CN106779489A - A kind of power engineering project management system - Google Patents

A kind of power engineering project management system Download PDF

Info

Publication number
CN106779489A
CN106779489A CN201710043864.5A CN201710043864A CN106779489A CN 106779489 A CN106779489 A CN 106779489A CN 201710043864 A CN201710043864 A CN 201710043864A CN 106779489 A CN106779489 A CN 106779489A
Authority
CN
China
Prior art keywords
information
unit
project
loop
shaft tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710043864.5A
Other languages
Chinese (zh)
Inventor
江春华
陈显龙
罗新伟
陈晓龙
孙敏杰
任秀英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Forever Technology Co Ltd
Original Assignee
Beijing Forever Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Forever Technology Co Ltd filed Critical Beijing Forever Technology Co Ltd
Priority to CN201710043864.5A priority Critical patent/CN106779489A/en
Publication of CN106779489A publication Critical patent/CN106779489A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Health & Medical Sciences (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Public Health (AREA)
  • Primary Health Care (AREA)
  • Water Supply & Treatment (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • General Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention provides a kind of power engineering project management system, project information unit, for stored items information;Loop information unit, for storing the bid corresponding loop information of section, and the corresponding section information in every loop, the loop information includes shaft tower information;Administrative unit, the handoff instructions for receiving user are transferred, and is sent to the designated person of operating maintenance department corresponding information in the loop information unit according to the handoff instructions.The information that engineering construction department stores is handed over to the designated person of operating maintenance department by electronic method for the present invention, is considerably reduced management cost, is effectively eliminated data redundancy.

Description

A kind of power engineering project management system
Technical field
The present invention relates to technical field of data processing, more specifically to a kind of power engineering project management system.
Background technology
The main information such as including trolley line, cable, shaft tower of line management.For engineering construction department, in engineering construction Cheng Zhong, returns the attributes such as number, section and corresponding shaft tower information and is managed by recording trolley line or cable length, circuit.When After completion of works puts into operation, represent that the engineering that engineering construction department is administered has built up completion, treat that follow-up operation maintenance department enters Row management.Due to the difference of department's responsibility, the information such as trolley line, shaft tower engineering construction department a set of administrative standard, Operating maintenance department cannot be applied to.Now, operating management department then establishes a set of to patrolling and examining overhead transmission line, shaft tower again Etc. being managed.Material is thus formed the same goods and materials various modes of management of correspondence, it is impossible to form data integrated, cause management It is relatively costly, and form data redundancy.
The content of the invention
In view of this, the present invention proposes a kind of power engineering project management system, is intended to realize reducing management cost, eliminates number According to the purpose of redundancy.
To achieve these goals, it is proposed that scheme it is as follows:
A kind of power engineering project management system, it is characterised in that including:
Project information unit, for stored items information, the project information includes:Project name, project code, project Portion's title, project management department's coding, individual works title, bid section engineering name and unit of taking part in building;
Loop information unit, for storing the bid corresponding loop information of section, and the corresponding section information in every loop, The loop information includes shaft tower information;
Transfer administrative unit, the handoff instructions for receiving user, and according to the handoff instructions by the loop information Corresponding information is sent to the designated person of operating maintenance department in unit.
Preferably, the system, also includes:
Project process unit, goes into operation flow, milestone plan and construction schedule for stored items.
Preferably, the system, also includes:
Design management unit, for storing the corresponding design drawing information of each project.
Preferably, the system, also includes:
Unit of taking part in building's administrative unit, the essential information for storing the unit of taking part in building for carrying out engineering construction.
Compared with prior art, technical scheme has advantages below:
A kind of power engineering project management system that above-mentioned technical proposal is provided, project information unit, for stored items Information;Loop information unit, for storing the bid corresponding loop information of section, and the corresponding section information in every loop, institute Stating loop information includes shaft tower information;Transfer administrative unit, the handoff instructions for receiving user, and according to the handoff instructions Corresponding information in the loop information unit is sent to the designated person of operating maintenance department.The present invention passes through electronization side Method, the designated person of operating maintenance department is handed over to by the information that engineering construction department stores, considerably reduce management cost, Effectively eliminate data redundancy.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing The accompanying drawing to be used needed for having technology description is briefly described, it should be apparent that, drawings in the following description are only this Some embodiments of invention, for those of ordinary skill in the art, on the premise of not paying creative work, can be with Other accompanying drawings are obtained according to these accompanying drawings.
Fig. 1 is a kind of flow chart of power engineering project management system provided in an embodiment of the present invention.
Specific embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments.It is based on Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under the premise of creative work is not made Embodiment, belongs to the scope of protection of the invention.
It is shown in Figure 1, it is a kind of power engineering project management system provided in an embodiment of the present invention, the system includes:
Project information unit 11, for stored items information, the project information includes:Project name, project code, item Mesh portion title, project management department's coding, individual works title, bid section engineering name and unit of taking part in building.Project management unit needs fixed Phase carries out the project planning deposit that straddles over year, and carrying out planned project according to actual conditions repaiies volume.After the completion of project planning, according to power grid construction Need, investment plan is assigned to the project that plan is implemented;After investment plan is assigned, project is proceeded by according to actual needs Build.It is embodied as project planning storehouse, project plan storehouse, project implementation storehouse (i.e. project information unit).Project planning storehouse leads to Crossing after reporting examination & verification can be directly entered project plan storehouse, and project plan storehouse can directly return project planning storehouse;Project implementation storehouse can Chosen from project plan storehouse, it is also possible to by the MIM message input module of power engineering project management system, directly enter.
Loop information unit 12, for storing the bid corresponding loop information of section, and the corresponding section letter in every loop Breath, the loop information includes shaft tower information.The shaft tower information management unit pair that user passes through power engineering project management system Shaft tower information, loop setting, section partition etc. are managed.Specifically, manually typing or template import circuit bid section Correspondence shaft tower information, shaft tower information includes but is not limited to tower number, pile No., shaft tower pattern, tower overall height etc., is that loop setting tower bar is carried For basic data;Loop sets main every loop to circuit bid section and carries out shaft tower setting, main to include selection shaft tower, lead Enter working column number etc.;Section partition is mainly divided to loop, is easy to circuit stringing.System provides general circuit, shaft tower Template, user can as needed enter row line, shaft tower typing or importing.After the completion of establishment of item, into Construction stage, Commencement of works, engineering construction, operation etc. of being completed are carried out successively.In project management process, main contents include project management, peace Full management, quality management, technical management, Cost Management etc..
Administrative unit 13, the handoff instructions for receiving user are transferred, and is believed the loop according to the handoff instructions Corresponding information is sent to the designated person of operating maintenance department in interest statement unit., it is necessary to production division after completion of works operation Engineering information is transferred, is easy to the production maintenance in later stage.By selecting engineering to carry out, respective lines are transferred and shaft tower is transferred.Circuit is moved Friendship includes that mode is transferred in single line transfer and the batch transfer of a plurality of circuit etc.;Shaft tower is transferred and entered by bid section subordinate loop Row shaft tower is transferred, including single base shaft tower is transferred, batch transfers two ways.
The detailed process that circuit is transferred:Individual works, system are first selected to obtain list of having gone into operation from loop information unit 12 The information such as item engineering corresponding line length, shaft tower sum, initial shaft tower, termination shaft tower;When user clicks on " batch is transferred ", system Selection recipient's page can be ejected, recipient's page information such as including the recipient of operating maintenance department, receiving department is selected, used After family is selected and is clicked on " confirmation ", transfer line length, shaft tower sum that administrative unit 13 will obtain by calling interface, The information such as initial shaft tower, termination shaft tower are handed over to the designated person of operating maintenance department.The correspondingly received portion of operating maintenance department The recipient of door can enter the reception of row information by logging in power engineering project management system.Single line hand-over, with Batch turning-over operation is differed only in:Single line of having gone into operation is selected, is clicked on " transfer ", other processes are with batch transfer side Formula.
The detailed process that shaft tower is transferred:User selects operation individual works and subordinate bid name section and loop title, System obtains the shaft tower information under currently selected bid section and loop from loop information unit 12;User clicks on " all transferring ", System can eject selection recipient's page, and selection recipient's page is believed including the recipient of operating maintenance department, receiving department etc. Breath, after user is selected and clicked on " confirmations ", transfers the tower bar information transfer that administrative unit 13 will be obtained by calling interface To the designated person of operating maintenance department.The recipient of the correspondingly received department of operating maintenance department can be by logging in electric power work Journey project management system enters the reception of row information.Single base shaft tower hand-over, differs only in batch turning-over operation:Selection is single Base shaft tower, clicks on " transfer ", and other processes transfer mode with batch.
A kind of power engineering project management system provided in an embodiment of the present invention, project information unit 11, for Storage Item Mesh information;Loop information unit 12, for storing the bid corresponding loop information of section, and the corresponding section letter in every loop Breath, the loop information includes shaft tower information;Transfer administrative unit 13, the handoff instructions for receiving user, and according to described Handoff instructions send to the designated person of operating maintenance department corresponding information in the loop information unit.The present invention passes through Electronic method, the information that engineering construction department stores is handed over to the designated person of operating maintenance department, is considerably reduced Management cost, effectively eliminate data redundancy.
Preferably, the system, can also include:Project process unit, goes into operation based on flow, milestone by stored items Draw and construction schedule.
Preferably, the system, can also include:Design management unit, for storing the corresponding design drawing of each project Paper information.
Preferably, the system, can also include:Unit of taking part in building's administrative unit, the ginseng of engineering construction is carried out for storing Build the essential information of unit.Unit of taking part in building is including designing unit, supervisor, unit in charge of construction etc..
System embodiment described above is only schematical, wherein the unit illustrated as separating component can To be or may not be physically separate, the part shown as unit can be or may not be physics list Unit, you can with positioned at a place, or can also be distributed on multiple NEs.It can according to the actual needs be selected In some or all of module realize the purpose of this embodiment scheme.Those of ordinary skill in the art are not paying creativeness In the case of work, you can to understand and implement.
Herein, term " including ", "comprising" or any other variant thereof is intended to cover non-exclusive inclusion, from And the process, method, article or the equipment that include a series of key elements is not only included those key elements, but also including not bright Other key elements really listed, or it is this process, method, article or the intrinsic key element of equipment also to include.Do not having In the case of more limitations, the key element limited by sentence "including a ...", it is not excluded that the process including the key element, Also there is other identical element in method, article or equipment.
To the described above of disclosed embodiment of this invention, professional and technical personnel in the field is realized or use this Invention.Various modifications to these embodiments will be apparent for those skilled in the art, institute herein The General Principle of definition can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, The present invention is not intended to be limited to the embodiments shown herein, and is to fit to special with principles disclosed herein and novelty The consistent scope most wide of point.

Claims (4)

1. a kind of power engineering project management system, it is characterised in that including:
Project information unit, for stored items information, the project information includes:Project name, project code, project management department's name Title, project management department's coding, individual works title, bid section engineering name and unit of taking part in building;
Loop information unit, for storing the bid corresponding loop information of section, and the corresponding section information in every loop, it is described Loop information includes shaft tower information;
Transfer administrative unit, the handoff instructions for receiving user, and according to the handoff instructions by the loop information unit In corresponding information send to the designated person of operating maintenance department.
2. system according to claim 1, it is characterised in that the system, also includes:
Project process unit, goes into operation flow, milestone plan and construction schedule for stored items.
3. system according to claim 1, it is characterised in that the system, also includes:
Design management unit, for storing the corresponding design drawing information of each project.
4. system according to claim 1, it is characterised in that the system, also includes:
Unit of taking part in building's administrative unit, the essential information for storing the unit of taking part in building for carrying out engineering construction.
CN201710043864.5A 2017-01-19 2017-01-19 A kind of power engineering project management system Pending CN106779489A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710043864.5A CN106779489A (en) 2017-01-19 2017-01-19 A kind of power engineering project management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710043864.5A CN106779489A (en) 2017-01-19 2017-01-19 A kind of power engineering project management system

Publications (1)

Publication Number Publication Date
CN106779489A true CN106779489A (en) 2017-05-31

Family

ID=58943568

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710043864.5A Pending CN106779489A (en) 2017-01-19 2017-01-19 A kind of power engineering project management system

Country Status (1)

Country Link
CN (1) CN106779489A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108549991A (en) * 2018-04-20 2018-09-18 北京宇时易能科技发展有限公司 Overhaul command system and lean inspection base
CN109034722A (en) * 2018-06-14 2018-12-18 中铁电气化局集团有限公司 High-speed railway touching net computing system, method and computer equipment
CN110570158A (en) * 2019-06-12 2019-12-13 陕西省地方电力(集团)有限公司 power grid standing book electronic transfer method and system and computer readable storage medium

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4261037A (en) * 1979-04-03 1981-04-07 Dupont Energy Management Corporation System for monitoring utility usage
CN101989336A (en) * 2010-12-09 2011-03-23 北京恒华伟业科技股份有限公司 Power transmission and transformation project schedule management system and method for power system
CN103915898A (en) * 2014-03-04 2014-07-09 广东电网公司珠海供电局 Operation and maintenance method for intelligent substation network

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4261037A (en) * 1979-04-03 1981-04-07 Dupont Energy Management Corporation System for monitoring utility usage
CN101989336A (en) * 2010-12-09 2011-03-23 北京恒华伟业科技股份有限公司 Power transmission and transformation project schedule management system and method for power system
CN103915898A (en) * 2014-03-04 2014-07-09 广东电网公司珠海供电局 Operation and maintenance method for intelligent substation network

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘书刚等: "输电线路信息管理系统", 《华北电力技术》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108549991A (en) * 2018-04-20 2018-09-18 北京宇时易能科技发展有限公司 Overhaul command system and lean inspection base
CN109034722A (en) * 2018-06-14 2018-12-18 中铁电气化局集团有限公司 High-speed railway touching net computing system, method and computer equipment
CN109034722B (en) * 2018-06-14 2021-01-05 中铁电气化局集团有限公司 High-speed railway contact net computing system and method and computer equipment
CN110570158A (en) * 2019-06-12 2019-12-13 陕西省地方电力(集团)有限公司 power grid standing book electronic transfer method and system and computer readable storage medium

Similar Documents

Publication Publication Date Title
CN106218671B (en) The control method and device of station train travel operation
CN107368967A (en) Engineering safety quality inspection intelligent management based on internet
CN206265072U (en) The control device of station train travel operation
CN106779489A (en) A kind of power engineering project management system
CN204938056U (en) Intelligent cargo cabinet
CN106056782B (en) A kind of automatic transaction apparatus of package
CN106934578A (en) One kind is based on import and export supply platform chain and its management method
EP0712519A1 (en) Ordering and billing equipment
CN107918848A (en) A kind of shops's purchase, sales and stock management software systems
CN103530757A (en) Network based multi-mode intelligent order following management method and intelligent management system
CN104925438A (en) Smart container and indirect logistics distribution method based on smart container
CN105354939B (en) The method and system extracted in Internet of Things using self-carry cabinet
CN107169539A (en) Reinforcing bar automation processing delivery system and method based on two-dimensional bar code
CN103679407A (en) Intelligent mailbox system
CN108154340A (en) Prefabricated component informationization management system based on BIM cloud platforms
CN107316086A (en) The main human rectal cancer system of substation equipment and O&M method
CN103093325B (en) A kind of electric power measure device management system and management method
CN107659607A (en) The external delivery system of gathered data based on distributed service processing
CN205518664U (en) Intelligence warehouse system of selecting based on pronunciation
DE1774943A1 (en) Information transfer arrangement
CN106780159A (en) A kind of construction information management system
CN110002167A (en) A kind of order review method and apparatus based on review wall
CN109146410A (en) A kind of multimedia advertising design platform
CN107247715A (en) The synchronous method of WMS systems and ERP system
CN108733752A (en) Autoreport storage method and system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170531