CN106869494A - A kind of steel column mould ruggedized construction construction method - Google Patents

A kind of steel column mould ruggedized construction construction method Download PDF

Info

Publication number
CN106869494A
CN106869494A CN201611263485.9A CN201611263485A CN106869494A CN 106869494 A CN106869494 A CN 106869494A CN 201611263485 A CN201611263485 A CN 201611263485A CN 106869494 A CN106869494 A CN 106869494A
Authority
CN
China
Prior art keywords
steel column
column mould
mould
steel
channel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611263485.9A
Other languages
Chinese (zh)
Inventor
李斌
陈喆
梁军
林作胜
陈忠良
彭伟炯
王珏非
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai No 7 Construction Co Ltd
Original Assignee
Shanghai No 7 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai No 7 Construction Co Ltd filed Critical Shanghai No 7 Construction Co Ltd
Priority to CN201611263485.9A priority Critical patent/CN106869494A/en
Publication of CN106869494A publication Critical patent/CN106869494A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/02Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for columns or like pillars; Special tying or clamping means therefor

Abstract

Steel pipe, fastener or built-in to pull bar reinforcement means are used for traditional section beam-column template, post concrete is easily caused and is risen mould, sectional dimension deviation, uneven surface, the problem that the phenomenon such as spillage occurs, the invention discloses a kind of steel column mould ruggedized construction construction method, including:Step 1:According to column dimensions assembly steel column mould;Step 2:Steel column mould is lifted to pillar position and steel column mould is installed;Step 3:Steel column mould surrounding along steel column mould some channel-section steel anchor ears of longitudinally spaced installation, the channel-section steel anchor ear fixed by being placed in the split bolt of post exterior side.Steel column mould ruggedized construction construction method of the invention, lead to some channel-section steel anchor ears of longitudinally spaced installation along steel column mould in steel column mould surrounding, the channel-section steel anchor ear is fixed by being placed in the split bolt of post exterior side, can effectively avoid rise mould, sectional dimension deviation of post concrete big, uneven surface, the phenomenons such as spillage occur, and material therefor cyclic utilization rate is high.

Description

A kind of steel column mould ruggedized construction construction method
Technical field
The present invention relates to technical field of building construction, and in particular to steel column mould ruggedized construction construction method.
Background technology
Traditional section beam-column template uses steel pipe, fastener or built-in to pull bar reinforcement means, easily causes post concrete and rises mould, section The phenomenons such as dimensional discrepancy, uneven surface, spillage occur, and have certain disadvantage.
How providing one kind can effectively avoid post concrete from rising by mould, sectional dimension deviation greatly, uneven surface, the phenomenon such as spillage Occur, and a kind of material therefor cyclic utilization rate steel column mould ruggedized construction construction method high is urgently to be resolved hurrily one in this area Individual technical problem.
The content of the invention
The present invention provides steel column mould ruggedized construction construction method, leads to the longitudinally spaced peace along steel column mould in steel column mould surrounding Some channel-section steel anchor ears are filled, the channel-section steel anchor ear is fixed by being placed in the split bolt of post exterior side, can effectively avoid post concrete Mould, the sectional dimension deviation of rising are big, uneven surface, and the phenomenon such as spillage occurs, and material therefor cyclic utilization rate is high.
A kind of steel column mould ruggedized construction construction method, including:
Step 1:According to column dimensions assembly steel column mould;
Step 2:Steel column mould is lifted to pillar position and steel column mould is installed;
Step 3:Steel column mould surrounding along steel column mould some channel-section steel anchor ears of longitudinally spaced installation, the channel-section steel anchor ear lead to Cross and be placed in the split bolt of post exterior side and fix.
Preferably, in above-mentioned steel column mould reinforcing construction way, in the step 3, the cross section of the steel column mould is Rectangle, each channel-section steel anchor ear includes four channel-section steels of the surrounding for being arranged at steel column mould, two grooves being parallel to each other in four channel-section steels The two ends of steel are connected by the split bolt.
Preferably, in above-mentioned steel column mould reinforcing construction way, the spacing between adjacent slot steel hoop is 400- 500mm。
Above-mentioned technical proposal can be seen that due to the present invention using intensity it is high it is repeatable by the use of steel column mould as post mould Plate, prior art is replaced using " to the external channel-section steel anchor ear formwork reinforcement of pull bar " advanced technologies, will channel-section steel anchor ear as steel column The ruggedized construction of mould, split bolt is arranged on post exterior side, it is to avoid the hole left of the split bolt after proposed pillar, Therefore the building method shown in the present invention can effectively avoid post concrete from rising by mould, sectional dimension deviation greatly, uneven surface, spillage etc. Phenomenon occurs, and material therefor cyclic utilization rate is high.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing The accompanying drawing to be used needed for having technology description is briefly described, it should be apparent that, drawings in the following description are only this Some embodiments of invention, for those of ordinary skill in the art, on the premise of not paying creative work, can be with Other accompanying drawings are obtained according to these accompanying drawings.
Fig. 1 is steel column mould reinforcing construction elevational schematic view in the present invention.
Fig. 2 is steel column mould reinforcing construction generalized section in the present invention.
In figure:1- pillars, 2- steel columns mould, 3- split bolts, 4- channel-section steels.
Specific embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments.It is based on Embodiment in the present invention, it is all other that those of ordinary skill in the art are obtained under the premise of creative work is not made Embodiment, belongs to the scope of protection of the invention.
The embodiment of the present invention provides steel column mould ruggedized construction construction method, can effectively avoid post concrete from rising mould, section chi Very little deviation is big, uneven surface, and the phenomenon such as spillage occurs, and material therefor cyclic utilization rate is high.Carry out individually below specifically It is bright.
Fig. 1 and Fig. 2 is referred to, the embodiment of the present invention provides a kind of steel column mould ruggedized construction construction method, including:
Step 1:According to the size of pillar 1 assembly steel column mould 2.
Step 2:Steel column mould 2 is lifted to the position of pillar 1 and steel column mould 2 is installed.
Step 3:The surrounding of steel column mould 2 along steel column mould 2 some channel-section steel anchor ears of longitudinally spaced installation, the channel-section steel anchor ear Fixed by the split bolt 3 for being placed in the outside of pillar 1.
Due to the present invention using intensity it is high it is repeatable by the use of steel column mould 2 as column template, using channel-section steel anchor ear as steel column The ruggedized construction of mould 2, split bolt 3 is arranged on the outside of pillar 1, it is to avoid the leaving after proposed pillar 1 of split bolt 3 Hole, therefore building method shown in the present invention can effectively avoid rise mould, sectional dimension deviation of post concrete big, uneven surface, The phenomenons such as spillage occur, and material therefor cyclic utilization rate is high.
Preferably, in the above-mentioned reinforcing construction way of steel column mould 2, in the step 3, the cross section of the steel column mould 2 It is rectangle, each channel-section steel anchor ear includes four channel-section steels 4 of the surrounding for being arranged at steel column mould 2, two be parallel to each other in four channel-section steels 4 The two ends of root channel-section steel 4 are connected by the split bolt 3.
Preferably, in the above-mentioned reinforcing construction way of steel column mould 2, the spacing between adjacent slot steel hoop is 400- 500mm。
In sum, due to the present invention using intensity it is high it is repeatable by the use of steel column mould as column template, using " to pull bar External channel-section steel anchor ear formwork reinforcement " advanced technologies replace prior art, will channel-section steel anchor ear as steel column mould ruggedized construction, it is right Bolt is drawn to be arranged on post exterior side, it is to avoid the hole left of the split bolt after proposed pillar, therefore shown in the present invention Building method can effectively avoid rise mould, sectional dimension deviation of post concrete big, uneven surface, the phenomenon such as spillage occurs, and Material therefor cyclic utilization rate is high.
The steel column mould ruggedized construction construction method for being provided the embodiment of the present invention above, is described in detail, herein In apply specific case principle of the invention and implementation method be set forth, the explanation of above example is only intended to side Assistant solves the method for the present invention and its core concept;Simultaneously for those of ordinary skill in the art, according to think of of the invention Think, will change in specific embodiments and applications, in sum, it is right that this specification content should not be construed as Limitation of the invention.

Claims (3)

1. a kind of steel column mould ruggedized construction construction method, it is characterised in that including:
Step 1:According to column dimensions assembly steel column mould;
Step 2:Steel column mould is lifted to pillar position and steel column mould is installed;
Step 3:Steel column mould surrounding along steel column mould some channel-section steel anchor ears of longitudinally spaced installation, the channel-section steel anchor ear is by putting Fixed in the split bolt of post exterior side.
2. steel column mould reinforcing construction way according to claim 1, it is characterised in that in the step 3, the steel column mould Cross section be rectangle, each channel-section steel anchor ear include be arranged at steel column mould surrounding four channel-section steels, in four channel-section steels mutually put down Two capable two ends of channel-section steel are connected by the split bolt.
3. steel column mould reinforcing construction way according to claim 2, it is characterised in that the spacing between adjacent slot steel hoop It is 400-500mm.
CN201611263485.9A 2016-12-30 2016-12-30 A kind of steel column mould ruggedized construction construction method Pending CN106869494A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611263485.9A CN106869494A (en) 2016-12-30 2016-12-30 A kind of steel column mould ruggedized construction construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611263485.9A CN106869494A (en) 2016-12-30 2016-12-30 A kind of steel column mould ruggedized construction construction method

Publications (1)

Publication Number Publication Date
CN106869494A true CN106869494A (en) 2017-06-20

Family

ID=59164456

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611263485.9A Pending CN106869494A (en) 2016-12-30 2016-12-30 A kind of steel column mould ruggedized construction construction method

Country Status (1)

Country Link
CN (1) CN106869494A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201391088Y (en) * 2009-01-22 2010-01-27 国核工程有限公司 As-cast-finish concrete section steel outside collar reinforcing column mold
CN103206089A (en) * 2013-04-18 2013-07-17 成军 Fabricated aluminum alloy formwork system construction method
CN203755661U (en) * 2014-03-03 2014-08-06 山西四建集团有限公司 Large-section stiffness steel rib column hoop erecting structure
CN104047422A (en) * 2014-06-13 2014-09-17 北京首钢建设集团有限公司 Cylinder die manufacturing and mounting method
CN104295092A (en) * 2014-08-28 2015-01-21 中国二十冶集团有限公司 Adjustable frame column formwork back arris system
CN104806018A (en) * 2015-05-08 2015-07-29 南通华新建工集团有限公司 Construction technology of steel frame and wood form type combined formwork

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201391088Y (en) * 2009-01-22 2010-01-27 国核工程有限公司 As-cast-finish concrete section steel outside collar reinforcing column mold
CN103206089A (en) * 2013-04-18 2013-07-17 成军 Fabricated aluminum alloy formwork system construction method
CN203755661U (en) * 2014-03-03 2014-08-06 山西四建集团有限公司 Large-section stiffness steel rib column hoop erecting structure
CN104047422A (en) * 2014-06-13 2014-09-17 北京首钢建设集团有限公司 Cylinder die manufacturing and mounting method
CN104295092A (en) * 2014-08-28 2015-01-21 中国二十冶集团有限公司 Adjustable frame column formwork back arris system
CN104806018A (en) * 2015-05-08 2015-07-29 南通华新建工集团有限公司 Construction technology of steel frame and wood form type combined formwork

Similar Documents

Publication Publication Date Title
CN204019724U (en) Make the mold of prefabricated case beam framework of steel reinforcement
CN205046677U (en) Assembled concrete frame nodal connection structure
CN204920990U (en) Two lining rebar positioning fixture in tunnel
CN104612300A (en) Hollow composite floor slab and construction method thereof
CN104727235A (en) Bridge overall strengthening device
CN204676879U (en) Model sheetinstallat structure
CN105569054A (en) Device and method for controlling direction and elevation of lattice column below ground
CN203160730U (en) Reinforced structure of concrete frame column
CN214272431U (en) Detachable assembled wallboard connection structure
CN103835303B (en) A kind of cast-type armored concrete shearing resistance method and structure
CN106869494A (en) A kind of steel column mould ruggedized construction construction method
CN206495329U (en) Adjustable accurately foot bolt reinforces mould and hardened system
CN105102734A (en) Hybrid structure and construction method for same
CN203391095U (en) Strapping mold for rebar framework of box girder
CN203393880U (en) Enhanced type reinforced concrete laminated floor slab
CN202416704U (en) Obliquely-arranged concrete cap
CN103452331A (en) Shear strengthening method of concrete beam
CN103206081B (en) Clamping fastening devices and clamping construction method
CN103397638A (en) Tie bar for supporting system in high-rigidity integral prestressed fabricated foundation pit support
CN103388336B (en) Main purline part for inner support
CN209429552U (en) A kind of vertical type concrete member steel bar cage mould
CN203891480U (en) Reinforced concrete column main reinforcement positioning hoop
CN204386168U (en) A kind of shaped steel assembly type type pillar shuttering clamp
CN106468101A (en) A kind of locating support for cast-in-place upper reversed beam side template
CN204826676U (en) Tension structure that has bonding prestressing tendons

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170620

WD01 Invention patent application deemed withdrawn after publication