CN106917462A - A kind of cavity thin-wall reinforced concrete wallboard fills out core construction method - Google Patents

A kind of cavity thin-wall reinforced concrete wallboard fills out core construction method Download PDF

Info

Publication number
CN106917462A
CN106917462A CN201710330324.5A CN201710330324A CN106917462A CN 106917462 A CN106917462 A CN 106917462A CN 201710330324 A CN201710330324 A CN 201710330324A CN 106917462 A CN106917462 A CN 106917462A
Authority
CN
China
Prior art keywords
wall
high density
reinforcing bar
thin
density foam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710330324.5A
Other languages
Chinese (zh)
Other versions
CN106917462B (en
Inventor
陈明宝
刘祖国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201710330324.5A priority Critical patent/CN106917462B/en
Publication of CN106917462A publication Critical patent/CN106917462A/en
Application granted granted Critical
Publication of CN106917462B publication Critical patent/CN106917462B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ

Abstract

Core construction method is filled out the invention discloses cavity thin-wall reinforced concrete wallboard, is carried out according to the following steps:1) surveying setting-outs, coordinate and center line datum mark according to job site SURVEYING CONTROL NETWORK throw 500 lines of survey with total powerstation or transit survey instrument outside every floor cornice sheathing;2) sets up shelf branch outboard template, and core body is filled out in reinforcing bar on the outside of colligation, pre-buried additional bar, support;3) processes hard high density foam by physical dimension, and hard high density foam is installed in segmentation;4) embedded U-shapeds reinforcing bar positioning;5) colligations inner side reinforcing bar, branch inner side template and reinforce;6) multi-cavities thin-wall slab reinforced concrete cast, using the symmetrical laminated pouring concrete of DLC, controls reinforced concrete structure size.It is an advantage of the invention that it is simple and practical, save man-hour, reduces cost, it is easy to construction.

Description

A kind of cavity thin-wall reinforced concrete wallboard fills out core construction method
Technical field
Core construction party is filled out the present invention relates to technical field of building construction, more particularly to cavity thin-wall reinforced concrete wallboard Method.
Background technology
Pursuit with people to architectural image, non-rectangle, cavity, thin-wall reinforced concrete structure are big in engineering design Amount application, in order to save armored concrete, its armored concrete wall thickness only has 150mm to this structure, even more small, mostly cavity And section is irregular.In order to ensure physical dimension, there is certain difficulty in the construction of this kind of structure.
The content of the invention
The problem that the purpose of the present invention exists aiming at prior art, there is provided cavity thin-wall reinforced concrete wallboard fills out core Construction method, the technical problem to be solved is, because cavity size is small, how to ensure that reinforced concrete structure size is in cavity How key, ensure in concreting process, template is not moved.
The object of the present invention is achieved like this:Cavity thin-wall reinforced concrete wallboard fills out core construction method, and its feature exists In carrying out according to the following steps:
1) surveying setting-outs:Coordinate and center line datum mark according to job site SURVEYING CONTROL NETWORK, with total powerstation or longitude and latitude Instrument measuring instrument to have been poured into a mould thrown outside concrete panel on every floor and surveyed 500 lines, then to go out cavity with tape measure snap the line thin-wall reinforced mixed The physical dimension of solidifying each side of cob wall template;
2) sets up shelf branch outboard template, and core body is filled out in reinforcing bar on the outside of colligation, pre-buried additional bar, support;
3) processes hard high density foam by physical dimension, and hard high density foam, hard high density are installed in segmentation Foams outside soft leather bound edge turns into R.C. wall board fills out core, and hard high density foam and soft leather bound edge are used as more The template of " inner bag " shell in chamber, outside is bundled with plastic adhesive tape;
4) embedded U-shapeds reinforcing bar positioning;
5) colligations inner side reinforcing bar, branch inner side template and with H200 type flitch back cords and back cord reinforcing, diameter 16mm to drawing spiral shell Bolt passes through PVC sleeve pipes, and PVC outer tubes are, when thin-wall internal-mould plate is shored, and for the sleeve pipe of split bolt, to control to fix it on an empty stomach With wall physical dimension;
6) multi-cavities thin-wall slab reinforced concrete cast, using the symmetrical laminated pouring concrete of DLC, control reinforcing bar is mixed Xtah Crude Clay structure size.
Step 3) the hard high density foam, it is the foamed polystyrene of 20-30kg/m3, soft leather bound edge is 4mm Polypropylene.
Step 4) the U-shaped reinforcing bar spacing according to depending on hard high density foam rigidity, dispose concrete cover, Every layer of hard high density foam and soft leather bound edge upper end are sealed using horizontally U-shaped reinforcing bar, hard when control concrete is poured into a mould High density foam and the displacement up and down of soft leather bound edge.
Step 5) internal model shores, in addition to PVC outer tubes before matched moulds, weld horizontal bar dowel positioning, length=wall Thickness -1mm;Drum reinforcing bar Control architecture position is welded into pre-buried vertical dowel point, in two rows the center of cage bar point gear, Ying Xian Four angles installation side of each cavity is rigidly in position, split bolt bar is extracted during dismounting out.
Step 6) the symmetrical laminated pouring concrete of DLC is to use a diameter 100mm conveying steel pipe and connect Bifurcated is DLC perpendicular to two 80mm self-control steel pipes of thin-walled, and with symmetrical laminated pouring concrete, symmetrical laminated pouring can Avoid liner hard high-density foam displacement body.
Compared with prior art, it is an advantage of the invention that:Practicality is not only simple, man-hour is saved, reduces cost is easy to apply Work.
Brief description of the drawings
Fig. 1:Wallboard floor map of the present invention.
Fig. 2:Wallboard profile of the present invention.
Fig. 3:Wallboard local nodes detail drawing of the present invention.
In figure:1st, split bolt 2, outboard template 3, outside reinforcing bar 4, U-shaped reinforcing bar 5, hard high density foam 6, PVC sleeve pipes 7, soft leather bound edge 8, H200 type flitches back cord 9, multi-cavity thin-walled wallboard 10, concrete 11, wallboard is poured into a mould Core 12, back cord .. 13, weld horizontal bar dowel are filled out in concrete.
Specific embodiment
To further describe the present invention, with reference to embodiment and accompanying drawing, the invention will be further described.
As illustrated, a kind of hanging type steel structure high-altitude operation mobile platform fast construction method, it is characterised in that by with Lower step is carried out:
1) surveying setting-outs:Coordinate and center line datum mark according to job site SURVEYING CONTROL NETWORK, with total powerstation or longitude and latitude Instrument measuring instrument has been poured into a mould outer throwing of concrete panel 10 on every floor and has surveyed 500 lines, then to go out cavity with tape measure snap the line thin-wall reinforced The physical dimension of each side of concrete wall template;
2) sets up shelf branch outboard template 2, and core body 5 is filled out in reinforcing bar 3 on the outside of colligation, the support of embedded U-shaped reinforcing bar 4;
3) by physical dimension processing hard high density foam 5, hard high density foam 5 is installed in segmentation to, and hard is highly dense The outside soft leather bound edge 7 of degree foams 5 in R.C. wall board as filling out core 11, hard high density foam 5 and soft suitcase Side 7 as " inner bag " shell of multi-cavity template, outside is bundled with plastic adhesive tape;
4) embedded U-shapeds reinforcing bar 4 is positioned;
5) colligations inner side reinforcing bar 3, branch inner side template 2 and reinforced with H200 type flitches back cord 8 and back cord 12, diameter 16mm Split bolt 1 passes through PVC sleeve pipes 6, PVC outer tubes 6 to be shored when thin-wall internal-mould plate, and for the sleeve pipe 6 of split bolt 1, every layer Template bottom and top in the side weld horizontal bar dowel of split bolt PVC outer tubes 6, control fix its on an empty stomach with wall dimensioning It is very little;
6) armored concrete of multi-cavities thin-walled wallboard 9 cast, using the symmetrical laminated pouring concrete of DLC, controls reinforcing bar Concrete structure size.
Step 3) the hard high density foam 5, it is the foamed polystyrene of 20-30kg/m3, soft leather bound edge 7 is The polypropylene of 4mm.
Step 4) the U-shaped reinforcing bar 4 spacing according to the rigidity of hard high density foam 5 depending on, dispose concrete protective Layer, every layer of hard high density foam 5 and the upper end of soft leather bound edge 7 are sealed using horizontally U-shaped reinforcing bar 4, control concrete cast When the hard high density foam 5 and displacement up and down of soft leather bound edge 7.
Step 5) internal model shores, and in addition to PVC outer tubes before matched moulds, weld horizontal bar dowel 13 is positioned, length= Wall thickness -1mm;Drum reinforcing bar Control architecture position is welded into pre-buried vertical dowel point, in two rows the center of cage bar point gear, should First four angles installation side of each cavity is rigidly in position, split bolt bar 1 is extracted during dismounting out.
Step 6) the symmetrical laminated pouring concrete of DLC is to use a diameter 100mm conveying steel pipe and connect Bifurcated is DLC perpendicular to two 80mm self-control steel pipes of thin-walled, and with symmetrical laminated pouring concrete, symmetrical laminated pouring can Avoid the displacement of liner hard high density foam 5.
The present invention solves the fanciful structures template system and coagulation of cavity, thin-walled in university of Kuwait project application The integrated biological pond system of native pouring technology and control structure physical dimension, changes traditional construction method and procedure connection side Formula, shortens the duration, reduces cost.

Claims (5)

1. cavity thin-wall reinforced concrete wallboard fills out core construction method, it is characterised in that carry out according to the following steps:
1) surveying setting-outs:Coordinate and center line datum mark according to job site SURVEYING CONTROL NETWORK, are surveyed with total powerstation or theodolite Measuring appratus have poured into a mould concrete panel (13) on every floor and have thrown 500 lines of survey outward, then to go out cavity with tape measure snap the line thin-wall reinforced mixed The physical dimension of solidifying each side of cob wall template;
2) sets up shelf branch outboard template (2), reinforcing bar (3) on the outside of colligation, embedded U-shaped reinforcing bar (4), and core body (5) is filled out in support;
3) processes hard high density foam (5) by physical dimension, and hard high density foam (5) is installed in segmentation, and hard is highly dense Degree foams (5) outside soft leather bound edge (7) as filling out core (11) in R.C. wall board, hard high density foam (5) and Soft leather bound edge (7) as " inner bag " shell of multi-cavity template, outside is bundled with plastic adhesive tape;
4) embedded U-shapeds reinforcing bar (4) positioning;
5) colligations inner side reinforcing bar (3), branch inner side template (2) and with H200 type flitches back cord (8) and back cord (12) reinforcing, diameter Through PVC sleeve pipes (6), PVC outer tubes (6) are when thin-wall internal-mould plate is shored, and for split bolt to 16mm split bolts (1) Sleeve pipe, every layer of template bottom and top split bolt PVC outer tube (6) side weld horizontal bar dowel, control fix its on an empty stomach with Wall physical dimension;
6) multi-cavities thin-wall slab reinforced concrete cast, using the symmetrical laminated pouring concrete of DLC, controls armored concrete Physical dimension.
2. cavity thin-wall reinforced concrete wallboard according to claim 1 fills out core construction method, it is characterised in that:Step 3) The hard high density foam, is the foamed polystyrene of 20-30kg/m3, and soft leather bound edge is the polypropylene of 4mm.
3. cavity thin-wall reinforced concrete wallboard according to claim 1 fills out core construction method, it is characterised in that:Step 4) The spacing of the U-shaped reinforcing bar (4) disposes concrete cover, every layer of hard according to depending on hard high density foam (5) rigidity High density foam (5) and soft leather bound edge (7) upper end are sealed using horizontally U-shaped reinforcing bar (4), hard when control concrete is poured into a mould High density foam (5) and soft leather bound edge (7) displacement up and down.
4. cavity thin-wall reinforced concrete wallboard according to claim 1 fills out core construction method, it is characterised in that:Step 5) The internal model is shored, in addition to PVC outer tubes before matched moulds, weld horizontal bar dowel (13) positioning, length=wall thickness -1mm;With it is pre- Bury vertical dowel point and be welded into drum reinforcing bar Control architecture position, in two rows the center of cage bar point gear, should first by each cavity Four angles installation side be rigidly in position, during dismounting extract out split bolt bar (1).
5. cavity thin-wall reinforced concrete wallboard according to claim 1 fills out core construction method, it is characterised in that:Step 6) The symmetrical laminated pouring concrete of DLC is using a diameter 100mm conveying steel pipe and connects bifurcated perpendicular to thin-walled Two 80mm self-control steel pipe be DLC, with symmetrical laminated pouring concrete, symmetrical laminated pouring can avoid liner hard high Density foam (5) displacement.
CN201710330324.5A 2017-05-11 2017-05-11 A kind of cavity thin-wall reinforced concrete wallboard fills out core construction method Active CN106917462B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710330324.5A CN106917462B (en) 2017-05-11 2017-05-11 A kind of cavity thin-wall reinforced concrete wallboard fills out core construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710330324.5A CN106917462B (en) 2017-05-11 2017-05-11 A kind of cavity thin-wall reinforced concrete wallboard fills out core construction method

Publications (2)

Publication Number Publication Date
CN106917462A true CN106917462A (en) 2017-07-04
CN106917462B CN106917462B (en) 2019-05-03

Family

ID=59568578

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710330324.5A Active CN106917462B (en) 2017-05-11 2017-05-11 A kind of cavity thin-wall reinforced concrete wallboard fills out core construction method

Country Status (1)

Country Link
CN (1) CN106917462B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109441031A (en) * 2018-12-18 2019-03-08 中铁建工集团有限公司 The open spiral stairs structure of the concealed overhanging type of structural beams and its construction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA1214657A (en) * 1983-11-03 1986-12-02 Sismo International Prefabricated structures, method for their manufacture and their use in the building industry
RU2119022C1 (en) * 1996-04-30 1998-09-20 Евгений Петрович Матвеев Method for erection of monolithic walls of buildings
CN1512019A (en) * 2002-12-30 2004-07-14 徐亚柯 Non-detachable steel net formwork for in-situ casting concrete wall and its use
CN101525917A (en) * 2009-04-21 2009-09-09 中建三局第二建设工程有限责任公司 Construction technology of wall body
CN104110083A (en) * 2013-04-16 2014-10-22 中冶天工上海十三冶建设有限公司 One-step-forming pouring construction method of ultrahigh thin wall
CN105040968A (en) * 2015-06-25 2015-11-11 中国十七冶集团有限公司 Device and method for supporting inclined high, large, empty and thin-walled reinforced concrete wall form
CN206110407U (en) * 2016-08-07 2017-04-19 宋宝玉 Building structure heat preservation integration system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA1214657A (en) * 1983-11-03 1986-12-02 Sismo International Prefabricated structures, method for their manufacture and their use in the building industry
RU2119022C1 (en) * 1996-04-30 1998-09-20 Евгений Петрович Матвеев Method for erection of monolithic walls of buildings
CN1512019A (en) * 2002-12-30 2004-07-14 徐亚柯 Non-detachable steel net formwork for in-situ casting concrete wall and its use
CN101525917A (en) * 2009-04-21 2009-09-09 中建三局第二建设工程有限责任公司 Construction technology of wall body
CN104110083A (en) * 2013-04-16 2014-10-22 中冶天工上海十三冶建设有限公司 One-step-forming pouring construction method of ultrahigh thin wall
CN105040968A (en) * 2015-06-25 2015-11-11 中国十七冶集团有限公司 Device and method for supporting inclined high, large, empty and thin-walled reinforced concrete wall form
CN206110407U (en) * 2016-08-07 2017-04-19 宋宝玉 Building structure heat preservation integration system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109441031A (en) * 2018-12-18 2019-03-08 中铁建工集团有限公司 The open spiral stairs structure of the concealed overhanging type of structural beams and its construction method
CN109441031B (en) * 2018-12-18 2023-11-14 中铁建工集团有限公司 Structure Liang Yincang type overhanging type open rotary stair structure and construction method thereof

Also Published As

Publication number Publication date
CN106917462B (en) 2019-05-03

Similar Documents

Publication Publication Date Title
CN107435544A (en) A kind of construction method of one-tunnel two-tracks composite lining shield tunnel internal structure
CN105178357B (en) Prefabricated subsurface structure under foundation trench open cutting condition and construction method for prefabricated subsurface structure under foundation trench open cutting condition
CN102996143B (en) Construction method of fully pouring tunnel inverted arch
CN101245600B (en) Construction method for generating horizontal reinforcing body by high-pressure-double-liquid rotary spray technique
CN106894422B (en) Complex environment deep foundation pit supporting construction method
CN108914965A (en) The continuous construction method of aluminum alloy mould plate for pipe gallery
CN110629744B (en) Construction process of steel pipe concrete pile of subway station
CN110331992A (en) A kind of hole daguanpeng construction method
CN105735319B (en) A kind of large diameter steel pipe stand column pile fast positioning plumbing device and construction method
CN103089014A (en) Construction method of through floor pipe
CN213710348U (en) Underground station side wall formwork supporting system combined with full support
CN105965664A (en) 3D printing system for prestressed piles and application method thereof
CN109854051A (en) A kind of large-sized concrete earthing tank segmentation casting method
CN110644363A (en) Construction method of underwater main tower of cross-river cable-stayed bridge of high-speed railway
CN108755972A (en) Prefabricated component feet and its application method
CN105089184B (en) Multi-curved concrete hollow modelling wall construction method and rhombic hollow structure formwork
CN104675405A (en) Rectangular pipe jacking machine tunnel entering auxiliary structure and construction method
CN106917462A (en) A kind of cavity thin-wall reinforced concrete wallboard fills out core construction method
CN109098207B (en) Template system of prefabricated gas cabin of underground comprehensive pipe rack and construction method
CN113417215A (en) Bridge construction method
CN105735323A (en) Shotcrete reverse construction and punching pile combined deep foundation pit retaining structure and construction method thereof
CN207905825U (en) A kind of circular cross section tunnel lining construction device three times
CN110985052A (en) Self-compacting concrete pouring construction process method
CN110273435A (en) A kind of construction of city open trench tunnel
CN109944478A (en) A kind of double-curve cooling column construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant