CN106815657B - Power distribution network double-layer planning method considering time sequence and reliability - Google Patents

Power distribution network double-layer planning method considering time sequence and reliability Download PDF

Info

Publication number
CN106815657B
CN106815657B CN201710006632.2A CN201710006632A CN106815657B CN 106815657 B CN106815657 B CN 106815657B CN 201710006632 A CN201710006632 A CN 201710006632A CN 106815657 B CN106815657 B CN 106815657B
Authority
CN
China
Prior art keywords
power
distribution network
constraint
power distribution
reliability
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710006632.2A
Other languages
Chinese (zh)
Other versions
CN106815657A (en
Inventor
郑洁云
张林垚
胡梦月
胡志坚
胡美玉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Economic and Technological Research Institute of State Grid Fujian Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Economic and Technological Research Institute of State Grid Fujian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Fujian Electric Power Co Ltd, Economic and Technological Research Institute of State Grid Fujian Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710006632.2A priority Critical patent/CN106815657B/en
Publication of CN106815657A publication Critical patent/CN106815657A/en
Application granted granted Critical
Publication of CN106815657B publication Critical patent/CN106815657B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply

Abstract

The invention relates to a power distribution network double-layer planning method considering time sequence and reliability. The method comprises the following steps: obtaining typical daily power time sequence curves of wind power, photovoltaic output and load in different seasons according to meteorological data and load power statistical data; establishing a power distribution network frame and distributed power supply capacity double-layer planning mathematical model based on an opportunity constraint planning method, wherein the mathematical model comprises a target function and constraint conditions; solving the model by utilizing a particle swarm optimization algorithm, and ensuring the radiation and connectivity structure of the power distribution network in the iterative process by utilizing a minimum spanning tree algorithm; and obtaining a Pareto optimal solution set of the target network frame and the capacity of the distributed power supply, and generating an optimal planning scheme. The method solves the problem of unnecessary construction investment of the power distribution network caused by the fact that the traditional power distribution network planning method containing the distributed power supply cannot reflect the typical output characteristics of the distributed new energy; (2) the power supply reliability of the power distribution network is brought into a model objective function, so that a certain reliability target is realized in a planning stage.

Description

Power distribution network double-layer planning method considering time sequence and reliability
Technical Field
The invention belongs to the technical field of power distribution network planning, and particularly relates to a power distribution network double-layer planning method considering time sequence and reliability.
Background
The increasing weight of Distributed Generation (DG) in the grid increases the uncertainty in the planning of the distribution network. Traditional power distribution network planning processes distributed power sources into fixed power sources, which obviously do not conform to the operating characteristics of the distributed power sources; or assuming that the wind power or photovoltaic output obeys certain distribution characteristics, then randomly sampling the DG by using a Monte Carlo sampling method and other sampling methods to simulate the output of the DG, but the variation of the DG output along with the power supply season and time period is not reflected, and the uncertainty of the load is usually ignored. In addition, a general power distribution network planning model usually takes economic indicators as a core, and people pay more and more attention to the reliability of a power distribution network along with the development of power technologies. To improve the reliability of the distribution network, consideration of achieving deterministic reliability goals in the planning phase is a recent technical challenge in planning.
The large-scale DG (particularly renewable energy power generation) is concentrated on a medium-voltage distribution network, so that the traditional passive unidirectional power supply distribution network is changed into a bidirectional multi-power supply distribution network, the traditional distribution network planning method cannot solve the technical problem caused by the change, and the active planning technology is developed. The double-layer planning method brings active planning into a lower-layer model, and is different from the traditional power distribution network planning method in that active management and planning on various controllable resources (such as distributed power supplies, transformer taps, reactive compensation equipment and the like) are considered more.
For solving problems of the planning model, most of common methods adopt an intelligent optimization algorithm to solve, but the intelligent algorithm has the defect that a plurality of infeasible solutions are easy to generate in the solving process. In order to ensure the connectivity and the radiancy of the power distribution network in the solving process, most methods carry out manual radiation type repair on the infeasible solutions generated in the calculating process, but the calculating process is complicated.
Disclosure of Invention
The invention aims to provide a power distribution network double-layer planning method considering time sequence and reliability, which solves the problem that the existing power distribution network planning method does not consider the time sequence of DGs and loads, realizes a certain reliability target in a planning stage, solves the problem of complex infeasible solution and repair in a model solving algorithm, improves the technical economy of a power distribution network planning scheme, and realizes a set power supply reliability target while realizing the optimal configuration of a distributed power supply.
In order to achieve the purpose, the technical scheme of the invention is as follows: a power distribution network double-layer planning method considering time sequence and reliability comprises the following steps,
s1, respectively establishing corresponding four-season typical time-series curve models for the wind power generation and photovoltaic power generation output and load power in the power distribution network;
s2, carrying out multi-scene chance constraint processing on the model in the step S1;
s3, establishing a power distribution network double-layer planning mathematical model considering time sequence and reliability, wherein the power distribution network double-layer planning mathematical model comprises a target function and a constraint condition;
and S4, solving the mathematical model in the step S3 by applying a particle swarm optimization algorithm, and ensuring the radiation and connectivity structure of the power distribution network in the iterative process by using a minimum spanning tree method.
In an embodiment of the present invention, the step S2 specifically includes: processing the time series curve data generated in the step S1, and taking the wind, the luminous output and the load power of each hour of each quarter as a scene, wherein the total number of the scenes is 96; carrying out load flow calculation under each scene, verifying whether a calculation result meets a constraint condition, counting the number of the scenes meeting the constraint condition, and dividing the number by the total number of the scenes to obtain the probability of meeting the constraint condition; if the probability reaches a preset value, the chance constraint condition is satisfied.
In an embodiment of the present invention, the mathematical model for double-layer planning of the power distribution network established in step S3 includes
1) Upper layer model
The objective function of the upper layer model is
Figure BDA0001203123640000021
In the formula: f. of1Expressed as an economic objective, where Cline、CDG、Cen、Closs、CuRespectively investment and operation and maintenance cost of a circuit, investment and operation and maintenance cost of a distributed power supply, power purchasing cost to an upper-level power grid, grid loss cost, environment-friendly and energy-saving benefits of renewable energy sources; f. of2Denotes the reliability target, λreliabilityRepresenting the power supply reliability of the power distribution network;
the constraint conditions of the upper layer model are as follows:
a. power balance constraint
Figure BDA0001203123640000022
In the formula: piInjecting power for the node i active power; qiReactive power injection for node i, j ∈ i is the set of all nodes directly connected to node i, UiNode/voltage amplitude; gijIs the real part of the nodal admittance matrix; b isijIs the imaginary part of the node admittance matrix; thetaijIs the voltage phase angle difference between nodes i and j;
b. probability constraint of upper and lower limits of node voltage
P{Umin≤U≤Umax}=ku/N≥βu(3)
In the formula: u shapemaxAnd UminThe upper limit and the lower limit of the node voltage are respectively; k is a radical ofuThe number of scenes satisfying the voltage upper and lower limit constraint in all scenes βuA confidence level for node voltage constraints;
c. branch power probability constraint
P{Pl≤Plmax}=kl/N≥βl(4)
In the formula: plIs the branch power; plmaxAn upper power limit allowed for the branch; k is a radical oflFor the number of scenarios satisfying the branch power constraint among all scenarios βlIs a confidence level of the branch power constraint;
d. inhibiting reverse power probabilistic constraints
P{PΣDG≤PΣL}=kB/N≥βB(5)
In the formula: pΣDGAnd PΣLRespectively representing DG total output and load active total demand; k is a radical ofBFor the number of scenarios satisfying the reverse power prohibition constraint among all scenarios βBA confidence level for disabling a reverse power constraint;
e. distributed power source installation capacity constraints
Figure BDA0001203123640000031
In the formula: pΣPVIs the PV total installation capacity; pΣWGWG total installed capacity; sigma is the maximum permeability of the DG as a renewable energy source; pΣLmaxThe sum of the maximum active load of the distribution network; pPVimaxThe maximum PV installation capacity of the grid-connected node i to be selected is obtained;
PWGimaxthe maximum WG installation capacity of the grid-connected node i to be selected is obtained;
2) lower model
The lower layer model objective function is that the expected value of DG annual active power removal is minimum, namely
Figure BDA0001203123640000032
In the formula: pcur,z-DGiThe active power removal amount of the ith DG under a scene z is obtained;
the lower layer model constraint conditions are as follows:
a. DG output resection constraint
Figure BDA0001203123640000033
In the formula:
Figure BDA0001203123640000041
and
Figure BDA0001203123640000042
respectively representing the lower limit and the upper limit of the ith DG output excision;
b. reactive compensation equipment switching amount constraint
Figure BDA0001203123640000043
In the formula: qCiRepresents the switching amount of the reactive compensation equipment at the ith DG installation node,
Figure BDA0001203123640000044
and
Figure BDA0001203123640000045
respectively representing the lower limit and the upper limit of the switching quantity of the reactive compensation equipment;
c. transformer tap adjustment range constraints
Figure BDA0001203123640000046
In the formula: t iskRepresents the switching amount of the reactive compensation equipment at the ith DG installation node,
Figure BDA0001203123640000047
and
Figure BDA0001203123640000048
respectively representing the lower and upper limits of the transformer tap adjustment range.
In an embodiment of the present invention, the step S4 of solving the mathematical model is as follows,
s41, initializing data; outputting original data of the power distribution network for planning, and setting parameter values;
s42, initializing a particle population; performing mixed coding according to the upgrading branch variable and the DG capacity variable, and randomly generating an initial population;
s43, obtaining an initial radial network topological structure by adopting a Kruskal algorithm;
s44, load flow calculation; calculating the power flow of the power distribution network by using MATPOWER according to the PV, WG and load power under each scene, and checking whether the constraint conditions of the formulas (2) to (4) are met; if the lower layer model meets the requirement, directly performing the next step, and if the lower layer model does not meet the requirement, starting the lower layer model;
s45, calculating a fitness value; calculating upper-layer objective function values of all individuals according to the load flow calculation result, and setting the fitness to be infinite for the individuals not meeting the probability constraint condition so as to eliminate the individuals in the iteration process; when calculating the power supply reliability of the power distribution network, firstly, carrying out breadth search on the network frame to find out a main feeder line and a branch feeder line, wherein the default longest generalized path is the main feeder line, and then, calculating according to the reliability calculation method in the step S43;
s46, selecting an individual optimal solution and a population optimal solution;
s47, constructing a Pareto optimal solution set of the population, calculating the crowdedness degree of individuals in the Pareto solution set, cutting, and storing the initial Pareto optimal solution set into a Pareto archive set;
s48, iteration, updating the dynamic weight and the learning factor of the particle, and updating the velocity and the position of the particle;
s49, revising the line parameters according to the updated particles, recalculating the branch weight, and obtaining a new network structure by using a minimum spanning tree algorithm; calculating the load flow, judging whether opportunity constraint conditions are met or not, starting a lower layer model if the opportunity constraint conditions are not met, calculating particle fitness values, and updating individual optimal solutions and population optimal solutions;
s410, storing the Pareto optimal solution set of the iterative population into a Pareto file set, processing the Pareto file set, deleting inferior solutions in the Pareto file set, calculating the crowding degree of individuals in the Pareto file set, and cutting the Pareto file set;
s411, judging whether an iteration termination condition is met, if so, outputting a Pareto archive set and ending, otherwise, repeating the steps S48 to S410 until an iteration termination standard is met;
and S42, sequencing the individuals on the Pareto frontier by utilizing an approximate ideal solution sequencing method, and selecting an optimal scheme.
Compared with the prior art, the invention has the following beneficial effects: the invention converts a complex power distribution system into a simple radial power distribution system by using an extent traversal algorithm, directly searches the position of a protection action by using a switch level matrix, analyzes the load fault type through a power accessibility result, calculates the reliability index, and can avoid repeatedly traversing the network topology, thereby greatly improving the efficiency of calculating the reliability of the power distribution network.
Drawings
FIG. 1 is a flow chart of the method of the present invention.
FIG. 2 is a flowchart illustrating the mathematical model solving process of step S4 according to the present invention.
FIG. 3 is an exemplary topology according to the present invention.
Detailed Description
The technical scheme of the invention is specifically explained below with reference to the accompanying drawings.
As shown in fig. 1, the method for planning a power distribution network in two layers in consideration of time sequence and reliability of the present invention includes the following steps,
s1, respectively establishing corresponding four-season typical time-series curve models for the wind power generation and photovoltaic power generation output and load power in the power distribution network;
s2, carrying out multi-scene chance constraint processing on the model in the step S1;
s3, establishing a power distribution network double-layer planning mathematical model considering time sequence and reliability, wherein the power distribution network double-layer planning mathematical model comprises a target function and a constraint condition;
and S4, solving the mathematical model in the step S3 by applying a particle swarm optimization algorithm, and ensuring the radiation and connectivity structure of the power distribution network in the iterative process by using a minimum spanning tree method.
The method described in step S2 is as follows:
the time series curve data generated in step S1 is processed, and the wind, the luminous output, and the load power for each hour of each quarter are treated as one scene for a total of 96 scenes. And performing load flow calculation in each scene, verifying whether the calculation result meets the constraint condition, counting the number of the scenes meeting the constraint condition, and dividing the number by the total number of the scenes to obtain the probability of meeting the constraint condition. If the probability reaches a predetermined value (e.g., 90%), the chance constraint is satisfied.
The power distribution network double-layer planning mathematical model established in the step S3 comprises
1) Upper layer model
The objective function of the upper model is that the decision variables are the line model to be upgraded, the line to be newly built and the installation capacity of the DG;
Figure BDA0001203123640000061
in the formula: f. of1Expressed as an economic objective, where Cline、CDG、Cen、Closs、CuRespectively investment and operation and maintenance cost of a circuit, investment and operation and maintenance cost of a distributed power supply, power purchasing cost to an upper-level power grid, grid loss cost, environment-friendly and energy-saving benefits of renewable energy sources; f. of2Denotes the reliability target, λreliabilityRepresenting the power supply reliability of the power distribution network;
in the formula (1) f1Including the following cost charges:
(1.1) investment and operation and maintenance costs of the line, the calculation formula is shown as formula (2) and formula (3), the line comprises an upgraded line and a newly-built line
Cline=CIline+COMline(2)
Figure BDA0001203123640000062
In the formula: cIlineThe equal annual value of investment is fixed for the line; cOMlineAnnual operating and maintenance costs for the line; omegaL1A set of newly-built lines is created; omegaL2Is a collection of upgrade lines; omegaLIs the set of all lines;
Figure BDA0001203123640000063
investment cost for newly building a line in unit length;
Figure BDA0001203123640000064
upgrading cost for upgrading the unit length of the line; l is the line length; r is the discount rate; n islineThe investment recovery period is fixed for the line; omegaLIs the set of all lines; gamma is the line maintenance costRate;
(1.2) investment and operation and maintenance costs of the distributed power supply, the calculation formula is shown as formula (4) and formula (5)
CDG=CIDG+COMDG(4)
Figure BDA0001203123640000065
In the formula, CIDGThe equal annual value of investment is fixed for renewable energy DG; cOMDGAnnual operating and maintenance costs for the renewable energy DG; cfPVInstallation cost per unit capacity of Photovoltaic (PV); omegapvCreating a new PV set; pPVjA PV mounting capacity; cfWGInstallation cost per unit capacity for wind power (WG); omegaWGCreating a WG set; pWGkInstalling capacity for WG; n isDGA fixed investment recovery period for DG; comPVTransportation and maintenance cost of PV unit electric quantity; comWGThe operating and maintenance cost of the WG unit electricity quantity. OmegazIs a collection of scenes; tau iszAccumulating the running time of the distribution network in the scene z; pz-PVjThe active output of the jth PV under the scene z is; pz-WGkThe active output of the kth WG in a scene z;
(1.3) cost of purchasing electricity to the upper-level power grid
Figure BDA0001203123640000071
In the formula: ceEnergy cost per unit of electricity; n is the total number of the distribution network load nodes; pz-LiThe active load power of the distribution network nodes under the scene z is obtained;
(1.4) loss on line cost
Figure BDA0001203123640000072
In the formula, △ Pz-iThe active power loss of the line i under the scene z;
(1.5) environmental protection and energy saving benefits of renewable energy
Expressed by government subsidies on renewable energy generation
Figure BDA0001203123640000073
In the formula: pz-DGiThe active output of the ith DG under the scene z;
in the formula (1) f2The calculation method of (2) is as follows:
f2middle lambdareliabilityI.e. the power supply reliability, the greater the power supply reliability for the distribution network, the better, here by f2Converting the power supply reliability index into a smaller and more optimal form, namely lambdareliabilityThe calculation procedure is as follows.
1. Inputting net rack topology parameters, fault rate, fault repair time, line length and load parameters;
2. establishing a feeder area by taking the switch element as a boundary;
3. enumerating faults in a feeder line area in sequence, and disconnecting an action breaker and an isolating switch;
4. from the DG access point, adopting the principle of near recovery, and searching the load capable of recovering power supply in a wide range;
5. and calculating a reliability index.
The constraint conditions of the upper layer model are as follows:
a. power balance constraint
Figure BDA0001203123640000081
In the formula: piInjecting power for the node i active power; qiReactive power injection for node i, j ∈ i is the set of all nodes directly connected to node i, UiNode/voltage amplitude; gijIs the real part of the nodal admittance matrix; b isijIs the imaginary part of the node admittance matrix; thetaijIs the voltage phase angle difference between nodes i and j;
b. probability constraint of upper and lower limits of node voltage
P{Umin≤U≤Umax}=ku/N≥βu(10)
In the formula: u shapemaxAnd UminThe upper limit and the lower limit of the node voltage are respectively; k is a radical ofuThe number of scenes satisfying the voltage upper and lower limit constraint in all scenes βuA confidence level for node voltage constraints;
c. branch power probability constraint
P{Pl≤Plmax}=kl/N≥βl(11)
In the formula: plIs the branch power; plmaxAn upper power limit allowed for the branch; k is a radical oflFor the number of scenarios satisfying the branch power constraint among all scenarios βlIs a confidence level of the branch power constraint;
d. inhibiting reverse power probabilistic constraints
P{PΣDG≤PΣL}=kB/N≥βB(12)
In the formula: pΣDGAnd PΣLRespectively representing DG total output and load active total demand; k is a radical ofBFor the number of scenarios satisfying the reverse power prohibition constraint among all scenarios βBA confidence level for disabling a reverse power constraint;
e. distributed power source installation capacity constraints
Figure BDA0001203123640000091
In the formula: pΣPVIs the PV total installation capacity; pΣWGWG total installed capacity; sigma is the maximum permeability of the DG as a renewable energy source; pΣLmaxThe sum of the maximum active load of the distribution network; pPVimaxThe maximum PV installation capacity of the grid-connected node i to be selected is obtained;
PWGimaxthe maximum WG installation capacity of the grid-connected node i to be selected is obtained;
2) lower model
The lower layer model objective function is that the expected value of DG annual active power removal is minimum, namely
Figure BDA0001203123640000092
In the formula: pcur,z-DGiThe active power removal amount of the ith DG under a scene z is obtained;
the lower layer model constraint conditions are as follows:
a. DG output resection constraint
Figure BDA0001203123640000093
In the formula:
Figure BDA0001203123640000094
and
Figure BDA0001203123640000095
respectively representing the lower limit and the upper limit of the ith DG output excision;
b. reactive compensation equipment switching amount constraint
Figure BDA0001203123640000096
In the formula: qCiRepresents the switching amount of the reactive compensation equipment at the ith DG installation node,
Figure BDA0001203123640000097
and
Figure BDA0001203123640000098
respectively representing the lower limit and the upper limit of the switching quantity of the reactive compensation equipment;
c. transformer tap adjustment range constraints
Figure BDA0001203123640000099
In the formula: t iskRepresents the switching amount of the reactive compensation equipment at the ith DG installation node,
Figure BDA00012031236400000910
and
Figure BDA00012031236400000911
respectively representing the lower and upper limits of the transformer tap adjustment range.
As shown in fig. 2, the mathematical model solving step of step S4 is as follows,
s41, initializing data; outputting original data of the power distribution network for planning, and setting parameter values;
s42, initializing a particle population; performing mixed coding according to the upgrading branch variable and the DG capacity variable, and randomly generating an initial population;
s43, obtaining an initial radial network topological structure by adopting a Kruskal algorithm;
s44, load flow calculation; calculating the power flow of the power distribution network by using MATPOWER according to the PV, WG and load power under each scene, and checking whether the constraint conditions of the formulas (2) to (4) are met; if the lower layer model meets the requirement, directly performing the next step, and if the lower layer model does not meet the requirement, starting the lower layer model;
s45, calculating a fitness value; calculating upper-layer objective function values of all individuals according to the load flow calculation result, and setting the fitness to be infinite for the individuals not meeting the probability constraint condition so as to eliminate the individuals in the iteration process; when calculating the power supply reliability of the power distribution network, firstly, carrying out breadth search on the network frame to find out a main feeder line and a branch feeder line, wherein the default longest generalized path is the main feeder line, and then, calculating according to the reliability calculation method in the step S43;
s46, selecting an individual optimal solution and a population optimal solution;
s47, constructing a Pareto optimal solution set of the population, calculating the crowdedness degree of individuals in the Pareto solution set, cutting, and storing the initial Pareto optimal solution set into a Pareto archive set;
s48, iteration, updating the dynamic weight and the learning factor of the particle, and updating the velocity and the position of the particle;
s49, revising the line parameters according to the updated particles, recalculating the branch weight, and obtaining a new network structure by using a minimum spanning tree algorithm; calculating the load flow, judging whether opportunity constraint conditions are met or not, starting a lower layer model if the opportunity constraint conditions are not met, calculating particle fitness values, and updating individual optimal solutions and population optimal solutions;
s410, storing the Pareto optimal solution set of the iterative population into a Pareto file set, processing the Pareto file set, deleting inferior solutions in the Pareto file set, calculating the crowding degree of individuals in the Pareto file set, and cutting the Pareto file set;
s411, judging whether an iteration termination condition is met, if so, outputting a Pareto archive set and ending, otherwise, repeating the steps S48 to S410 until an iteration termination standard is met;
and S42, sequencing the individuals on the Pareto frontier by utilizing an approximate ideal solution sequencing method, and selecting an optimal scheme.
The technical scheme of the invention is further explained by combining specific examples.
The method of the invention is applied to plan the line selection to be upgraded, the position of the newly-built line and the capacity of the distributed power supply for the power distribution network calculation example shown in figure 3. In fig. 3, the solid line is the established line and the line to be upgraded, the dotted line is the line to be newly established, the number represents the node number, and the number in the parenthesis represents the line number. Wherein 6 load nodes (nodes 34-39) are newly added, and 24 lines (branches 38-61) are to be newly built. The confidence level for all opportunity constraints is taken to be 90%. The installation reference capacity of the DGs is 100kW, and the maximum permeability is 50%. Table 1 shows the upper limit of the positions and the installation numbers of the nodes to be connected to the distributed power supply. The original line parameters are: the unit cost is 6 ten thousand yuan/km, the unit impedance is 0.85+ j0.42 omega/km, and the maximum current is 170A. The parameters of the upgrade line type 1 are: the unit cost is 8 ten thousand yuan/km, the unit impedance is 0.45+ j0.40 omega/km, and the maximum current is 380A. The parameters of upgrade line type 2 are: the unit cost is 10 ten thousand yuan/km, the unit impedance is 0.27+ j0.38 omega/km, and the maximum current is 275A. The line operation maintenance cost rate is 0.03, the fixed investment recovery period is 20 years, and the discount rate is 10%. The fixed investment recovery period of DG is 10 years, and the investment cost of unit electric quantity PV and WG is 0.8 and 0.6 ten thousand yuan/kW respectively; the operation and maintenance costs of the unit electric quantity PV and the unit electric quantity WG are 0.15 yuan/kW.h and 0.2 yuan/kW.h respectively; the energy cost per unit of electricity is 0.4 yuan/kW.h. To compare the timing of DG and load with the effect of random sampling on the planning, DG and load are set to obey the following distribution. WG: the shape parameter of Weibull distribution is 3.97, the scale parameter is 10.7, the cut-in wind speed is 3m/s, the rated wind speed is 14m/s, and the cut-off wind speed is 25 m/s; PV: beta has a shape parameter alpha of 2, Beta of 0.8 and a maximum illumination intensity of 600W/m 2; loading: obeying a normal distribution with a variance of 0.2Pload, expected to be Pload.
TABLE 1 upper limit of installation position and installation number of distributed power supplies
Figure BDA0001203123640000111
The planning scheme obtained by the method is marked as scheme 1; the time sequence is not considered, the DG and the load power are obtained by a random sampling method, and the obtained planning scheme is recorded as a scheme 2; regardless of reliability, the resulting planning scheme is denoted as scheme 3. The planning results are shown in table 2. Wherein, the numbers in brackets of the upgrade circuit and the model represent line types, and the numbers outside the number represent the circuit number; the newly-built line represents the serial number of the line to be newly built; the numbers in the brackets of the DG capacity indicate the node positions, and the numbers outside the brackets indicate the number of installations.
Table 2 plan scheme results comparison
Figure BDA0001203123640000112
As can be seen from table 2, the method adopted by the present invention ensures the reliability of the distribution network while reducing the planning economic cost, and although the scheme 3 reduces the economic cost, the reliability is also reduced.
The above are preferred embodiments of the present invention, and all changes made according to the technical scheme of the present invention that produce functional effects do not exceed the scope of the technical scheme of the present invention belong to the protection scope of the present invention.

Claims (3)

1. A power distribution network double-layer planning method considering time sequence and reliability is characterized in that: comprises the following steps of (a) carrying out,
s1, respectively establishing corresponding four-season typical time-series curve models for the wind power generation and photovoltaic power generation output and load power in the power distribution network;
s2, carrying out multi-scene chance constraint processing on the model in the step S1;
s3, establishing a power distribution network double-layer planning mathematical model considering time sequence and reliability, wherein the power distribution network double-layer planning mathematical model comprises a target function and a constraint condition;
s4, solving the mathematical model in the step S3 by applying a particle swarm optimization algorithm, and ensuring the radiation and connectivity structure of the power distribution network in the iterative process by using a minimum spanning tree method;
the power distribution network double-layer planning mathematical model established in the step S3 comprises
1) Upper layer model
The objective function of the upper layer model is
Figure FDA0002453036800000011
In the formula: f. of1Expressed as an economic objective, where Cline、CDG、Cen、Closs、CuRespectively investment and operation and maintenance cost of a circuit, investment and operation and maintenance cost of a distributed power supply, power purchasing cost to an upper-level power grid, grid loss cost, environment-friendly and energy-saving benefits of renewable energy sources; f. of2Denotes the reliability target, λreliabilityRepresenting the power supply reliability of the power distribution network;
the constraint conditions of the upper layer model are as follows:
a. power balance constraint
Figure FDA0002453036800000012
In the formula: piInjecting power for the node i active power; qiReactive power injection for node i, j ∈ i is the set of all nodes directly connected to node i, UiIs the voltage amplitude of node i, UjIs the voltage amplitude of node j; gijIs the real part of the nodal admittance matrix; b isijIs the imaginary part of the node admittance matrix; thetaijIs the voltage phase angle difference between nodes i and j;
b. probability constraint of upper and lower limits of node voltage
P{Umin≤U≤Umax}=ku/N≥βu(3)
In the formula: u shapemaxAnd UminThe upper limit and the lower limit of the node voltage are respectively; k is a radical ofuThe number of scenes satisfying the voltage upper and lower limit constraint in all scenes βuA confidence level for node voltage constraints; n is the total number of scenes;
c. branch power probability constraint
P{Pl≤Plmax}=kl/N≥βl(4)
In the formula: plIs the branch power; plmaxAn upper power limit allowed for the branch; k is a radical oflFor the number of scenarios satisfying the branch power constraint among all scenarios βlIs a confidence level of the branch power constraint;
d. inhibiting reverse power probabilistic constraints
P{PΣDG≤PΣL}=kB/N≥βB(5)
In the formula: pΣDGAnd PΣLRespectively representing DG total output and load active total demand; k is a radical ofBFor the number of scenarios satisfying the reverse power prohibition constraint among all scenarios βBA confidence level for disabling a reverse power constraint;
e. distributed power source installation capacity constraints
Figure FDA0002453036800000021
In the formula: pΣPVIs the PV total installation capacity; pΣWGWG total installed capacity; sigma is the maximum permeability of the DG as a renewable energy source; pΣLmaxThe sum of the maximum active load of the distribution network; pPVimaxThe maximum PV installation capacity of the grid-connected node i to be selected is obtained; pWGimaxThe maximum WG installation capacity of the grid-connected node i to be selected is obtained; wherein PV represents photovoltaic and WG represents wind power;
2) lower model
The lower layer model objective function is that the expected value of DG annual active power removal is minimum, namely
Figure FDA0002453036800000022
In the formula: f is the lower model objective function, τZCumulative running time of distribution network in scene zcur,z-DGiIs the active power removal amount, omega, of the ith DG under the scene zzFor the set of all scenes, ΩDGIs the set of all DGs;
the lower layer model constraint conditions are as follows:
a. DG output resection constraint
Figure FDA0002453036800000023
In the formula: pcur,z-DGiFor the amount of active power cut of the ith DG in scene z,
Figure FDA0002453036800000031
and
Figure FDA0002453036800000032
respectively representing the lower limit and the upper limit of the ith DG output excision;
b. reactive compensation equipment switching amount constraint
Figure FDA0002453036800000033
In the formula: qCiRepresents the switching amount of the reactive compensation equipment at the ith DG installation node,
Figure FDA0002453036800000034
and
Figure FDA0002453036800000035
respectively representing the lower limit and the upper limit of the switching quantity of the reactive compensation equipment;
c. transformer tap adjustment range constraints
Figure FDA0002453036800000036
In the formula: t iskRepresents the switching amount of the reactive compensation equipment at the ith DG installation node,
Figure FDA0002453036800000037
and
Figure FDA0002453036800000038
respectively representing the lower and upper limits of the transformer tap adjustment range.
2. The power distribution network double-layer planning method considering time sequence and reliability according to claim 1, characterized in that: the step S2 specifically includes: processing the time series curve data generated in the step S1, and taking the wind, the luminous output and the load power of each hour of each quarter as a scene, wherein the total number of the scenes is 96; carrying out load flow calculation under each scene, verifying whether a calculation result meets a constraint condition, counting the number of the scenes meeting the constraint condition, and dividing the number by the total number of the scenes to obtain the probability of meeting the constraint condition; if the probability reaches a preset value, the chance constraint condition is satisfied.
3. The power distribution network double-layer planning method considering time sequence and reliability according to claim 1, characterized in that: the step S4 solving the mathematical model is as follows,
s41, initializing data; outputting original data of the power distribution network for planning, and setting parameter values;
s42, initializing a particle population; performing mixed coding according to the upgrading branch variable and the DG capacity variable, and randomly generating an initial population;
s43, obtaining an initial radial network topological structure by adopting a Kruskal algorithm;
s44, load flow calculation; calculating the power flow of the power distribution network by using MATPOWER according to the PV, WG and load power under each scene, and checking whether the constraint conditions of the formulas (2) to (4) are met; if the lower layer model meets the requirement, directly performing the next step, and if the lower layer model does not meet the requirement, starting the lower layer model;
s45, calculating a fitness value; calculating upper-layer objective function values of all individuals according to the load flow calculation result, and setting the fitness to be infinite for the individuals not meeting the probability constraint condition so as to eliminate the individuals in the iteration process; when calculating the power supply reliability of the power distribution network, firstly, carrying out breadth search on the network frame to find out a main feeder line and a branch feeder line, wherein the default longest generalized path is the main feeder line, and then, calculating according to the reliability calculation method in the step S43;
s46, selecting an individual optimal solution and a population optimal solution;
s47, constructing a Pareto optimal solution set of the population, calculating the crowdedness degree of individuals in the Pareto solution set, cutting, and storing the initial Pareto optimal solution set into a Pareto archive set;
s48, iteration, updating the dynamic weight and the learning factor of the particle, and updating the velocity and the position of the particle;
s49, revising the line parameters according to the updated particles, recalculating the branch weight, and obtaining a new network structure by using a minimum spanning tree algorithm; calculating the load flow, judging whether opportunity constraint conditions are met or not, starting a lower layer model if the opportunity constraint conditions are not met, calculating particle fitness values, and updating individual optimal solutions and population optimal solutions;
s410, storing the Pareto optimal solution set of the iterative population into a Pareto file set, processing the Pareto file set, deleting inferior solutions in the Pareto file set, calculating the crowding degree of individuals in the Pareto file set, and cutting the Pareto file set;
s411, judging whether an iteration termination condition is met, if so, outputting a Pareto archive set and ending, otherwise, repeating the steps S48 to S410 until an iteration termination standard is met;
and S42, sequencing the individuals on the Pareto frontier by utilizing an approximate ideal solution sequencing method, and selecting an optimal scheme.
CN201710006632.2A 2017-01-05 2017-01-05 Power distribution network double-layer planning method considering time sequence and reliability Active CN106815657B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710006632.2A CN106815657B (en) 2017-01-05 2017-01-05 Power distribution network double-layer planning method considering time sequence and reliability

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710006632.2A CN106815657B (en) 2017-01-05 2017-01-05 Power distribution network double-layer planning method considering time sequence and reliability

Publications (2)

Publication Number Publication Date
CN106815657A CN106815657A (en) 2017-06-09
CN106815657B true CN106815657B (en) 2020-08-14

Family

ID=59109380

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710006632.2A Active CN106815657B (en) 2017-01-05 2017-01-05 Power distribution network double-layer planning method considering time sequence and reliability

Country Status (1)

Country Link
CN (1) CN106815657B (en)

Families Citing this family (68)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109119985A (en) * 2017-06-23 2019-01-01 南京理工大学 A kind of active distribution network energy source optimization configuration method
CN107316115A (en) * 2017-07-28 2017-11-03 国网山东省电力公司经济技术研究院 Rack planing method under distributed power source difference permeability
CN107506854B (en) * 2017-08-04 2021-04-20 国网浙江省电力公司经济技术研究院 220kV power grid structure planning method considering differentiation scene
CN107491845B (en) * 2017-08-28 2021-02-12 国网能源研究院有限公司 Accurate investment method for planning and constructing power grid
CN107342592B (en) * 2017-08-31 2022-05-13 国电南瑞科技股份有限公司 Safety and stability control method for emergency coordination of electric load balancing and rapid load shedding measures based on fault triggering
CN107679107B (en) * 2017-09-13 2020-10-27 全球能源互联网研究院有限公司 Graph database-based power grid equipment reachability query method and system
CN107591841B (en) * 2017-09-26 2019-11-22 清华大学 Power grid Evolution Simulation method under being accessed on a large scale suitable for new energy
CN107679658B (en) * 2017-09-28 2021-05-14 国网四川省电力公司经济技术研究院 Power transmission network planning method under high-proportion clean energy access
CN107834540B (en) * 2017-10-17 2021-04-16 国网宁夏电力公司固原供电公司 Method for determining distributed photovoltaic access capacity based on probability constraint
CN108563803A (en) * 2018-01-04 2018-09-21 国网能源研究院有限公司 Electric power pattern construction method towards connection to global networks
CN108470239B (en) * 2018-03-01 2020-09-04 国网福建省电力有限公司 Active power distribution network multi-target layered planning method considering demand side management and energy storage
CN108446796A (en) * 2018-03-01 2018-08-24 国网福建省电力有限公司 Consider net-source-lotus coordinated planning method of electric automobile load demand response
CN108539781B (en) * 2018-03-29 2020-03-10 国网江苏省电力有限公司电力科学研究院 Extended black start scheme two-layer planning optimization method for improving safety of recovery process
CN108446809B (en) * 2018-04-09 2020-12-25 国网河南省电力公司经济技术研究院 Regional comprehensive energy equipment and network double-layer optimization configuration method
CN108764519B (en) * 2018-04-11 2021-10-26 华南理工大学 Optimal configuration method for capacity of park energy Internet energy equipment
CN108599237A (en) * 2018-04-24 2018-09-28 南京理工大学 A kind of active distribution network dual layer resist DG Optimal Configuration Methods
CN108681823A (en) * 2018-05-23 2018-10-19 云南电网有限责任公司 A kind of power distribution network distributed generation resource planing method containing micro-capacitance sensor
CN109325608B (en) * 2018-06-01 2022-04-01 国网上海市电力公司 Distributed power supply optimal configuration method considering energy storage and considering photovoltaic randomness
CN108830479A (en) * 2018-06-12 2018-11-16 清华大学 It is a kind of meter and the full cost chain of power grid master match collaborative planning method
CN109190813B (en) * 2018-08-22 2022-05-24 华南理工大学 Shared bicycle region putting planning method based on double-layer planning
CN109242177B (en) * 2018-08-30 2021-07-23 国网江西省电力有限公司经济技术研究院 Active power distribution network planning method
CN109149635B (en) * 2018-09-03 2022-03-11 国网江西省电力有限公司电力科学研究院 Distributed photovoltaic parallel optimization configuration method and system for power distribution network
CN109002938B (en) * 2018-09-17 2021-06-01 东南大学 Double-layer planning method for alternating current-direct current hybrid power distribution network considering N-1 safety criterion
CN109829560B (en) * 2018-10-18 2023-07-18 天津大学 Renewable energy power generation cluster access planning method for power distribution network
CN109598377B (en) * 2018-11-28 2020-12-22 国网江苏省电力有限公司 AC/DC hybrid power distribution network robust planning method based on fault constraint
CN109670981B (en) * 2018-11-30 2022-12-13 国网江西省电力有限公司经济技术研究院 Active power distribution network planning method based on benefit balance and planning operation alternation optimization
US10880362B2 (en) 2018-12-03 2020-12-29 Intel Corporation Virtual electrical networks
CN109728602A (en) * 2018-12-21 2019-05-07 燕山大学 A kind of micro-capacitance sensor harmonic wave management method based on the distribution of multi-functional gird-connected inverter capacity
CN109726919B (en) * 2018-12-29 2021-04-09 华北电力大学 Power distribution network FTU optimal configuration method based on fault observability index
CN110210659B (en) * 2019-05-24 2021-04-02 清华大学 Power distribution network planning method considering reliability constraint
CN110110948B (en) * 2019-06-13 2023-01-20 广东电网有限责任公司 Multi-target distributed power supply optimal configuration method
CN110380408B (en) * 2019-07-08 2022-12-06 国网湖北省电力有限公司宜昌供电公司 Partition planning method for power distribution network with distributed power supplies
CN110570015B (en) * 2019-08-07 2022-07-26 广东电网有限责任公司 Multi-target planning method for power distribution network
CN110502814B (en) * 2019-08-09 2023-07-21 国家电网有限公司 Active power distribution network multi-target planning method considering energy storage and load management technology
CN110336298A (en) * 2019-08-17 2019-10-15 广东博慎智库能源科技发展有限公司 A kind of idle planing method of the distribution containing distributed generation resource based on integrated intelligent algorithm
CN110635478B (en) * 2019-10-23 2022-04-05 西南交通大学 Optimization method for power transmission network planning under new energy access based on single target
CN110826780B (en) * 2019-10-24 2022-06-17 华北电力大学 Injection upper limit optimization method and system during distributed power supply communication fault
CN111079972A (en) * 2019-11-04 2020-04-28 深圳供电局有限公司 Method, device and medium for planning reliability of active power distribution network
CN111144655A (en) * 2019-12-27 2020-05-12 国网河北省电力有限公司经济技术研究院 Combined optimization method for site selection, volume fixing and power distribution network frame of distributed power supply
CN111049151A (en) * 2020-01-03 2020-04-21 云南电网有限责任公司电力科学研究院 NSGA 2-based two-stage optimization algorithm for power distribution network voltage
CN111210068B (en) * 2020-01-03 2022-06-07 合肥工业大学 Power distribution network expansion double-layer planning method based on cluster division
CN111555266B (en) * 2020-04-09 2021-08-17 清华大学 Comprehensive planning method for distribution network automation system based on reliability constraint
CN111598399B (en) * 2020-04-17 2023-04-28 西安理工大学 Ultra-large-scale power transmission network expansion planning method based on distributed computing platform
CN111641205B (en) * 2020-05-11 2021-12-17 浙江工业大学 Active power distribution network fault management method based on random optimization
CN111652411B (en) * 2020-05-15 2022-07-15 三峡大学 Distributed power supply double-layer planning method
CN111682574B (en) * 2020-06-18 2021-10-15 国网江苏省电力有限公司电力科学研究院 Method for identifying running scene of alternating current-direct current hybrid system, storage medium and equipment
CN111724064B (en) * 2020-06-20 2023-01-10 国网福建省电力有限公司 Energy-storage-containing power distribution network planning method based on improved immune algorithm
CN111768033A (en) * 2020-06-28 2020-10-13 广东电网有限责任公司 Multi-target alternating current/direct current power distribution network planning method and device
CN112036611B (en) * 2020-08-12 2022-06-07 国网山东省电力公司经济技术研究院 Power grid optimization planning method considering risks
CN112103988B (en) * 2020-08-12 2022-06-14 南昌大学 Method for establishing cluster division double-layer model combined with network reconstruction
CN112132427B (en) * 2020-09-10 2022-11-22 国家电网有限公司 Power grid multi-layer planning method considering user side multiple resource access
CN112467722B (en) * 2020-09-30 2022-05-13 国网福建省电力有限公司 Active power distribution network source-network-load-storage coordination planning method considering electric vehicle charging station
CN112380694B (en) * 2020-11-13 2022-10-18 华北电力大学(保定) Power distribution network optimization planning method based on differential reliability requirements
CN112633699A (en) * 2020-12-24 2021-04-09 深圳供电局有限公司 Active power distribution network frame planning method and device, computer equipment and storage medium
CN112836957B (en) * 2021-01-29 2023-05-26 西安理工大学 Regional comprehensive energy system planning method considering power supply reliability
CN113162060B (en) * 2021-03-17 2022-10-04 武汉工程大学 Opportunity constraint optimization-based active power distribution network two-stage reactive power regulation method
CN112966959B (en) * 2021-03-23 2024-04-09 海南电网有限责任公司 Comprehensive evaluation method for grid structure of power distribution network considering load release
CN113224755B (en) * 2021-05-13 2022-06-14 中国电力科学研究院有限公司 Power grid static safety analysis method and system under electric vehicle fast charging load access
CN113268815B (en) * 2021-06-24 2023-04-07 南方电网科学研究院有限责任公司 Power distribution network double-layer planning method, device, equipment and storage medium
CN113780722B (en) * 2021-07-30 2022-12-16 广东电网有限责任公司广州供电局 Joint planning method and device for power distribution network, computer equipment and storage medium
CN113723807B (en) * 2021-08-30 2023-09-26 国网山东省电力公司经济技术研究院 Energy storage and information system double-layer collaborative planning method, device and medium
CN113762622B (en) * 2021-09-09 2023-09-19 国网上海市电力公司 Virtual power plant access point and capacity optimization planning method
CN114123294B (en) * 2021-10-22 2023-09-15 杭州电子科技大学 Multi-target photovoltaic single-phase grid-connected capacity planning method considering three-phase unbalance
CN114035434B (en) * 2021-11-22 2023-09-01 西南石油大学 Operation optimization method of gas-steam combined cycle power generation system
CN115147014A (en) * 2022-08-31 2022-10-04 国网浙江省电力有限公司宁波供电公司 Multi-target balanced distribution method of comprehensive energy system
CN116227232A (en) * 2023-04-28 2023-06-06 南方电网数字电网研究院有限公司 Multi-stage planning method and device for active power distribution network and computer equipment
CN116993032B (en) * 2023-09-28 2024-01-19 国网山西省电力公司运城供电公司 Distribution network planning method, distribution network planning device, storage medium and computer equipment
CN117526432A (en) * 2023-10-23 2024-02-06 杭州绿藤数智科技有限公司 Distribution network regulation and control system and method for source-load interaction

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101752903A (en) * 2009-11-27 2010-06-23 清华大学 Time sequence progressive power dispatching method
CN106230026A (en) * 2016-08-30 2016-12-14 华北电力大学(保定) The power distribution network bilayer coordinated planning method containing distributed power source analyzed based on temporal characteristics

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9571074B2 (en) * 2014-10-27 2017-02-14 Samsung Electronics Co., Ltd. Efficient skew scheduling methodology for performance and low power of a clock-mesh implementation

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101752903A (en) * 2009-11-27 2010-06-23 清华大学 Time sequence progressive power dispatching method
CN106230026A (en) * 2016-08-30 2016-12-14 华北电力大学(保定) The power distribution network bilayer coordinated planning method containing distributed power source analyzed based on temporal characteristics

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
考虑不同类型DG和负荷建模的主动配电网协同规划;高红均;刘俊勇;《中国电机工程学报》;20160920;第4911~4922页 *

Also Published As

Publication number Publication date
CN106815657A (en) 2017-06-09

Similar Documents

Publication Publication Date Title
CN106815657B (en) Power distribution network double-layer planning method considering time sequence and reliability
Hamida et al. Optimal network reconfiguration and renewable DG integration considering time sequence variation in load and DGs
CN108470239B (en) Active power distribution network multi-target layered planning method considering demand side management and energy storage
CN105449713B (en) Consider the intelligent Sofe Switch planing method of active power distribution network of distributed power source characteristic
Haesens et al. Optimal placement and sizing of distributed generator units using genetic optimization algorithms
Zhao et al. Service restoration for a renewable-powered microgrid in unscheduled island mode
Xie et al. Reliability-oriented networking planning for meshed VSC-HVDC grids
CN104751246A (en) Active distribution network planning method based on stochastic chance constraint
CN108304972B (en) Active power distribution network frame planning method based on supply and demand interaction and DG (distributed generation) operation characteristics
Zhao et al. Distributed risk-limiting load restoration for wind power penetrated bulk system
CN101539963A (en) Model conversion proposal from mechanical-electrical transient to electromagnetic transient and implementation method
CN109598377B (en) AC/DC hybrid power distribution network robust planning method based on fault constraint
Agajie et al. Optimal sizing and siting of distributed generators for minimization of power losses and voltage deviation
CN112561273B (en) Active power distribution network renewable DG planning method based on improved PSO
CN104866919A (en) Multi-target planning method for power grid of wind farms based on improved NSGA-II
CN115995790A (en) Power distribution network fault recovery method, system, equipment and medium
Tian et al. Optimal feeder reconfiguration and distributed generation placement for reliability improvement
CN108306334A (en) Idle work optimization strategy inside wind power plant based on particle swarm optimization algorithm
Shereen Optimal allocation of DG units for radial distribution systems using genetic algorithm
Belbachir et al. Multi-objective optimal renewable distributed generator integration in distribution systems using grasshopper optimization algorithm considering overcurrent relay indices
Ymeri et al. Optimal location and sizing of photovoltaic systems in order to reduce power losses and voltage drops in the distribution grid
CN109888817A (en) Position deployment and method for planning capacity are carried out to photovoltaic plant and data center
CN110135640B (en) Wind power distribution network optimal scheduling method based on fuzzy clustering improved harmony algorithm
Yu et al. Optimization of an offshore oilfield multi-platform interconnected power system structure
El-Werfelli et al. Backbone-network reconfiguration for power system restoration using genetic algorithm and expert system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant