CN106885961A - MMC HVDC black starting-ups simulation experiment systems and test method - Google Patents

MMC HVDC black starting-ups simulation experiment systems and test method Download PDF

Info

Publication number
CN106885961A
CN106885961A CN201710142799.1A CN201710142799A CN106885961A CN 106885961 A CN106885961 A CN 106885961A CN 201710142799 A CN201710142799 A CN 201710142799A CN 106885961 A CN106885961 A CN 106885961A
Authority
CN
China
Prior art keywords
mmc
switch
power network
voltage
black starting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710142799.1A
Other languages
Chinese (zh)
Other versions
CN106885961B (en
Inventor
范彩云
司志磊
韩坤
夏克鹏
甄帅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
XJ Electric Co Ltd
Original Assignee
XJ Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by XJ Electric Co Ltd filed Critical XJ Electric Co Ltd
Priority to CN201710142799.1A priority Critical patent/CN106885961B/en
Publication of CN106885961A publication Critical patent/CN106885961A/en
Application granted granted Critical
Publication of CN106885961B publication Critical patent/CN106885961B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere

Abstract

The present invention relates to MMC HVDC black starting-ups simulation experiment systems and test method, simulated test switch is disconnected first, simulate one of electrical breakdown, and corresponding two breakers of two power networks of disconnection;Then two chargings and start-up operation of MMC are carried out, after the alternating-voltage stabilization of the corresponding MMC outputs of power network of last dead electricity, detect the voltage magnitude and phase of the second power network, and the voltage-phase to the second power network enters horizontal lock, when the voltage-phase of the second power network is consistent with the phase of the alternating voltage that the 2nd MMC is exported, control the second breaker of closure to carry out grid-connected, realize the simulated test of black starting-up.So; the test method can simulate the black starting-up that power network is effectively realized when power network breaks down; realize the effective control to MMC HVDC black starting-ups; and black starting-up performance study can be carried out to flexible direct current power transmission system, to instruct product development of the transverter with Control protection system and engineering construction.

Description

MMC-HVDC black starting-ups simulation experiment system and test method
Technical field
The present invention relates to a kind of MMC-HVDC black starting-ups simulation experiment system and test method.
Background technology
With the application of the development and Power Electronic Technique of all-controlling power electronics device in power system, based on voltage High voltage dc transmission technology (the Voltage-Sourced Converter High Voltage Direct of source transverter Current, VSC-HVDC) it is increasingly subject to pay attention to.Modularization multi-level converter (MMC, Modular Multilevel Converter) be voltage source converter in flexible direct current power transmission system application one kind, be widely used in its significant advantage Flexible DC power transmission and new energy access system.
Realize that the research of power grid"black-start" is received significant attention as black starting-up power supply using VSC-HVDC.It is so-called black to open It is dynamic, refer to that after whole system hinders stoppage in transit for some reason, system all has a power failure (be not excluded for isolated minor scale power net and still maintain operation), in complete " black " state, is independent of other web help, is started by the generating set with self-startup ability in system, drives nothing to open certainly The generating set of kinetic force, gradually expands system and recovers scope, finally realizes the recovery of whole system.Compared to using in system The generating set of self-startup ability carry out black starting-up, MMC transverters have a clear superiority as black starting-up power supply, and it does not exist Black starting-up unit self-excitation problem, and, can control to make alternating voltage change by setting curve by soft start, it is to avoid non-loaded line Road closing overvoltage problem.
First, in the prior art for MMC black start-up ability research also in starting stage, and existing utilization The Starting mode that MMC carries out power grid"black-start" is that this mode is only real in real MMC-HVDC transmission systems Transmission system in implement after can show the Starting mode correctness, but a kind of if Starting mode mistake Mode, then, this can not only cause the failure of black starting-up, due to carrying out black starting-up in real MMC-HVDC transmission systems, So, once black starting-up fails, will have a power failure in large area in power supply area, huge economic damage can be caused to enterprise's production Lose, very big inconvenience is brought to resident's daily life.
When MMC-HVDC is used for power grid"black-start", power failure end can be equivalent to passive network, now need by there is source The startup of current conversion station is realized, the recovery of whole power network is then driven.For one-port, (I ends have been equivalent to source current conversion station system System, II ends are dead terminal current conversion station system), II ends have a power failure on a large scale then two ends current conversion station while out of service.
The content of the invention
It is an object of the invention to provide a kind of MMC-HVDC black starting-ups simulation experiment system and test method.
To achieve the above object, the solution of the present invention includes:A kind of MMC-HVDC black starting-ups simulation experiment system, its feature It is, including I ends current conversion station system and II current conversion station systems, the I ends current conversion station system is including a MMC and for controlling First control system of a MMC is stated, the II ends current conversion station system includes the 2nd MMC and for controlling the 2nd MMC's Second control system, the DC side of a MMC connects the DC side of the 2nd MMC, described first by line simulation device The AC of MMC is used to connect the first power network, and the AC of the 2nd MMC is used to connect the second power network, the exchange of a MMC String is provided with the first breaker on connection line between side and the first power network, between the AC and the second power network of the 2nd MMC String is provided with the second breaker on connection line, and string is provided with simulation on the connection line between second breaker and the second power network Test switch, the line simulation device is used to simulate the reality between the DC side and the DC side of the 2nd MMC of a MMC Border transmission line.
The simulation experiment system also includes first switch, second switch and the 3rd switch, and first power network passes through institute State first switch to power connection first control system, second power network is by the described 3rd switch power supply one electricity of connection Motivation, the motor and a generator mechanical drive connection, the electric energy output end of the generator are connected to a conversion One movable contact of switch;Tie point between second breaker and simulated test switch is connected by the second switch Another movable contact of the change-over switch, the stationary contact of the change-over switch is powered and connects second control system.
Also string is provided with the first soft starting device on connection line between the AC and the first power network of the first MMC, Also string is provided with the second soft starting device on connection line between the AC and the second power network of the 2nd MMC.
The line simulation device includes first resistor group, the first inductive bank, second resistance group, the second inductive bank, first Capacitance group, the second capacitance group, the 3rd capacitance group and the 4th capacitance group, electrode input end and the positive pole of the line simulation device are exported String sets the first resistor group and the first inductive bank between end, the negative input and cathode output end of the line simulation device it Between string set the second resistance group and the second inductive bank, between the electrode input end and negative input of the line simulation device String is provided with the first capacitance group and the 3rd capacitance group on connection line, on the connection line between cathode output end and cathode output end String is provided with the second capacitance group and the 4th capacitance group, tie point and the second capacitance group between the first capacitance group and the 3rd capacitance group and Tie point ground connection between 4th capacitance group;The first resistor group and second resistance group are by least one rheostat series connection structure Into first inductive bank and the second inductive bank are a controllable impedance for having several taps, first capacitance group, At least one of two capacitance groups, the 3rd capacitance group and the 4th capacitance group capacitance group is for an electric capacity or by least two electric capacity Parallel connection is constituted.
A kind of MMC-HVDC black starting-up simulation experiment methods for being exclusively used in above-mentioned MMC-HVDC black starting-ups simulation experiment system, Comprise the following steps:
(1) simulated test switch, is disconnected, the second electrical breakdown is simulated, and disconnect the first breaker and the second breaker;
(2) the first breaker, active startup the MMC, are closed, the 2nd MMC is in passive starting state, a MMC and Submodule in 2nd MMC is started to charge up;
(3), after the submodule charging complete in a MMC and the 2nd MMC, a MMC is unlocked, and control startup first MMC;
(4), after after the DC voltage stability of a MMC DC sides, the 2nd MMC is unlocked, and controls to start the 2nd MMC;
(5), after the alternating-voltage stabilization of the 2nd MMC outputs, the voltage magnitude and phase of the second power network are detected, and to the The voltage-phase of two power networks enters horizontal lock, when the phase one of the alternating voltage that the voltage-phase of the second power network and the 2nd MMC are exported During cause, control the second breaker of closure to carry out grid-connected, realize the simulated test of black starting-up.
Between the step (1) and step (2), the test method is further comprising the steps of:Closure first switch and 3rd switch, makes the first power network by first switch for the first control system is powered, and makes the electric energy that generator sends by conversion Switch as the second control system is powered.
In the step (5), when the alternating-voltage stabilization of the 2nd MMC outputs, closure simulated test switch and the Two switches, disconnect the 3rd and switch, and simulated test is switched and second switch is the to pass sequentially through the second power network by change-over switch Two control systems are powered.
In the step (3), when the control starts a MMC, a MMC is to determine DC voltage, determine reactive power control Molding formula;In the step (4), when the control starts two MMC, the 2nd MMC is controlled to determine alternating voltage, determining a-c cycle Pattern.
In the step (4), when the 2nd MMC is to determine alternating voltage, determine the operation of a-c cycle control model, control second The alternating voltage of MMC ACs increases according to the rate of voltage rise of setting.
The present invention provides a kind of MMC-HVDC black starting-ups simulation experiment system, and the pilot system can be to the black of MMC-HVDC Startup ability is simulated experiment, it is not necessary to specially black starting-up test is carried out in real MMC-HVDC transmission systems, using this Pilot system can promptly and accurately know the black start-up ability of MMC-HVDC, and, even if the black startup test failure of simulation, Serious consequence will not be produced, it is to avoid in the power supply area that real MMC-HVDC transmission systems are caused when black starting-up fails Large-area power-cuts.
And, the black starting-up simulation experiment method that the present invention is provided is that the analog study of MMC-HVDC black starting-ups is obtained, When carrying out black startup test using the pilot system, simulated test switch is disconnected first, simulate one of electrical breakdown, and break Open corresponding two breakers of two power networks;Then two chargings and start-up operation of MMC, the power network correspondence of last dead electricity are carried out MMC outputs alternating-voltage stabilization after, the voltage magnitude and phase of the second power network are detected, and to the voltage-phase of the second power network Enter horizontal lock, when the voltage-phase of the second power network is consistent with the phase of the alternating voltage that the 2nd MMC is exported, control closure second Breaker carries out grid-connected, realizes the simulated test of black starting-up.So, the test method can be simulated to be had when power network breaks down Effect realizes the black starting-up of power network, realizes the effective control to MMC-HVDC black starting-ups, and can be to flexible direct current power transmission system Black starting-up performance study is carried out, to instruct product development of the transverter (valve) with Control protection system and engineering construction.
Brief description of the drawings
Fig. 1 is MMC-HVDC black starting-up simulation experiment system structural representations;
Fig. 2 is the structural representation of one of implementation method of change-over switch;
Fig. 3 is MMC structural representations;
Fig. 4-a are the structural representations of half-bridge submodule;
Fig. 4-b are the structural representations of full-bridge submodule;
Fig. 4-c are the structural representations of clamp formula Shuangzi module;
Fig. 5 is the structural representation of line simulation device.
Specific embodiment
The present invention will be further described in detail below in conjunction with the accompanying drawings.
Embodiment 1
As shown in figure 1, MMC-HVDC black starting-ups simulation experiment system includes I ends current conversion station system and II current conversion station systems, I End current conversion station system connects II current conversion station systems by line simulation device, wherein, the core in I ends current conversion station and II ends current conversion station Center portion point is MMC, is respectively MMC1 and MMC2.I ends current conversion station system and II current conversion stations system are real transverter systems System, the power network in I ends current conversion station system and II current conversion station systems is real power network.
First has been sequentially connected in series on connection line between the AC of the MMC1 in the first power network and I ends current conversion station system Between the AC and simulating grid of the MMC2 in circuit breaker Q F1, the first soft starting device and transformer T1, II current conversion station system Connection line on be sequentially connected in series transformer T2, the second soft starting device, the second circuit breaker Q F2 and simulated test switch K4.
Also include the first control system for controlling MMC1 in the current conversion station system of I ends, also wrapped in the current conversion station system of II ends Include the second control system for controlling MMC2.First power network connects the feeder ear of the first control system by first switch K1; As shown in figure 1, the tie point between the second circuit breaker Q F2 and simulated test switch K4 connects change-over switch by second switch K2 A movable contact, simulating grid supplies electrical connection electric motor M, motor M and generator G machine drivings by the 3rd switch K3 Connection, the electric energy output end of generator G connects another movable contact of change-over switch.Motor M and generator G are single-phase electricity Machine, the stationary contact of change-over switch connects the feeder ear of the second control system, and generator G can provide work for the second control system Voltage.As shown in Fig. 2 give a specific embodiment of change-over switch, its equivalent to a single-pole double-throw switch (SPDT), wherein, D1 is stationary contact, and d2 and d3 is two movable contacts, by select d1 and d2 to turn on or d1 and d3 turn on can make switch beat to Second switch K2 or generator G.In addition, it is generally the case that control system is put with the cooling system for being cooled down to MMC Put at one piece, when being powered for control system, also correspondingly for cooling system is powered, cooling system belongs to conventional Technology, prior art is belonged on its concrete structure and the course of work, and, this implementation unrelated with technical scheme Example is not described in detail.
As shown in figure 3, the MMC1 and MMC2 in the pilot system are six bridge arm MMC, per mutually including upper and lower two bridges Arm, the submodule on each bridge arm is not limited to half-bridge submodule as depicted in fig. 4-a, or as shown in Fig. 4-b Full-bridge submodule and the clamp formula Shuangzi module as shown in Fig. 4-c, in addition, the switching element T 0, T1 in these three submodules, T2, T3, T4, T5, T6, T11, T12, T21, T22 are not limited to IGBT device, can also be MOSFET element or other complete Control type switching device or half control type switching device, are considered with adapting to different voltage power grades and reducing system cost.
As shown in figure 5, line simulation device is used to realize to (several kilometers) framves to (thousands of miles) over long distances of short distance The simulation of the flexible DC power transmission circuit of ceases to be busy, cable and trolley line+cable series-parallel connection.The structure of the line simulation device and multiple Miscellaneous degree is configured according to actual conditions.The present embodiment provides a specific embodiment, it on the whole by equivalent resistance, etc. Effect inductance and equivalent capacity composition, specifically include first resistor group R1, the first inductive bank L1, second resistance group R2, the second inductance Group L2, the first capacitance group C1, the second capacitance group C2, the 3rd capacitance group C3 and the 4th capacitance group C4.The line simulation device is just String sets first resistor group R1 and the first inductive bank L1, negative input and cathode output end between pole input and cathode output end Between string set second resistance group R2 and the second inductive bank L2;Between the electrode input end and negative input of the line simulation device Connection line on string set the first capacitance group C1 and the 3rd capacitance group C3, the connecting line between cathode output end and cathode output end String sets the second capacitance group C2 and the 4th capacitance group C4 on road, wherein, the connection between the first capacitance group C1 and the 3rd capacitance group C3 Point and the ground connection of the tie point between the second capacitance group C2 and the 4th capacitance group C4.R1 and R2 are by least one for the two resistance groups Rheostat is in series, by the change for correspondingly adjusting the resistance that can realize whole resistance group;First inductive bank and second Inductive bank is a controllable impedance for having several taps, and the change of inductance value is realized by the regulation of tap;First electric capacity At least one of group, the second capacitance group, the 3rd capacitance group and the 4th capacitance group capacitance group is an electric capacity, or by least two Individual electric capacity is in parallel to be constituted, and by putting into or cutting off the electric capacity of different numbers, realizes the change of the capacitance of each capacitance group.It is comprehensive On, by regulation, the resistance value in the line simulation device, inductance value and capacitance can be made correspondingly to be changed, namely Realized to different length, the simulation of different type transmission line of electricity by the value to different electric component gears.
, it is necessary to carry out following preparation before black starting-up simulation experiment method is carried out using the pilot system:
First by I ends, II ends killer switch QF1, QF2 disconnect, MMC1 and MMC2 lockings access line simulation device System, resistance value, inductance value and capacitance in adjusting circuit analogue means simulate different DC line length.Specifically For:Change resistance group R1, R2 in resistance, and L1, L2 tap wiring, thus it is possible to vary in access system resistance value and Inductance value;Changing shunt capacitance number can change capacitor's capacity in access system, and different resistance, inductance and capacitor combination exist Together, can it is equivalent go out different transmission line of electricity.
Black starting-up simulation experiment method, specially following steps are carried out using the pilot system:
1st, simulated test switch K4 is disconnected, II end system electrical breakdowns, and cut-off breaker switch QF1 and QF2 is simulated.
2nd, closure first switch K1, I end control system is powered with cooling system and in normal operating conditions;I ends control After system and cooling system normal work, it is both-end HVDC operational modes to set the control of I ends pole, active startup, pole connection status, and Set I ends to be constant DC voltage control, determine Reactive Power Control pattern, that is, it is voltage-controlled to determine direct current that the control model of MMC1 is set Make, determine Reactive Power Control pattern.
Close the 3rd switch K3, disconnect second switch K2, power network provides electric energy for single-phase motor M, motor M operate into And generator G is driven, generator sends single-phase 220V alternating currents, and makes generator G be II end control systems by change-over switch Electric energy is provided with cooling system.
After II end control systems are in normal operating conditions with cooling system, it is passive startup mould to set II ends pole control system Formula, and set II ends be determine alternating voltage, the control model of determining a-c cycle control model, i.e. MMC2 is to determine alternating voltage, calmly A-c cycle control model.
3rd, I ends pole control issues startup order, and circuit breaker Q F1 closures, end I system is in active soft start state, in MMC1 Submodule start to charge up;II systems are held to be in passive starting state simultaneously, the submodule in MMC2 is started to charge up.
The double ended system charging stage is comprising uncontrollable rectifier and determines the DC voltage charging stage.In the charging stage, to keep son Module voltage uniformity, practicable soft opening press strategy (using switching KM1, KM2 and resistance in parallel with KM1 and KM2 realization Soft start), i.e., in the charging stage, capacitance voltage highest submodule is in excision state, and excision number and excision speed receive submodule Block capacitor charge and discharge characteristic influences.When submodule voltage in MMC1 reaches setting value, pole control performs the soft contactor KM1 that opens and closes Strategy, resistance excision is opened by soft.
4th, after the submodule capacitor voltage stabilization in MMC1 and MMC2, i.e., after charging complete, pole control issues unlocking command, I End system is unlocked, that is, MMC1 is unlocked, because the control mode above to I end systems has carried out prior setting, so straight here The MMC1 for connecing control I end systems is in constant DC voltage control, determines Reactive Power Control pattern, i.e., in reactive power according to fixation Slope is slowly risen to from zero and be controlled with the reactive power definite value after certain value.
After MMC1 starts, the DC terminal voltage of DC side is gradually increasing, when the DC voltage of the DC side of MMC1 reaches The DC voltage value can be stable at during the DC voltage value of setting, at this moment, the unblock of II end systems unlocks MMC2, similarly, by Prior setting is carried out in the control mode above to II end systems, so directly the MMC2 of control II end systems is in here Determine alternating voltage control, determine a-c cycle control model.Pole control sets the alternating voltage of MMC2 ACs output according to setting Slope realizes the soft start to transformer from zero slow rising.
5th, the alternating voltage of MMC2 ACs is gradually increasing, and the exchange can be stable at when the ac voltage of setting is reached Magnitude of voltage, at this moment, closure simulated test switch K4 and second switch K2, change-over switch is realized that the seamless of power supply takes over seamlessly, is made II end control systems and cooling system power supply are powered by generator G and are converted into power network by second switch offer, after power good, Disconnect the 3rd switch K3.
6th, the amplitude and phase of II ends pole control detection II ends line voltage, II ends power network electricity is locked by software phase-lock loop The phase of pressure, when the phase of II ends line voltage is consistent with the alternating voltage phase that MMC2 is exported, issues circuit breaker Q F2 closures Order, implements grid-connected.
So far completed based on MMC-HVDC black starting-ups physical simulation experiment.
In above-described embodiment, before circuit breaker Q F1 closures, setting MMC1 is constant DC voltage control, determines reactive power Control, MMC2 determines a-c cycle control to determine alternating voltage, and the control model of MMC1 and MMC2 is merely just set in advance, Do not carry out practical operation control to it, and reality is carried out respectively to it again after submodule charging complete in two MMC Control, so, the control model of the two MMC can in advance be set in any time before actual control, certainly, also Can be configured while actually control.And, constant DC voltage control, determine the control model of Reactive Power Control and fixed Alternating voltage, the control model for determining a-c cycle control belongs to the ordinary control mode of MMC, and just no longer the two are controlled here Molding formula is explained in itself.
In above-described embodiment, the first and second soft starting devices are the technical characteristic of further optimization, certainly, as it His embodiment, the two soft starting devices can be omitted, and similarly, the transformer in the simulation experiment system can not also Set.
Embodiment 2
Compared with above-described embodiment, in the embodiment, MMC-HVDC black starting-ups simulation experiment system include motor and Generator, then the mode that II end control systems are powered only has one kind --- power network, correspondingly, change-over switch need not just be set, So, in the black starting-up simulation experiment method based on the system just the power supply without II end control systems switching correlation Step.
So, based on the simulation experiment system in the present embodiment, black starting-up simulation experiment method is integrally comprised the following steps:
(1), disconnect simulated test switch K4, simulate II end system electrical breakdowns, and cut-off breaker switch QF1 and QF2;
(2), close circuit breaker QF1, active startup MMC1, passive startup MMC2, the submodule BOB(beginning of block) in the two MMC fills Electricity;
(3), after the submodule charging complete in MMC1 and MMC2, MMC1 is unlocked, and controls to start MMC1;
(4), after after the DC voltage stability of MMC1 DC sides, MMC2 is unlocked, and controls to start MMC2;
(5), after the alternating-voltage stabilization of MMC2 outputs, the voltage magnitude and phase of detection II ends power network, and to II ends The voltage-phase of power network enters horizontal lock, when the voltage-phase of II ends power network is consistent with the phase of the alternating voltage that MMC2 is exported, Control close circuit breaker QF2 to carry out grid-connected, realize the simulated test of black starting-up.
Due in embodiment 1 to above-mentioned test method in each step be described in detail, just no longer have here Body explanation.
Specific embodiment is presented above, but the present invention is not limited to described implementation method.Base of the invention This thinking is above-mentioned basic scheme, and for those of ordinary skill in the art, various changes are designed in teaching of the invention The model of shape, formula, parameter simultaneously need not spend creative work.It is right without departing from the principles and spirit of the present invention Change, modification, replacement and the modification that implementation method is carried out are still fallen within protection scope of the present invention.

Claims (9)

1. a kind of MMC-HVDC black starting-ups simulation experiment system, it is characterised in that including I ends current conversion station system and II current conversion stations system System, the I ends current conversion station system includes a MMC and the first control system for controlling a MMC, and the II ends are changed Stream station system includes the 2nd MMC and the second control system for controlling the 2nd MMC, and the DC side of a MMC leads to The DC side that line simulation device connects the 2nd MMC is crossed, the AC of a MMC is used to connect the first power network, the 2nd MMC AC be used for connect the second power network, gone here and there on the connection line between the AC and the first power network of a MMC and be provided with First breaker, string is provided with the second breaker, described second on the connection line between the AC and the second power network of the 2nd MMC String is provided with simulated test switch on connection line between breaker and the second power network, and the line simulation device is used to simulate institute State the actual transmissions circuit between the DC side of a MMC and the DC side of the 2nd MMC.
2. MMC-HVDC black starting-ups simulation experiment system according to claim 1, it is characterised in that the simulated test system System also includes first switch, second switch and the 3rd switch, and first power network is powered described in connection by the first switch First control system, second power network is by the described 3rd switch power supply one motor of connection, the motor and one Generator mechanical is connected, and the electric energy output end of the generator is connected to change-over switch movable contact;It is described Tie point between second breaker and simulated test switch passes through another of the second switch connection change-over switch Movable contact, the stationary contact of the change-over switch is powered and connects second control system.
3. MMC-HVDC black starting-ups simulation experiment system according to claim 1 and 2 a, it is characterised in that MMC AC and the first power network between connection line on also string be provided with the first soft starting device, the AC of the 2nd MMC and the Also string is provided with the second soft starting device on connection line between two power networks.
4. MMC-HVDC black starting-ups simulation experiment system according to claim 1 and 2, it is characterised in that the circuit mould Intend device include first resistor group, the first inductive bank, second resistance group, the second inductive bank, the first capacitance group, the second capacitance group, 3rd capacitance group and the 4th capacitance group, string sets described first between the electrode input end and cathode output end of the line simulation device Resistance group and the first inductive bank, string sets the second resistance between the negative input and cathode output end of the line simulation device Group and the second inductive bank, string is provided with the on the connection line between the electrode input end and negative input of the line simulation device One capacitance group and the 3rd capacitance group, on the connection line between cathode output end and cathode output end string be provided with the second capacitance group and 4th capacitance group, the tie point between the first capacitance group and the 3rd capacitance group and the company between the second capacitance group and the 4th capacitance group Contact is grounded;The first resistor group and second resistance group are in series by least one rheostat, first inductive bank A controllable impedance for there are several taps, first capacitance group, the second capacitance group, the 3rd electric capacity are with the second inductive bank At least one of group and the 4th capacitance group capacitance group are an electric capacity or are made up of at least two electric capacity parallel connections.
5. a kind of MMC-HVDC black starting-ups simulation examination for being exclusively used in MMC-HVDC black starting-ups simulation experiment system described in claim 1 Proved recipe method, it is characterised in that comprise the following steps:
(1) simulated test switch, is disconnected, the second electrical breakdown is simulated, and disconnect the first breaker and the second breaker;
(2) the first breaker, is closed, active startup a MMC, the 2nd MMC are in passive starting state, a MMC and second Submodule in MMC is started to charge up;
(3), after the submodule charging complete in a MMC and the 2nd MMC, a MMC is unlocked, and controls to start a MMC;
(4), after after the DC voltage stability of a MMC DC sides, the 2nd MMC is unlocked, and controls to start the 2nd MMC;
(5), after the alternating-voltage stabilization of the 2nd MMC outputs, the voltage magnitude and phase of the second power network are detected, and to the second electricity The voltage-phase of net enters horizontal lock, when the voltage-phase of the second power network is consistent with the phase of the alternating voltage that the 2nd MMC is exported, Control the second breaker of closure to carry out grid-connected, realize the simulated test of black starting-up.
6. MMC-HVDC black starting-ups simulation experiment method according to claim 5, it is characterised in that in the step (1) And step (2) between, the test method is further comprising the steps of:Closure first switch and the 3rd switch, lead to the first power network First switch is crossed for the first control system is powered, makes the electric energy that generator sends by change-over switch for the second control system is supplied Electricity.
7. MMC-HVDC black starting-ups simulation experiment method according to claim 6, it is characterised in that in the step (5), When the alternating-voltage stabilization of the 2nd MMC outputs, closure simulated test is switched and second switch, is disconnected the 3rd and is switched, and is led to Crossing change-over switch makes the second power network pass sequentially through simulated test switch and second switch for the second control system is powered.
8. MMC-HVDC black starting-ups simulation experiment method according to claim 5, it is characterised in that in the step (3), When the control starts a MMC, a MMC is to determine DC voltage, determine Reactive Power Control pattern;In the step (4), institute When stating control two MMC of startup, the 2nd MMC is to determine alternating voltage, determine a-c cycle control model.
9. MMC-HVDC black starting-ups simulation experiment method according to claim 8, it is characterised in that in the step (4), When the 2nd MMC is to determine alternating voltage, determine the operation of a-c cycle control model, the alternating voltage of the 2nd MMC ACs is controlled to press According to the rate of voltage rise increase of setting.
CN201710142799.1A 2017-03-10 2017-03-10 MMC-HVDC black starting-up simulation experiment system and test method Active CN106885961B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710142799.1A CN106885961B (en) 2017-03-10 2017-03-10 MMC-HVDC black starting-up simulation experiment system and test method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710142799.1A CN106885961B (en) 2017-03-10 2017-03-10 MMC-HVDC black starting-up simulation experiment system and test method

Publications (2)

Publication Number Publication Date
CN106885961A true CN106885961A (en) 2017-06-23
CN106885961B CN106885961B (en) 2019-09-20

Family

ID=59180312

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710142799.1A Active CN106885961B (en) 2017-03-10 2017-03-10 MMC-HVDC black starting-up simulation experiment system and test method

Country Status (1)

Country Link
CN (1) CN106885961B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109861266A (en) * 2019-01-15 2019-06-07 南京工程学院 The flexible starting method of the flexible HVDC transmission system of the access containing extensive new energy
CN109884439A (en) * 2019-04-04 2019-06-14 西安热工研究院有限公司 A kind of black startup test system and method for electric system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4133026A (en) * 1976-02-13 1979-01-02 Bbc, Aktiengesellschaft Brown, Boveri & Cie Method of starting up a high-voltage d-c inverter or transmission station in isolated or island operation
EP1909371A2 (en) * 2006-10-04 2008-04-09 General Electric Company Method, apparatus and computer program product for wind turbine start-up and operation without grid power
CN102938564A (en) * 2012-10-31 2013-02-20 深圳供电局有限公司 Closed-loop power distribution network system based on flexible direct current
CN102983568A (en) * 2012-11-12 2013-03-20 华北电力大学 Modular multilevel converter high voltage direct current (MMC-HVDC) converter station starting method used for power network black start
CN103840479A (en) * 2013-12-16 2014-06-04 南方电网科学研究院有限责任公司 Start control method for VSC-HVDC-based alternating current-direct current parallel system
CN104953608A (en) * 2014-03-26 2015-09-30 常勇 DC-side pre-charging starting method for modular multi-level converter type high-voltage DC power transmission system connected with passive network

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4133026A (en) * 1976-02-13 1979-01-02 Bbc, Aktiengesellschaft Brown, Boveri & Cie Method of starting up a high-voltage d-c inverter or transmission station in isolated or island operation
EP1909371A2 (en) * 2006-10-04 2008-04-09 General Electric Company Method, apparatus and computer program product for wind turbine start-up and operation without grid power
CN102938564A (en) * 2012-10-31 2013-02-20 深圳供电局有限公司 Closed-loop power distribution network system based on flexible direct current
CN102983568A (en) * 2012-11-12 2013-03-20 华北电力大学 Modular multilevel converter high voltage direct current (MMC-HVDC) converter station starting method used for power network black start
CN103840479A (en) * 2013-12-16 2014-06-04 南方电网科学研究院有限责任公司 Start control method for VSC-HVDC-based alternating current-direct current parallel system
CN104953608A (en) * 2014-03-26 2015-09-30 常勇 DC-side pre-charging starting method for modular multi-level converter type high-voltage DC power transmission system connected with passive network

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
岳伟等: "基于MMC的风电场柔性直流输电启动控制策略", 《电网与清洁能源》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109861266A (en) * 2019-01-15 2019-06-07 南京工程学院 The flexible starting method of the flexible HVDC transmission system of the access containing extensive new energy
CN109861266B (en) * 2019-01-15 2023-02-10 南京工程学院 Flexible starting method of flexible direct current transmission system with large-scale new energy access
CN109884439A (en) * 2019-04-04 2019-06-14 西安热工研究院有限公司 A kind of black startup test system and method for electric system
CN109884439B (en) * 2019-04-04 2024-02-23 西安热工研究院有限公司 Black-start test system and method for power system

Also Published As

Publication number Publication date
CN106885961B (en) 2019-09-20

Similar Documents

Publication Publication Date Title
CN102281014B (en) Multilevel current converter with function of processing direct current fault
US10523131B2 (en) Reconfigurable MMC sub-module unit and control unit thereof
CN103001242B (en) A kind of HVDC based on modularization multi-level converter holds concurrently UPFC system
CN102938560A (en) Direct-current converter station based on bipolar structure
CN102231520A (en) Hybrid DC (direct current) electric power transmission system
CN109245557A (en) A kind of modular converter plant, combined inverter and control method
CN104953873B (en) A kind of mixed structure modularization multi-level converter simulation model
CN104714132A (en) Flexible direct current power transmission converter performance testing platform and control method thereof
CN207134804U (en) A kind of tandem type energy storage converter device utilized based on different battery modules differentiation
CN103023312A (en) MMC (Modular Multi-level Converter) converter valve submodule device based on thyristor device and controlling method of submodule device
CN102244466A (en) Voltage sag generator
CN105191091A (en) Voltage source converter
CN203399013U (en) Static synchronous compensator based on three-level H bridge cascade and voltage source inversion module
CN102013690A (en) MMC (multimedia controller)-based modular multi-level transformerless inductive energy storage topological structure
CN113655324B (en) Converter valve operation test topology platform
CN106885961B (en) MMC-HVDC black starting-up simulation experiment system and test method
CN105633994A (en) Starting method of FMMC-LCC hybrid DC power transmission system
CN110797899A (en) Direct current system with dynamic reactive power compensation device and control method thereof
CN106570226A (en) Mean value model in modular multilevel converter, and simulation method of the same
CN204424920U (en) Based on mixed DC system topology and the real-time simulation device thereof of LCC and MMC parallel connection
EP3157120B1 (en) Modular multi-level flexible direct-current topology circuit suitable for fault ride-through
CN106972748B (en) A kind of more level power translation circuits and system
CN102983586B (en) A kind of HVDC based on three-level voltage source converter holds concurrently UPFC system
CN104866656B (en) A kind of full bridge structure multi-level inverter bridge arm equivalent circuit
CN102013696A (en) Transformer free inductance energy-storing topological structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant