CN106894643A - A kind of adjustable height Interim Standard guardrail - Google Patents

A kind of adjustable height Interim Standard guardrail Download PDF

Info

Publication number
CN106894643A
CN106894643A CN201710150350.XA CN201710150350A CN106894643A CN 106894643 A CN106894643 A CN 106894643A CN 201710150350 A CN201710150350 A CN 201710150350A CN 106894643 A CN106894643 A CN 106894643A
Authority
CN
China
Prior art keywords
steel pipe
guardrail
sleeve
vertical
regulation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710150350.XA
Other languages
Chinese (zh)
Inventor
罗家宇
丁延书
罗浩
陈�胜
李翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Engineering Co Ltd
No 2 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Original Assignee
CCCC First Highway Engineering Co Ltd
No 2 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Engineering Co Ltd, No 2 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd filed Critical CCCC First Highway Engineering Co Ltd
Priority to CN201710150350.XA priority Critical patent/CN106894643A/en
Publication of CN106894643A publication Critical patent/CN106894643A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/32Safety or protective measures for persons during the construction of buildings
    • E04G21/3204Safety or protective measures for persons during the construction of buildings against falling down
    • E04G21/3223Means supported by building floors or flat roofs, e.g. safety railings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The present invention is intended to provide a kind of adjustable height Interim Standard guardrail, including one-level construction guardrail and secondary safety guardrail.One-level construction guardrail includes vertical steel pipe, horizontal steel pipe and sleeve, vertical steel pipe is anchored in ground and at least two, the top of vertical steel pipe is also welded with sleeve, and sleeve is hollow steel tube, and horizontal steel pipe is welded between every two adjacent vertical steel pipes and with adjacent two vertical steel pipes.Secondary safety guardrail includes regulation steel pipe, limiter and steel wire rope, the external diameter for adjusting steel pipe is not more than the internal diameter of sleeve, limiter is welded in the bottom of regulation steel pipe, positioned in regulation steel pipe insertion sleeve and vertically by limiter, a pair of through holes are additionally provided with the top tube wall for adjusting steel pipe, the through hole of all regulation steel pipes of steel wire penetrating, the two ends of steel wire rope are anchored in ground.It is simple structure of the present invention, easy to make, guardrail height can be simply, easily adjusted, can ensure safety, construction can be easy to again.

Description

A kind of adjustable height Interim Standard guardrail
Technical field
The present invention relates to the field of keeping the safety in production, more particularly to a kind of Interim Standard guardrail that can adjust height.
Background technology
Guardrail is essential temporary structure thing in engineering safety production work, for isolation job site, prevents people Member rushes and avoiding article from falling causes unexpected injury to play vital effect.
But at the scene in work progress, due to reasons such as place limitations, guardrail sometimes interferes with the logical of construction machinery Cross or operate, and general guardrail height is fixed, and guardrail height is forever reduced if mechanical for convenience, can not be risen To due protective action.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of adjustable height Interim Standard guardrail, it is intended to solve solid Determine the problem of height guardrail influence construction machinery operating.
In order to solve the above-mentioned technical problem, the present invention is achieved by the following technical solutions:A kind of adjustable height faces When standard guardrail, including one-level construction guardrail and secondary safety guardrail.One-level construction guardrail include vertical steel pipe, horizontal steel pipe and Sleeve, vertical steel pipe is anchored in ground and at least two, and the top of vertical steel pipe is also welded with sleeve, and sleeve is cored steel Pipe, horizontal steel pipe is welded between every two adjacent vertical steel pipes and with adjacent two vertical steel pipes.Secondary safety guardrail bag Regulation steel pipe, limiter and steel wire rope are included, the external diameter for adjusting steel pipe is not more than the internal diameter of sleeve, and limiter is welded in regulation steel pipe Bottom, positioned in regulation steel pipe insertion sleeve and vertically by limiter, be additionally provided with one on the top tube wall of regulation steel pipe To through hole, the through hole of all regulation steel pipes of steel wire penetrating, the two ends of steel wire rope are anchored in ground.
In this programme, one-level construction guardrail is a highly relatively low fixed standard guardrail, and the height of the guardrail is not with Construction is hindered to be defined.Vertical steel pipe is anchored in ground, and is fixed by welding horizontal steel pipe, and bonding strength is high, stability It is good.Height standard guardrail higher, the entirety of this guardrail are constituted after secondary safety guardrail is installed on into one-level construction guardrail Height is defined by utmost ensureing safety.Horizontal fixation is carried out by steel wire rope between the regulation steel pipe of secondary safety guardrail, It is readily disassembled.When the height of guardrail hinders mechanical execution and needs to reduce height, steel wire rope need to only be separated from ground, you can Regulation steel pipe is removed successively, and dismounting difficulty is low, and workload is small, and application is flexible.
Further, horizontal steel pipe between every two adjacent vertical steel pipes at least provided with two.Horizontal steel pipe is company The device of vertical steel pipe is connect, horizontal steel pipe sets more, then the connection between vertical steel pipe is more firm, one-level construction guardrail Bonding strength it is just higher, the damage to guardrail when machinery unintentionally encounters guardrail can be reduced in work progress.
Further, limiter is an inverted L-shaped sheet metal component, by being welded and fixed between limiter and vertical steel pipe.L Shape sheet metal component can batch making, low cost efficiency high.Can ensure simple structure and process is simple using being welded and fixed, reduce into This.
Further, the length of regulation steel pipe is not more than the length of vertical steel pipe.Due to one-level construction guardrail it is vertical It is to use to be fixedly connected between steel pipe and horizontal steel pipe, vertical steel pipe is anchored in ground, so one-level construction guardrail is used Be to be rigidly connected, intensity is high.And secondary safety guardrail is not used and is rigidly connected, so the connection of secondary safety guardrail is strong Degree is weaker than one-level construction guardrail, therefore by limiting the length of regulation steel pipe, can at utmost ensure the entirety of standard guardrail Intensity.
Compared with prior art, usefulness of the present invention is:This adjustable height Interim Standard guard bar structure is simple, Easy to make, while the characteristics of having adjustable-height, and adjusting method is simple, easily realize, can isolate job site guarantor Barrier safety, and can be mechanical normal operation provides convenient.
Brief description of the drawings
The present invention is further described below in conjunction with the accompanying drawings.
Fig. 1 is this adjustable height Interim Standard guardrail positive structure schematic.
Fig. 2 is this adjustable height Interim Standard guardrail side structure schematic diagram.
Fig. 3 is this adjustable height Interim Standard guardrail overlooking the structure diagram.
In figure:1st, vertical steel pipe;2nd, horizontal steel pipe;3rd, sleeve;4th, steel pipe is adjusted;5th, limiter;6th, steel wire rope;7th, lead to Hole.
Specific embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, it is right below in conjunction with drawings and Examples The present invention is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, and It is not used in the restriction present invention.
Adjustable height Interim Standard guardrail as shown in Figure 1, Figure 2 and Figure 3, including one-level construction guardrail and secondary safety Guardrail.One-level construction guardrail includes vertical steel pipe 1, horizontal steel pipe 2 and sleeve 3, and vertical steel pipe 1 is anchored in ground, is provided with many Root.The top of vertical steel pipe 1 is also welded with sleeve 3, and sleeve 3 is hollow steel tube.It is provided between every two adjacent vertical steel pipes 1 Two horizontal steel pipes 2, use between the two ends of horizontal steel pipe 2 and adjacent two vertical steel pipes 1 and are welded and fixed.Secondary safety guardrail Including regulation steel pipe 4, limiter 5 and steel wire rope 6.The length of the length less than vertical steel pipe 1 of steel pipe 4 is adjusted, regulation steel pipe 4 Less than the internal diameter of sleeve 3, limiter 5 is inverted L-shaped sheet metal component and is welded in the bottom of regulation steel pipe 4 external diameter, and regulation steel pipe 4 is inserted Vertically positioned in sleeve 3 and by limiter 5, a pair of through holes 7 are additionally provided with the top tube wall for adjusting steel pipe 4, steel wire rope 6 is worn The through hole 7 of all regulation steel pipes 4 is crossed, the two ends of steel wire rope 6 are anchored in ground.
The specific mounting means of this adjustable height Interim Standard guardrail is as follows:
Every vertical steel pipe 1 is anchored in ground by interval of the length of horizontal steel pipe 2 first, it is then adjacent vertical at every two Two horizontal steel pipes 2 are welded between steel pipe 1, is spaced a distance between two horizontal steel pipes 2.The top of vertical steel pipe 1 is Sleeve 3 is welded with advance, and sleeve 3 is hollow steel tube.
After installing above section, that is, the installation of one-level construction guardrail is completed.The length of vertical steel pipe 1 needs basis The requirement of the specific machinery in Specific construction place is configured.
The external diameter for adjusting steel pipe 4 is not more than the internal diameter of sleeve 3, and the bottom for adjusting steel pipe 4 is welded with as spacing in advance The L-shaped sheet metal component of device 5.After regulation steel pipe 4 is inserted into the sleeve 3 on the top of vertical steel pipe 1 from top to bottom, then by steel wire rope 6 successively Through the through hole 7 on all regulation steel pipe 4 tops, the two ends of steel wire rope 6 are then anchored in ground again.
After installing above section, the just whole installations of Interim Standard guardrail.
Now, Interim Standard guardrail includes one-level construction guardrail and secondary safety guardrail, and the whole height of guardrail is with most Big degree is designed for the purpose of ensuring safety, and the specific machinery that specific height still needs to refer to job site is designed.
When the integrated guard rail for assembling completely has influence on mechanical execution, the two ends of steel wire rope 6 are all torn open from ground first From, regulation steel pipe 4 is extracted from sleeve 3 successively again then, so just secondary safety guardrail is dismantled completely.Because one-level is applied The height of work guardrail just already allows for the situation of mechanical execution in design, therefore it does not interfere with mechanical execution highly. Meanwhile, one-level construction guardrail can still play a part of isolation, can while convenient construction as far as possible support personnel peace Entirely.
It is emphasized that:The above is only presently preferred embodiments of the present invention, not make any formal to the present invention Limitation, every any simple modification, equivalent variations and modification made to above example according to technical spirit of the invention, Still fall within the range of technical solution of the present invention.

Claims (4)

1. a kind of adjustable height Interim Standard guardrail, it is characterised in that constructed guardrail and secondary safety guardrail, including one-level Level construction guardrail includes vertical steel pipe(1), horizontal steel pipe(2)And sleeve(3), the vertical steel pipe(1)It is anchored in ground and extremely It is less two, the vertical steel pipe(2)Top be also welded with sleeve(3), the sleeve(3)It is hollow steel tube, the transverse direction Steel pipe(2)Located at every two adjacent vertical steel pipes(1)Between and with adjacent two vertical steel pipes(1)Welding, the secondary safety Guardrail includes regulation steel pipe(4), limiter(5)And steel wire rope(6), the regulation steel pipe(4)External diameter be not more than sleeve(3)'s Internal diameter, the limiter(5)It is welded in regulation steel pipe(4)Bottom, adjust steel pipe(4)Insertion sleeve(3)It is interior and by spacing Device(5)Vertical positioning, adjusts steel pipe(4)Top tube wall on be additionally provided with a pair of through holes(7), steel wire rope(6)Through all tune Section steel pipe(4)Through hole(7), steel wire rope(6)Two ends be anchored in ground.
2. adjustable height Interim Standard guardrail according to claim 1, it is characterised in that the horizontal steel pipe(2) Every two adjacent vertical steel pipes(1)Between at least provided with two.
3. adjustable height Interim Standard guardrail according to claim 1, it is characterised in that the limiter(5)It is one Individual inverted L-shaped sheet metal component, limiter(5)With vertical steel pipe(1)Between by being welded and fixed.
4. adjustable height Interim Standard guardrail according to claim 1, it is characterised in that the regulation steel pipe(4)'s Length is not more than vertical steel pipe(1)Length.
CN201710150350.XA 2017-03-14 2017-03-14 A kind of adjustable height Interim Standard guardrail Pending CN106894643A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710150350.XA CN106894643A (en) 2017-03-14 2017-03-14 A kind of adjustable height Interim Standard guardrail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710150350.XA CN106894643A (en) 2017-03-14 2017-03-14 A kind of adjustable height Interim Standard guardrail

Publications (1)

Publication Number Publication Date
CN106894643A true CN106894643A (en) 2017-06-27

Family

ID=59192213

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710150350.XA Pending CN106894643A (en) 2017-03-14 2017-03-14 A kind of adjustable height Interim Standard guardrail

Country Status (1)

Country Link
CN (1) CN106894643A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2264202Y (en) * 1996-08-13 1997-10-08 龙口矿务局洼里煤矿 High speed railroad guardrail for underground tunnel
US6270057B1 (en) * 1998-12-16 2001-08-07 Centurion Construction Company Reuseable multi-story building construction guardrail system
GB0511439D0 (en) * 2004-06-04 2005-07-13 Hugh Logan Plant & Engineering Pedestrian guardrail
CN203613817U (en) * 2013-10-14 2014-05-28 中国建筑第八工程局有限公司 Base device for steel-structured safety protection fence
CN105696850A (en) * 2016-04-05 2016-06-22 四川奥特机械设备有限公司 Animal protecting grid
CN205348818U (en) * 2015-12-08 2016-06-29 戴学树 Protection guardrail with adjustable assembled height
CN106285195A (en) * 2015-06-08 2017-01-04 天津市孝德彩钢压型板有限公司 A kind of Novel engineering height adjustable construction surrounding baffle

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2264202Y (en) * 1996-08-13 1997-10-08 龙口矿务局洼里煤矿 High speed railroad guardrail for underground tunnel
US6270057B1 (en) * 1998-12-16 2001-08-07 Centurion Construction Company Reuseable multi-story building construction guardrail system
GB0511439D0 (en) * 2004-06-04 2005-07-13 Hugh Logan Plant & Engineering Pedestrian guardrail
CN203613817U (en) * 2013-10-14 2014-05-28 中国建筑第八工程局有限公司 Base device for steel-structured safety protection fence
CN106285195A (en) * 2015-06-08 2017-01-04 天津市孝德彩钢压型板有限公司 A kind of Novel engineering height adjustable construction surrounding baffle
CN205348818U (en) * 2015-12-08 2016-06-29 戴学树 Protection guardrail with adjustable assembled height
CN105696850A (en) * 2016-04-05 2016-06-22 四川奥特机械设备有限公司 Animal protecting grid

Similar Documents

Publication Publication Date Title
CN102337781B (en) Tool-type combined and attached lifting scaffold
CN108915355B (en) Building site rail guard convenient to adjust
CN106894643A (en) A kind of adjustable height Interim Standard guardrail
CN104213707B (en) All steel climbing frame inside contracts attached climbing device and the mounting method thereof at place in structure
CN205763139U (en) A kind of band iron bending device for power construction
CN104763102B (en) House roof truss structure
CN207518084U (en) A kind of steady type cabinet
CN105311771A (en) Safety belt suspending device for upper construction of transformer
CN109779291A (en) A kind of girder with rolled steel section en cased in concrete bottom template reinforcing device and method
CN105863192B (en) A kind of balcony guardrail
CN104963410B (en) Beam column of steel structure is slidably connected node
CN204057560U (en) Be attached to attached wall connection structure in the jacking system of section
CN103231711B (en) Cantilever fixing device used for protective and sealed partition door in subway section
CN207392198U (en) A kind of highway guard rail upright post fixing device for installing
CN203881136U (en) High-ductility heating furnace shockproof steel structure node
JP2016084701A (en) Vibration control building
CN206722069U (en) It is a kind of to be used to be arranged on the removably bracket that support is provided on frame column
CN205447177U (en) Equipment for power transmission and distribution rack
CN215830073U (en) Instrument formula safety is chosen net
CN214576286U (en) Protective fence upright post
CN204289206U (en) The lattice installing rack switch fixed Combination device that isolating switch is vertically opened
CN107190965A (en) Upper suspension centre supporting structure
CN213361302U (en) Oil gas pipeline hydraulic support device based on stress compensation
CN209244239U (en) It is a kind of for building the guide rail of climbing frame
CN104051963B (en) Transformer station's door framework insulation column hangs system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170627