CN106790192A - Electric network data acquisition method and system based on mobile GIS - Google Patents

Electric network data acquisition method and system based on mobile GIS Download PDF

Info

Publication number
CN106790192A
CN106790192A CN201611262498.4A CN201611262498A CN106790192A CN 106790192 A CN106790192 A CN 106790192A CN 201611262498 A CN201611262498 A CN 201611262498A CN 106790192 A CN106790192 A CN 106790192A
Authority
CN
China
Prior art keywords
gis
data acquisition
mobile
electric network
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611262498.4A
Other languages
Chinese (zh)
Inventor
张广梅
朱皓
曾勇
贺彦
张小情
邓良平
崔久东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Power Grid Co Ltd
Original Assignee
Beijing Thp Technology Co ltd
Liupanshui Power Supply Bureau of Guizhou Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Thp Technology Co ltd, Liupanshui Power Supply Bureau of Guizhou Power Grid Co Ltd filed Critical Beijing Thp Technology Co ltd
Priority to CN201611262498.4A priority Critical patent/CN106790192A/en
Publication of CN106790192A publication Critical patent/CN106790192A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L67/00Network arrangements or protocols for supporting network services or applications
    • H04L67/01Protocols
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01SRADIO DIRECTION-FINDING; RADIO NAVIGATION; DETERMINING DISTANCE OR VELOCITY BY USE OF RADIO WAVES; LOCATING OR PRESENCE-DETECTING BY USE OF THE REFLECTION OR RERADIATION OF RADIO WAVES; ANALOGOUS ARRANGEMENTS USING OTHER WAVES
    • G01S19/00Satellite radio beacon positioning systems; Determining position, velocity or attitude using signals transmitted by such systems
    • G01S19/38Determining a navigation solution using signals transmitted by a satellite radio beacon positioning system
    • G01S19/39Determining a navigation solution using signals transmitted by a satellite radio beacon positioning system the satellite radio beacon positioning system transmitting time-stamped messages, e.g. GPS [Global Positioning System], GLONASS [Global Orbiting Navigation Satellite System] or GALILEO
    • G01S19/42Determining position
    • GPHYSICS
    • G08SIGNALLING
    • G08CTRANSMISSION SYSTEMS FOR MEASURED VALUES, CONTROL OR SIMILAR SIGNALS
    • G08C17/00Arrangements for transmitting signals characterised by the use of a wireless electrical link
    • G08C17/02Arrangements for transmitting signals characterised by the use of a wireless electrical link using a radio link

Abstract

The invention discloses a kind of electric network data acquisition method based on mobile GIS, the present invention is combined by by management change and technological means, complete the collection and typing of equipment alteration data at the scene using the mobile GIS based on panel computer by distribution operations staff, solve the problems, such as that the artwork of town and country system changes delayed scene, meeting distribution scheduling uninterruptedly carries out the demand of electrical network analysis and supervision application in circuit operation process, the present invention can lift electric network data accuracy, while promptness, reduce the secondary overlapping investment checked and bring, for follow-up system is integrated with automated system and merges and provides thinking and best practices, power-assisted is in the lifting of power grid enterprises' integrated management level.In addition, the invention also discloses a kind of electric network data acquisition system based on mobile GIS.

Description

Electric network data acquisition method and system based on mobile GIS
Technical field
The present invention relates to electric power data acquisition technical field, more particularly to a kind of electric network data collection based on mobile GIS Method and system.
Background technology
There is the field operations such as many power failure plans, equipment fault repairing in current power distribution network, but these are located The equipment running status of reason do not represent in power grid GIS so that dispatcher or field operator can not intuitively see The information such as the power transmission state of cable, trouble point of equipment in current electric grid, control centre can not see the reality of field operation Working condition, so as to cause the artwork data in scene and system inconsistent, many bases and advanced analysis function in system Cannot carry out, serious system for restricting it is practical.So the on-site data gathering based on mobile GIS has become the task of top priority, It is therefore desirable to be studied this, develop a kind of new electric network data acquisition method based on mobile GIS, by management and The means that technology is combined, solve accuracy and timely sex chromosome mosaicism that data update.
The content of the invention
In view of this, an object of the present invention is to provide a kind of electric network data acquisition method based on mobile GIS, can Ensure artwork, measure and live uniformity, promptness, both solve the practical bottleneck problem of system, and be follow-up Integrated, the fusion of system and automated system provide referential thinking;The second object of the present invention is to provide a kind of based on shifting The electric network data acquisition system of dynamic GIS.
An object of the present invention is achieved through the following technical solutions:
Electric network data acquisition method based on mobile GIS of the invention, comprises the following steps:
Step one:Integrated GIS platform is set, and the platform includes server host, GIS database subsystem and interface Subsystem;
Step 2:Some mobile GIS terminals are configured, are registered in integrated GIS platform by by mobile GIS terminal, Obtain GIS platform mandate;
Step 3:Engineering proposal power network number based on GIS platform is downloaded from integrated GIS platform by mobile GIS terminal According to mobile terminal, the method being combined by GPS location and map location carries out data acquisition, the device coordinate of line facility With the verification of connections mode;
Step 4:After data acquisition is finished, the data that will be collected imported into integrated GIS platform and are stored and managed Reason.
Especially, in step 3, packet bat is carried out across, attached, secondary, panorama etc. according to label, nameplate, friendship to equipment Take the photograph and manage.
Especially, in the step 3, the GIS mobile terminals are internally provided with mobile GIS data acquisition system, described Mobile GIS data acquisition system includes equipment icon and mark display module, equipment basic operation module, equipment and circuit modeling Module, grid equipment enquiry module, the taking pictures of equipment, line chart and circuit line chart check module, track record module, number According to upload download module, photo upload download module.
The second object of the present invention is achieved through the following technical solutions:
This kind is based on the electric network data acquisition system of mobile GIS, including
Integrated GIS platform, the platform includes server host, GIS database subsystem and interface subsystem;
Mobile GIS terminal, for being communicated wirelessly with integrated GIS platform, downloads from integrated GIS platform and is based on The engineering proposal electric network data of GIS platform, and gather the data of line facility and be transmitted back to integrated GIS platform.
Especially, the GIS mobile terminals are internally provided with mobile GIS data acquisition system, and the mobile GIS data is adopted Collecting system includes equipment icon and mark display module, equipment basic operation module, equipment and circuit MBM, grid equipment Enquiry module, the taking pictures of equipment, line chart and circuit line chart check that module, track record module, data are uploaded and download mould Block, photo upload download module.
Especially, the grid equipment enquiry module include power network resources inquiry submodule, buffering area inquiry submodule, GPS location submodule.
Especially, the mobile GIS terminal also includes off-line data interface, for the offline data for deriving collection.
The beneficial effects of the invention are as follows:
The present invention is combined by by management change and technological means, and the data after common equipment is gone into operation is transferred and typing Work moves forward to work progress and checks and accepts link, and the mobile GIS based on panel computer is used at the scene by distribution operations staff The collection and typing of equipment alteration data are completed, solves the problems, such as that the artwork of town and country system changes delayed scene, meet distribution tune Degree uninterruptedly carries out the demand of electrical network analysis and supervision application in circuit operation process, and it is accurate that the present invention can lift electric network data Property, promptness while, reduce it is secondary check the overlapping investment that brings, be that follow-up system is integrated with automated system Thinking and best practices are provided with fusion, power-assisted is in the lifting of power grid enterprises' integrated management level.
Other advantages of the invention, target and feature will be illustrated in the following description to a certain extent, and And to a certain extent, based on being will be apparent to those skilled in the art to investigating hereafter, Huo Zheke To be instructed from the practice of the present invention.Target of the invention and other advantages can be wanted by following specification and right Book is sought to realize and obtain.
Brief description of the drawings
In order that the object, technical solutions and advantages of the present invention are clearer, below in conjunction with accompanying drawing the present invention is made into The detailed description of one step, wherein:
Fig. 1 is flow chart of the method for the present invention;
Fig. 2 is system architecture schematic diagram of the invention;
Fig. 3 is the module composition figure of mobile GIS data acquisition system of the invention.
Specific embodiment
Hereinafter with reference to accompanying drawing, the preferred embodiments of the present invention are described in detail.It should be appreciated that preferred embodiment Only for the explanation present invention, rather than in order to limit the scope of the invention.
As shown in figure 1, the electric network data acquisition method based on mobile GIS of the invention, comprises the following steps:
Step one:Integrated GIS platform is set, and the platform includes server host, GIS database subsystem and interface Subsystem;
Step 2:Some mobile GIS terminals are configured, are registered in integrated GIS platform by by mobile GIS terminal, Obtain GIS platform mandate;
Step 3:Engineering proposal power network number based on GIS platform is downloaded from integrated GIS platform by mobile GIS terminal According to mobile terminal, the method being combined by GPS location and map location carries out data acquisition, the device coordinate of line facility With the verification of connections mode;In order to preferably be managed grid equipment and attached or secondary device, to equipment Carry out being grouped shooting and management across, attached, secondary, panorama etc. according to label, nameplate, friendship;
Step 4:After data acquisition is finished, the data that will be collected imported into integrated GIS platform and are stored and managed Reason, also including being derived off-line data by off-line data interface, so that data have more preferable security.
During integrated GIS platform is imported data to, it is related to the data of power network to be directed to integrated GIS platform The prerelease version of power network is set up, picture data is managed collectively (MongoDB study courses MongoDB in being then passed to MongoDB It is a database based on distributed document storage.Write by C Plus Plus, it is intended to for WEB application provides expansible property high Energy Data Storage Solution), the present invention is by setting up the prerelease version of power network artwork in integrated GIS platform (with operation Version isolation), the circuit transaction data of mobile GIS collection in worksite is imported, the artwork that existing electronization is transferred is safeguarded that link is carried Preceding to be gone into operation " before power transmission " to engineering, the version to be put into operation based on GIS sets up the quiet of "-line-change of standing " before circuit operation power transmission The measurement dynamic model of states model, distribution line and SCADA/TTU, automatically updates the Dispatching Drawings after putting into operation and computation model, Scheduling carries out advanced analysis when channel of command puts into operation using " red and black " two sets of figures and two sets of computation models for going into operation forward and backward, Realize the continual electrical network analysis of operation process and supervision application.
As shown in Fig. 2 the electric network data acquisition system based on mobile GIS of the invention, including integrated GIS platform, put down Platform includes server host, GIS database subsystem and interface subsystem;And
Mobile GIS terminal, for being communicated wirelessly with integrated GIS platform, downloads from integrated GIS platform and is based on The engineering proposal electric network data of GIS platform, and gather the data of line facility and be transmitted back to integrated GIS platform.
As shown in figure 3, GIS mobile terminals can realize the acquisition function of basic image, audio, video, inside also sets Be equipped with mobile GIS data acquisition system, the framework of mobile GIS data acquisition system include equipment icon and mark display module, Equipment basic operation module, equipment and circuit MBM, grid equipment enquiry module, the photo/line chart/circuit list of equipment Line chart checks module, track record module, data upload/download module, photo upload/download module, and each module can be real Existing corresponding various functions, wherein equipment basic operation module can realize the functions such as amplification, diminution, the translation of figure, power network Equipment query module includes power network resources inquiry submodule, buffering area inquiry submodule, GPS location submodule.
Mobile GIS terminal also includes off-line data interface, for the offline data for deriving collection.
The present invention is combined by by management change and technological means, and the data after common equipment is gone into operation is transferred and typing Work moves forward to work progress and checks and accepts link, and the mobile GIS based on panel computer is used at the scene by distribution operations staff The collection and typing of equipment alteration data are completed, solves the problems, such as that the artwork of town and country system changes delayed scene, meet distribution tune Degree uninterruptedly carries out the demand of electrical network analysis and supervision application in circuit operation process, and it is accurate that the present invention can lift electric network data Property, promptness while, reduce it is secondary check the overlapping investment that brings, be that follow-up system is integrated with automated system Thinking and best practices are provided with fusion, power-assisted is in the lifting of power grid enterprises' integrated management level.
Finally illustrate, the above embodiments are merely illustrative of the technical solutions of the present invention and it is unrestricted, although with reference to compared with Good embodiment has been described in detail to the present invention, it will be understood by those within the art that, can be to skill of the invention Art scheme is modified or equivalent, and without deviating from the objective and scope of the technical program, it all should cover in the present invention Right in the middle of.

Claims (8)

1. the electric network data acquisition method of mobile GIS is based on, it is characterised in that:The described method comprises the following steps:
Step one:Integrated GIS platform is set, and the platform includes server host, GIS database subsystem and interface subsystem System;
Step 2:Some mobile GIS terminals are configured, is registered in integrated GIS platform by by mobile GIS terminal, obtained GIS platform mandate;
Step 3:By mobile GIS terminal from integrated GIS platform download the engineering proposal electric network data based on GIS platform to Mobile terminal, the method being combined by GPS location and map location carries out data acquisition, device coordinate and the line of line facility The verification of the road mode of connection;
Step 4:After data acquisition is finished, the data that will be collected imported into integrated GIS platform and are stored and managed.
2. according to claim 1 based on the electric network data acquisition method for moving GIS, it is characterised in that:In step 3, Equipment is carried out being grouped shooting and management according to label, nameplate, friendship across, attached, secondary, panorama etc..
3. according to claim 1 based on the electric network data acquisition method for moving GIS, it is characterised in that:The step 3 In, the GIS mobile terminals are internally provided with mobile GIS data acquisition system, and the mobile GIS data acquisition system includes setting For icon and mark display module, equipment basic operation module, equipment and circuit MBM, grid equipment enquiry module, set It is standby take pictures, line chart and circuit line chart check that module, track record module, data upload download module, photo upload Download module.
4. according to claim 1 based on the electric network data acquisition method for moving GIS, it is characterised in that:In step 4, Also include deriving off-line data by off-line data interface.
5. the electric network data acquisition system of mobile GIS is based on, it is characterised in that:The system includes
Integrated GIS platform, the platform includes server host, GIS database subsystem and interface subsystem;
Mobile GIS terminal, for being communicated wirelessly with integrated GIS platform, downloads flat based on GIS from integrated GIS platform The engineering proposal electric network data of platform, and gather the data of line facility and be transmitted back to integrated GIS platform.
6. according to claim 5 based on the electric network data acquisition system for moving GIS, it is characterised in that:The GIS movements Terminal inner is provided with mobile GIS data acquisition system, and the mobile GIS data acquisition system includes that equipment icon and mark are aobvious Show module, equipment basic operation module, equipment and circuit MBM, grid equipment enquiry module, the taking pictures of equipment, line chart With circuit line chart check module, track record module, data upload download module, photo upload download module.
7. according to claim 6 based on the electric network data acquisition method and system that move GIS, it is characterised in that:It is described Grid equipment enquiry module includes power network resources inquiry submodule, buffering area inquiry submodule, GPS location submodule.
8. the electric network data acquisition method based on mobile GIS and system according to claim 5 or 6, it is characterised in that:Institute Stating mobile GIS terminal also includes off-line data interface, for the offline data for deriving collection.
CN201611262498.4A 2016-12-30 2016-12-30 Electric network data acquisition method and system based on mobile GIS Pending CN106790192A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611262498.4A CN106790192A (en) 2016-12-30 2016-12-30 Electric network data acquisition method and system based on mobile GIS

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611262498.4A CN106790192A (en) 2016-12-30 2016-12-30 Electric network data acquisition method and system based on mobile GIS

Publications (1)

Publication Number Publication Date
CN106790192A true CN106790192A (en) 2017-05-31

Family

ID=58953994

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611262498.4A Pending CN106790192A (en) 2016-12-30 2016-12-30 Electric network data acquisition method and system based on mobile GIS

Country Status (1)

Country Link
CN (1) CN106790192A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108647320A (en) * 2018-05-10 2018-10-12 国网冀北电力有限公司秦皇岛供电公司 Power distribution automation main station system based on GIS
CN113468387A (en) * 2021-06-30 2021-10-01 贵州电网有限责任公司 System and method for detecting validity of electric power field test data

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102375879A (en) * 2011-08-22 2012-03-14 河南理工大学 Mobile GIS (Geographic Information System) system based on intelligent mobile phone and application thereof
CN202353099U (en) * 2011-12-08 2012-07-25 重庆市电力公司检修分公司 Routing inspection and analysis integrated management system for ultra-high voltage/extra high voltage transmission line
EP2541717A2 (en) * 2011-06-30 2013-01-02 General Electric Company System and method for automated fault control and restoration of smart grids
CN103426280A (en) * 2013-07-24 2013-12-04 北京科东电力控制系统有限责任公司 Intelligent handheld terminal for electric power mobile operation
CN104850596A (en) * 2015-04-28 2015-08-19 国家电网公司 Distribution network data processing method based on mobile GIS (Geographic Information System) and RTK (Real Time Kinematic) positioning
CN105069051A (en) * 2015-07-24 2015-11-18 国家电网公司 Mobile GIS (Geographic Information System) assisted method for acquiring medium and low-voltage power grid resource data
CN106056272A (en) * 2016-05-18 2016-10-26 国网山东省电力公司经济技术研究院 Power grid programming, management and controlling method and system based on mobile GIS

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2541717A2 (en) * 2011-06-30 2013-01-02 General Electric Company System and method for automated fault control and restoration of smart grids
CN102375879A (en) * 2011-08-22 2012-03-14 河南理工大学 Mobile GIS (Geographic Information System) system based on intelligent mobile phone and application thereof
CN202353099U (en) * 2011-12-08 2012-07-25 重庆市电力公司检修分公司 Routing inspection and analysis integrated management system for ultra-high voltage/extra high voltage transmission line
CN103426280A (en) * 2013-07-24 2013-12-04 北京科东电力控制系统有限责任公司 Intelligent handheld terminal for electric power mobile operation
CN104850596A (en) * 2015-04-28 2015-08-19 国家电网公司 Distribution network data processing method based on mobile GIS (Geographic Information System) and RTK (Real Time Kinematic) positioning
CN105069051A (en) * 2015-07-24 2015-11-18 国家电网公司 Mobile GIS (Geographic Information System) assisted method for acquiring medium and low-voltage power grid resource data
CN106056272A (en) * 2016-05-18 2016-10-26 国网山东省电力公司经济技术研究院 Power grid programming, management and controlling method and system based on mobile GIS

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108647320A (en) * 2018-05-10 2018-10-12 国网冀北电力有限公司秦皇岛供电公司 Power distribution automation main station system based on GIS
CN113468387A (en) * 2021-06-30 2021-10-01 贵州电网有限责任公司 System and method for detecting validity of electric power field test data

Similar Documents

Publication Publication Date Title
CN106920049A (en) A kind of Project Management System platform based on BIM network technologies
CN106595565A (en) BIM-based intelligent monitoring system
CN108520567A (en) A kind of auxiliary method for inspecting identified by capture apparatus operation image
CN109471142B (en) Working track identification method based on RTK differential positioning
CN107516282A (en) Three look into the Land Change Survey information management system of unification
CN106066849B (en) A kind of template page editing system and method
CN103618382A (en) Transformer substation operation and maintenance integration field work data collection and field work instruction system
CN107610238B (en) AR dynamic model system of power equipment and working method thereof
CN111062504A (en) AR technology-based intelligent power distribution station operation and maintenance system and method
CN112272236A (en) Routing inspection system and method based on BIM
CN114077764A (en) Method for establishing temporary model based on three-dimensional GIS and BIM integration and application
CN116298701A (en) Power distribution network fault detection method and related device based on digital twin system
CN107368972A (en) It is a kind of that work platform and its application method are sent based on BIM technology
CN106790192A (en) Electric network data acquisition method and system based on mobile GIS
CN102495598B (en) System and method for monitoring battery charging and replacing station of electric vehicle based on virtual reality technology
CN112884164B (en) Federal machine learning migration method and system for intelligent mobile terminal
CN112907390A (en) Building full life cycle dynamic intelligent management system and method based on BIM
CN106685091B (en) Backstage distributing monitoring system based on Google Earth
CN111858521A (en) Distribution network engineering design data sharing cloud platform and application method
CN103606041A (en) A power distribution terminal operation and maintenance management system
CN105184680A (en) GIS-based power grid infrastructure mobile information acquisition and synchronous updating system
CN112102490B (en) Modeling method for three-dimensional model of transformer substation
CN108363315A (en) A kind of long-distance intelligent TT&C system based on Internet of Things
CN110781549A (en) Panoramic roaming inspection method and system for pump station
CN110765655B (en) Dispatching automation simulation system and construction method and device of SCADA model thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20210310

Address after: No.17 Binhe Road, Nanming District, Guiyang City, Guizhou Province

Applicant after: GUIZHOU POWER GRID Corp.

Address before: No. 45, Zhongshan Middle Road, Liupanshui City, Guizhou Province 553001

Applicant before: LIUPANSHUI POWER SUPPLY BUREAU OF GUIZHOU POWER GRID Co.,Ltd.

Applicant before: BEIJING THP TECHNOLOGY Co.,Ltd.

TA01 Transfer of patent application right
RJ01 Rejection of invention patent application after publication

Application publication date: 20170531

RJ01 Rejection of invention patent application after publication