CN106871364A - A kind of control method of central air conditioner system cooling tower leaving water temperature - Google Patents

A kind of control method of central air conditioner system cooling tower leaving water temperature Download PDF

Info

Publication number
CN106871364A
CN106871364A CN201710136349.1A CN201710136349A CN106871364A CN 106871364 A CN106871364 A CN 106871364A CN 201710136349 A CN201710136349 A CN 201710136349A CN 106871364 A CN106871364 A CN 106871364A
Authority
CN
China
Prior art keywords
cooling tower
temperature
cooling
blower fan
preset duration
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710136349.1A
Other languages
Chinese (zh)
Other versions
CN106871364B (en
Inventor
姜春苗
钟兴宁
丁文涛
何玉雪
王聪
杨金龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gree Electric Appliances Inc of Zhuhai
Original Assignee
Gree Electric Appliances Inc of Zhuhai
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gree Electric Appliances Inc of Zhuhai filed Critical Gree Electric Appliances Inc of Zhuhai
Priority to CN201710136349.1A priority Critical patent/CN106871364B/en
Publication of CN106871364A publication Critical patent/CN106871364A/en
Application granted granted Critical
Publication of CN106871364B publication Critical patent/CN106871364B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/30Control or safety arrangements for purposes related to the operation of the system, e.g. for safety or monitoring
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/62Control or safety arrangements characterised by the type of control or by internal processing, e.g. using fuzzy logic, adaptive control or estimation of values
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/70Control systems characterised by their outputs; Constructional details thereof
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F28HEAT EXCHANGE IN GENERAL
    • F28FDETAILS OF HEAT-EXCHANGE AND HEAT-TRANSFER APPARATUS, OF GENERAL APPLICATION
    • F28F27/00Control arrangements or safety devices specially adapted for heat-exchange or heat-transfer apparatus
    • F28F27/003Control arrangements or safety devices specially adapted for heat-exchange or heat-transfer apparatus specially adapted for cooling towers
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/62Control or safety arrangements characterised by the type of control or by internal processing, e.g. using fuzzy logic, adaptive control or estimation of values
    • F24F11/63Electronic processing
    • F24F11/64Electronic processing using pre-stored data
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B30/00Energy efficient heating, ventilation or air conditioning [HVAC]
    • Y02B30/70Efficient control or regulation technologies, e.g. for control of refrigerant flow, motor or heating

Abstract

The invention discloses a kind of control method of central air conditioner system cooling tower leaving water temperature, the central air conditioner system includes control device, cooling tower group, cooling pump group and handpiece Water Chilling Units, the entrance side of the cooling pump group connects the water tank side of the cooling tower group, the outlet side of the cooling pump group connects the cold side water inlet of the handpiece Water Chilling Units, the cold side delivery port of the handpiece Water Chilling Units connects the spray side of the cooling tower group, and the control device is connected with the cooling tower group, the cooling pump group;Wherein, the control method includes step:The control device is by the quantity that controls cooling tower to put into operation, and/or the number of units and/or frequency of control blower fan of cooling tower operation are reached realizing cooling tower leaving water temperature or close to outdoor wet-bulb temperature.Control method of the invention enables that cooling tower leaving water temperature reaches or close to outdoor wet-bulb temperature, central air conditioner system is had from the characteristic for seeking wet-bulb temperature.

Description

A kind of control method of central air conditioner system cooling tower leaving water temperature
Technical field
The present invention relates to air-conditioning technical field, and in particular to a kind of controlling party of central air conditioner system cooling tower leaving water temperature Method.
Background technology
In central air conditioner system, the cold side return water temperature (namely leaving water temperature of cooling tower) of handpiece Water Chilling Units is to unit energy Consumption influence is very big, for example, cold side return water temperature often raises 1 DEG C, the COP of unit may reduce by 3%.Cast aside cooling tower sheet The performance of body, the leaving water temperature of cooling tower is influenceed by outdoor wet-bulb temperature, that is to say, that outdoor wet-bulb temperature is higher, cooling The water outlet lower limit temperature of tower is also higher.
However, outdoor wet-bulb temperature be over time, the change of weather and change.Although can be passed by wet-bulb temperature Sensor or Temperature Humidity Sensor are measured to outdoor wet-bulb temperature, but are constrained to the position of sensor installation, often not The wet-bulb temperature on cooling tower periphery can be accurately measured, causes measurement error larger.In addition, wet bulb temperature sensor or humiture The certainty of measurement of sensor can also shift over time.Therefore, according to outdoor wet bulb temperature sensor or temperature The wet-bulb temperature of humidity sensor measurement is often inaccurate come the leaving water temperature for controlling cooling tower.
The content of the invention
Based on above-mentioned present situation, it is a primary object of the present invention to provide a kind of central air conditioner system cooling tower leaving water temperature Control method, the control method does not need the outer wet-bulb temperature of measuring chamber, and cooling tower can be made to be kept on the premise of more energy-conservation Leaving water temperature is constantly near lower limit temperature.
To reach above-mentioned purpose, the technical solution adopted by the present invention is as follows:
A kind of control method of central air conditioner system cooling tower leaving water temperature, the central air conditioner system includes that control is filled Put, cooling tower group, cooling pump group and handpiece Water Chilling Units, the entrance side of the cooling pump group connects the water tank side of the cooling tower group, The outlet side of the cooling pump group connects the cold side water inlet of the handpiece Water Chilling Units, the cold side delivery port of the handpiece Water Chilling Units The spray side of the cooling tower group is connected, the control device is connected with the cooling tower group, the cooling pump group;Wherein, institute Stating control method includes step:The control device is by the quantity that controls cooling tower to put into operation, and/or control cooling tower wind The number of units and/or frequency of machine operation are reached realizing cooling tower leaving water temperature or close to outdoor wet-bulb temperature.
Preferably, when central air conditioner system starts, the step of the quantity that the control device control cooling tower puts into operation Suddenly include:
Quantity according to the cooling water pump of actual motion in the cooling pump group determines the quantity that cooling tower puts into operation.
Preferably, the principle for determining the quantity that cooling tower puts into operation is:The quantity that cooling tower puts into operation be more than etc. In the smallest positive integral of quantity × 1.5 of cooling water pump operation.
Preferably, during central air conditioner system is run, the quantity that the control device control cooling tower puts into operation Step includes:
Make the quantity that cooling tower puts into operation between maximum and minimum value, wherein, cooling tower puts into operation quantity Maximum be quantity × 1.5 run more than or equal to cooling water pump smallest positive integral, cooling tower puts into operation the minimum of quantity Quantity of the value equal to cooling water pump operation.
Preferably, during central air conditioner system is run, the quantity that the control device control cooling tower puts into operation Step also includes:
Judge whether to need to reduce by an operation for cooling tower, if desired, then close accumulated running time cooling most long Tower;
And/or, judge whether to need to increase an operation for cooling tower, if desired, then open accumulated running time most short Cooling tower.
Preferably, when any one of following condition C 01-C04 meets, the control device is to be judged as needing reduction one The operation of platform cooling tower:
The quantity of the quantity > cooling water pumps that C01, cooling tower put into operation;
C02, in Jia Ta or when subtracting cumulative time >=the first prefixed time interval after tower flow terminates, if when first is default Continuously meet in t1 long:The default temperature drop rate of temperature drop rate≤the first of cooling tower outfall sewer;
Temperature≤the first desired temperature of C03, cooling tower outfall sewer;
C04, cooling tower the quantity > cooling towers that put into operation put into operation the maximum of quantity;
And/or, when any one of following condition C 11-C13 meets, the control device is to be judged as needing increase by The operation of platform cooling tower:
C11, in Jia Ta or when subtracting cumulative time >=the first prefixed time interval after tower flow terminates, if when second is default Continuously meet in t2 long:The default temperature rise rate of temperature rise rate >=the first of cooling tower outfall sewer;
Temperature >=second temperature the setting value of C12, cooling tower outfall sewer;
The quantity of the quantity < cooling water pumps operation that C13, cooling tower put into operation.
Preferably, first prefixed time interval is 5~20 minutes;
And/or, the first preset duration t1 is 60~180 seconds;
And/or, the described first default temperature drop rate is 0.1~0.2 DEG C/min;
And/or, first desired temperature is 18-20 DEG C;
And/or, the second preset duration t2 is 60~180 seconds;
And/or, the described first default temperature rise rate is 0.1~0.2 DEG C/min;
And/or, the second temperature setting value is 28~32 DEG C.
Preferably, also including step:
During central air conditioner system is run, if continuously meeting in the 3rd preset duration t3:Cooling tower outfall sewer Temperature >=the 3rd desired temperature, then open the blower fan of all cooling towers for putting into operation;
And/or, during central air conditioner system is run, when all cooling water pumps are to close, or, if default the 6th Continuously meet in duration t6:The desired temperatures of temperature < the 6th of cooling tower outfall sewer, then close the wind of all of cooling tower Machine.
Preferably, the 3rd preset duration t3 is 30~90 seconds;
And/or, the 3rd desired temperature is 20~24 DEG C;
And/or, the 6th preset duration t6 is 5~30 seconds;
And/or, the 6th desired temperature is 14~20 DEG C.
Preferably, the step of number of units and/or frequency of the control device control blower fan of cooling tower operation includes:
If blower fan of cooling tower adjusts the number of units of the fan operation of the cooling tower for putting into operation to determine frequency blower fan;
If blower fan of cooling tower is frequency conversion fan, the frequency of the blower fan of all cooling towers for putting into operation is adjusted in synchronism.
Include preferably for the step of determining frequency blower fan, the number of units of the control device adjustment blower fan of cooling tower operation:
Judge whether to need to increase an operation for blower fan of cooling tower, if desired, then open accumulated running time most short Blower fan of cooling tower;
And/or, judge whether to need to reduce by an operation for blower fan of cooling tower, if desired, then close accumulated running time Blower fan of cooling tower most long.
Preferably, when following condition Cs 21 are met, the control device is to be judged as needing to increase a blower fan of cooling tower Operation:
C21, continuously meet in the 4th preset duration t4:The temperature of cooling tower outfall sewer >=the 4th desired temperature;
And/or, when following condition Cs 22 are met, the control device is to be judged as needing to reduce by a blower fan of cooling tower Operation:
C22, continuously meet in the 5th preset duration t5:The temperature of six desired temperatures≤cooling tower outfall sewer≤ 5th desired temperature.
Preferably, the 4th preset duration t4 is 30~90 seconds;
And/or, the 4th desired temperature is 24~28 DEG C;
And/or, the 5th preset duration t5 is 30~90 seconds;
And/or, the 5th desired temperature is 20~24 DEG C;
And/or, the 6th desired temperature is 14~20 DEG C.
Include preferably for frequency conversion fan, the step of the control device is adjusted in synchronism the frequency of all blower fans:
If continuously meeting in the 7th preset duration t7:The temperature of cooling tower outfall sewer >=the 7th desired temperature, then The frequency of all blower fans is raised into F1;
If continuously meeting in the 7th preset duration t7:The temperature < of eight desired temperatures≤cooling tower outfall sewer Seven desired temperatures, then raise F2 by the frequency of all blower fans, wherein, F2 < F1;
And/or,
If continuously meeting in the 8th preset duration t8:The temperature < of nine desired temperatures≤cooling tower outfall sewer Ten desired temperatures, then by the frequency reduction F3 of all blower fans;
If continuously meeting in the 8th preset duration t8:The temperature < of 11 desired temperatures≤cooling tower outfall sewer 9th desired temperature, then by the frequency reduction F4 of all blower fans, wherein, F3 < F4.
Preferably, the 7th preset duration t7 is 5~30 seconds;
And/or, the 7th desired temperature is 28~30 DEG C;
And/or, the 8th desired temperature is 26~28 DEG C.
And/or, F1=2~8Hz;
And/or, F2=0.5~2Hz;
And/or, the 8th preset duration t8 is 5~30 seconds;
And/or, the 9th desired temperature is 14~19 DEG C;
And/or, the tenth desired temperature is 20~24 DEG C.
And/or, the 11st desired temperature is 14~19 DEG C;
And/or, F3=0.5~2Hz;
And/or, F4=2~8Hz.
Control method of the invention by the number of units and/or the number of units of blower fan of cooling tower that control cooling tower to put into operation and/ Or frequency, and monitor the temperature of cooling tower outfall sewer and carry out feedback control, so as to can reach optimal geomantic omen ratio so that cooling Tower leaving water temperature can reach or close to outdoor wet-bulb temperature, system is had from the characteristic for seeking wet-bulb temperature, without surveying The outdoor wet-bulb temperature of amount.
Especially, the cooling of temperature drop rate and air-conditioner water system that control method of the invention passes through cooling tower outfall sewer System geomantic omen than control method come the number of units and the number of units of blower fan of cooling tower and/or frequency that control cooling tower to put into operation, from And realize system from the characteristic for seeking wet-bulb temperature.
Brief description of the drawings
Hereinafter with reference to accompanying drawing to the excellent of the control method of central air conditioner system cooling tower leaving water temperature of the invention Implementation method is selected to be described.In figure:
Fig. 1 is the schematic diagram of the handpiece Water Chilling Units cold side according to central air conditioner system of the invention;
Fig. 2 is to be shown according to the basic control flow journey of the control method of central air conditioner system cooling tower leaving water temperature of the invention It is intended to;
Fig. 3 is the preferred embodiment of the control method according to central air conditioner system cooling tower leaving water temperature of the invention Control flow schematic diagram.
Specific embodiment
Referring first to Fig. 1, the master of the handpiece Water Chilling Units cold side of central air conditioner system involved in the present invention is illustrated therein is Want part.As shown in figure 1, central air conditioner system of the present invention includes control device 100, cooling tower group 200, cooling Pump group 300 and handpiece Water Chilling Units 400.Wherein, the entrance side of the cooling pump group 300 connects the water tank side of the cooling tower group 200 (i.e. water outlet side), the outlet side of the cooling pump group 300 connects the cold side water inlet of the handpiece Water Chilling Units 400, the cold water The cold side delivery port of unit 400 connects the spray side (i.e. influent side) of the cooling tower group 200, the control device 100 with The cooling tower group 200, the cooling pump group 300 are connected.
Specifically, cooling tower group 200 includes many cooling towers, such as CT1, CT2, CT3 shown in Fig. 1 ... CTn, N platforms, have blower fan of cooling tower inside every cooling tower altogether, and the blower fan of cooling tower can be frequency conversion fan, or determine frequency Blower fan.Generally, the blower fan type of each cooling tower in cooling tower group 200 is consistent, otherwise frequency conversion fan is all, or It is all and determines frequency blower fan.As shown in figure 1, every blower fan of cooling tower is connected with control device 100, so that can be by control device 100 Control its on off state and/or running frequency.
As shown in figure 1, be respectively equipped with can be by the controlling switch of control device 100 for the spray side (i.e. influent side) of each cooling tower Valve, V1 as shown in Figure 1, V2, V3 ..., Vn, being also respectively equipped with can for the water tank side (i.e. water outlet side) of each cooling tower By the valve of the controlling switch of control device 100, V1 ' as shown in Figure 1, V2 ', V3 ' ..., Vn '.Preferably, these valves It is electric butterfly valve.Control device 100 is by controlling the on off state of the valve of the Inlet and outlet water both sides of each cooling tower, you can control The switch of the passage of corresponding cooling tower is made, so as to control whether the cooling tower puts into operation.
In the present invention, for a cooling tower, as long as the valve of its Inlet and outlet water both sides is opened, then the cooling tower is logical Road has just been opened, that is, think that the cooling tower has put into operation.In the case where cooling tower puts into operation, its internal blower fan can be with It is to open running status, or closed mode.It is easily understood that for the cooling tower for putting into operation, when in it When the blower fan in portion opens operation, the cold water temperature when cold water temperature in its water tank can be closed significantly lower than blower fan.
As shown in figure 1, cooling pump group 300 includes many cooling water pumps, and in the case where the number of units of cooling tower is for n, cooling The number of units of water pump can be n or n+1, for example, show n+1 platform cooling water pumps in figure, respectively CWP1, CWP2, CWP3 ... CWPn, CWP (n+1), these cooling water pumps are connected with control device 100, so as to can be opened under the control of control device 100 Or close.
As shown in figure 1, handpiece Water Chilling Units 400 include many handpiece Water Chilling Units, such as the n platforms of diagram.
In addition, as shown in figure 1, being provided with cooling water house steward between cold water pump group 300 and handpiece Water Chilling Units 400 One temperature sensor 501, for measuring cold side return water temperature (namely the temperature of cooling tower outfall sewer of handpiece Water Chilling Units 400 Degree, its leaving water temperature for representing cooling tower);On cooling water return main between handpiece Water Chilling Units 400 and cooling tower group 200 also Second temperature sensor 502 can be provided with, for measuring cold side supply water temperature (namely the cooling tower of handpiece Water Chilling Units 400 Inflow temperature).It should be noted that control method of the invention and cold side supply water temperature need not be measured.
In view of the inaccuracy of outdoor wet-bulb temperature measurement, the present invention proposes a kind of central air conditioner system cooling tower and goes out The control method of coolant-temperature gage, it eliminates the measurement to outdoor wet-bulb temperature, but the platform by controlling cooling tower to put into operation Number of units and/or frequency, the platform of cooling water pump of number (specially controlling the valve of cooling tower Inlet and outlet water both sides) and blower fan of cooling tower Number etc., and monitor the temperature of cooling tower outfall sewer and carry out feedback control, so as to can reach optimal geomantic omen ratio so that cooling tower Leaving water temperature can reach or close to outdoor wet-bulb temperature, and it (or is from seeking central air conditioner system is had from wet-bulb temperature is sought It is excellent) characteristic.
Specifically, as shown in Fig. 2 the control method of central air conditioner system cooling tower leaving water temperature of the invention includes step Suddenly:The control device 100 by the quantity that controls cooling tower to put into operation, and/or control blower fan of cooling tower operation number of units And/or frequency is reached realizing cooling tower leaving water temperature or close to outdoor wet-bulb temperature.
The inflow temperature of cooling tower is determined by the operating condition of air-conditioner set, and the leaving water temperature of cooling tower is by cold But the conditional decision such as performance (such as air quantity, filler etc.), outdoor temperature humidity, inflow temperature, flow of tower.The present invention is by regulation The number of units and/or frequency of quantity that cooling tower puts into operation, control blower fan, i.e., by control the geomantic omen of cooling system than side Formula, water-carrying capacity stablize it is constant on the premise of, with the change of the load variations and outdoor environment humiture of air-conditioner set, can Cooling tower is allowed with energy-conservation the most, simple mode, and cooling tower leaving water temperature is tried one's best reduction.
Preferably, the quantity that the quantity of cooling water pump operation is run with handpiece Water Chilling Units is consistent.For example:3 cooling waters 3 handpiece Water Chilling Units of pump correspondence, 2 cooling water pump 2 handpiece Water Chilling Units of correspondence.Because the cooling water channel of system is generally open type system System, water-carrying capacity is substantially corresponding with handpiece Water Chilling Units flow, if the quantity of cooling water pump operation is more than the quantity that handpiece Water Chilling Units are run, Then cooling tower has the possibility sprayed water outward;If the quantity of cooling water pump operation is fewer than the quantity that handpiece Water Chilling Units are run, cold Water dispenser group is possible to all report water flow switch to protect.Therefore the operation quantity of cooling water pump preferably keeps with the quantity of handpiece Water Chilling Units Unanimously.
Shown in preferred specific control flow Fig. 3 of control method of the invention.
Preferably, when central air conditioner system starts, it is necessary first to open cooling tower passage, namely need to throw cooling tower Enter operation, therefore, the control device 100 control cooling tower put into operation quantity the step of include:
Quantity according to the cooling water pump of actual motion in the cooling pump group determines the quantity that cooling tower puts into operation, really Determining principle is:The quantity that cooling tower puts into operation is the smallest positive integral of quantity × 1.5 run more than or equal to cooling water pump.
That is, upon power-up of the system, by the principle of minimum run time, the quantity for determining as follows opens cooling tower Passage (opening the valves of cooling tower Inlet and outlet water both sides):
Quantity × 1.5 of the quantity that cooling tower puts into operation=cooling water pump operation, due to the number that cooling tower puts into operation Amount can only be integer and can not be decimal, therefore should round up, as long as that is, there is decimal place after decimal point, then upward carry, Round the integer that numerical digit plus 1 and obtained.
Such as, 1 cooling water pump 2 cooling tower of correspondence, 2 cooling water pump 3 cooling towers of correspondence, 3 cooling water pump correspondences 5 Platform cooling tower, the like.It is to be noted that, because the maximum number of cooling tower in system is n platforms, therefore, n platform cooling waters Pump is finally likely to correspondence n platform cooling towers.
By above-mentioned control mode, can be dropped to cooling circulating water with most fast speed when central air conditioner system is opened Temperature, and by water temperature stability in an ideal value.
Preferably, during central air conditioner system is run, the quantity that the control cooling tower of the control device 100 puts into operation The step of include:
Make the quantity that cooling tower puts into operation between maximum and minimum value, wherein, cooling tower puts into operation quantity Maximum be quantity × 1.5 run more than or equal to cooling water pump smallest positive integral, cooling tower puts into operation the minimum of quantity Quantity of the value equal to cooling water pump operation.
The maximum of quantity=cooling water pump operation quantity × 1.5 that is, cooling tower puts into operation, and round up ( That is, as long as there is decimal place after decimal point, then upward carry rounds the integer that numerical digit plus 1 and obtained).For example, 1 cooling water pump At most corresponding 2 cooling towers, 2 at most corresponding 3 cooling towers of cooling water pump, 3 cooling water pump 5 cooling towers of most correspondences, The like.It is to be noted that, because the maximum number of cooling tower in system is n platforms, therefore, n platforms cooling water pump is at most N platform cooling tower passages can only be corresponded to.
The quantity that the cooling tower determined according to above-mentioned maximum and minimum value puts into operation, the geomantic omen ratio of the cooling tower for obtaining It is able to ensure that the heat-sinking capability of cooling tower is strong, system operation compares more efficient.
Preferably, during central air conditioner system is run, the quantity that the control cooling tower of the control device 100 puts into operation The step of also include:
Judge whether to need to reduce by an operation for cooling tower, if desired, then close accumulated running time cooling most long Tower;
And/or, judge whether to need to increase an operation for cooling tower, if desired, then open accumulated running time most short Cooling tower.
That is, during central air conditioner system is run, control device 100 can judge whether to need to close (to subtract at any time One or passage for cooling tower of unlatching (increasing) less), if desired, then correspondingly turn off or on a cooling tower.Tool Body ground, when needing to close a cooling tower, then closes accumulated running time that cooling tower most long, and preferably also simultaneously Close the blower fan of the cooling tower;When needing to open a cooling tower, then accumulated running time most short that cooling tower is opened, And it is preferred that the blower fan of the cooling tower is also opened simultaneously.
Accumulated running time on cooling tower, the aggregate-value of the fan operation time of the cooling tower is referred to, work as blower fan During operation, then run time is added up, and when blower fan stops, then run time stops accumulative, but run time before this is not Can reset.The accumulated running time of cooling tower for example can be in units of hour, and precision is, for example, 0.1 hour.
Preferably, when any one of following condition C 01-C04 meets, the control device 100 is judged as that needs subtract A few operation for cooling tower:
The quantity of the quantity > cooling water pumps operation that C01, cooling tower put into operation;
C02, add tower in previous cooling tower or subtract the feelings of cumulative time >=the first prefixed time interval after tower flow terminates Under condition, if continuously meeting in the first preset duration t1:The default temperature drop rate of temperature drop rate≤the first of cooling tower outfall sewer;
Temperature≤the first desired temperature of C03, cooling tower outfall sewer;
C04, cooling tower the quantity > cooling towers that put into operation put into operation the maximum of quantity;
Wherein, the setting meaning of condition C 01 is that, when there is handpiece Water Chilling Units to close, correspondingly can also close cooling water pump, Thus the quantity for causing cooling water pump to run is reduced, when the quantity of cooling water pump operation is less than the quantity that cooling tower puts into operation When, then need to reduce by an operation for cooling tower.
In condition C 02, the first prefixed time interval may be defined as cooling tower plus-minus tower time interval, and the principle of setting should For:When adding tower or subtract after tower flow terminates the cumulative time and be more than the time interval in previous cooling tower, cooling tower goes out water temperature Degree has reached stabilization, carries out subsequent adjustment after stable in outlet water temperature again just meaningful.First prefixed time interval is preferably 5~ 20 minutes, more preferably 15 minutes.The setting meaning of condition C 02 is, when the leaving water temperature of cooling tower no longer declines, can taste Examination is closed a cooling tower and checks whether leaving water temperature raises;If water temperature is not raised after closing, illustrate that the cooling tower goes out water temperature Degree is close to wet-bulb temperature critical value.Wherein, the first preset duration t1 is preferably 60~180 seconds, more preferably 120 seconds;Described first default temperature drop rate is preferably 0.1~0.2 DEG C/min, more preferably 0.1 DEG C/min, and preferably every The temperature drop rate for calculating primary cooling tower outfall sewer in 10 seconds.
In condition C 03, first desired temperature is 18-20 DEG C, for example, being the field of screw machine for handpiece Water Chilling Units Close, the first desired temperature is preferably 20 DEG C, be the occasion of centrifuge for handpiece Water Chilling Units, the first desired temperature is preferably 18 ℃.The setting meaning of the condition C 03 is that the minimum temperature of cooling tower water outlet must meet the cooling water temperature requirement of unit, because For cooling water temperature is too low, unit may report high voltage protective, therefore cooling tower leaving water temperature should be prevented too low.
In condition C 04, cooling tower put into operation quantity maximum for current cooling water pump run quantity × 1.5, and to On round.Because the operation quantity of cooling water pump can be adjusted according to the operating mode of system, therefore, the maximum of cooling tower passage is opened Open the actual motion quantity that quantity (namely cooling tower put into operation the maximum of quantity) should be all the time to cooling water pump related.
Preferably, when any one of following condition C 11-C13 meets, the control device 100 is judged as needing to increase Plus an operation for cooling tower:
C11, add tower in previous cooling tower or subtract the feelings of cumulative time >=the first prefixed time interval after tower flow terminates Under condition, if continuously meeting in the second preset duration t2:The default temperature rise rate of temperature rise rate >=the first of cooling tower outfall sewer;
Temperature >=second temperature the setting value of C12, cooling tower outfall sewer;
The quantity of the quantity < cooling water pumps operation that C13, cooling tower put into operation.
Wherein, the setting meaning of condition C 11 is that, if water temperature rises, deviate from outdoor wet-bulb temperature value, then increase by one Cooling tower passage, to reduce temperature.Specifically, the meaning of the first prefixed time interval is the same, and the second preset duration t2 is preferably 60~180 seconds, more preferably 120 seconds, the first default temperature rise rate was preferably 0.1~0.2 DEG C/min, more preferably 0.2 DEG C/ Minute, and calculate within preferably every 10 seconds the temperature rise rate of primary cooling tower outfall sewer.
The setting meaning of condition C 12 is, if water temperature over-high, unit efficiency declines, it is therefore desirable to plus a cooling tower Passage, to reduce temperature.Specifically, the second temperature setting value is preferably 28~32 DEG C, more preferably 30 DEG C.
The setting meaning of condition C 13 is that the quantity that cooling tower puts into operation is too small (being less than its minimum value), causes cooling The heat-sinking capability of tower declines, it is therefore desirable to increase a cooling tower passage, to reduce temperature.
When in one cooling tower of closing in the case of meeting above-mentioned condition or increase, can guarantee that water temperature change is more steady It is fixed, and close outdoor wet-bulb temperature.
Preferably, control method of the invention also includes being controlled the number of units of blower fan of cooling tower, specifically includes step:
During central air conditioner system is run, if continuously meeting in the 3rd preset duration t3:Cooling tower outfall sewer Temperature >=the 3rd desired temperature, then open the blower fan of all cooling towers for putting into operation;
And/or, during central air conditioner system is run, when all cooling water pumps are to close, or, if default the 6th Continuously meet in duration t6:The desired temperatures of temperature < the 6th of cooling tower outfall sewer, then close the wind of all of cooling tower Machine.
That is, when system blower fan of cooling tower runs, if the temperature of cooling tower outfall sewer >=the 3rd desired temperature is (excellent Elect 20~24 DEG C as, more preferably 24 DEG C, because 24 DEG C are relatively reasonable blower fans and start point) when, and in the 3rd preset duration When continuously meeting in t3 (preferably 30~90 seconds, more preferably 60 seconds), then the blower fan of cooling tower that all passages have been opened is opened, No matter each blower fan of cooling tower is frequency conversion fan or determines frequency blower fan.
And during central air conditioner system is run, when all cooling water pumps are to close, then all cooling towers are closed immediately Blower fan, to avoid waste of energy.Or, the desired temperatures of temperature < the 6th of cooling tower outfall sewer (may be defined as unit cold But return water temperature protection value, more preferably preferably 14~20 DEG C, 18 DEG C), and in the 6th preset duration t6 (preferably 5~30 Second, more preferably 20 seconds) in it is continuous when meeting, all blower fans are also switched off, so as to protect handpiece Water Chilling Units, it is to avoid water temperature is too low to be caused Unit report high voltage protective.
Preferably, the step of number of units and/or frequency of the operation of the control of the control device 100 blower fan of cooling tower includes:
If blower fan of cooling tower adjusts the number of units of the fan operation of the cooling tower for putting into operation to determine frequency blower fan;
If blower fan of cooling tower is frequency conversion fan, the frequency of the blower fan of all cooling towers for putting into operation is adjusted in synchronism, and It is preferred that the control of blower fan number of units can not be related to these blower fans with opening with pass.
That is, when blower fan of cooling tower is to determine frequency blower fan, suitable wind can be realized by controlling the number of units of fan operation Water ratio;And if when blower fan of cooling tower is frequency conversion fan, suitable geomantic omen can be realized by controlling the running frequency of blower fan Than, it is not necessary to change the number of units of fan operation.
Wrapped preferably for the step of determining frequency blower fan, the number of units of the adjustment blower fan of cooling tower operation of the control device 100 Include:
Judge whether to need to increase an operation for blower fan of cooling tower, if desired, then open accumulated running time most short Blower fan of cooling tower;
And/or, judge whether to need to reduce by an operation for blower fan of cooling tower, if desired, then close accumulated running time Blower fan of cooling tower most long, but should ensure that at least remaining Fans operation.
Specifically, for determining frequency blower fan, when following condition Cs 21 are met, the control device 100 is judged as needing to increase Plus an operation for blower fan of cooling tower:
C21, continuously meet in the 4th preset duration t4 (preferably 30~90 seconds, more preferably 60 seconds):Cooling tower goes out The temperature of supply mains >=the 4th desired temperature (preferably 24~28 DEG C, more preferably 26 DEG C).
When following condition Cs 22 are met, the control device 100 is judged as needing to reduce by a fortune for blower fan of cooling tower OK:
C22, continuously meet in the 5th preset duration t5 (preferably 30~90 seconds, more preferably 60 seconds):6th temperature The temperature of setting value≤cooling tower outfall sewer≤the 5th desired temperature (preferably 20~24 DEG C, more preferably 22 DEG C).Its In the 6th design temperature with it is hereinbefore consistent, be unit cooling backwater temperature protection value, preferably 14~20 DEG C, more preferably 18 ℃。
In other cases, the operation number of units of blower fan of cooling tower keeps constant.
Added by above-mentioned blower fan, Control of decreasing load, can try one's best by cooling tower leaving water temperature control between 22~26 DEG C.
Include preferably for frequency conversion fan, the step of the control device 100 is adjusted in synchronism the frequency of all blower fans:
If continuously meeting in the 7th preset duration t7 (preferably 5~30 seconds, more preferably 10 seconds):Cooling tower water outlet is total The temperature of pipe >=the 7th desired temperature (preferably 28~30 DEG C, more preferably 28 DEG C), then raise the frequency of all blower fans F1;
If continuously meeting in the 7th preset duration t7 (preferably 5~30 seconds, more preferably 10 seconds):8th temperature sets It is worth the desired temperatures of temperature < the 7th of (preferably 26~28 DEG C, more preferably 26 DEG C)≤cooling tower outfall sewer (preferably 28~30 DEG C, more preferably 28 DEG C), then the frequency of all blower fans is raised into F2, wherein, F2 < F1;For example, F1=2~8Hz, F2=0.5~2Hz, it is preferable that F1=5Hz;F2=2Hz.
Controlled by above-mentioned raising frequency, can tried one's best the control of cooling tower leaving water temperature between 20~28 DEG C.
If continuously meeting in the 8th preset duration t8 (preferably 5~30 seconds, more preferably 20 seconds):9th temperature sets It is worth the desired temperatures of temperature < the tenth of (preferably 14~19 DEG C, more preferably 19 DEG C)≤cooling tower outfall sewer (preferably 20~24 DEG C, more preferably 22 DEG C), then by the frequency reduction F3 of all blower fans;
If continuously meeting in the 8th preset duration t8 (preferably 5~30 seconds, more preferably 20 seconds):11st temperature sets The desired temperatures of temperature < the 9th of definite value (preferably 14~19 DEG C, more preferably 18 DEG C)≤cooling tower outfall sewer are (preferably It is 14~19 DEG C, more preferably 19 DEG C), then by the frequency reduction F4 of all blower fans, wherein, F3 < F4;For example, F3=0.5~ 2Hz, F4=2~8Hz, it is preferable that F3=2Hz;F4=5Hz.
Controlled by above-mentioned frequency reducing, can tried one's best the control of cooling tower leaving water temperature between 20~28 DEG C.
The frequency of blower fan is not adjusted in the case of other then.
To sum up, contrast is in the prior art using " method for installing outdoor temperature humidity sensor ", control method of the invention Control cooling tower leaving water temperature is relatively reliable, and need not install outdoor temperature humidity sensor, because the present invention dissipating by water temperature Thermal characteristics and geomantic omen than method, cooling tower leaving water temperature on the premise of more energy-conservation can be allowed to be constantly in lower limit temperature attached Closely, so as to allow handpiece Water Chilling Units more energy-conservation.
Those skilled in the art is it is easily understood that on the premise of not conflicting, above-mentioned each preferred scheme can be free Ground combination, superposition.
It should be appreciated that above-mentioned implementation method is only illustrative, and not restrictive, without departing from of the invention basic In the case of principle, various obvious or equivalent modification or replace that those skilled in the art can make for above-mentioned details Change, be all included in scope of the presently claimed invention.

Claims (15)

1. a kind of control method of central air conditioner system cooling tower leaving water temperature, the central air conditioner system include control device, Cooling tower group, cooling pump group and handpiece Water Chilling Units, the entrance side of the cooling pump group connects the water tank side of the cooling tower group, described The outlet side for cooling down pump group connects the cold side water inlet of the handpiece Water Chilling Units, the cold side delivery port connection of the handpiece Water Chilling Units The spray side of the cooling tower group, the control device is connected with the cooling tower group, the cooling pump group;Characterized in that, The control method includes step:The control device is by the quantity that controls cooling tower to put into operation, and/or control cooling tower The number of units and/or frequency of fan operation are reached realizing cooling tower leaving water temperature or close to outdoor wet-bulb temperature.
2. control method according to claim 1, it is characterised in that when central air conditioner system starts, the control dress The step of putting the quantity for controlling cooling tower to put into operation includes:
Quantity according to the cooling water pump of actual motion in the cooling pump group determines the quantity that cooling tower puts into operation.
3. control method according to claim 2, it is characterised in that determine the principle of the quantity that cooling tower puts into operation For:The quantity that cooling tower puts into operation is the smallest positive integral of quantity × 1.5 run more than or equal to cooling water pump.
4. control method according to claim 1, it is characterised in that during central air conditioner system is run, the control The step of quantity that device control cooling tower puts into operation, includes:
Make the quantity that cooling tower puts into operation between maximum and minimum value, wherein, cooling tower puts quantity into operation most Big value is the smallest positive integral of quantity × 1.5 more than or equal to cooling water pump operation, and cooling tower puts into operation the minimum value etc. of quantity In the quantity of cooling water pump operation.
5. control method according to claim 4, it is characterised in that during central air conditioner system is run, the control The step of quantity that device control cooling tower puts into operation, also includes:
Judge whether to need to reduce by an operation for cooling tower, if desired, then close accumulated running time cooling tower most long;
And/or, judge whether to need to increase an operation for cooling tower, if desired, then open accumulated running time most short cold But tower.
6. control method according to claim 5, it is characterised in that
When any one of following condition C 01-C04 meets, the control device is to be judged as needing to reduce by a cooling tower Operation:
The quantity of the quantity > cooling water pumps that C01, cooling tower put into operation;
C02, in Jia Ta or when subtracting cumulative time >=the first prefixed time interval after tower flow terminates, if in the first preset duration t1 Interior continuous satisfaction:The default temperature drop rate of temperature drop rate≤the first of cooling tower outfall sewer;
Temperature≤the first desired temperature of C03, cooling tower outfall sewer;
C04, cooling tower the quantity > cooling towers that put into operation put into operation the maximum of quantity;
And/or,
When any one of following condition C 11-C13 meets, the control device is to be judged as needing to increase a cooling tower Operation:
C11, in Jia Ta or when subtracting cumulative time >=the first prefixed time interval after tower flow terminates, if in the second preset duration t2 Interior continuous satisfaction:The default temperature rise rate of temperature rise rate >=the first of cooling tower outfall sewer;
Temperature >=second temperature the setting value of C12, cooling tower outfall sewer;
The quantity of the quantity < cooling water pumps operation that C13, cooling tower put into operation.
7. control method according to claim 6, it is characterised in that
First prefixed time interval is 5~20 minutes;
And/or, the first preset duration t1 is 60~180 seconds;
And/or, the described first default temperature drop rate is 0.1~0.2 DEG C/min;
And/or, first desired temperature is 18-20 DEG C;
And/or, the second preset duration t2 is 60~180 seconds;
And/or, the described first default temperature rise rate is 0.1~0.2 DEG C/min;
And/or, the second temperature setting value is 28~32 DEG C.
8. control method according to claim 1, it is characterised in that also including step:
During central air conditioner system is run, if continuously meeting in the 3rd preset duration t3:The temperature of cooling tower outfall sewer >=the three desired temperature, then open the blower fan of all cooling towers for putting into operation;
And/or, during central air conditioner system is run, when all cooling water pumps are to close, or, if in the 6th preset duration Continuously meet in t6:The desired temperatures of temperature < the 6th of cooling tower outfall sewer, then close the blower fan of all of cooling tower.
9. control method according to claim 8, it is characterised in that
The 3rd preset duration t3 is 30~90 seconds;
And/or, the 3rd desired temperature is 20~24 DEG C;
And/or, the 6th preset duration t6 is 5~30 seconds;
And/or, the 6th desired temperature is 14~20 DEG C.
10. according to the control method that one of claim 1-9 is described, it is characterised in that the control device controls cooling tower wind The step of number of units and/or frequency of machine operation, includes:
If blower fan of cooling tower adjusts the number of units of the fan operation of the cooling tower for putting into operation to determine frequency blower fan;
If blower fan of cooling tower is frequency conversion fan, the frequency of the blower fan of all cooling towers for putting into operation is adjusted in synchronism.
11. control methods according to claim 10, it is characterised in that for determining frequency blower fan, the control device adjustment The step of number of units of blower fan of cooling tower operation, includes:
Judge whether to need to increase an operation for blower fan of cooling tower, if desired, then open accumulated running time most short cooling Tower blower fan;
And/or, judge whether to need to reduce by an operation for blower fan of cooling tower, if desired, then close accumulated running time most long Blower fan of cooling tower.
12. control methods according to claim 11, it is characterised in that
When following condition Cs 21 are met, the control device is to be judged as needing to increase an operation for blower fan of cooling tower:
C21, continuously meet in the 4th preset duration t4:The temperature of cooling tower outfall sewer >=the 4th desired temperature;
And/or, when following condition Cs 22 are met, the control device is to be judged as needing to reduce by a fortune for blower fan of cooling tower OK:
C22, continuously meet in the 5th preset duration t5:Temperature≤the 5th of six desired temperatures≤cooling tower outfall sewer Desired temperature.
13. control methods according to claim 12, it is characterised in that
The 4th preset duration t4 is 30~90 seconds;
And/or, the 4th desired temperature is 24~28 DEG C;
And/or, the 5th preset duration t5 is 30~90 seconds;
And/or, the 5th desired temperature is 20~24 DEG C;
And/or, the 6th desired temperature is 14~20 DEG C.
14. control methods according to claim 10, it is characterised in that for frequency conversion fan, the control device synchronization The step of frequency for adjusting all blower fans, includes:
If continuously meeting in the 7th preset duration t7:The temperature of cooling tower outfall sewer >=the 7th desired temperature, then by institute The frequency for having blower fan raises F1;
If continuously meeting in the 7th preset duration t7:The temperature of temperature < the 7th of eight desired temperatures≤cooling tower outfall sewer Degree setting value, then raise F2 by the frequency of all blower fans, wherein, F2 < F1;
And/or,
If continuously meeting in the 8th preset duration t8:The temperature of temperature < the tenth of nine desired temperatures≤cooling tower outfall sewer Degree setting value, then by the frequency reduction F3 of all blower fans;
If continuously meeting in the 8th preset duration t8:The temperature < the 9th of 11 desired temperatures≤cooling tower outfall sewer Desired temperature, then by the frequency reduction F4 of all blower fans, wherein, F3 < F4.
15. control methods according to claim 14, it is characterised in that
The 7th preset duration t7 is 5~30 seconds;
And/or, the 7th desired temperature is 28~30 DEG C;
And/or, the 8th desired temperature is 26~28 DEG C.
And/or, F1=2~8Hz;
And/or, F2=0.5~2Hz;
And/or, the 8th preset duration t8 is 5~30 seconds;
And/or, the 9th desired temperature is 14~19 DEG C;
And/or, the tenth desired temperature is 20~24 DEG C.
And/or, the 11st desired temperature is 14~19 DEG C;
And/or, F3=0.5~2Hz;
And/or, F4=2~8Hz.
CN201710136349.1A 2017-03-09 2017-03-09 Method for controlling outlet water temperature of cooling tower of central air-conditioning system Active CN106871364B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710136349.1A CN106871364B (en) 2017-03-09 2017-03-09 Method for controlling outlet water temperature of cooling tower of central air-conditioning system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710136349.1A CN106871364B (en) 2017-03-09 2017-03-09 Method for controlling outlet water temperature of cooling tower of central air-conditioning system

Publications (2)

Publication Number Publication Date
CN106871364A true CN106871364A (en) 2017-06-20
CN106871364B CN106871364B (en) 2020-12-04

Family

ID=59170219

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710136349.1A Active CN106871364B (en) 2017-03-09 2017-03-09 Method for controlling outlet water temperature of cooling tower of central air-conditioning system

Country Status (1)

Country Link
CN (1) CN106871364B (en)

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107388882A (en) * 2017-08-02 2017-11-24 南京理工大学 The multi fan of cooling tower sprays collaboration fuzzy control method more
CN107525430A (en) * 2017-09-19 2017-12-29 上海大众祥源动力供应有限公司 A kind of cooling tower frequency conversion fan control system and method
CN107831720A (en) * 2017-10-20 2018-03-23 爱普(福建)科技有限公司 Optimize the control method and computer equipment of equipment operating mode
CN108224624A (en) * 2017-12-18 2018-06-29 青岛海尔空调电子有限公司 For the control method and device of cooling-water machine system
CN108775673A (en) * 2018-08-06 2018-11-09 珠海格力电器股份有限公司 Air-conditioning site monitor, air-conditioning group control system and air-conditioning
CN109595746A (en) * 2018-12-20 2019-04-09 珠海格力电器股份有限公司 Water pump efficiency optimal control method, device and computer equipment
CN109751911A (en) * 2019-01-24 2019-05-14 珠海格力电器股份有限公司 Blower fan of cooling tower frequency adaptive regulation method and air-conditioning system
CN110360868A (en) * 2019-07-17 2019-10-22 珠海格力电器股份有限公司 Cooling tower and its frequency conversion fan upper limiting frequency adjusting method, device, air-conditioner set
CN110398034A (en) * 2019-07-15 2019-11-01 广东美的暖通设备有限公司 Cooling tower control method, system and the air-conditioning of air-conditioning
CN110553369A (en) * 2019-09-04 2019-12-10 珠海格力电器股份有限公司 Multi-fan cooling tower control method, cooling tower and air conditioner
CN111076345A (en) * 2019-12-11 2020-04-28 珠海格力电器股份有限公司 Prediction device and method of central air-conditioning system and terminal equipment
CN112377996A (en) * 2020-11-18 2021-02-19 厦门烟草工业有限责任公司 Air conditioning system and control method thereof
CN112556485A (en) * 2020-12-29 2021-03-26 昆山璟赫机电工程有限公司 Operation control system and operation control method for cooling tower of ice machine
CN112857132A (en) * 2021-01-07 2021-05-28 丁一 Cooling tower, cooling tower detection control method, device, equipment and storage medium
CN112857131A (en) * 2021-01-07 2021-05-28 丁一 Cooling tower control method and device and cooling system
CN113187756A (en) * 2021-06-15 2021-07-30 河南艾牧智能设备有限公司 Livestock and poultry house temperature gentle control method
CN113916024A (en) * 2021-10-26 2022-01-11 珠海格力电器股份有限公司 Management method, device and equipment of cooling tower, cooling tower and temperature control system
CN114857687A (en) * 2022-04-15 2022-08-05 中国建筑西南设计研究院有限公司 Control system and method for cooling water system of water-cooled central air conditioner
CN114893870A (en) * 2022-05-17 2022-08-12 广州大学 Predictive control method for natural cooling system operation mode
CN115183408A (en) * 2022-06-17 2022-10-14 珠海格力电器股份有限公司 Control method and control device for variable flow operation of cooling water system
CN107525430B (en) * 2017-09-19 2024-05-03 上海大众祥源动力供应有限公司 Cooling tower variable frequency fan control system and method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011185478A (en) * 2010-03-05 2011-09-22 Hitachi Plant Technologies Ltd Cooling system
JP2013164260A (en) * 2013-05-28 2013-08-22 Toshiba Corp Air conditioning control device, air conditioning control method, and program for air conditioning control
WO2016006872A1 (en) * 2014-07-08 2016-01-14 Lg Electronics Inc. Chiller
CN205317074U (en) * 2015-12-04 2016-06-15 河南中烟工业有限责任公司许昌卷烟厂 Cooling tower water temperature control system
CN205536262U (en) * 2016-02-01 2016-08-31 大连中盈机电工程有限公司 Freezing water system of energy -conserving building
CN105953602A (en) * 2016-04-25 2016-09-21 珠海格力电器股份有限公司 Energy-saving control method and device used for cooling tower and air-conditioning system
CN106123215A (en) * 2016-06-27 2016-11-16 新奥泛能网络科技股份有限公司 A kind of air conditioning cooling water system control method and device
CN205783571U (en) * 2016-05-26 2016-12-07 深圳市新环能科技有限公司 A kind of central air conditioner cooling system energy-saving control apparatus

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011185478A (en) * 2010-03-05 2011-09-22 Hitachi Plant Technologies Ltd Cooling system
JP2013164260A (en) * 2013-05-28 2013-08-22 Toshiba Corp Air conditioning control device, air conditioning control method, and program for air conditioning control
WO2016006872A1 (en) * 2014-07-08 2016-01-14 Lg Electronics Inc. Chiller
CN205317074U (en) * 2015-12-04 2016-06-15 河南中烟工业有限责任公司许昌卷烟厂 Cooling tower water temperature control system
CN205536262U (en) * 2016-02-01 2016-08-31 大连中盈机电工程有限公司 Freezing water system of energy -conserving building
CN105953602A (en) * 2016-04-25 2016-09-21 珠海格力电器股份有限公司 Energy-saving control method and device used for cooling tower and air-conditioning system
CN205783571U (en) * 2016-05-26 2016-12-07 深圳市新环能科技有限公司 A kind of central air conditioner cooling system energy-saving control apparatus
CN106123215A (en) * 2016-06-27 2016-11-16 新奥泛能网络科技股份有限公司 A kind of air conditioning cooling water system control method and device

Cited By (30)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107388882A (en) * 2017-08-02 2017-11-24 南京理工大学 The multi fan of cooling tower sprays collaboration fuzzy control method more
CN107525430A (en) * 2017-09-19 2017-12-29 上海大众祥源动力供应有限公司 A kind of cooling tower frequency conversion fan control system and method
CN107525430B (en) * 2017-09-19 2024-05-03 上海大众祥源动力供应有限公司 Cooling tower variable frequency fan control system and method
CN107831720A (en) * 2017-10-20 2018-03-23 爱普(福建)科技有限公司 Optimize the control method and computer equipment of equipment operating mode
CN108224624B (en) * 2017-12-18 2020-08-18 青岛海尔空调电子有限公司 Control method and device for water chiller system
CN108224624A (en) * 2017-12-18 2018-06-29 青岛海尔空调电子有限公司 For the control method and device of cooling-water machine system
CN108775673A (en) * 2018-08-06 2018-11-09 珠海格力电器股份有限公司 Air-conditioning site monitor, air-conditioning group control system and air-conditioning
CN109595746A (en) * 2018-12-20 2019-04-09 珠海格力电器股份有限公司 Water pump efficiency optimal control method, device and computer equipment
CN109751911A (en) * 2019-01-24 2019-05-14 珠海格力电器股份有限公司 Blower fan of cooling tower frequency adaptive regulation method and air-conditioning system
CN109751911B (en) * 2019-01-24 2019-12-13 珠海格力电器股份有限公司 Self-adaptive adjusting method for fan frequency of cooling tower and air conditioning system
CN110398034A (en) * 2019-07-15 2019-11-01 广东美的暖通设备有限公司 Cooling tower control method, system and the air-conditioning of air-conditioning
CN110398034B (en) * 2019-07-15 2021-05-04 上海美控智慧建筑有限公司 Cooling tower control method and system of air conditioner and air conditioner
CN110360868A (en) * 2019-07-17 2019-10-22 珠海格力电器股份有限公司 Cooling tower and its frequency conversion fan upper limiting frequency adjusting method, device, air-conditioner set
CN110360868B (en) * 2019-07-17 2020-06-26 珠海格力电器股份有限公司 Cooling tower, method and device for adjusting upper limit frequency of variable frequency fan of cooling tower and air conditioning unit
CN110553369B (en) * 2019-09-04 2020-08-11 珠海格力电器股份有限公司 Multi-fan cooling tower control method, cooling tower and air conditioner
CN110553369A (en) * 2019-09-04 2019-12-10 珠海格力电器股份有限公司 Multi-fan cooling tower control method, cooling tower and air conditioner
CN111076345B (en) * 2019-12-11 2021-03-30 珠海格力电器股份有限公司 Prediction device and method of central air-conditioning system and terminal equipment
CN111076345A (en) * 2019-12-11 2020-04-28 珠海格力电器股份有限公司 Prediction device and method of central air-conditioning system and terminal equipment
CN112377996B (en) * 2020-11-18 2022-07-26 厦门烟草工业有限责任公司 Air conditioning system and control method thereof
CN112377996A (en) * 2020-11-18 2021-02-19 厦门烟草工业有限责任公司 Air conditioning system and control method thereof
CN112556485A (en) * 2020-12-29 2021-03-26 昆山璟赫机电工程有限公司 Operation control system and operation control method for cooling tower of ice machine
CN112857132A (en) * 2021-01-07 2021-05-28 丁一 Cooling tower, cooling tower detection control method, device, equipment and storage medium
CN112857131A (en) * 2021-01-07 2021-05-28 丁一 Cooling tower control method and device and cooling system
CN113187756A (en) * 2021-06-15 2021-07-30 河南艾牧智能设备有限公司 Livestock and poultry house temperature gentle control method
CN113916024A (en) * 2021-10-26 2022-01-11 珠海格力电器股份有限公司 Management method, device and equipment of cooling tower, cooling tower and temperature control system
CN114857687A (en) * 2022-04-15 2022-08-05 中国建筑西南设计研究院有限公司 Control system and method for cooling water system of water-cooled central air conditioner
CN114857687B (en) * 2022-04-15 2024-01-23 中国建筑西南设计研究院有限公司 Control system and method for water-cooled central air conditioner cooling water system
CN114893870A (en) * 2022-05-17 2022-08-12 广州大学 Predictive control method for natural cooling system operation mode
CN114893870B (en) * 2022-05-17 2023-10-03 广州大学 Predictive control method for natural cooling system operation mode
CN115183408A (en) * 2022-06-17 2022-10-14 珠海格力电器股份有限公司 Control method and control device for variable flow operation of cooling water system

Also Published As

Publication number Publication date
CN106871364B (en) 2020-12-04

Similar Documents

Publication Publication Date Title
CN106871364A (en) A kind of control method of central air conditioner system cooling tower leaving water temperature
CA2562062C (en) Damper control in space heating and cooling
CN103423837B (en) Free static pressure air-cooled ducted air conditioner
CN104121666B (en) For central air-conditioning wind system by time frequency conversion air feed system and control method
JP5872509B2 (en) Server room cooling apparatus and method using natural air
CN103206747B (en) For the cooling system of server in server room
CN104713205A (en) Ventilation air conditioning energy saving system for subway
CN102306044A (en) Automatic control refrigeration system for high-density computer room and method thereof
CN107917512B (en) Control method and device of air conditioning system and air conditioner
CN109751911A (en) Blower fan of cooling tower frequency adaptive regulation method and air-conditioning system
CN104374036A (en) Control method of air conditioner and air conditioning unit
CN106287964A (en) Air-conditioner and cleaning control method thereof and device
WO2013034627A1 (en) Wind turbine with tower climatisation system using outside air
CN109827300A (en) The new blower of mixed wind ratio and specific purpose tool and adjusting method inside and outside adjustable chamber
CN105157182A (en) Intelligent management and energy saving system for heat source of base station
CN106594930A (en) Energy-saving computer room air conditioning system
CN105157187A (en) Intelligent base station heat source management energy-saving system
CN205784825U (en) A kind of based on a point cooling tower energy-saving control device for tower heat radiation
CN109253492A (en) A kind of adjusting method solving heating system hydraulic misadjustment
CN109595841A (en) Air-conditioning system and its control method
KR101385584B1 (en) An automatic control system for cooling/heating and air-pressure in the buiding using the smart grid
CN105352136A (en) Intelligent workshop air conditioning system
CN205119351U (en) Basic station heat source intelligent management economizer system
CN204555143U (en) High voltage converter computer room temperature and negative pressure adjustment structure
CN204559375U (en) High voltage converter computer room temperature adjustment structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant