CN106854864A - Port engineering platoon formula prestressed reinforced concrete Big Pipe Pile new construction - Google Patents

Port engineering platoon formula prestressed reinforced concrete Big Pipe Pile new construction Download PDF

Info

Publication number
CN106854864A
CN106854864A CN201510946377.0A CN201510946377A CN106854864A CN 106854864 A CN106854864 A CN 106854864A CN 201510946377 A CN201510946377 A CN 201510946377A CN 106854864 A CN106854864 A CN 106854864A
Authority
CN
China
Prior art keywords
platoon
stake
reinforced concrete
pile
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510946377.0A
Other languages
Chinese (zh)
Inventor
连卫东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Tong Tong Engineering Management Consulting Co Ltd
Original Assignee
Shandong Tong Tong Engineering Management Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Tong Tong Engineering Management Consulting Co Ltd filed Critical Shandong Tong Tong Engineering Management Consulting Co Ltd
Priority to CN201510946377.0A priority Critical patent/CN106854864A/en
Publication of CN106854864A publication Critical patent/CN106854864A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • E02B3/066Quays
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Abstract

A kind of port engineering new construction.By diameter 800mm above prestressed reinforced concrete pipe piles straight stake (1) platoon arrangement, arrange that taper pile (2) resists backfill (16) or wave force simultaneously, be coupled with cast-in-situ steel reinforced concrete beam (10) between platoon stake (1) and taper pile (2).Stake interleaves reinforced concrete prefabricated board (4) and cast-in-place concrete (5), or sets rock mound (18) and inverted filter (19), (20), prevents backfill (16) from spilling.The structure is used for harbour, and platoon stake (1) is both soil-baffling structure and shore approach structure;The structure is used for cofferdam, and platoon stake (1) is both soil-baffling structure and wave screening structure;The structure is used for breakwater, taper pile (2) is arranged in platoon stake (1) both sides, as wave screening structure.The present invention is applied to the port engineerings such as the thicker situation lower terminal of mud, cofferdam, breakwater, and construction equipment is simple, and technique is easy, can greatly speed up speed of application, reduces construction costs.

Description

Port engineering platoon formula prestressed reinforced concrete Big Pipe Pile new construction
Technical field
The present invention relates to a kind of new port structure, prestressed reinforced concrete Big Pipe Pile platoon arrangement as port and pier, cofferdam, is prevented The earth-retaining of ripple dike etc., wave screening structure.
Background technology
The features such as prestressed reinforced concrete Big Pipe Pile is because of its resistance to compression, good anti-bending strength, factorial praluction low cost, has been widely used for land each The foundation construction of engineering is planted, is also progressively applied in the port engineerings such as port and pier in recent years.At present, prestressed reinforced concrete Big Pipe Pile is at harbour Application in engineering is mainly used in the construction of long piled wharf, and reinforced concrete rectangle pile is substituted with Big Pipe Pile, and overall structure does not have essence change, high Stake wharf shore-connecting structure is long, invest big problem is not resolved.Big Pipe Pile is not yet applied to the engineering constructions such as cofferdam, breakwater.
The content of the invention
The present invention is a kind of new port structure, using prestressed reinforced concrete Big Pipe Pile anti-bending strength it is good the characteristics of, by Big Pipe Pile platoon cloth Put, stake interleaves reinforced concrete prefabricated board and cast-in-place concrete, or sets rock mound and inverted filter, prevent backfill from being spilt between being stitched from stake, make Earth-retaining, wave screening structure for port and pier, cofferdam, breakwater etc., at the same time as the shore approach structure of harbour, greatly reduce construction costs.
The technical solution adopted in the present invention is:Armored concrete Big Pipe Pile is prefabricated in the factory, and the straight stake of Big Pipe Pile is squeezed into design soil layer using pile driving barge, Piling is spaced during piling, beats in a row, while according to design requirement batter piling.Reinforced concrete prefabricated board is respectively inserted in both sides between Big Pipe Pile, in advance Making sheet top is coupled with reinforcing bar, cast-in-place concrete after borehole cleaning.The abundant area of stone material can be not inserted into reinforced concrete prefabricated board and pouring concrete, set Rock mound and inverted filter.In the top cast-in-situ steel reinforced concrete linking beam of stake, straight stake, taper pile, prefabricated board are coupled to form entirety, as earth-retaining, When unrestrained structure or wharf shore-connecting structure.Platoon stake rear backfill, forms land-based area.
The beneficial effects of the invention are as follows:
1st, armored concrete Big Pipe Pile can factorial praluction, construction investment is saved in job site without build concrete prefabricated factory again.
2nd, Big Pipe Pile construction technology is ripe, and equipment is simple, can be built without large-scale over-water construction equipment, and unit in charge of construction's input cost is low.
3rd, Big Pipe Pile platoon formula arrangement need not dredge, and be particularly suited for the thicker regional port engineering project of mud.
4th, Big Pipe Pile platoon formula arrangement may be designed as without jackstone structure, and concrete amount is few, be particularly suited for lacking sand material area harbour work Journey project.
5th, Big Pipe Pile platoon formula arrangement is used as deep water breakwater engineering, and structure section change is little, greatlys save investment.
6th, Big Pipe Pile platoon arrangement is simple, during especially as harbour, can not only be used for harbour soil-baffling structure, but also as wharf shore-connecting structure, Greatly reduce construction costs.
7th, Big Pipe Pile platoon arrangement reduces marine throwing sludge-polluted and sand material exploitation, reaches saving, the effect of environmental protection.
Brief description of the drawings
The present invention is further described with reference to the accompanying drawings and examples.
Fig. 1 is that dock structure Big Pipe Pile arranges horizontal layout schematic diagram.
Fig. 2 is platoon Big Pipe Pile dock structure sectional schematic diagram.
Fig. 3 is connection diagram between platoon stake.
Fig. 4 is platoon Big Pipe Pile cofferdam sectional schematic diagram.
Fig. 5 is platoon Big Pipe Pile independence breakwater sectional schematic diagram.
In figure:1st, the straight stake of prestressed reinforced concrete Big Pipe Pile platoon;2nd, prestressed reinforced concrete Big Pipe Pile taper pile;3rd, deformed bar is mixed The solidifying independent straight stake of soil Big Pipe Pile;4th, prefabricated reinforced concrete plate;5th, cast-in-place concrete;6th, mud face;7th, wharf apron line;8th, extra large side;9、 Land side;10th, cast-in-situ steel reinforced concrete linking beam;11st, reinforced concrete beams;12nd, Wharf Surface;13rd, bollard;14th, track girder;15、 Berthing member;16th, backfill;17th, wave wall;18th, rock mound;19th, two slabstone inverted filter;20th, rubble inverted filter;21st, the water surface; 22nd, supporting course;23rd, cast-in-situ steel reinforced concrete cushion cap.
Specific embodiment
Prestressed reinforced concrete Big Pipe Pile 1 is prefabricated in the factory, and the diameter of stake determines according to soil pressure, wave force and other power COMPREHENSIVE CALCULATINGs, if Meter should beMore than.Job site is transported to by ship after the completion of prefabricated, is driven piles by pile driving barge, the straight stake 1 of platoon stake will be adopted during injection Interval piling method piling is taken, to prevent influence of the soil compaction effect to driving piles.While injection Big Pipe Pile taper pile 2, the spacing distance of taper pile 2 is according to soil pressure Power and wave force calculation determine.Platoon stake 1, the driving depth of taper pile 2, according to born soil pressure, wave force, geological conditions and other The COMPREHENSIVE CALCULATINGs such as active force determine.As shown in Figure 1 and Figure 2.
Gap is about 30cm or so between platoon stake 1, and gap is comprehensively determined with geological condition, execution conditions etc., it is desirable to which gap reduces as far as possible. Gap between stake can be processed by two ways:
1. armored concrete plate 4 is inserted in both sides respectively between platoon stake 1, and insertion depth regards soil property, top filled slope and determines, after closure Leakage soil is not defined from below.Cast-in-place concrete 5 is blocked after borehole cleaning between plate 4.Platoon stake 1 can directly banket 16 below.Such as Fig. 1, Fig. 3 institute Show.
2. in the abundant area of stone material, can be in platoon stake rear throwing rock mound 18, block stone size determines according to gap between platoon stake 1, must not leak Stone.Rib body rear sets two slabstone inverted filters 19 and rubble inverted filter 20, the 16 leakages soil in case non-return bankets.As shown in Figure 4.
3. when platoon pilework is used as independent breakwater, according to institute's sheltered waters wave requirement, gap between stake can not also be dealt with.Such as Fig. 5 It is shown.
The top cast-in-situ steel reinforced concrete linking beam 10 of platoon stake 1, by platoon stake 1, cast-in-place concrete 5 between taper pile 2 and plate 4 and plate 4 Knot forms overall.
When platoon pilework is used as dock structure, in the independent straight stake 3 of the front arrangement of platoon stake 1 and backslash stake 2, and cushion cap 23 is set on top, held The top of platform 23 sets reinforced concrete beams 11 and cast-in-place concrete Wharf Surface 12 as load-carrying members, if berthing member 15, bollard 13 etc. are attached Category facility is used as by ship structure.Independent straight stake 3 sets track girder 14 with 1 top of platoon stake, and distance is general with door between independent straight stake 3 and platoon stake 1 And orbital distance is defined design.Can block behind gap directly backfill 16 after platoon stake 1, or do rock mound 18, two slabstone inverted filters 19, Backfill 16 again after rubble inverted filter 20.Platoon stake is 1 both as rear wharf portal crane track, the load-carrying members of top beam slab, and earth-retaining as harbour connects Bank structure, enormously simplify terminal designs section.As shown in Figure 1, Figure 2.
When platoon stake 1 is used as cofferdam structure, the direct backfill 16 behind the closure gap of 1 rear of platoon stake, or do rock mound 18, two slabstones Backfill 16 again after inverted filter 19, rubble inverted filter 20, platoon stake 1 is used as earth-retaining, wave screening structure;Taper pile 2 undertakes soil pressure and wave force Horizontal force.Such as Fig. 4.
When platoon stake 1 is used as independent breakwater structure, it is necessary to increase taper pile 2 in inner side.Gear wave effect is played in platoon stake 1, and both sides taper pile 2 holds Load wave horizontal force.Such as Fig. 5
The characteristics of port engineering platoon formula prestressed reinforced concrete Big Pipe Pile structure makes full use of prestressed reinforced concrete Big Pipe Pile anti-bending strength good, Pile tube is continuously arranged and taper pile is set and undertake horizontal force, as earth-retaining, wave screening structure, simple structure, easy construction is particularly suited for mud Thicker geology, or sand material lacks area, can greatly save construction costs.Total concrete amount is less, and sea can be reduced during construction Sludge-polluted and sand material exploitation are thrown, saving, the effect of environmental protection is reached.

Claims (8)

1. a kind of port engineering new construction, is mainly used in port and pier, cofferdam, breakwater engineering.DiameterAbove deformed bar Big Pipe Pile of Concrete (1) is prefabricated in the factory, and is transported to job site and plays straight stake (1) according to the method platoon of interval piling by pile driving barge, while injection Taper pile (2).Be coupled with cast-in-situ steel reinforced concrete linking beam (10) between platoon stake (1) and taper pile (2), formation integrally as soil-baffling structure or Wave screening structure.The prefabricated plate of slotting armored concrete (4) and cast-in-place concrete (5) are taken in gap between platoon stake (1), or set rock mound (18) and inverted filter (19), (20), prevent rear backfill (16) from being spilt between being stitched from stake.
2. in structure according to claim 1, it is characterised in that prestressed reinforced concrete Big Pipe Pile (1) wants platoon to arrange, is used to keep off Soil, gear wave and load-bearing, horizontal force is undertaken with taper pile (2).
3. in structure according to claim 1, it is characterised in that gap about 30cm or so between platoon stake (1), take slotting reinforcing bar to mix Solidifying native prefabricated plate (4) and cast-in-place concrete (5), or rock mound (18) and inverted filter (19), (20) are set, prevent rear backfill (16) spilt between being stitched from stake.
4. in structure according to claim 1, it is characterised in that use cast-in-place concrete linking beam between platoon stake (1) and taper pile (2) (10) it is coupled, forms overall, as earth-retaining or wave screening structure.
5. in structure according to claim 1, it is characterised in that when taking the prefabricated plate of slotting armored concrete (4) and cast-in-place concrete (5) Between closure platoon stake (1) during gap, after can direct backfill (16).
6. in structure according to claim 1, it is characterised in that when platoon pilework is used as dock structure, platoon stake (1) is both gear Soil structure, is again wharf shore-connecting structure, its front one row's high-pile beam formula structure of arrangement as harbour, front-seat independent stake (3) and platoon stake (1) Distance designed by standard of wharf portal crane track distance.
7. it is again gear in structure according to claim 1, it is characterised in that be both soil-baffling structure when platoon pilework is used as cofferdam Unrestrained structure.Platoon stake (1) crest level can be flushed with rear backfill ground, require to accomplish wave wall (17) height also dependent on gear wave, while can Wave wall (17) is not set.
8. in structure according to claim 1, it is characterised in that when platoon pilework is used as breakwater, should be in platoon stake (1) inner side Increase taper pile (2), to keep out wave force.Gap between platoon stake, requires according to sheltering condition, can block, and can not also block.
CN201510946377.0A 2015-12-09 2015-12-09 Port engineering platoon formula prestressed reinforced concrete Big Pipe Pile new construction Pending CN106854864A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510946377.0A CN106854864A (en) 2015-12-09 2015-12-09 Port engineering platoon formula prestressed reinforced concrete Big Pipe Pile new construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510946377.0A CN106854864A (en) 2015-12-09 2015-12-09 Port engineering platoon formula prestressed reinforced concrete Big Pipe Pile new construction

Publications (1)

Publication Number Publication Date
CN106854864A true CN106854864A (en) 2017-06-16

Family

ID=59125647

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510946377.0A Pending CN106854864A (en) 2015-12-09 2015-12-09 Port engineering platoon formula prestressed reinforced concrete Big Pipe Pile new construction

Country Status (1)

Country Link
CN (1) CN106854864A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110004873A (en) * 2019-03-27 2019-07-12 中交第三航务工程勘察设计院有限公司 Water conservancy diversion breakwater based on piling strtucture
CN113481932A (en) * 2021-07-20 2021-10-08 上海市政工程设计研究总院(集团)有限公司 High pile bearing platform type seawall

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BE1010514A4 (en) * 1992-12-18 1998-10-06 Herbosch Kiere N V Restoration and reinforcement of earth-retaining constructions
CN201883449U (en) * 2010-11-25 2011-06-29 中国京冶工程技术有限公司 Sea wall structure of compound pile
CN103215961A (en) * 2012-01-20 2013-07-24 陈东曙 Construction method of super large diameter tubular pile cofferdam
CN203834422U (en) * 2014-04-08 2014-09-17 天津港航工程有限公司 Novel high-pile wharf
CN105064271A (en) * 2015-09-08 2015-11-18 天津港第四港埠有限公司 Wharf transformation structure and wharf transformation construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BE1010514A4 (en) * 1992-12-18 1998-10-06 Herbosch Kiere N V Restoration and reinforcement of earth-retaining constructions
CN201883449U (en) * 2010-11-25 2011-06-29 中国京冶工程技术有限公司 Sea wall structure of compound pile
CN103215961A (en) * 2012-01-20 2013-07-24 陈东曙 Construction method of super large diameter tubular pile cofferdam
CN203834422U (en) * 2014-04-08 2014-09-17 天津港航工程有限公司 Novel high-pile wharf
CN105064271A (en) * 2015-09-08 2015-11-18 天津港第四港埠有限公司 Wharf transformation structure and wharf transformation construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110004873A (en) * 2019-03-27 2019-07-12 中交第三航务工程勘察设计院有限公司 Water conservancy diversion breakwater based on piling strtucture
CN113481932A (en) * 2021-07-20 2021-10-08 上海市政工程设计研究总院(集团)有限公司 High pile bearing platform type seawall

Similar Documents

Publication Publication Date Title
CN103321241B (en) Deep water open type combination foundation harbour and construction method thereof
CN102995602B (en) Silt coast sheep pile wharf structure and construction method
CN1837511A (en) Double-rowed cofferdam and method for manufacturing the same
CN109339065B (en) Method for deep water exposed bedrock close-packed pile supporting construction bearing platform
CN202925511U (en) Sheet-pile wharf structure for soft soil foundation
CN102864780A (en) Supporting structure and supporting method of foundation pit
CN203834422U (en) Novel high-pile wharf
CN103898868A (en) Novel high-pile wharf
CN204753262U (en) A fender structure on high embankment of existing railway
CN106854864A (en) Port engineering platoon formula prestressed reinforced concrete Big Pipe Pile new construction
CN108411934B (en) Floating tubular pile, dam retaining structure and construction method thereof
CN113047215B (en) High stake pier structure of medium plate stake
CN106149624A (en) A kind of gravity type quay being applicable to roadbed of alluvial silt and construction method thereof
CN211815989U (en) Over-current type permeable breakwater structure
CN113585168A (en) Sheet pile shore-connection type high-pile wharf structure suitable for deep peat soil soft foundation and construction method
CN105569055A (en) Structure for preventing mountain landslide
CN209958290U (en) Take shore protection structure of pile foundation
CN111663493A (en) Repairing and reinforcing method suitable for block wharf after foundation damage
CN208472649U (en) A kind of Gravity Type Casisson Berth structure setting friction pile in foundation
CN215629710U (en) Sheet pile shore-connection type high-pile wharf structure suitable for deep peat soil soft foundation
CN201713761U (en) Hollow and closed type steel caisson cofferdam
CN211228348U (en) Combined sheet pile structure with drainage channel
CN110397051A (en) A kind of cofferdam structure and construction method
CN215887944U (en) Island platform is built in advancing of deep water high flow velocity river course embankment
CN205421307U (en) Novel low stake bearing platform structure of empty formula type of falling pi is passed through in inland river

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170616

RJ01 Rejection of invention patent application after publication