes through XYPEX " Sai Baisi " material, adds its cooperation and effective combination of special process, obtains the unforeseen good result of those skilled in the art, solves the problem of long-standing problem building field technical staff.

Description

A kind of technique administered to underground Tipple Bottom plate seepage based on XYPEX materials
Technical field
The invention belongs to building field, and in particular to a kind of underground Tipple Bottom plate seepage is carried out based on XYPEX materials The technique of improvement.
Background technology
In the prior art, pile crown platform meets Cha Chu with base plate micro-cracks, and platform connects raft internal corner part part with base plate There is percolating water, there is serious leakage water at post-cast strip, there is percolating water at steel bar end, though the method for grouting for water plugging can be taken to process, But effect not it is obvious that can only temporarily leak-stopping and can not fundamentally improve the density of concrete, slurries to a certain extent Foaming further increase the hole and hole of concrete, cannot turn into an entirety with concrete at all.
The content of the invention
It is an object of the invention to provide it is a kind of efficiently, persistently, the solution underground of entirety can be turned into concrete The technique of Tipple Bottom plate seepage.
A kind of technique administered to underground Tipple Bottom plate seepage based on XYPEX materials, in the technical process, matches somebody with somebody Close and use XYPEX materials;
The XYPEX materials be XYPEX " concentrating agents " mortar and, XYPEX " concentrating agents " half-dried dough, XYPEX " blend One or more in agent " mortar, XYPEX " synergist " mortar or XYPEX " sealing agent ";
Wherein, in XYPEX " concentrating agents " mortar, XYPEX " concentrating agents " powder is 5: 2~2.5 with the volume ratio of water;XYPEX In " concentrating agents " half-dried dough, XYPEX " concentrating agents " powder is 6: 1 with the volume ratio of water;
In XYPEX " admixture " mortar, cement, the weight ratio of thick middle sand, water and XYPEX " admixture " are 1:2.5: 0.4:0.03-0.04;
XYPEX " sealing agent " dough powder is 3.5: 1 with the volume ratio of water;
XYPEX " synergist " powder is 5: 2 with the volume ratio of water.
It is preferred that the technique is comprised the following steps:
Base treatment, leak stopping sealing, privileged sites are strengthened, XYPEX " concentrating agents " mortar, maintenance, examination are brushed in layering.
During base treatment, preferably the eliminating impurities such as exotic, loose material, greasy dirt are first done with grinding machine by basic unit Only, treatment then with water purification is rinsed to concrete surface, concrete capillary is opened wide.
During base treatment, preferred pair percolating water crack, construction joint or structural cracks width are more than 0.4mm, dig into " U " type groove, the size of groove is 30mm × 30mm or 30mm × 70mm.
Preferably for the construction joint in F3/B3 base plate, post-cast strip and the structural cracks through crack wide more than 0.4mm, Neat seam centre chisel is first applied and brushes one times XYPEX " concentrating agents " mortar, after initial set into " U " type groove of 30 × 30mm or 30mm × 70mm With the half-dried dough hands of XYPEX " concentrating agents " and hand hammer make firm by ramming compacting it is floating in " U " type groove, link into an integrated entity, then above Apply again and brush one times XYPEX " concentrating agents " mortar;The structural cracks wide less than 0.4mm brushes twice XYPEX " concentration at crack The reinforcement of agent " mortar is processed.
Need to add preferably for weak parts such as the wall pipe on the structure wall in F3/B3 base plate, sleeve pipe, bolts Gu treatment, the upstream face to weakness such as embedded wall penetration sleeve pipe, reserved steel bar head, the turnover mouths of pipe digs into " U " type of 30 × 30mm Groove, the interior water of groove washes away totally, and removes surface Ming Shui, then brushes XYPEX " concentrating agents " mortar in " U " type groove, treats initial set Afterwards, then by the half-dried dough pointings of XYPEX " concentrating agents " enter in seam, compacting is made firm by ramming in " U " type groove with hand or hammer, and seam both sides It is floating with basal plane, after the completion of brush one XYPEX " concentrating agents " mortar again.Both sides respectively extend the ㎜ of brushing 50~100.
Preferably for the steel bar end in F3/B3 base plate, steel bar end is cut off, and makes its recessed structures surface about 20mm, One XYPEX " concentrating agents " mortar bed is first brushed after cleaning, cleaning, then with XYPEX " admixture " mortar pointing, is consolidated close Envelope, one layer of XYPEX " concentrating agents " mortar bed is brushed above after pointing material is pre-hardening again.
The XYPEX materials used in the present invention are XYPEX cement-base infiltration crystallization type materials.
XYPEX materials of the invention are purchased from city of Beijing honor waterproof material Co., Ltd or Sichuan generation Condar civil engineering skill Art Co., Ltd.
The present invention not using only material hydrophilic it is nontoxic, it is tasteless, pollution-free, nonflammable, with waterproof, protection and improve The combination property of concrete.And it produces the complicated and confused shape crystalline solid for being insoluble in water in the hole and capillary channel of concrete. The packing of concrete can be improved, an entirety is turned into concrete, prevent any liquid from invading, prevent concrete because severe Environmental influence its quality.
By using material of the invention and technique, penetrant crystalline depth free from worldly cares can be obtained, the time is more long, and crystallization is oozed It is thoroughly deeper.Japanese building association carries out overtesting, after test specimen is placed 12 months, measures its depth up to 300mm.
There is the ability of self-regeneration after the crack chance water of the 0.4~1mm occurred for concrete structure, if coagulation local products Raw crack, running into water can be crystallized with secondary, three inferior multiple generations again, crack be blocked, with permanent waterproof action.
And it does not influence the breathing of concrete, the infiltration of water can be stopped, concrete is kept dry and comfortable, it is not moist.
Concrete strength up to 20~29% can be effectively improved.
After using technique of the invention, puncture is not afraid of after curing period of having constructed and is collided with.
And the erosion of various chemical substances can be resisted, antiacid alkali Long Term Contact pH is up to 3.0~11.0, Intermittent Contact PH2.0~12.0.Also radioresistance, exposed to 5.76 × 104Without any damage under rad gamma ray.
Anti-carbonation, the harm of resisting chloride ion penetration, alkali-aggregate reaction (AAR) can be suppressed.
Under -32 DEG C~+130 DEG C of sustaining temperature, it is kept to act at -185 DEG C~+1530 DEG C intermittent temperature. The size of humidity size, ultraviolet power and oxidation is on it without influence.
Freeze thawing resistance circulation is up to 350 with last time.
Reinforcing bar and metal embedded part can be protected not to be corroded.
Nontoxic, tasteless, pollution-free category environmental protection.
Construction method simplicity, therefore saving of labor, material-saving, overall economic efficiency rationally, the ability of self-regeneration are sewed with due to counterincision, The maintenance cost in later stage can be reduced.
Not only coagulation soil characteristics can be improved with waterproof, antiseepage, anti-corrosion, administer the disease problem of concrete, extend coagulation The service life of soil structure durability and building.
The use that the present invention passes through XYPEX " Sai Baisi " material, adds effective combination of its cooperation and special process, obtains Those skilled in the art unforeseen good results, solve the problem of long-standing problem building field technical staff.This hair Bright inventor not only for how using the material to have carried out substantial amounts of technology exploration, to how to be used in combination the same of the material When, suitable technique is obtained so as to farthest play the effect of the material has been also carried out substantial amounts of technical research, consume Workman and the substantial amounts of energy of research staff, while also obtain good effect.
Brief description of the drawings
Fig. 1 is that waterproof construction sequential configuration schematic diagram is strengthened in construction joint or structural cracks repairing.
Fig. 2 is that waterproof construction sequential configuration schematic diagram is strengthened on wall pipe root periphery.
Fig. 3 is that waterproof construction sequential configuration schematic diagram is strengthened on wall pipe root periphery.
Specific embodiment
Operating condition
(1) basal plane at percolating water position is cleaned out.
(2) concrete structure to waterproof construction position carries out hidden inspection receipts;Fixed form bolt, useless steel bar end, steel Pipe etc. cuts off from root, and depth inside recessed concrete is no less than 20mm.
(3) repairing of special weak part, reparation, the consolidation process of basal plane concrete:Post-cast strip, steel bar end, construction joint, wear Wall coil, body structure surface honeycomb, hole and open structure reinforcement and repair are disposed.
Construction is arranged
1st, technological process:Base treatment → leak stopping sealing → privileged sites strengthen → layering brushing XYPEX " concentrating agents " ash Slurry → maintenance → check and accept.
2nd, base treatment:
(1) basic unit first uses grinding machine (or perching knife and chisel) by debris such as exotic, loose material, greasy dirt and other materials Remove clean;Treatment is rinsed to concrete surface with water purification, concrete capillary is opened wide, water is penetrated into inside coagulation, is had Go deep into crystal growth in concrete structure beneficial to XYPEX " concentrating agents " waterproof material.It is also to close that basic unit's polishing cleaning is cleaned up Key successful first is closed.
(2), by the basal plane after chisel cleaning of clearing up, polish, pick, the disease that concrete structure is present can intuitively be found, Beneficial to targetedly with according to situation XYPEX series materials cooperation technology improvement privileged sites and weak link.
(3) " U " type groove all should be dug into more than 0.4mm to percolating water crack, construction joint or structural cracks width, groove 30mm × 30mm or 30mm × 70mm (according to the situation), embedded body periphery digs into " U " type, and deep width is ibid.(never allow chisel " V " type groove is carried out).
If (4) having honeycomb and open structure all should cut, rinsed well up to seeing hard concrete base layer with water, and One layer of XYPEX " concentrating agents " coating is brushed in moist basic unit, (pressure is filled up with the half-dried dough of sealing agent in the case of having flowing water It is real, fill up compacting with the half-dried dough of concentrating agents in the case of no flowing water.Then repair, large area technological process ibid, is used XYPEX concentrating agents mortar brushing three times).
(5) there is the big face of steel bar end or steel plate to chisel to leave " U " type groove and carry out reinforcing and repairing repair process.
3rd, cleaning moistening basic unit:
The scope of operation is scrubbed with clear water, concrete surface is moistened (but without bright water) completely, allow concrete structure pore In have full moisture content, be easy to XYPEX " concentrating agents " be catalyzed penetrant crystalline effect.
4th, the modulation of XYPEX waterproof materials:
(1) brushing slurrying materials proportioning
The slurrying of XYPEX " concentrating agents " mortar:XYPEX " concentrating agents " powder: water=5: 2 (volume ratios)
(2) repairing condiment proportioning
1. the modulation of XYPEX " concentrating agents " half-dried dough:XYPEX " concentrating agents " powder: water=6: 1 (volume ratio)
2. the modulation of XYPEX " sealing agent " dough:XYPEX " concentrating agents " powder: water=3.5: 1 (volume ratio)
(3) spraying slurrying materials are with when construction method
1. " concentrating agents " spraying process slurrying:" concentrating agents " powder:Water=5:3~3.5 (volume ratios);
2. spray and should be greater than 10 air pressure using the pressure of air pump, the bore of the nozzle of spray gun is starched for 6mm or using guarantee The equipment that material can be ejected equably;Nozzle is preferably controlled in 200mm away from interlamellar spacing is applied during spraying, to ensure mortar energy spirt table In face micropore or crackle.
5th, concrete privileged sites repairing leak stopping, reinforcing, reparation
(1) construction joint, the treatment of late poured band structure crack repairing reinforcement and repair
The through crack wide more than 0.4mm to construction joint, post-cast strip and structural cracks answers junction of the edges of two sheets of paper centre chisel into 30 × 30mm Or " U " type groove (according to the situation) of 30mm × 70mm, first apply and brush one times XYPEX " concentrating agents " mortar, used after initial set The half-dried dough hands of XYPEX " concentrating agents " and hand hammer make firm by ramming compacting it is floating in " U " type groove, special west is sewed on and smear back and forth pressure, Link into an integrated entity, then brush one times XYPEX " concentrating agents " mortar with painting again above.The structural cracks wide less than 0.4mm is in crack Two times XYPEX " concentrating agents " mortar reinforcements of brush treatment is rubbed in place's painting.Waterproof construction order structure is strengthened in construction joint or structural cracks repairing Make schematic diagram (Fig. 1)
(2) construction part is strengthened on wall pipe, sleeve pipe, bolt periphery
The weak parts such as wall pipe, sleeve pipe, bolt on structure wall need to do consolidation process.To embedded wall penetration sleeve pipe, in advance Staying steel bar end, the upstream face of the turnover weakness such as the mouth of pipe should dig into " U " type groove (note of 30 × 30mm:All raggles must be " U " Type, and " V " type is never to fill perhaps), the interior water of groove washes away totally, and removes surface Ming Shui, then brushes XYPEX " concentrating agents " ashes Starch in " U " type groove, after after initial set, then the half-dried dough pointings of XYPEX " concentrating agents " are entered in seam, making compacting firm by ramming with hand or hammer exists In " U " type groove, and seam both sides should be floating with basal plane, after the completion of brush one XYPEX " concentrating agents " mortar again.Both sides respectively extend Brush 50~100 ㎜;Strengthen waterproof construction sequential configuration schematic diagram (Fig. 2) in wall pipe root periphery;
(3)Steel bar end:Steel bar end is that the passage of percolating water must cut off, and recessed structures surface about 20mm.Cleaning, cleaning One XYPEX " concentrating agents " mortar bed of brushing is first rubbed afterwards, and afterwards with XYPEX " admixture " mortar pointing, pointing material is treated in tamping sealing Rub one layer of XYPEX " concentrating agents " mortar bed of brushing after material initial set again above.The reinforcement of fixed form bolt or steel bar end Waterproof construction sequential configuration schematic diagram (Fig. 3)
(4) structure surface quality rejected region treatment
Concrete structural surface honeycomb and open structure all should be cut to dense layer, then is rinsed well with water, until seeing To hard concrete, then applied in moist substrate surface and brush one times XYPEX " concentrating agents " mortar bed, XYPEX " concentrating agents " is half-dried Dough fills consolidation process, is applied again on its surface after solidification and brushes one times XYPEX " concentrating agents " mortar reinforcing Seal treatment.
The rejected region of base treatment structure, XYPEX " concentrating agents " and XYPEX " sealing agent " is first used if any Seepage water Leak stopping to seal carry out again after not flowing water privileged sites reinforcement and repair and finish and should in time handle hidden inspection and receive formality.
5th, the construction point of large area brushing XYPEX coating:
(1) slurrying:The pigment material that will be measured is taken up in order of priority to pour into cylinder and (first pours into cylinder water, then delay powder Slowly it is added to the water stirring, is stirred when powder is added).It is uniform with low-speed agitator or stirring rod mix.The quantity of each mix should By calculating, it is ensured that each mix is finished within the stipulated time from spice (about 20min), if compounding substances during use Retrogradation should carry out continual stirring, forbid midway add water, feed, and can otherwise influence the construction quality of XYPEX.
(2) the per pass consumption and total consumption of XYPEX " concentrating agents " ashes paste paint should meet design requirement, every square metre of consumption It is 1.0~1.2kg/m2(not including repairing consumption).
(3) when brushing XYPEX " concentrating agents " mortar, floor surface should be without bright water.The order of waterproof layer brushing should typically be abided by The principle of " base plate after big face, first wall after low after first height, first thin portion reinforcement " is followed, or brushing is rubbed using power is round, or using specially Use spray gun spraying.When there is particular/special requirement, can be constructed according to mobilization.
1. per pass coating spraying or rub after brushing finishes final set, can enter after relevant technical staff, management acceptance(check) The construction of Hang Xia roads coating.But the interval time of two coating brushings is unsuitable long, is brushed again after should otherwise moistening.
2. upper one spraying or brushing direction Ying Yuxia roads are mutually perpendicular to during construction, and should replace when every time spraying or brushing Change and brush direction.With the priority of layer coatingOverlap joint stubble width is 30 ㎜~50mm.Application of force rubs brushing back and forth during brushing, to protect Demonstrate,proving concavo-convex place can paint and answer uniform.
3. per pass coating answers thickness uniform, brush is not leaked, is not revealed the exact details.
4. after coating has been constructed, should check whether uniformly, for uneven position, it is necessary to be repaired again;If any rise Skin phenomenon, should remove peeling position, re-start base treatment, the brushing paint again after being sufficiently humidified so as to.
Maintenance:
(1) conserve particularly significant, it is necessary to conserved meticulously with water purification, when coating is in leather hard, using vaporific water curing, Avoid directly being washed away with water pipe.Need to typically spray water daily 3~5 times, continuous 72h.For the basement for drawing badly, can reduce The number of times of wet curing.
(2) less than 4 DEG C of low temperature is prevented after constructing in 48h;
(3) there must not be any phenomenon of colliding with during conserving.
Waterproof construction acceptance inspeciton
(1) checked by total consumption control methods, it is ensured that the consumption of unit area.XYPEX " concentrating agents " consumption should meet construction Specify to require in scheme, every layer of consumption control is in 0.5~0.6kg/m2, two throughout repairing overall control in 2kg/m2Within.Mixed XYPEX " concentrating agents " mortar is brushed on Xtah Crude Clay structure two times.
(2) checked with observation:Apply thickness uniform, be not allow for holiday and show-through, it is all it is undesirable should be again Finishing.
(3) coating is firmly bonded with structured base layer, and hollowing, peeling, peeling, basic unit's flawless are not allowed;Weak part adds Strong layer should be bonded firmly with basic unit, and surfacing, brushing are uniform, must not there is the defects such as trickling, fold, bubbling;
(4) the reinforcement process issue in crack repairing, steel bar end and wall pipe is illustrated by waterproof construction sequential configuration is strengthened Figure carries out operation construction (see photo).

Claims (7)

1. a kind of technique administered to underground Tipple Bottom plate seepage based on XYPEX materials, it is characterised in that in the technique During, with the use of XYPEX materials;
The XYPEX materials be XYPEX " concentrating agents " mortar and, XYPEX " concentrating agents " half-dried dough, XYPEX " admixture " One or more in mortar, XYPEX " synergist " mortar or XYPEX " sealing agent ";
Wherein, in XYPEX " concentrating agents " mortar, XYPEX " concentrating agents " powder is 5: 2~2.5 with the volume ratio of water;
In XYPEX " concentrating agents " half-dried dough, XYPEX " concentrating agents " powder is 6: 1 with the volume ratio of water;
In XYPEX " admixture " mortar, cement, the weight ratio of thick middle sand, water and XYPEX " admixture " are 1:2.5:0.4: 0.03-0.04;
XYPEX " sealing agent " dough powder is 3.5: 1 with the volume ratio of water;
XYPEX " synergist " powder is 5: 2 with the volume ratio of water.
2. technique according to claim 1, it is characterised in that the technique is comprised the following steps:Base treatment, leak stopping stop Water, privileged sites are strengthened, XYPEX " concentrating agents " mortar, maintenance, examination are brushed in layering.
3. technique according to claim 2, it is characterised in that during base treatment, basic unit first will be outer with grinding machine Carry out the eliminating impurities such as thing, loose material, greasy dirt clean, then treatment is rinsed to concrete surface with water purification, make concrete capillary Pipe is opened wide.
4. technique according to claim 2, it is characterised in that during base treatment, to percolating water crack, construction joint or Structural cracks width is more than 0.4mm's, digs into " U " type groove, and the size of groove is 30mm × 30mm or 30mm × 70mm.
5. technique according to claim 1, it is characterised in that for the construction joint in F3/B3 base plate, post-cast strip and The structural cracks through crack wide more than 0.4mm, neat seam centre chisel is first applied into " U " type groove of 30 × 30mm or 30mm × 70mm XYPEX " concentrating agents " mortar is brushed one times, compacting is made firm by ramming at " U " with the half-dried dough hands of XYPEX " concentrating agents " and hand hammer after initial set It is floating in type groove, link into an integrated entity, then apply again above and brush one times XYPEX " concentrating agents " mortar;The structure wide less than 0.4mm is split It is sewn at crack and brushes twice XYPEX " concentrating agents " mortar reinforcement treatment.
6. technique according to claim 1, it is characterised in that for through walls on the structure wall in F3/B3 base plate The weak parts such as pipe, sleeve pipe, bolt need to do consolidation process, to weakness such as embedded wall penetration sleeve pipe, reserved steel bar head, the turnover mouths of pipe Upstream face dig into " U " type groove of 30 × 30mm, the interior water of groove washes away totally, and removes surface Ming Shui, then to brush XYPEX " dense Contracting agent " mortar after after initial set, then the half-dried dough pointings of XYPEX " concentrating agents " is entered in seam in " U " type groove, is smash with hand or hammer In tangible " U " type groove of solid pressure, and seam both sides are floating with basal plane, after the completion of brush one XYPEX " concentrating agents " mortar again.Both sides Each extension brushes 50~100 ㎜.
7. technique according to claim 1, it is characterised in that for the steel bar end in F3/B3 base plate, by steel bar end Excision, and make its recessed structures surface about 20mm, first brush one XYPEX " concentrating agents " mortar bed, Ran Houyong after cleaning, cleaning XYPEX " admixture " mortar pointing, tamping sealing brushes one layer of XYPEX " concentrating agents " above again after pointing material is pre-hardening Mortar bed.
CN201511008597.5A 2015-12-29 2015-12-29 A kind of technique administered to underground Tipple Bottom plate seepage based on XYPEX materials Pending CN106930337A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201511008597.5A CN106930337A (en) 2015-12-29 2015-12-29 A kind of technique administered to underground Tipple Bottom plate seepage based on XYPEX materials

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201511008597.5A CN106930337A (en) 2015-12-29 2015-12-29 A kind of technique administered to underground Tipple Bottom plate seepage based on XYPEX materials

Publications (1)

Publication Number Publication Date
CN106930337A true CN106930337A (en) 2017-07-07

Family

ID=59458975

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201511008597.5A Pending CN106930337A (en) 2015-12-29 2015-12-29 A kind of technique administered to underground Tipple Bottom plate seepage based on XYPEX materials

Country Status (1)

Country Link
CN (1) CN106930337A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109667294A (en) * 2017-10-17 2019-04-23 上海宝冶集团有限公司 The casing gushed on anti-underground water in basement bored pile construction and pile-driving method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101392538A (en) * 2008-11-03 2009-03-25 江苏江中集团有限公司 Basement detail water proof method
CN102505663A (en) * 2011-10-14 2012-06-20 中煤建筑安装工程公司第七十三工程处 Method for repairing seepage of concentration tank and water tank
AU2015100834A4 (en) * 2015-06-23 2015-09-03 Petrik, George Mark Mr Waterseal Track

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101392538A (en) * 2008-11-03 2009-03-25 江苏江中集团有限公司 Basement detail water proof method
CN102505663A (en) * 2011-10-14 2012-06-20 中煤建筑安装工程公司第七十三工程处 Method for repairing seepage of concentration tank and water tank
AU2015100834A4 (en) * 2015-06-23 2015-09-03 Petrik, George Mark Mr Waterseal Track

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
贾嘉陵等: "中国人寿数据中心底板结构渗漏防水治理研究", 《中国建筑学会施工与建材分会防水技术专业委员会换届年会暨防水堵漏工程"系统"应用技术交流会论文集》 *
韩喜林: "《新型防水材料应用技术》", 31 March 2003, 中国建材工业出版社 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109667294A (en) * 2017-10-17 2019-04-23 上海宝冶集团有限公司 The casing gushed on anti-underground water in basement bored pile construction and pile-driving method

Similar Documents

Publication Publication Date Title
CN101565997A (en) Construction method for large-area irregular floor tile
CN109336531A (en) A kind of two-component penetrant crystalline distress in concrete waterproof repair liquid and construction method
CN107143111A (en) A kind of construction method of abrasion-proof terrace
CN102776897A (en) Wash apron anti-settling anti-cracking construction method and structure
CN104153401A (en) Waterproof construction method for anti-floating anchor rods
CN106810155A (en) Tunnel reinforcement lining cutting, injection steel fibre new-old concrete adhesive bonding method and adhesive
CN203654485U (en) Polyurethane foaming plugging structure for shear wall bolt hole
CN101545269B (en) Method for rigid waterproof construction of beam and slab type basement
CN2921135Y (en) Special concrete crack induction strip for concrete construction joint
CN101560777A (en) Waterproof construction method for bottom plate of basement with anti-float anchor rod
CN111535322A (en) Distorted concrete construction method with bottom grouting
CN110714781A (en) Tunnel expansion joint repairing method
CN102344278B (en) Permeable crystallization type cement-based waterproof mucilage
CN106930337A (en) A kind of technique administered to underground Tipple Bottom plate seepage based on XYPEX materials
CN112408851A (en) Anti-radiation semi-permanent nano-penetration crystallization sealing compacting agent and use method thereof
CN109162732A (en) A kind of shotcrete construction method
CN106759979A (en) A kind of external wall exterior heat preserving construction technique
CN103774696A (en) Construction process of cement-based permeable-crystallization type waterproof material
KR20130113568A (en) Concrete crack repair method and repair mortar manufacturing method
CN202577381U (en) Repairing and reinforcing structure for ocean splash zone pile foundation
CN102535493B (en) Method for constructing inverted type foundation beam
CN104452813B (en) A kind of underground power house gate shaft protected against the effects of immersion method
CN106930417A (en) It is a kind of based on XYPEX materials to circulating water pool antiseepage water-tight corrosion-proof concrete structure reinforcement and repair technique
CN106930548A (en) A kind of technique processed deformation joint seepage based on XYPEX materials
CN211705994U (en) High-efficient sedimentation tank

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170707