CN106812545A - A kind of tunnel aseismatic joint water guide formula waterstop - Google Patents
A kind of tunnel aseismatic joint water guide formula waterstop Download PDFInfo
- Publication number
- CN106812545A CN106812545A CN201710128705.5A CN201710128705A CN106812545A CN 106812545 A CN106812545 A CN 106812545A CN 201710128705 A CN201710128705 A CN 201710128705A CN 106812545 A CN106812545 A CN 106812545A
- Authority
- CN
- China
- Prior art keywords
- groove
- waterstop
- deformation
- tunnel
- deformation groove
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title claims abstract description 34
- 239000011241 protective layer Substances 0.000 claims abstract description 26
- 238000004873 anchoring Methods 0.000 claims abstract description 12
- 238000000034 method Methods 0.000 claims description 8
- 230000008569 process Effects 0.000 claims description 2
- 230000001681 protective effect Effects 0.000 claims 1
- 230000000694 effects Effects 0.000 abstract description 8
- 238000006073 displacement reaction Methods 0.000 abstract description 3
- 230000008901 benefit Effects 0.000 abstract description 2
- 230000006378 damage Effects 0.000 abstract 2
- 239000004744 fabric Substances 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 7
- 230000006870 function Effects 0.000 description 4
- 238000007789 sealing Methods 0.000 description 4
- 230000008859 change Effects 0.000 description 2
- 230000008878 coupling Effects 0.000 description 2
- 238000010168 coupling process Methods 0.000 description 2
- 238000005859 coupling reaction Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 241000208340 Araliaceae Species 0.000 description 1
- 241000145637 Lepturus Species 0.000 description 1
- 241000406668 Loxodonta cyclotis Species 0.000 description 1
- 235000005035 Panax pseudoginseng ssp. pseudoginseng Nutrition 0.000 description 1
- 235000003140 Panax quinquefolius Nutrition 0.000 description 1
- 241001494479 Pecora Species 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 235000008434 ginseng Nutrition 0.000 description 1
- 230000008595 infiltration Effects 0.000 description 1
- 238000001764 infiltration Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000000750 progressive effect Effects 0.000 description 1
- 239000003566 sealing material Substances 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/38—Waterproofing; Heat insulating; Soundproofing; Electric insulating
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/38—Waterproofing; Heat insulating; Soundproofing; Electric insulating
- E21D11/385—Sealing means positioned between adjacent lining members
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
The invention provides a kind of tunnel aseismatic joint water guide formula waterstop, including anchoring section, deform groove, deform groove protective layer, earthquake protection groove, diversion seam;Wherein, anchoring section is located at the two ends of waterstop;Deformation groove is located at the middle part of waterstop;Deformation groove protective layer is located at the top of deformation groove;Earthquake protection groove is located at the middle part of deformation groove protective layer;Diversion seam is distributed in earthquake protection groove.When the present invention bears the small deformations such as the temperature deformation of tunnel-liner, uneven displacement, there is overall deformation, deformation groove protective layer can make deformation groove not filled by sandstone and reduce or lose deformation effect;When an earthquake occurs, earthquake protection groove fracture, obtains deformation groove and more obtains bigger deformation without destruction, it is ensured that the water-stagnating effect of waterstop;The design of diversion seam of the present invention allows tunnel periphery water smoothly to be derived from deformation groove, it is to avoid destruction of the hydraulic pressure high to waterstop, takes full advantage of the deformation groove of waterstop, improves the Fabric utilization of waterstop.
Description
Technical field
Stop water guide field, more particularly to a kind of tunnel aseismatic joint water guide formula the invention belongs to yielding regional tunnel aseismatic joint
Waterstop.
Background technology
Waterstop is one of sealing material that concrete seam is generally used in tunnel construction, mixed installed in tunnel double-lining
In the middle of solidifying soil, the thin tail sheep deformation of movement joint is adapted to without losing water stopping function.The reason for causing waterstop to fail at present,
One is that waterstop deformation is excessive, i.e. the displacement of movement joint has exceeded the deformation displacement of waterstop, and waterstop is drawn into bad;Two be with both
There is waterstop not possess good drain function, be easily caused and bear larger effect of water pressure, cause waterstop autoclasia or stop
Water band and tunnel lining concrete separation failure, cause waterstop to fail.
Current waterstop can bear the stretcher strain of below 3cm due to reasons in structure, when deformation is when big, waterstop
Deformed area rubber will be stretched thinning, while pulling force can be passed into anchorage zone rubber with deformed area, make anchorage zone rubber same
When tension-thining, make to produce gap between waterstop and concrete, the water of tunnel internal can bypass waterstop, tunnel along this gap
There is drainage, this is also one of the reason for waterstop fails.And existing drainage type waterstop, it is by waterstop deformed area
U-type groove is designed to, a gap of about 4mm wide is left in U-type groove, the presence in this gap can fall into the debris of tunnel internal
It is particularly evident when waterstop occurs stretcher strain inside water stop U type groove, after debris fall into U-type groove inside, when waterstop hair
During raw compression, debris can break waterstop, waterstop is lost sealing effect.
In earthquake intensity area high, due to earthquake reason, cause geology soft, because length of tunnel is very long, by this
The tunnel in area will have very big deformation., it is necessary to a plurality of width of segment design is up to 10cm's in tunnel total length during Tunnel Design
Aseismatic joint, causes the deformation in tunnel to be distributed in each aseismatic joint earthquake, for adapting to the deformation that earthquake is caused.Due to antidetonation
Seam width reaches 10cm, and existing waterstop is no longer applicable.
The content of the invention
The embodiment provides a kind of tunnel aseismatic joint water guide formula waterstop, be a kind of deflection up to 10cm without
Lose the product of water stopping function, according to aseismatic joint it is relatively wide the characteristics of, aseismatic joint water guide formula waterstop in tunnel also has prevents miscellaneous
Thing enters waterstop deformed area and water guide structure.
To achieve these goals, this invention takes following technical scheme:
A kind of tunnel aseismatic joint water guide formula waterstop, it is characterised in that including anchoring section, deformation groove, deformation groove protective layer,
Earthquake protection groove, diversion seam;Wherein:
The anchoring section is located at the two ends of waterstop, for waterstop to be fixedly connected with tunnel-liner, the deformation groove
The middle part deformed area of waterstop is built up in, waterstop is realized stretching or deformed by the deformation groove;The deformation groove protective layer
Positioned at the top of the deformation groove;The earthquake protection groove is arranged at the deformation groove protective layer centre position;The diversion seam
It is arranged in the earthquake protection groove.
The deformation groove is dovetail groove or V-groove.
When waterstop bears the small deformations such as temperature deformation, the differential settlement of tunnel-liner, the earthquake protection groove is not
It is broken, deforms with the deformation groove.
When waterstop bears the seismic deformation in tunnel, the earthquake protection groove is taken the lead in being broken by geological process power.
The diversion seam is intermittently-arranged along the length direction of the earthquake protection groove, and the diversion seam is through the whole change
Shape groove protective layer, tunnel periphery water is stitched by the diversion and flowed into the deformation groove, and the deformation groove is derived as guiding gutter
Water in groove.
The ragged edge size of the deformation groove is consistent with tunnel-liner aseismatic joint width dimensions.
The thickness setting number range of the deformation groove protective layer, the depth of the earthquake protection groove is the deformation groove guarantor
The 2/3 of covering thickness.
The diversion seam is to arrange 200mm every 1000mm along the intermittently-arranged size of earthquake protection groove.
The diversion seam seam is wide to be not more than 1mm.
The anchoring section is buried in being or back sticking type.
The technical scheme provided by embodiments of the invention described above can be seen that present invention reduces deformation groove protective layer pair
The effect of pullling at other positions of waterstop, preferably protects the water-stagnating effect of waterstop.Waterstop is make use of to greatest extent
Deformation groove, improve Water stop structure utilization rate.
The additional aspect of the present invention and advantage will be set forth in part in the description, and these will become from the following description
Obtain substantially, or recognized by practice of the invention.
Brief description of the drawings
Technical scheme in order to illustrate more clearly the embodiments of the present invention, below will be to that will use needed for embodiment description
Accompanying drawing be briefly described, it should be apparent that, drawings in the following description are only some embodiments of the present invention, for this
For the those of ordinary skill of field, without having to pay creative labor, other can also be obtained according to these accompanying drawings
Accompanying drawing.
Fig. 1 is a kind of dovetail groove section structure diagram of tunnel aseismatic joint water guide formula waterstop provided in an embodiment of the present invention
It is intended to;
Fig. 2 is a kind of V-groove section structure diagram of tunnel aseismatic joint water guide formula waterstop provided in an embodiment of the present invention
It is intended to;
Fig. 3 is that a kind of earthquake protection slot structure of tunnel aseismatic joint water guide formula waterstop provided in an embodiment of the present invention is illustrated
Figure;
Fig. 4 is a kind of diversion crack structure schematic diagram of tunnel aseismatic joint water guide formula waterstop provided in an embodiment of the present invention.
【Reference】
The earthquake protection groove 3 of the deformation deformation groove of groove 1 protective layer 2
4 anchoring sections 5 are stitched in diversion
Specific embodiment
Embodiments of the present invention are described below in detail, the example of the implementation method is shown in the drawings, wherein ad initio
Same or similar element or element with same or like function are represented to same or similar label eventually.Below by ginseng
The implementation method for examining Description of Drawings is exemplary, is only used for explaining the present invention, and is not construed as limiting the claims.
Those skilled in the art of the present technique are appreciated that unless expressly stated, singulative " " used herein, " one
It is individual ", " described " and " being somebody's turn to do " may also comprise plural form.It is to be further understood that what is used in specification of the invention arranges
Diction " including " refer to the presence of the feature, integer, step, operation, element and/or component, but it is not excluded that in the presence of or addition
One or more other features, integer, step, operation, element, component and/or their group.It should be understood that when we claim unit
Part is " connected " or during " coupled " to another element, and it can be directly connected or coupled to other elements, or can also exist
Intermediary element.Additionally, " connection " used herein or " coupling " can include wireless connection or coupling.Wording used herein
"and/or" includes one or more associated any cells for listing item and all combines.
Those skilled in the art of the present technique are appreciated that unless otherwise defined, all terms used herein (including technology art
Language and scientific terminology) have with art of the present invention in those of ordinary skill general understanding identical meaning.Should also
Understand, those terms defined in such as general dictionary should be understood that the meaning having with the context of prior art
The consistent meaning of justice, and unless defined as here, will not be with idealizing or excessively formal implication be explained.
For ease of the understanding to the embodiment of the present invention, done by taking several specific embodiments as an example further below in conjunction with accompanying drawing
Explanation, and each embodiment does not constitute the restriction to the embodiment of the present invention.
Fig. 1 is the dovetail groove section structure that waterstop is buried in a kind of tunnel aseismatic joint water guide formula provided in an embodiment of the present invention
Diagram is intended to, and Fig. 2 is a kind of V-groove section structure of tunnel aseismatic joint water guide formula back of the body patch waterstop provided in an embodiment of the present invention
Diagram is intended to, as shown in Figure 1 with Figure 2:
The waterstop deformed area includes anchoring section 5, deforms groove 1, deformation groove protective layer 2, earthquake protection groove 3;
Anchoring section 5 is located at the two ends of waterstop, for waterstop to be connected with tunnel-liner;Deformation groove 1 is built up in only
The middle part deformed area of water band, waterstop realizes stretching or deformation by deforming groove 1;Deformation groove protective layer 2 is located at the top of deformation groove 1
Portion;Waterstop can be prevented, and debris are fallen into 1 in deformation groove when mounted, are prevented debris influence waterstop deformation and failure waterstop and are showed
The appearance of elephant, earthquake protection groove 3 is located at deformation groove 1 protective layer centre position.
The deformation groove can be dovetail groove or V-groove;
The anchoring section 5 is buried in being or back sticking type, is embedded into concrete during installation, for by waterstop and tunnel
Lining cutting is fixedly connected.
Fig. 3 is that a kind of earthquake protection slot structure of tunnel aseismatic joint water guide formula waterstop provided in an embodiment of the present invention is illustrated
Figure, as shown in Figure 3:
Described earthquake protection groove 3, positioned at the centre position of deformation groove protective layer 2, when the temperature that waterstop bears tunnel becomes
During shape, the earthquake protection groove 3 is not broken, as the deformation groove 1 deforms together;When waterstop bears the earthquake in tunnel
During deformation, the earthquake protection groove 3 can occur rupture failure, so as to reduce the stress to other positions of waterstop, protect sealing
The sealing ability of band.
Fig. 4 is a kind of diversion crack structure schematic diagram of tunnel aseismatic joint water guide formula waterstop provided in an embodiment of the present invention.
As shown in Figure 4:
Waterstop deformed area also includes diversion seam 4, and described diversion seam 4 is located at 3 in earthquake protection groove, along earthquake protection groove
3 length directions are intermittently-arranged, and diversion seam 4 runs through whole deformation groove protective layer 2, and tunnel periphery water can be flowed into from diversion seam 4
1 in deformation groove, derived from deformation groove 1, at this moment deform groove 1 and also serve as guiding gutter and use.
Described deformation groove 1 provides stretching or detrusion ability for waterstop;
The deformation ragged edge size of groove 1 is consistent with aseismatic joint width dimensions, is easy to model sheetinstallat;
The deformation groove 1 will be processed into plane below, be easy to model sheetinstallat and pointing to install.
The deformation groove 1 protective layer thickness setting number range, its scope is generally:2-4mm;
The depth of the earthquake protection groove 3 is about the 2/3 of protective layer thickness;
The diversion seam 4 is to arrange 200mm every 1000mm along the intermittently-arranged size of earthquake protection groove 3;
The diversion seam seam 4 is wide to be not more than 1mm.
In sum, the embodiment of the present invention buries waterstop by tunnel aseismatic joint water guide formula, with it is existing in bury sealing
Band is compared, instant invention overcomes two weak links that it is present:One is the design of shockproof groove, when waterstop bears the temperature in tunnel
During degree deformation, shockproof groove is not broken, and deforms with deformation groove, deformation groove protective layer is protected deformation groove well;When
When waterstop bears the seismic deformation in tunnel, shockproof groove is broken, and reduces deformation groove protective layer to other positions of waterstop
The effect of pullling, preferably protect the water-stagnating effect of waterstop.Two is the design of diversion seam, and the presence of permeable joints makes outside tunnel
Enclosing water can smoothly be derived from deformation groove, and the deformation groove of waterstop is also make use of to greatest extent, improve waterstop knot
Structure utilization rate.Infiltration simultaneously is not more than 1mm, can effectively prevent debris from falling into waterstop deformation groove, preferably protects waterstop
Safety when using.
One of ordinary skill in the art will appreciate that:Accompanying drawing is the schematic diagram of one embodiment, module in accompanying drawing or
Flow is not necessarily implemented necessary to the present invention.
Each embodiment in this specification is described by the way of progressive, identical similar portion between each embodiment
Divide mutually referring to what each embodiment was stressed is the difference with other embodiment.Especially for device or
For system embodiment, because it is substantially similar to embodiment of the method, so describing fairly simple, related part is referring to method
The part explanation of embodiment.Apparatus and system embodiment described above is only schematical, wherein the conduct
Separating component explanation unit can be or may not be it is physically separate, the part shown as unit can be or
Person may not be physical location, you can with positioned at a place, or can also be distributed on multiple NEs.Can be with root
Some or all of module therein is factually selected the need for border to realize the purpose of this embodiment scheme.Ordinary skill
Personnel are without creative efforts, you can to understand and implement.
The above, the only present invention preferably specific embodiment, but protection scope of the present invention is not limited thereto,
Any one skilled in the art the invention discloses technical scope in, the change or replacement that can be readily occurred in,
Should all be included within the scope of the present invention.Therefore, protection scope of the present invention should be with scope of the claims
It is defined.
Claims (10)
1. a kind of tunnel aseismatic joint water guide formula waterstop, it is characterised in that including anchoring section, deformation groove, deformation groove protective layer,
Shake protective trough, diversion seam;Wherein:
The anchoring section is located at the two ends of waterstop, and for waterstop to be fixedly connected with tunnel-liner, the deformation groove is set up
In the middle part deformed area of waterstop, waterstop is realized stretching or is deformed by the deformation groove;The deformation groove protective layer is located at
The top of the deformation groove;The earthquake protection groove is arranged at the deformation groove protective layer centre position;The diversion is seamed puts
In in the earthquake protection groove.
2. waterstop according to claim 1, it is characterised in that the deformation groove is dovetail groove or V-groove.
3. waterstop according to claim 1, it is characterised in that when waterstop bears the temperature deformation, no of tunnel-liner
During the small deformations such as uniform settlement, the earthquake protection groove is not broken, and deforms with the deformation groove.
4. waterstop according to claim 1, it is characterised in that described when waterstop bears the seismic deformation in tunnel
Earthquake protection groove is taken the lead in being broken by geological process power.
5. waterstop according to claim 1, it is characterised in that the diversion seam along the earthquake protection groove length side
To intermittently-arranged, the diversion seam stitches inflow institute through the whole deformation groove protective layer, tunnel periphery water by the diversion
State in deformation groove, the deformation groove derives the water in groove as guiding gutter.
6. waterstop according to claim 1, it is characterised in that the ragged edge size of the deformation groove resists with tunnel-liner
Shake seam width dimensions are consistent.
7. waterstop according to claim 1, it is characterised in that the thickness setting numerical value model of the deformation groove protective layer
Enclose, the depth of the earthquake protection groove is the 2/3 of the deformation groove protective layer thickness.
8. waterstop according to claim 1, it is characterised in that the diversion seam is along the intermittently-arranged size of earthquake protection groove
It is to arrange 200mm every 1000mm.
9. waterstop according to claim 1, it is characterised in that the diversion seam seam is wide to be not more than 1mm.
10. waterstop according to claim 1, it is characterised in that the anchoring section is buried in being or back sticking type.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710128705.5A CN106812545A (en) | 2017-03-06 | 2017-03-06 | A kind of tunnel aseismatic joint water guide formula waterstop |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710128705.5A CN106812545A (en) | 2017-03-06 | 2017-03-06 | A kind of tunnel aseismatic joint water guide formula waterstop |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106812545A true CN106812545A (en) | 2017-06-09 |
Family
ID=59115123
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710128705.5A Pending CN106812545A (en) | 2017-03-06 | 2017-03-06 | A kind of tunnel aseismatic joint water guide formula waterstop |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106812545A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114016625A (en) * | 2021-11-08 | 2022-02-08 | 四川宏亿复合材料工程技术有限公司 | Buried type drainable composite water stopping assembly and use method thereof |
CN114352311A (en) * | 2021-11-26 | 2022-04-15 | 中铁二十五局集团第一工程有限公司 | Multi-section lining structure for tunnel to penetrate through movable fracture zone and construction method |
CN114352312A (en) * | 2021-11-26 | 2022-04-15 | 中铁二十五局集团第一工程有限公司 | Unequal-length self-adaptive multi-segment lining structure for tunnel crossing movable fracture zone |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201265162Y (en) * | 2008-09-25 | 2009-07-01 | 伍毅敏 | Back sticking type water stop capable of draining water |
JP4401249B2 (en) * | 2004-06-23 | 2010-01-20 | シバタ工業株式会社 | Impermeable structure for joints |
CN103590429A (en) * | 2013-12-03 | 2014-02-19 | 中铁二院工程集团有限责任公司 | Cast-in-place concrete structure deforming seam structure of underground engineering |
CN205035764U (en) * | 2015-09-29 | 2016-02-17 | 浙江水利水电学院 | Novel rubber waterstop |
CN106337690A (en) * | 2016-11-16 | 2017-01-18 | 中国科学院武汉岩土力学研究所 | Waterproof joint structure of tunnel lining in cross fault area and construction method thereof |
CN106437786A (en) * | 2016-10-21 | 2017-02-22 | 丰泽工程橡胶科技开发股份有限公司 | Water diversion type water-stop belt of tunnel 5 cm seismic joint |
-
2017
- 2017-03-06 CN CN201710128705.5A patent/CN106812545A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4401249B2 (en) * | 2004-06-23 | 2010-01-20 | シバタ工業株式会社 | Impermeable structure for joints |
CN201265162Y (en) * | 2008-09-25 | 2009-07-01 | 伍毅敏 | Back sticking type water stop capable of draining water |
CN103590429A (en) * | 2013-12-03 | 2014-02-19 | 中铁二院工程集团有限责任公司 | Cast-in-place concrete structure deforming seam structure of underground engineering |
CN205035764U (en) * | 2015-09-29 | 2016-02-17 | 浙江水利水电学院 | Novel rubber waterstop |
CN106437786A (en) * | 2016-10-21 | 2017-02-22 | 丰泽工程橡胶科技开发股份有限公司 | Water diversion type water-stop belt of tunnel 5 cm seismic joint |
CN106337690A (en) * | 2016-11-16 | 2017-01-18 | 中国科学院武汉岩土力学研究所 | Waterproof joint structure of tunnel lining in cross fault area and construction method thereof |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114016625A (en) * | 2021-11-08 | 2022-02-08 | 四川宏亿复合材料工程技术有限公司 | Buried type drainable composite water stopping assembly and use method thereof |
CN114352311A (en) * | 2021-11-26 | 2022-04-15 | 中铁二十五局集团第一工程有限公司 | Multi-section lining structure for tunnel to penetrate through movable fracture zone and construction method |
CN114352312A (en) * | 2021-11-26 | 2022-04-15 | 中铁二十五局集团第一工程有限公司 | Unequal-length self-adaptive multi-segment lining structure for tunnel crossing movable fracture zone |
CN114352312B (en) * | 2021-11-26 | 2024-07-30 | 中铁二十五局集团第一工程有限公司 | Unequal-length self-adaptive multi-section lining structure for tunnel crossing movable fracture zone |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106812545A (en) | A kind of tunnel aseismatic joint water guide formula waterstop | |
CN106337690B (en) | Fracture zone-crossing tunnel lining waterproof joint structure and construction method thereof | |
CN103195447B (en) | Construction method of quake-proof tunnel structure penetrating through flexible fracture zone | |
CN104863615B (en) | Across large-scale activity fracture belt tunnel Anti-seismic structure | |
CN109899086A (en) | A kind of tunnel is every shock absorption system | |
US20070231085A1 (en) | Grout pack restraining system | |
CN207177967U (en) | A kind of tunnel pressure release ejectment water installations | |
BR0318564B1 (en) | "DOUBLE TORTION WIRE PROTECTIVE SCREEN WITH HEXAGONAL MESHES AND PROTECTIVE STRUCTURE". | |
CN102409640A (en) | Passive-drainage emergency rescue method in case of earth-rock dam break | |
CN106437789A (en) | Tunnel lining waterproof joint | |
CN112746846B (en) | Non-settling coal mining method and device for mining and filling parallel with ground directional long drill hole | |
CN108691551A (en) | A kind of novel muzzle-loading normal pressure tool changing knife wound packages is set and its installation method | |
CN111608727A (en) | Cold region mountain tunnel composite drainage system and construction method thereof | |
CN106049550A (en) | Active and passive integrated water-stopping middle-buried type water-stopping strip structure for deformation joint | |
JP3619312B2 (en) | Seismic isolation structure of fill dam body | |
CN104775441A (en) | Interlocking type slope protecting block and method for carrying out slope protection by interlocking | |
CN107059669A (en) | Assembled Spatial Cable support flexible hangar tunnel | |
CN106437786A (en) | Water diversion type water-stop belt of tunnel 5 cm seismic joint | |
CN110468821A (en) | A kind of brush nettle-rope-type straw checkerboard barrier sand-protecting barrier and preparation method thereof | |
JP5921035B2 (en) | Earthquake response manhole protection method | |
CN210862412U (en) | Protection device suitable for high steep side slope goes out hole blasting | |
CN206092032U (en) | Tunnel 5cm seismic joint water guide wherein buries waterstop | |
KR101484005B1 (en) | Wirenet for being adhered on rock and connecting method thereof | |
CN207295623U (en) | A kind of staggered water conservancy slope protection net | |
CN209324370U (en) | A kind of support system excavated for tunnel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170609 |
|
RJ01 | Rejection of invention patent application after publication |