CN106930196A - Pier top double pad cooperative bearing method when steel trussed beam cantilever is assembled - Google Patents

Pier top double pad cooperative bearing method when steel trussed beam cantilever is assembled Download PDF

Info

Publication number
CN106930196A
CN106930196A CN201710325861.0A CN201710325861A CN106930196A CN 106930196 A CN106930196 A CN 106930196A CN 201710325861 A CN201710325861 A CN 201710325861A CN 106930196 A CN106930196 A CN 106930196A
Authority
CN
China
Prior art keywords
pad
steel
row
cantilever
truss girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710325861.0A
Other languages
Chinese (zh)
Other versions
CN106930196B (en
Inventor
李有为
唐启
马勇
韩治忠
项梁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
CCCC SHEC Fourth Engineering Co Ltd
CCCC Highway Long Bridge Construction National Engineering Research Center Co Ltd
Original Assignee
CCCC Second Harbor Engineering Co
CCCC SHEC Fourth Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co, CCCC SHEC Fourth Engineering Co Ltd filed Critical CCCC Second Harbor Engineering Co
Priority to CN201710325861.0A priority Critical patent/CN106930196B/en
Publication of CN106930196A publication Critical patent/CN106930196A/en
Application granted granted Critical
Publication of CN106930196B publication Critical patent/CN106930196B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • E01D21/105Balanced cantilevered erection

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses pier top double pad cooperative bearing method during a kind of assembly of steel trussed beam cantilever, belong to technical field of bridge engineering;It is specifically included in during steel trussed beam cantilever assembly, by in continuous Dun Dundingchu, one row's heel row pad is first set, after the several internodes of free cantilever erection, with the rule of development that free cantilever erection deforms, the front-seat pad of second row is set up in continuous pier pier top, do not padded first when front-seat pad is installed, and reserved 1 2mm gaps, as steel truss girder continues free cantilever erection, front-seat pad is gradually compacted, and undertaken load is increasing, thus, two row's pads coordinate stress, the load undertaken to the maximum cantilever assembly row's pad of state two is suitable, so as to improve the stress of pier top regional structure when steel trussed beam cantilever is constructed, reduce construction risk.

Description

Pier top double pad cooperative bearing method when steel trussed beam cantilever is assembled
Technical field
It is assembled the invention belongs to science of bridge building field, more particularly to steel trussed beam cantilever.
Background technology
Steel trussed beam cantilever assembling construction process is widely used in current bridge construction field, and general construction method is to use Existing method assembly first across steel truss girder, then in the case where support is not set up free cantilever erection second across steel truss girder.Second During across steel trussed beam cantilever assembly, one row's pad is set in continuous pier pier top and is supported.
In the case, at continuous pier pier top second across steel truss girder and the first across steel truss girder connecting portion, steel must both be born Moment of flexure under trusses great cantilever assembly state, bears the shearing that the deadweight of cantilever erection girder steel causes again, forms curved scissors combination, right Structural system stress has a negative impact.
The content of the invention
It is an object of the invention to:In view of the shortcomings of the prior art, it is continuous when proposing that a kind of steel trussed beam cantilever is assembled The double pad cooperative bearing adaptive approach of pier pier top, the double pad that continuous Dun Dundingchu is set in the method can be in steel truss girder Coordinate stress during free cantilever erection, and under maximum cantilever assembly state, realize that two row's pad stress are substantially uniform, so as to change The stress of pier top regional structure, reduces construction risk when kind steel trussed beam cantilever is constructed.
The object of the invention is realized by following technical proposals:
A kind of pier top double pad cooperative bearing method when steel trussed beam cantilever is assembled, comprises the following steps:Constructing certain One across after steel truss girder, and next across steel truss girder, and across steel truss girder handing-over position setting is connected temporarily and free cantilever erection is next across steel truss Liang Shi, row's heel row pad is first set by continuous Dun Dundingchu, and in several sections of next across steel trussed beam cantilever assembly Between after, then set up row front row pad in continuous pier pier top, and front-seat pad is installed opportunity and be should be, and is being provided only with heel row pad In the case of, if it is X to calculate the maximum lower flexure strain value produced with respect to heel row branch pad position at front-seat pad, work as cantilever shalving If after N number of internode, if relative heel row branch pad position lower flexure strain value reaches 0.5X or more at front-seat pad, setting up N Start that front-seat pad is installed after individual internode;Front-seat pad and heel row pad are pressed steel trussed beam cantilever assembly direction front and rear row and are set, and Front of the front-seat pad in the steel trussed beam cantilever assembly direction of heel row pad;Heel row pad is using rigid branch pad mode, front row branch Pad uses partially flexible branch pad mode, and front-seat pad top surface reserves certain clear height with steel truss soffit.
Alternatively, using Support Method assembly first across steel truss girder, then in the second steel truss across steel truss girder and its afterwards Beam is using front-seat pad and the free cantilever erection of the double pad of heel row pad.
Alternatively, in addition to top surface or bottom surface set copper plate or stereotype, remaining is by some steel plates or steel for heel row pad Structure cushion block stacking composition.
Alternatively, front-seat pad is made up of some steel plates or steel construction cushion block and rubber cushion blocks stacking.
Alternatively, front-seat pad top surface and the reserved 1-2mm clear height in steel truss soffit.
Foregoing main scheme of the invention and its each further selection scheme can be this with independent assortment to form multiple schemes Invention can be used and claimed scheme;And the present invention, between (each non conflicting selection) selection and and other selections between Can also independent assortment.Those skilled in the art can understand have after the present invention program is understood according to prior art and common knowledge Multiple combination, is claimed technical scheme of the invention, and exhaustion is not done herein.
The course of work is:Free cantilever erection is next across steel truss girder and previous across the steel truss girder company for having constructed at continuous pier pier top Socket part position, must both bear steel truss girder great cantilever assembly state under moment of flexure, bear again cantilever erection girder steel deadweight cause cut Power, forms curved scissors combination, has a negative impact to structural system stress.In the prior art, in next across steel trussed beam cantilever assembly During, one row's pad is set in continuous pier pier top and is supported.The single pad stress is excessive, and as steel trussed beam cantilever is spelled The increase of length is filled, its cantilever deflection is increased.If using the double pad of front and rear row, the erection opportunity of the front-seat pad for increasing newly It is crucial, if support too early, may cause most of load transfer to front-seat pad so that front-seat pad stress is excessive, If supporting too late, may cause most of load still in heel row pad so that heel row pad stress is excessive, only opportunity Appropriately, the double pad producing balanced forces of front and rear row could be realized, about 50% or so is each shared.Thus, when free cantilever erection is continued, Reach double pad counter-force dynamic equilibrium, realize " two row's pads realize cooperative bearing ", solve double at pier top in work progress Arrange uniformity of the pad in the most unfavorable processing condition lower stress, and then pier top region steel truss girder stress when improving cantilever construction.
By taking certain bridge across steel truss erections of 112m as an example, 10 internodes are often set altogether across steel truss girder, in steel truss girder using branch Frame method or other method set up and complete first across after steel truss girder, by second across steel truss girder and the first across steel truss girder handing-over position Interim connection is set, temporary continuation state is realized, then in the case where support is not set up free cantilever erection second across steel truss girder. During second across steel trussed beam cantilever preceding four internodes of assembly, one row's pad is only set in continuous pier pier top and is supported, i.e., only Heel row pad.Wherein, using " the rigid branch pad mode " substantially without compression, i.e., the pad is all by steel plate group for heel row pad Into.
As steel truss girder continues free cantilever erection forward, to the 5th internode free cantilever erection, set up in continuous pier pier top One row's pad, i.e., (front-seat pad uses " partially flexible branch pad mode " to front-seat pad, i.e., pad is by steel plate and rubber cushion blocks group Into adapting to a small amount of compression), now front-seat pad is not padded, and 1-2mm gaps are stayed between pad and girder steel bottom surface;With Steel truss girder and continue free cantilever erection forward, steel truss girder continues downwarp under Gravitative Loads at front-seat pad, so as in free cantilever erection Realize being padded naturally at front-seat pad during six, the seven internodes, hereafter, front-seat pad is functioned to, and shares continuous Dun Dun Girder steel load at top.
As steel truss girder continues free cantilever erection, it is increasing to undertake load at front-seat pad, to free cantilever erection to the 9th Internode is completed, and when carrying out the most unfavorable processing condition condition of upper pier between protelum, the load that front-seat pad is shared reaches maximum, and rear Row's pad quite, is achieved in, " double pad coordination stress ", so as to improve pier top regional structure when steel trussed beam cantilever is constructed Stress, reduces construction risk.
Beneficial effects of the present invention:Technical solution of the present invention is primarily adapted for use in the construction of continuous steel girder cantilever erection.Pass through Continuous pier pier top double pad cooperative bearing adaptive approach when steel trussed beam cantilever is assembled, continuous Dun Dundingchu is set in the method Double pad can coordinate stress during steel trussed beam cantilever assembly, and under maximum cantilever assembly state, realize two row's branch Pad stress is substantially uniform, so as to improve the stress of pier top regional structure when steel trussed beam cantilever is constructed, reduces construction risk.
Brief description of the drawings
Heel row pad individually supports stress schematic diagram when Fig. 1 is steel trussed beam cantilever assembly former internodes;
Fig. 2 is assembled support stress schematic diagram when front-seat pad is set up after certain internode of steel trussed beam cantilever;
Fig. 3 is steel trussed beam cantilever assembled to the double bolster support stress schematic diagram under maximum cantilever state;
Fig. 4 is holding state schematic diagram when front-seat pad is just installed in Fig. 2;
Fig. 5 is holding state schematic diagram of the front-seat pad after steel truss girder continues assembled deformation compacting in Fig. 2;
Wherein 1-bridge pier, 2-set up completion across steel truss girder, 3-free cantilever erection across steel truss girder, 4-interim connection, 5- Heel row pad, 6-front-seat pad, 7-general steel plate, 8-copper sheet or rolled lead, 9-rubber cushion blocks, 10-thin stainless steel Plate, 11-gap.
Specific embodiment
Following non-limiting examples are used to illustrate the present invention.
Referring to figs. 1 to showing 3 bridge piers shown in 5, in figure, two across in steel truss girder, figure from left to right for set up completion across Steel truss girder 2 and free cantilever erection are from left to right free cantilever erection across the assembled direction of steel truss girder 3 across steel truss girder 3.A kind of steel truss girder hangs Pier top double pad cooperative bearing method when arm is assembled, comprises the following steps:A certain (completion has been set up having constructed across steel truss girder Across steel truss girder 2) after, it is next (to have set up and complete across steel truss girder 2) across steel truss girder with this across steel truss girder (free cantilever erection is across steel truss girder 3) Handing-over position sets interim connection 4 and free cantilever erection is next when steel truss girder (free cantilever erection is across steel truss girder 3), by continuous pier One row's heel row pad 5 is first set at pier top, and after next several internodes of across steel trussed beam cantilever assembly, then in continuous Dun Dun Row front row pad 6 is set up on top, and the front-seat installation opportunity of pad 6 should be, in the case where heel row pad 5 is provided only with, if meter The maximum lower flexure strain value for calculating to be produced with respect to the position of heel row pad 5 at front-seat pad 6 is X, when the N number of internode of cantilever erection Afterwards, if the relative position lower flexure strain value of heel row pad 5 reaches 0.5X or more at front-seat pad 6, after n-th internode is set up Start that front-seat pad 6 is installed;Front-seat pad 6 and heel row pad 5 are set by free cantilever erection across the free cantilever erection direction front and rear row of steel truss girder 3 Put, and front-seat pad 6 is in the front in the steel trussed beam cantilever assembly direction of heel row pad 5;Heel row pad 5 is using rigid pad side Formula, front-seat pad 6 uses partially flexible branch pad mode, and the front-seat top surface of pad 6 reserves one with free cantilever erection across the bottom surface of steel truss girder 3 Determine clear height.
By taking certain bridge across steel truss erections of 112m as an example, 10 internodes, with reference to shown in Fig. 1, Fig. 1 are often set altogether across steel truss girder Middle free cantilever erection across the free cantilever erection of steel truss girder 3 between Section 4, through analysis, in free cantilever erection across the cantilever erection process of steel truss girder 3 In, as cantilever is lengthened, under conditions of continuous pier pier top only has the support of heel row pad 5, girder steel will be with big outstanding at front-seat pad 6 Arm support sets and gradually reduces, and peak stress later amplification between cantilever erection Section 5 is obvious, in free cantilever erection between Section 10 During pier, pier top regional stress value reaches maximum rating.
If setting two row's pads in continuous pier pier top and making its uniform stressed, interim junction shearing will be greatly reduced, Front and rear each internode stress will also make moderate progress.If but support too early, most of load transfer may be caused to preceding Row pad on, and if support too late, may cause most of load still in heel row pad so that heel row pad stress mistake Greatly.
The fulcrum discrepancy in elevation and steel truss stress beam summary sheet when the heel row pad of table 1 is individually supported
Drawn from table 1:Add up deformation difference when the 6th or 7 internode of completion is set up, at steel truss girder rear fulcrum and exceed half More than, and steel truss girder stress level is acceptable, now, in the case where heel row pad 5 is provided only with, (is calculated through theoretical calculation Method can be using existing various methods well known in the art, such as the most frequently used finite element analysis Structure Calculation) obtain front-seat pad 6 The maximum lower flexure strain value that place produces with respect to the position of heel row pad 5 is X, after 5 internodes of cantilever erection, at front-seat pad 6 0.5X or more is reached with respect to the position lower flexure strain value of heel row pad 5;Therefore may be selected before 6 or 7 internodes set up completion in steel Padded using rubber cushion blocks at the fulcrum of beam front end, pad force request can be met, in reduction before pier steel truss girder peak stress.Adopt After taking measure, analysis pads (without deformation) completely by between erection Section 7, and as a result as shown in table 2, each reaction of supports is in maximum Reached during cantilever with stress level assumes the basically identical of calculating with above uniform stressed.
Front-seat pad pads rear each internode and sets up stressing conditions when being set up between the Section 7 of table 2
Analyzed according to more than, after the completion of being set up after the completion of being set up between Section 6 or between Section 7, carried out firm at front-seat pad Property pad, the most favourable to the distribution of front and rear row pad load, now steel truss stress beam is in kilter, and meeting specification will Ask.Therefore, emphasis is taken measures in work progress, it is ensured that rigid pad " is setting up after the completion of being set up between Section 6, between Section 7 Before completion " reach compacting loaded state.Specific control method is as follows:
1. heel row pad 5 is contour is inserted into the 5th internode;Heel row pad 5, using " rigid branch pad mode ", i.e., the pad is complete Portion is made up of pad general steel plate 7, and its top surface or ground set copper sheet or rolled lead 8, to adapt to micro-deformation needs.
2. front-seat pad 6, fulcrum requirement are set at front-seat fulcrum:
A, in view of front-seat pad 6 is fixed pad, slide block structure need to be set in front-seat pad 6, in order to it in temperature Freely stretched under degree change condition.
B, front-seat pad 6, using " partially flexible branch pad mode ", i.e. pad cushion block by stiffness bearer (general steel plate 7) and The two parts of rubber cushion blocks 9 are constituted, and adapt to a small amount of compression.
Two pieces of 80mm thickness rubber cushion blocks are respectively provided with C, front-seat pad 6, are easy to installation between Section 6 to adapt to one after padding Fixed elastic compression.
After D, the 5th internode installation, front-seat pad 6 is carried out, total height about 300mm is pre- at the top of it after pad pad Certain clear height is stayed, with reference to shown in Fig. 4, the top surface of front-seat pad 6 and free cantilever erection leave gap between the bottom surface of steel truss girder 3.
3. with reference to shown in Fig. 2, steel trussed beam cantilever assembly is between Section 6 in Fig. 2.After taking above pad measure, it can be ensured that Pad " is set up before completing " after completing between Section 6, between Section 7 in cantilever erection for steel truss girder and girder steel reaches the state of padding, So as to continuous pier pier top front and rear row pad stress be coordinated to optimal interval.With reference to shown in Fig. 5, the top surface of front-seat pad 6 and cantilever Assembly is compacted between the bottom surface of steel truss girder 3.
Presently preferred embodiments of the present invention is the foregoing is only, is not intended to limit the invention, it is all in essence of the invention Any modification, equivalent and improvement made within god and principle etc., should be included within the scope of the present invention.

Claims (5)

1. a kind of pier top double pad cooperative bearing method when steel trussed beam cantilever is assembled, it is characterised in that comprise the following steps: Construct a certain across after steel truss girder, it is next that interim connection and under free cantilever erection is set with across steel truss girder handing-over position is somebody's turn to do across steel truss girder One it is across steel truss girder when, one row's heel row pad is first set by continuous Dun Dundingchu, and in next across steel trussed beam cantilever assembly After several internodes, then row front row pad is set up in continuous pier pier top, and front-seat pad installation opportunity should be, and be provided only with In the case of heel row pad, if it is X to calculate the maximum lower flexure strain value produced with respect to heel row branch pad position at front-seat pad, After cantilever erection N number of internode, if relative heel row branch pad position lower flexure strain value reaches 0.5X or more at front-seat pad, After setting up n-th internode start that front-seat pad is installed;Front-seat pad and heel row pad press steel trussed beam cantilever assembly direction front and rear row Set, and front-seat pad is in the front in the steel trussed beam cantilever assembly direction of heel row pad;Heel row pad uses rigid branch pad mode, Front-seat pad uses partially flexible branch pad mode, and front-seat pad top surface reserves certain clear height with steel truss soffit.
2. pier top double pad cooperative bearing method when steel trussed beam cantilever as claimed in claim 1 is assembled, it is characterised in that:Adopt With Support Method assembly first across steel truss girder, then in the second steel truss girder across steel truss girder and its afterwards using front-seat pad and heel row The free cantilever erection of the double pad of pad.
3. pier top double pad cooperative bearing method when steel trussed beam cantilever as claimed in claim 1 is assembled, it is characterised in that:Afterwards In addition to top surface or bottom surface set copper plate or stereotype, remaining is by some steel plates or steel construction cushion block stacking composition for row's pad.
4. pier top double pad cooperative bearing method when steel trussed beam cantilever as claimed in claim 1 is assembled, it is characterised in that:Before Row's pad is made up of some steel plates or steel construction cushion block and rubber cushion blocks stacking.
5. pier top double pad cooperative bearing method when steel trussed beam cantilever as claimed in claim 1 is assembled, it is characterised in that:Before Row's pad top surface and the reserved 1-2mm clear height in steel truss soffit.
CN201710325861.0A 2017-05-10 2017-05-10 Pier top double support pad cooperative bearing method when steel trussed beam cantilever assembly Active CN106930196B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710325861.0A CN106930196B (en) 2017-05-10 2017-05-10 Pier top double support pad cooperative bearing method when steel trussed beam cantilever assembly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710325861.0A CN106930196B (en) 2017-05-10 2017-05-10 Pier top double support pad cooperative bearing method when steel trussed beam cantilever assembly

Publications (2)

Publication Number Publication Date
CN106930196A true CN106930196A (en) 2017-07-07
CN106930196B CN106930196B (en) 2018-08-24

Family

ID=59429433

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710325861.0A Active CN106930196B (en) 2017-05-10 2017-05-10 Pier top double support pad cooperative bearing method when steel trussed beam cantilever assembly

Country Status (1)

Country Link
CN (1) CN106930196B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1359392A1 (en) * 1986-06-04 1987-12-15 Центральный научно-исследовательский и проектный институт строительных металлоконструкций им.Н.П.Мельникова Multispan bridge
US5072474A (en) * 1989-07-12 1991-12-17 Dilger Walter H Bridge construction
CN101139821A (en) * 2007-10-16 2008-03-12 中铁大桥局集团第四工程有限公司 Method and system for erecting steel trusses by stay cable auxiliary complete cantilever
CN102121234A (en) * 2011-04-23 2011-07-13 中铁三局集团有限公司 Quick construction method of two-tower five-span steel truss girder cable-stayed bridge
CN105256728A (en) * 2015-09-02 2016-01-20 中铁大桥局集团有限公司 Cable-stayed bridge warren steel truss cantilever erection method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1359392A1 (en) * 1986-06-04 1987-12-15 Центральный научно-исследовательский и проектный институт строительных металлоконструкций им.Н.П.Мельникова Multispan bridge
US5072474A (en) * 1989-07-12 1991-12-17 Dilger Walter H Bridge construction
CN101139821A (en) * 2007-10-16 2008-03-12 中铁大桥局集团第四工程有限公司 Method and system for erecting steel trusses by stay cable auxiliary complete cantilever
CN102121234A (en) * 2011-04-23 2011-07-13 中铁三局集团有限公司 Quick construction method of two-tower five-span steel truss girder cable-stayed bridge
CN105256728A (en) * 2015-09-02 2016-01-20 中铁大桥局集团有限公司 Cable-stayed bridge warren steel truss cantilever erection method

Also Published As

Publication number Publication date
CN106930196B (en) 2018-08-24

Similar Documents

Publication Publication Date Title
Fleischman et al. Seismic behavior of precast parking structure diaphragms
CN109344437B (en) Reinforced concrete complex stress component reinforcement design method based on force transmission path
CN101435182B (en) Steel bridge folding temporary locking method
CN104533105B (en) A kind of Strengthening by Steel-Packing post pre-applied force device
CN106948268A (en) Variable Section Steel box beam pushing tow is combined the unit and application method
CN107034790B (en) Method for reducing support internal force during steel beam symmetrical double-cantilever assembly
CN108149591A (en) Bridge superstructure deviation correcting device and method based on jack counter-force self-balancing
CN111428296B (en) Pre-camber design method for continuous steel truss girder
JP2000282413A (en) Launching machine with deflection eliminator
CN206887788U (en) Pier top double pad cooperative bearing system during steel trussed beam cantilever assembly
CN106930196A (en) Pier top double pad cooperative bearing method when steel trussed beam cantilever is assembled
Savage et al. Behavior and design of double tees with web openings
RU2346878C2 (en) Method for unloading deteriorating reinforced-concrete cantilevers
CN109056533B (en) Method for determining bridge-forming cable force of cable cooperation system bridge
CN203546599U (en) Pier-side bracket
CN208455499U (en) Bridge superstructure deviation correcting device based on jack counter-force self-balancing
CN109577201A (en) A kind of walking constructing device and its construction method for steel truss girder pushing tow
CN205224266U (en) Overlength super large area bottom plate post -cast strip structure
CN108103953A (en) Suitable for high-block bridge degree steel truss girder bridge double-slider push construction method
CN113718662B (en) Pushing and sliding method suitable for steel truss girder with complex vertical curve
CN109555021A (en) It is a kind of without pre-buried, movable continuous beam 0# block bracket
CN102383529B (en) Method for determining relation between stiffness reduction of steel concrete beam under use bending moment and reinforcement ratio
CN201786040U (en) Temporary supporting structure suitable for reinforced concrete plate beam
US4343123A (en) Composite bridge with precompression system
CN210002824U (en) Large-span arch curved surface grid roof construction platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20210902

Address after: 241009 R & D Center (buildings 4 and 5), No. 17-8 Fumin Road, Jiujiang Economic Development Zone, Jiujiang District, Wuhu City, Anhui Province

Patentee after: CCCC SHEC FOURTH ENGINEERING Co.,Ltd.

Patentee after: The Second Harbor Engineering Co.

Patentee after: CCCC HIGHWAY BRIDGES NATIONAL ENGINEERING RESEARCH CENTER Co.,Ltd.

Address before: 241009 Building 1, West Side of Innovation Road, Jiujiang Economic Development Zone, Wuhu City, Anhui Province

Patentee before: CCCC SHEC FOURTH ENGINEERING Co.,Ltd.

Patentee before: The Second Harbor Engineering Co.