CN106787205A - Data acquisition mutual Preparation Method on demand between a kind of isomorphism electric power scheduling automatization system - Google Patents

Data acquisition mutual Preparation Method on demand between a kind of isomorphism electric power scheduling automatization system Download PDF

Info

Publication number
CN106787205A
CN106787205A CN201710015451.6A CN201710015451A CN106787205A CN 106787205 A CN106787205 A CN 106787205A CN 201710015451 A CN201710015451 A CN 201710015451A CN 106787205 A CN106787205 A CN 106787205A
Authority
CN
China
Prior art keywords
plant stand
data acquisition
isomorphism
systems
electric power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710015451.6A
Other languages
Chinese (zh)
Other versions
CN106787205B (en
Inventor
韩冰
赵家庆
吕洋
丁宏恩
吴博文
赵慧
陈宁
孙文彦
王强
张留留
王军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Nari Technology Co Ltd
NARI Nanjing Control System Co Ltd
Nanjing NARI Group Corp
Suzhou Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Nari Technology Co Ltd
NARI Nanjing Control System Co Ltd
Nanjing NARI Group Corp
Suzhou Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Jiangsu Electric Power Co Ltd, Nari Technology Co Ltd, NARI Nanjing Control System Co Ltd, Nanjing NARI Group Corp, Suzhou Power Supply Co of State Grid Jiangsu Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710015451.6A priority Critical patent/CN106787205B/en
Publication of CN106787205A publication Critical patent/CN106787205A/en
Application granted granted Critical
Publication of CN106787205B publication Critical patent/CN106787205B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • H02J13/0006

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a kind of mutual Preparation Method on demand of data acquisition between isomorphism electric power scheduling automatization system, in the case of the communication channel for not increasing plant stand end, the plant stand gathered between by comparing isomorphism electric power scheduling automatization system, the automatic data acquisition automatic mutual between the plant stand offer system of common collection partially or fully is for function, it is effective to utilize multiple isomorphism existing data acquisition resources of system, improve the ability to ward off risks of system.

Description

Data acquisition mutual Preparation Method on demand between a kind of isomorphism electric power scheduling automatization system
Technical field
The present invention relates to a kind of mutual Preparation Method on demand of data acquisition between isomorphism electric power scheduling automatization system, belong to electric power tune Degree technical field of automation.
Background technology
At present, the requirement more and more higher to electric power scheduling automatization system operational reliability, provincial and the above electric power is adjusted Degree automated system has all built a set of back-up system in addition outside original system, and area power dispatching automated system is general Another area power dispatching automated system near selecting is mutually unified between standby system to safeguard each other as back-up system, Respective gathered data, each self-operating.For the ease of daily maintenance, what these systems standby each other generally were isomorphism is System.The advantage of the electric power scheduling automatization system of isomorphism is that the unique index ID of same measuring point is identical, database structure phase Together, the information such as user's attended operation that set of system is carried out wherein need not be changed just can very easily be synchronized to it is another In set system, it is ensured that the uniformity between system.
In system operation, primary electric power scheduling automatization system data acquisition occurs local failure once in a while, leads The communicating interrupt of the even whole plant stands of indivedual plant stands is caused, if now total system is transferred to back-up system operation, consumption is needed Expense great effort is estimated to the operation conditions of back-up system first, confirms that it is really available.Therefore, pass through between some systems The real time data that the system is received mutually is forwarded to other systems by stipulations pass-through mode, and receiving terminal system is by these forwarding channels The alternate channel of plant stand is gathered as the system to process, these can be utilized if original direct acquisition channel failure The real time data supplement that forwarding channel forwarding comes, realizes the mutually standby on demand of inter-system data collection.But this mode usually needs dimension Mutual forwarding channel is protected, and when system data acquisition application and trouble, all of direct acquisition channel and forwarding channel are also all All interrupt, system also just cannot normally be run.
The content of the invention
In order to solve the above-mentioned technical problem, the invention provides data acquisition between a kind of isomorphism electric power scheduling automatization system Mutual Preparation Method on demand.
In order to achieve the above object, the technical solution adopted in the present invention is:
Data acquisition mutual Preparation Method on demand, comprises the following steps between a kind of isomorphism electric power scheduling automatization system,
Step 1, the system each gathers corresponding plant stand and channel information with other systems, plant stand and lead to that interaction is each gathered Road information, and calculate the common plant stand for gathering between different system;
Step 2, the system each gathers the current operating conditions of corresponding plant stand and passage, interaction each collection with other systems Plant stand and passage current operating conditions;
Step 3, judges whether the system receives the current operating conditions of the plant stand that other systems send over and passage, if received Arrive, go to step 4, if do not received, go to 5;
Step 4, if the system and normal to passage between the plant stand of side system common collection, in side system and this plant stand passage It is disconnected, then judge to need the system by this plant stand the real time data comprising measuring point be sent to side system;
It is normal to side system and this plant stand passage if the system and to channel interrupt between the plant stand of side system common collection, then Judge that the control command of this plant stand in the system needs to be issued by side system;
Step 5, if the system data acquisition application is normal, judges the data acquisition application and trouble to side system, to side-line Unite with the channel interrupt of all plant stands, it is necessary to the system to be included the real-time number of measuring point with the plant stand to the common collection of side system According to being sent to side system;
If the system data acquisition application and trouble, depending on the channel interrupt of the system and all plant stands, each plant stand in the system Control command need to be issued by the normal system of other passages.
Before step 1, the system each sets gathered plant stand and affiliated passage with other systems, and each passage is closed The gathered measuring point of connection.
The unique identification ID in different system is identical for same plant stand, uniqueness of the same observation station in different system ID is identical for mark.
Also included delay judgement before step 5, that is, judge whether not no more than N seconds to receive what other systems were sended over The current operating conditions of plant stand and passage, if it is, going to step 5.
N=10。
The data acquisition of the system applies the SCADA transmitted to the system in the real time data that will have been processed to apply When, judge whether each real time data needs to be sent to other systems, real time data packing is sent to other systems if necessary SCADA application.
The SCADA of the system is applied when control command order is issued, and judges whether to need to be issued from other systems, if Control command is then sent to needs the data acquisition application of other systems.
The beneficial effect that the present invention is reached:The present invention in the case of the communication channel for not increasing plant stand end, by comparing The plant stand gathered between isomorphism electric power scheduling automatization system, automatically between the plant stand offer system of common collection partially or fully Data acquisition automatic mutual for function, it is effective using multiple isomorphism existing data acquisition resources of system, improve the anti-of system Risk ability.
Brief description of the drawings
Fig. 1 is flow chart of the invention.
Specific embodiment
The invention will be further described below in conjunction with the accompanying drawings.Following examples are only used for clearly illustrating the present invention Technical scheme, and can not be limited the scope of the invention with this.
As shown in figure 1, data acquisition mutual Preparation Method on demand between a kind of isomorphism electric power scheduling automatization system, including following step Suddenly:
Step 1, the system each sets gathered plant stand and affiliated passage with other systems, and the association of each passage is gathered Measuring point, wherein, the unique identification ID in different system is identical for same plant stand, and same observation station is unique in different system Property mark ID it is all identical.
The real time data that the data acquisition application of each system will be collected during normal operation is sent to the SCADA of the system Using, and the control command that only treatment the system is issued(Remote control, set up an office order).
Step 2, the system each gathers corresponding plant stand and channel information, the plant stand that interaction is each gathered with other systems And channel information, and calculate the common plant stand for gathering between different system.
The step is real-time in the case where all systems are normally run, so that common collection between obtaining different system Plant stand, the only common plant stand for gathering can just be realized mutually standby between system.
Step 3, the system each gathers the current operating conditions of corresponding plant stand and passage with other systems, and interaction is respective The plant stand of collection and the current operating conditions of passage.
Step 4, judges whether the system receives the current operating conditions of the plant stand that other systems send over and passage, such as Fruit receives, and goes to step 5, if do not received, goes to 6.
Step 5, if the system and normal to passage between the plant stand of side system common collection, leads to side system and this plant stand Road interrupt, then judge need the system by this plant stand the real time data comprising measuring point be sent to side system;If the system The channel interrupt between the plant stand the common collection of side system, it is normal to side system and this plant stand passage, then judge in the system this The control command of plant stand needs to be issued by side system.
If the measure-point amount that this plant stand is gathered in the system is more than to side system, the real time data of unnecessary measuring point is sent out To after the SCADA to side system, can be dropped without influenceing the normal operation to side system;If this plant stand institute in the system The measure-point amount of collection is less than to side system, then the measuring point that side system this plant stand has more cannot be realized standby.
Control command be controlled measuring point ID be keyword, if in offside system data acquisition application without this measuring point or this Measuring point issues setting without control command, then side system can be abandoned this control command, is not in the phenomenon of wrong control.
Step 6, judges whether the not no current operation for receiving plant stand and passage that other systems are sended over more than 10 seconds State, if it is, step 7 is gone to, if it is not, then continue waiting for, until more than 10 seconds, the not no other systems that receive sent The plant stand and the current operating conditions of passage for coming over, go to step 7.
Step 7, if the system data acquisition application is normal, judges the data acquisition application and trouble to side system, right The channel interrupt of side system and all plant stands is, it is necessary to the system to be included the reality of measuring point with the plant stand to the common collection of side system When data be sent to side system;If the system data acquisition application and trouble, depending on the channel interrupt of the system and all plant stands, The control command of each plant stand needs to be issued by the normal system of other passages in the system.
The data acquisition of the system is applied and transmitted to the system in the real time data that will have been processed in the above method When SCADA is applied, judge whether each real time data needs to be sent to other systems, be if necessary sent to real time data packing The SCADA applications of other systems.The SCADA of the system is applied when control command order is issued, and judges whether to need from other System is issued, and control command is sent to the data acquisition application of other systems if necessary.
The above method in the case of the communication channel for not increasing plant stand end, by comparing isomorphism electric power scheduling automatization system Between the plant stand that is gathered, automatically the data acquisition automatic mutual between the plant stand offer system of common collection partially or fully for work( Can, i.e., using the normal data acquisition of other systems come the data acquisition of locally even replacing whole the system failure, it is ensured that The normal operation of original system, it is effective using multiple isomorphism existing data acquisition resources of system, improve the anti-risk of system Ability, improves the reliability of system, and Maintenance free, can mitigate the workload of automated maintenance personnel.
The above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, on the premise of the technology of the present invention principle is not departed from, some improvement and deformation can also be made, these improve and deform Also should be regarded as protection scope of the present invention.

Claims (7)

1. data acquisition mutual Preparation Method on demand between a kind of isomorphism electric power scheduling automatization system, it is characterised in that:Including following step Suddenly,
Step 1, the system each gathers corresponding plant stand and channel information with other systems, plant stand and lead to that interaction is each gathered Road information, and calculate the common plant stand for gathering between different system;
Step 2, the system each gathers the current operating conditions of corresponding plant stand and passage, interaction each collection with other systems Plant stand and passage current operating conditions;
Step 3, judges whether the system receives the current operating conditions of the plant stand that other systems send over and passage, if received Arrive, go to step 4, if do not received, go to 5;
Step 4, if the system and normal to passage between the plant stand of side system common collection, in side system and this plant stand passage It is disconnected, then judge to need the system by this plant stand the real time data comprising measuring point be sent to side system;
It is normal to side system and this plant stand passage if the system and to channel interrupt between the plant stand of side system common collection, then Judge that the control command of this plant stand in the system needs to be issued by side system;
Step 5, if the system data acquisition application is normal, judges the data acquisition application and trouble to side system, to side-line Unite with the channel interrupt of all plant stands, it is necessary to the system to be included the real-time number of measuring point with the plant stand to the common collection of side system According to being sent to side system;
If the system data acquisition application and trouble, depending on the channel interrupt of the system and all plant stands, each plant stand in the system Control command need to be issued by the normal system of other passages.
2. data acquisition mutual Preparation Method on demand between a kind of isomorphism electric power scheduling automatization system according to claim 1, its It is characterised by:Before step 1, the system each sets gathered plant stand and affiliated passage, each passage with other systems The gathered measuring point of association.
3. data acquisition mutual Preparation Method on demand between a kind of isomorphism electric power scheduling automatization system according to claim 2, its It is characterised by:The unique identification ID in different system is identical for same plant stand, and same observation station is unique in different system Property mark ID it is all identical.
4. data acquisition mutual Preparation Method on demand between a kind of isomorphism electric power scheduling automatization system according to claim 1, its It is characterised by:Also included delay judgement before step 5, that is, judge whether that the not no other systems that receive were sended over more than N seconds Plant stand and passage current operating conditions, if it is, going to step 5.
5. data acquisition mutual Preparation Method on demand between a kind of isomorphism electric power scheduling automatization system according to claim 4, its It is characterised by:N=10.
6. data acquisition mutual Preparation Method on demand between a kind of isomorphism electric power scheduling automatization system according to claim 1, its It is characterised by:The data acquisition of the system applies the SCADA transmitted to the system in the real time data that will have been processed to apply When, judge whether each real time data needs to be sent to other systems, real time data packing is sent to other systems if necessary SCADA application.
7. data acquisition mutual Preparation Method on demand between a kind of isomorphism electric power scheduling automatization system according to claim 1, its It is characterised by:The SCADA of the system is applied when control command order is issued, and judges whether to need to be issued from other systems, such as Fruit needs that control command is then sent to the data acquisition application of other systems.
CN201710015451.6A 2017-01-10 2017-01-10 Data acquire mutual Preparation Method on demand between a kind of isomorphism electric power scheduling automatization system Active CN106787205B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710015451.6A CN106787205B (en) 2017-01-10 2017-01-10 Data acquire mutual Preparation Method on demand between a kind of isomorphism electric power scheduling automatization system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710015451.6A CN106787205B (en) 2017-01-10 2017-01-10 Data acquire mutual Preparation Method on demand between a kind of isomorphism electric power scheduling automatization system

Publications (2)

Publication Number Publication Date
CN106787205A true CN106787205A (en) 2017-05-31
CN106787205B CN106787205B (en) 2019-05-28

Family

ID=58948763

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710015451.6A Active CN106787205B (en) 2017-01-10 2017-01-10 Data acquire mutual Preparation Method on demand between a kind of isomorphism electric power scheduling automatization system

Country Status (1)

Country Link
CN (1) CN106787205B (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101958547A (en) * 2010-10-29 2011-01-26 国电南瑞科技股份有限公司 Hot standby method of distributed data acquisition subareas of power dispatching automation system
CN101976886A (en) * 2010-10-29 2011-02-16 国电南瑞科技股份有限公司 Distributed data collection partitioning mutual backup method for power dispatching automation system
CN103715770A (en) * 2013-12-20 2014-04-09 国电南瑞科技股份有限公司 Wide-area-distributed city/county scheduling and monitoring integrated system subarea disconnection/connection operation method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101958547A (en) * 2010-10-29 2011-01-26 国电南瑞科技股份有限公司 Hot standby method of distributed data acquisition subareas of power dispatching automation system
CN101976886A (en) * 2010-10-29 2011-02-16 国电南瑞科技股份有限公司 Distributed data collection partitioning mutual backup method for power dispatching automation system
CN103715770A (en) * 2013-12-20 2014-04-09 国电南瑞科技股份有限公司 Wide-area-distributed city/county scheduling and monitoring integrated system subarea disconnection/connection operation method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
郑翔 等: "基于多域共享技术的调度集控互备系统", 《电力系统自动化》 *

Also Published As

Publication number Publication date
CN106787205B (en) 2019-05-28

Similar Documents

Publication Publication Date Title
CN105388768B (en) remote circuit control system and method based on cloud platform
CN103729806A (en) Transformer substation alarming graph gateway minimizing system and achieving method thereof
CN101867226B (en) Wide-area distribution type data collection method for dispatching automation system
CN103545826A (en) Intelligent low-voltage power load distribution system and method
CN105790990A (en) Method and system for monitoring and managing power distribution and utilization communication business
CN106006248B (en) A kind of multiple lift control system and method based on remote monitoring
CN101976886B (en) Distributed data collection partitioning mutual backup method for power dispatching automation system
CN104659920A (en) Topology configuration method of distribution circuit
CN105071535B (en) A kind of the time synchronization management system and implementation method of network system
CN104332993B (en) A kind of intelligent distribution type feeder automation load transfer method
CN107995019A (en) Network equipment method and system are safeguarded in a kind of remote debugging based on virtual linkage
CN102360473A (en) Data sharing method for land-saving power dispatching automation systems
CN102832708B (en) Intelligent transformer substation based on integrated multi-stage server framework
CN106209468A (en) The method and system of synchronizing information are operated between the active and standby dispatch automated system of isomery
CN106787205A (en) Data acquisition mutual Preparation Method on demand between a kind of isomorphism electric power scheduling automatization system
CN104317868A (en) Control integration method based on single-front and multi-SCADA (Supervisory Control and Data Acquisition) application
CN205265371U (en) Transformer substation's long -range fortune dimension management and control device
CN105488990A (en) Industrial real-time data acquisition system based on wireless adapters
WO2023168911A1 (en) Low-voltage user demand response interaction apparatus and operation method therefor
CN202651896U (en) Coordinated control system of micro power grid
CN101958547A (en) Hot standby method of distributed data acquisition subareas of power dispatching automation system
CN105226819A (en) A kind of distributed power source monitoring management system based on IEC61850
CN101499682A (en) Improved implementation method for power distribution automation
CN102566550A (en) Low-voltage communication system
CN107995300A (en) Intelligent cutoff maximum load power remote monitors regulator control system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant