Shaft tower rescue tool and method Download PDFInfo
- Publication number
- CN106823184A CN106823184A CN201710028745.2A CN201710028745A CN106823184A CN 106823184 A CN106823184 A CN 106823184A CN 201710028745 A CN201710028745 A CN 201710028745A CN 106823184 A CN106823184 A CN 106823184A
- Authority
- CN
- China
- Prior art keywords
- shaft tower
- personnel
- rescue
- lifting rope
- clasp
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- A—HUMAN NECESSITIES
- A62—LIFE-SAVING; FIRE-FIGHTING
- A62B—DEVICES, APPARATUS OR METHODS FOR LIFE-SAVING
- A62B35/00—Safety belts or body harnesses; Similar equipment for limiting displacement of the human body, especially in case of sudden changes of motion
- A62B35/0006—Harnesses; Accessories therefor
- A62B35/0025—Details and accessories
Abstract
The invention discloses a kind of shaft tower rescue tool and method, the shaft tower rescue tool includes fixing band, connection ring and lifting rope, one end of the fixing band is provided with the first clasp, the other end is provided with fixing port, the fixing band is set around on shaft tower and first clasp passes through the fixing port, the connection ring is removably detained on first clasp, and described lifting rope one end is used to be connected with personnel to be rescued, and the other end is used to be pulled by rescue personnel through the connection ring.Fixing band colligation of the present invention is fixed on shaft tower, for creating interim point of suspension, connection ring is clasped by the first clasp, the supporting body that connection ring is then slided as lifting rope, can ensure that the personnel to be rescued of lifting rope one end slowly decline under the control of the rescue personnel of the other end, so as to personnel to be rescued are transferred to Ground-Holding first aid.The invention provides a kind of simple and assembling efficiently rescue tool and rescue mode, can greatly shorten rescue time, improve electric shock first aid efficiency.
Description
Technical field
The present invention relates to electrician tool technical field, more particularly, to a kind of shaft tower rescue tool and method.
Background technology
In ultra-high-tension power transmission line maintenance repair operation, because human users are improper, equipment operation condition is not good, external environment condition
The reasons such as influence, easily cause operating personnel's electric shock injury accident.Get an electric shock and hang rescue means deficiency, electric shock people in existing high-altitude
Member's rescue time is universal more long, it is necessary to take hours, rescue difficulty is high, and the death rate is high.It occur frequently that because of rescue time
Electric shock personnel CPR or suspension cannot be carried out more long to be caused to be choked to death.
The content of the invention
Based on this, the invention reside in the defect for overcoming prior art, there is provided a kind of shaft tower rescue tool and method, for each
The aerial suspension Quick rescue under operating environment is planted, greatly shortens effective rescue time, improve electric shock first aid efficiency.
Its technical scheme is as follows:
A kind of shaft tower rescue tool, including fixing band, connection ring and lifting rope, one end of the fixing band are provided with the first button
Ring, the other end is provided with fixing port, and the fixing band is set around on shaft tower and first clasp passes through the fixing port, the company
Connect ring removably to detain on first clasp, described lifting rope one end is used to be connected with personnel to be rescued, and the other end passes through institute
Connection ring is stated for being pulled by rescue personnel.
Wherein in one embodiment, the connection ring includes the first ring body arranged up and down, the second ring body and is located at
Connecting portion between first ring body and second ring body, the lifting rope bypasses the connecting portion, and its two ends is towards same
One direction passes second ring body, and first ring body is fastened with first clasp.
Wherein in one embodiment, the lifting rope is included positioned at the first rope body in the left side of the connecting portion and positioned at institute
State connecting portion right side second rope body, it is described first rope body stretched out from the left of second ring body, it is described second rope body from
Stretched out on the right side of second ring body.
Wherein in one embodiment, the internal diameter of the internal diameter more than first ring body of second ring body.
Wherein in one embodiment, the lifting rope is provided with second fastened for the once safety band with personnel to be rescued and buckles
Ring.
Wherein in one embodiment, the material of the connection ring is that aluminium alloy is zinc-plated.
Wherein in one embodiment, the gravity that bears of the fixing band is more than or equal to 300kg.
Wherein in one embodiment, the lifting rope is climbing rope.
Wherein in one embodiment, also including the cutter of the secondary safety belt for cutting off personnel to be rescued.
The technical program additionally provides a kind of shaft tower rescue mode, comprises the following steps:
Lifting rope is sheathed in connection ring in advance;
Rescue personnel fastens the once safety band of itself, and carries shaft tower rescue tool and step on bar;
Rescue personnel completes inherently safe measure on shaft tower;
The good fixing band of rescue personnel's colligation on shaft tower so that the first clasp of fixing band is set down;
The connection ring of lifting rope will be connected with to be buckled on the first clasp;
One end of lifting rope is connected with the once safety band of personnel to be rescued, the other end is used to be pulled by rescue personnel;
Cut off the secondary safety belt of personnel to be rescued;
Rescue personnel slowly puts rope makes personnel to be rescued transfer to ground.
The advantage or principle to preceding solution are illustrated below:
Shaft tower rescue tool of the present invention and method, including fixing band, connection ring and lifting rope, first by fixing band colligation
It is fixed on shaft tower, for creating interim point of suspension, connection ring, connection ring is clasped by the first clasp in fixing band again afterwards
The supporting body for then being slided as lifting rope, it is ensured that the personnel to be rescued of lifting rope one end are slow under the control of the rescue personnel of the other end
Decline, so as to personnel to be rescued are transferred to Ground-Holding first aid.The invention provides a kind of simple and work is efficiently rescued in assembling
Tool and rescue mode, can greatly shorten rescue time, improve electric shock first aid efficiency, and it can be used under various operating environments
Aerial suspension Quick rescue, with preferable practicality and versatility.
Connection ring of the present invention is the word ring of class 8, and lifting rope may pass through the second ring body on the downside of connection ring again from the of upside
Under one ring body set, finally it is locked on connecting portion, can so increases the frictional force between lifting rope and connection ring, it is ensured that personnel to be rescued
Delay drop in the state of controllable.
The both sides of first rope body of the lifting rope both sides and the second rope body respectively from the second ring body are stretched out, and are used to ensure first
Rope body and the second rope body will not cross, it is ensured that personnel to be rescued can stablize and decline, and will not shake.
The internal diameter of second ring body is larger, prevents the first rope body and the second rope body phase mutual connection from touching wiping, and rope is put in influence.
The lifting rope is additionally provided with the second clasp, is used to realize the quick connection of lifting rope and personnel to be rescued.
The material of the connection ring is that aluminium alloy is zinc-plated, is used to the frictional force needed for improving slow drop.
The gravity that bears of the fixing band is more than 300kg, it is ensured that the intensity of fixing band, so as to ensure whole rescue tool peace
It is complete reliable.
The lifting rope is climbing rope, with larger stretching resistance, it is ensured that rescue tool is firm.
Brief description of the drawings
Fig. 1 is the operating diagram of the shaft tower rescue tool described in the embodiment of the present invention.
Description of reference numerals:
10th, shaft tower, 20, personnel to be rescued, 30, once safety band, 40, secondary safety belt, 100, fixing band, the 110, first button
Ring, 120, fixing port, 200, connection ring, the 210, first ring body, the 220, second ring body, 230, connecting portion, 300, lifting rope, 310,
One rope body, the 311, second clasp, the 320, second rope body.
Specific embodiment
To make the objects, technical solutions and advantages of the present invention become more apparent, below in conjunction with accompanying drawing and specific embodiment party
Formula, is described in further detail to the present invention.It should be appreciated that specific embodiment described herein is only used to solve
The present invention is released, protection scope of the present invention is not limited.
It should be noted that when element is referred to as " being located at " or " being fixed on " another element, it can be directly arranged in
Or be fixed on another element or can also be located at by element placed in the middle or be fixed on another element.When an element
It is known as " connection " another element, it can be directly to another element or can also be by unit placed in the middle
Part and be connected to another element.
Additionally, unless otherwise indicated, the description such as term " first " and " second " otherwise in specification is used only for distinguishing
Each component, element, step in specification etc., without being intended to indicate that each component, the logical relation between element, step
Or ordinal relation etc..
As shown in figure 1, shaft tower rescue tool of the present invention, including fixing band 100, connection ring 200 and lifting rope 300.
One end of the fixing band 100 is provided with the first clasp 110, and the other end is provided with fixing port 120, and the fixing band 100 is set around bar
On tower 10 and first clasp 110 pass through the fixing port 120, now fixing band 100 should be connected with the first clasp 110
One end tense and by the other end of fixing band 100 towards shaft tower 10 a side compression so that fixing band 100 is firmly fixed at
On shaft tower 10.Specifically, the fixing band 100 can be double seal formula annulus, and one end is sewed with first clasp 110, the
One clasp 110 is passed through from the inner side of the other end of closed annulus, and the inner side of the other end of the closed annulus is described solid
Determine mouth 120;Or the fixing band 100 is single belt, one end is sewed with first clasp 100, and the other end sutures and to form one and consolidate
Fixed circle, the inner side of the retainer plate is then fixing port 120.The connection ring 200 is removably detained located at first clasp 110
On.The one end of the lifting rope 300 is used to be connected with the once safety band 30 of personnel to be rescued 20 (electric shock stupor person etc.), and the other end is bypassed
The connection ring 200 is used to pull slow drop by rescue personnel's (accompanying drawing is not shown).It should be noted that once pacifying described in this area
Complete is to tie up the safety belt with staff with 30, and secondary safety belt 40 is then connection peace of the once safety with 30 and shaft tower 10
Full band.
The operation principle of the shaft tower rescue tool is as follows:First the colligation of fixing band 100 is fixed on shaft tower 10, for creating
Make interim point of suspension;Connection ring 200, the then conduct of connection ring 200 are clasped by the first clasp 110 in fixing band 100 again afterwards
The supporting body that lifting rope 300 is slided, it is ensured that the personnel to be rescued of the one end of lifting rope 300 are under slow under the rescue personnel of the other end controls
Drop, so as to personnel to be rescued 20 are transferred to Ground-Holding first aid.The invention provides a kind of simple and work is efficiently rescued in assembling
Tool, can greatly shorten rescue time, improve electric shock first aid efficiency, and the aerial suspension that it can be used under various operating environments is fast
Speed rescue, with preferable practicality and versatility.
In the present embodiment, the connection ring 200 includes the first ring body 210, the second ring body 220 and the position arranged up and down
Connecting portion 230 between first ring body 210 and second ring body 220.The individual pen of the lifting rope 300 is set around the company
In socket part 230, and its two ends is passed through in second ring body 220 in the same direction, as can be from second ring body 220
Front side is worn to rear side, or is worn to front side from rear side.First ring body 210 is then fastened with first clasp 110.Can from above
Know, connection ring of the present invention 200 is the word ring of class 8, lifting rope 300 may pass through the second ring body 220 of the downside of connection ring 200 again from upper
Under 210 sets of first ring body of side, finally it is locked on connecting portion 230, can so increases between lifting rope 300 and connection ring 200
Frictional force, it is ensured that personnel to be rescued 20 delay drop in the state of controllable.
Preferably, the lifting rope 300 is included positioned at the first rope body 310 in the left side of the connecting portion 230 and positioned at described
The second rope body 320 on the right side of connecting portion 230 is (also including relative with connecting portion 230 the 3rd rope on connecting portion 230
Body).The first rope body 310 stretches out from the left side of second ring body 220, and the second rope body 320 is from second ring body
220 right side is stretched out.It follows that both sides of the lifting rope 300 of both sides respectively from the second ring body 220 are stretched out, it is used to ensure first
The rope rope body 320 of body 310 and second will not cross, it is ensured that personnel to be rescued can stablize and decline, and will not shake.Need explanation
, term as used herein " on ", D score "front", "rear", "left", "right" and similar statement simply to illustrate that
Purpose, it is unique implementation method to be not offered as.
In the present embodiment, the internal diameter of second ring body 220 prevents first more than the internal diameter of first ring body 210
Rope body 310 and second rope body 320 puts rope in the interior friction that contacts with each other of the second ring body 220, influence.It should be noted that described
The internal diameter of two ring bodies 220 also may be less than or equal to the internal diameter of first ring body 210.
Preferably, the lifting rope 300 is provided with for the once safety with personnel to be rescued 20 with 30 the second clasps for fastening
311, it is used to realize the once safety of lifting rope 300 and personnel to be rescued 20 with 30 quick connection.The present invention is also dependent on actual need
The 3rd clasp (accompanying drawing is not shown) to be fastened with the once safety band of rescue personnel in the setting of the other end of the lifting rope 300,
Now, rescue personnel can pull any position on the second rope body 320.
Present invention additionally comprises the cutter of the secondary safety belt 40 for cutting off personnel to be rescued 20, in lifting rope 300 and people to be rescued
After the once safety band 30 of member 20 is connected, the secondary safety belt 40 on personnel to be rescued 20 can be cut off by cutter so that
Personnel to be rescued 20 depart from the constraint of shaft tower 10.
In the present embodiment, the fixing band 100 is the rope made of hemp or other similar materials, 90~150cm of length, preferably with it is outstanding
The girth for hanging position matches;Its load-bearing is not less than 300kg, it is ensured that the intensity of fixing band 100, so as to ensure whole rescue tool
It is safe and reliable.The material of the connection ring 200 is used to the friction needed for improving slow drop for aluminium alloy is zinc-plated or other metal materials
Power.The lifting rope 300 is climbing rope, and with larger stretching resistance, it is ensured that rescue tool is solid and reliable, the present invention is also dependent on reality
Border is needed using the rope made of hemp as lifting rope 300.The cutter can be common electrician's knife.
Present invention also offers a kind of shaft tower rescue mode, comprise the following steps:
Step one, lifting rope 300 is sheathed in connection ring 200 in advance;
Step 2, rescue personnel fasten the once safety band of itself, and carry shaft tower rescue tool and step on bar;
Step 3, rescue personnel complete inherently safe measure on shaft tower 10, and secondary safety is such as fixed on shaft tower 10
Band;
The good fixing band 100 of step 4, the rescue personnel colligation on shaft tower 10, fixing band 100 need to be fixedly secured in shaft tower 10
On, the first clasp 110 of fixing band 100 should be set down;
Step 5, the connection ring 200 of lifting rope 300 will be connected with it has been buckled in the first clasp 110;
Step 6, the once safety band 30 of one end of lifting rope 300 and personnel to be rescued 20 be connected, the other end is wound on rescues people
Member on hand be used for pull, rescue personnel can use around elbow method that lifting rope 300 is pre-fixed;
Step 7, the secondary safety belt 40 of personnel to be rescued 20 is cut off using cutter;
Step 8, rescue personnel slowly put rope makes personnel to be rescued 20 transfer to ground.
The emergency relief measure such as CPR can be carried out putting to ground wait the personnel that rescue 20.It should be noted that this hair
The bright sequencing to above-mentioned steps one to step 8 is not limited, and those skilled in the art can according to actual needs to corresponding
Priority execution sequence is adjusted, and is used to reduce rescue time, realizes most fast rescue.
In sum, the invention provides a kind of simple and assembling efficiently rescue tool and rescue mode, can be significantly
Ground shortens rescue time (shaft tower electric shock suspension Quick rescue can be completed in 5 minutes), improves electric shock first aid efficiency, Neng Gouji
The big death by suffocation probability for reducing high-altitude electric shock suspension personnel;Its aerial suspension that can be used under various operating environments is quickly rescued
Help, such as can be used to fault rod climbing tower personnel rescuing, electric operating personnel and step on uncomfortable slow drop after bar, high altitude firefighting succouring
In the case of various scenes such as landing, with preferable versatility and practicality;Additionally, its simple structure, lighter in weight, it is easy to
Bar is stepped in carrying, and its operation is also easy, one man relief is capable of achieving, with preferable promotion prospect.
Each technical characteristic of embodiment described above can be combined arbitrarily, to make description succinct, not to above-mentioned reality
Apply all possible combination of each technical characteristic in example to be all described, as long as however, the combination of these technical characteristics is not deposited
In contradiction, the scope of this specification record is all considered to be.
Embodiment described above only expresses several embodiments of the invention, and its description is more specific and detailed, but simultaneously
Can not therefore be construed as limiting the scope of the patent.It should be pointed out that coming for one of ordinary skill in the art
Say, without departing from the inventive concept of the premise, can also make number deformation and improve, these belong to protection model of the invention
Enclose.
Claims (10)
1. a kind of shaft tower rescue tool, it is characterised in that including fixing band, connection ring and lifting rope, one end of the fixing band sets
There is the first clasp, the other end is provided with fixing port, and the fixing band is set around on shaft tower and first clasp passes through the fixation
Mouthful, the connection ring is removably detained on first clasp, and described lifting rope one end is used to be connected with personnel to be rescued, another
End is used to be pulled by rescue personnel through the connection ring.
2. shaft tower rescue tool according to claim 1, it is characterised in that the connection ring includes arrange up and down first
Ring body, the second ring body and the connecting portion between first ring body and second ring body, the lifting rope bypass described
Connecting portion, and its two ends passes second ring body in the same direction, first ring body is fastened with first clasp.
3. shaft tower rescue tool according to claim 2, it is characterised in that the lifting rope is included positioned at the connecting portion
The first rope body in left side and restricted body positioned at the second of the right side of the connecting portion, the first rope body is from a left side for second ring body
Side is stretched out, and the second rope body stretches out from the right side of second ring body.
4. shaft tower rescue tool according to claim 3, it is characterised in that the internal diameter of second ring body is more than described the
The internal diameter of one ring body.
5. shaft tower rescue tool according to claim 1, it is characterised in that the lifting rope is provided with for personnel's to be rescued
The second clasp that once safety band is fastened.
6. shaft tower rescue tool according to any one of claim 1 to 5, it is characterised in that the material of the connection ring
For aluminium alloy is zinc-plated.
7. shaft tower rescue tool according to any one of claim 1 to 5, it is characterised in that the fixing band is born
Gravity is more than or equal to 300kg.
8. shaft tower rescue tool according to any one of claim 1 to 5, it is characterised in that the lifting rope is climbing rope.
9. shaft tower rescue tool according to any one of claim 1 to 5, it is characterised in that also including treating for cutting off
Rescue the cutter of the secondary safety belt of personnel.
10. a kind of shaft tower rescue mode of the shaft tower rescue tool any one of use claim 1 to 9, its feature exists
In comprising the following steps:
Lifting rope is sheathed in connection ring in advance;
Rescue personnel fastens the once safety band of itself, and carries shaft tower rescue tool and step on bar;
Rescue personnel completes inherently safe measure on shaft tower;
The good fixing band of rescue personnel's colligation on shaft tower so that the first clasp of fixing band is set down;
The connection ring of lifting rope will be connected with to be buckled on the first clasp;
One end of lifting rope is connected with the once safety band of personnel to be rescued, the other end is used to be pulled by rescue personnel;
Cut off the secondary safety belt of personnel to be rescued;
Rescue personnel slowly puts rope makes personnel to be rescued transfer to ground.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710028745.2A CN106823184A (en) | 2017-01-16 | 2017-01-16 | Shaft tower rescue tool and method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710028745.2A CN106823184A (en) | 2017-01-16 | 2017-01-16 | Shaft tower rescue tool and method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106823184A true CN106823184A (en) | 2017-06-13 |
Family
ID=59124881
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710028745.2A Pending CN106823184A (en) | 2017-01-16 | 2017-01-16 | Shaft tower rescue tool and method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106823184A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107742851A (en) * | 2017-11-14 | 2018-02-27 | 国网四川省电力公司攀枝花供电公司 | A kind of disconnecting switch insulation operation platform |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10216253A (en) * | 1997-02-12 | 1998-08-18 | Nippon Retsuku Kk | Ropeway rescue device and its mounting method |
CN201404604Y (en) * | 2009-05-04 | 2010-02-17 | 河南省电力公司郑州供电公司 | High risk tower urgent repair staff protecting device |
CN203108018U (en) * | 2013-03-13 | 2013-08-07 | 深圳市锋瑞佳实业发展有限公司 | Overhead rope lifesaving escape device |
CN203507340U (en) * | 2013-10-10 | 2014-04-02 | 国家电网公司 | Gourd type high-altitude accident rescue equipment |
DE102013012968A1 (en) * | 2013-08-03 | 2015-02-05 | Sabine Dietberga Heide | Rescue point for portable fire ladder |
CN206483009U (en) * | 2017-01-16 | 2017-09-12 | 广州供电局有限公司 | Shaft tower rescue tool |
-
2017
- 2017-01-16 CN CN201710028745.2A patent/CN106823184A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10216253A (en) * | 1997-02-12 | 1998-08-18 | Nippon Retsuku Kk | Ropeway rescue device and its mounting method |
CN201404604Y (en) * | 2009-05-04 | 2010-02-17 | 河南省电力公司郑州供电公司 | High risk tower urgent repair staff protecting device |
CN203108018U (en) * | 2013-03-13 | 2013-08-07 | 深圳市锋瑞佳实业发展有限公司 | Overhead rope lifesaving escape device |
DE102013012968A1 (en) * | 2013-08-03 | 2015-02-05 | Sabine Dietberga Heide | Rescue point for portable fire ladder |
CN203507340U (en) * | 2013-10-10 | 2014-04-02 | 国家电网公司 | Gourd type high-altitude accident rescue equipment |
CN206483009U (en) * | 2017-01-16 | 2017-09-12 | 广州供电局有限公司 | Shaft tower rescue tool |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107742851A (en) * | 2017-11-14 | 2018-02-27 | 国网四川省电力公司攀枝花供电公司 | A kind of disconnecting switch insulation operation platform |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8430204B1 (en) | Rapid rescue apparatus | |
US4714135A (en) | Rappel rescue system | |
US6732834B2 (en) | Combination trucker's belt and extrication harness | |
US20170281989A1 (en) | FireCoat FEDS (Fullbody Emergency Descent System) | |
CN206483008U (en) | Integral type shaft tower rescue tool | |
US7025172B2 (en) | Fixed strand descending and lowering system | |
US9694220B2 (en) | Rescue strap | |
CN206483009U (en) | Shaft tower rescue tool | |
CN106823184A (en) | Shaft tower rescue tool and method | |
CN202179825U (en) | Climbing rope and climbing device | |
US10603528B1 (en) | Rapid extraction system | |
US11766265B1 (en) | Climbing harness with built-in tourniquet | |
CN203279856U (en) | Emergency rescue vest | |
CN210904709U (en) | Emergency escape self-rescue bag | |
CN201227476Y (en) | Safety band | |
CN207856108U (en) | A kind of construction and management safety belt | |
CN106564602B (en) | A kind of high building escape parachute | |
CN105344024A (en) | Hat-type low-altitude emergency escape parachute | |
CN204798669U (en) | Emergent lifesaving package | |
CN207323855U (en) | Building escape device fixed frame | |
CN106218898A (en) | Automatic inflation type low-altitude parachute | |
CN105857622A (en) | Parachute with descent control device | |
CN205287281U (en) | Emergent lifesaving umbrella in hat type low latitude | |
CN201299911Y (en) | Falling protection automatic-locking safety belt | |
CN205268851U (en) | High -altitude emergency escape device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20201009 Address after: 510620 Tianhe District, Guangzhou, Tianhe South Road, No. two, No. 2, No. Applicant after: Guangzhou Power Supply Bureau of Guangdong Power Grid Co.,Ltd. Address before: 510620 Tianhe District, Guangzhou, Tianhe South Road, No. two, No. 2, No. Applicant before: GUANGZHOU POWER SUPPLY Co.,Ltd. |
|
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170613 |