CN106774095B - A kind of Industrial Wastewater Treatment control method and system based on intelligent data analysis - Google Patents
A kind of Industrial Wastewater Treatment control method and system based on intelligent data analysis Download PDFInfo
- Publication number
- CN106774095B CN106774095B CN201710068233.9A CN201710068233A CN106774095B CN 106774095 B CN106774095 B CN 106774095B CN 201710068233 A CN201710068233 A CN 201710068233A CN 106774095 B CN106774095 B CN 106774095B
- Authority
- CN
- China
- Prior art keywords
- water
- central control
- control room
- personnel
- upper computer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B19/00—Programme-control systems
- G05B19/02—Programme-control systems electric
- G05B19/04—Programme control other than numerical control, i.e. in sequence controllers or logic controllers
- G05B19/048—Monitoring; Safety
Landscapes
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Engineering & Computer Science (AREA)
- Automation & Control Theory (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
A kind of method that the present invention provides the Industrial Wastewater Treatment control system based on intelligent data analysis and runs in the system, it includes central control room upper computer, process control modules, operating cost control module, personnel control module are provided in central control room upper computer, it is respectively used to control technique, operating cost and personnel, information can also be carried out data transmission by way of wireless network with mobile phone terminal in central control room upper computer, mobile phone terminal executes early warning function, executes the typing of work order operation information in, data analysis result and function is presented;The system integrates technique, cost, personnel's intelligentized control method, pass through the Industrial Wastewater Treatment control method of operation data intellectual analysis, the timely all-around intelligentization control of industrial wastewater treatment system comprehensively realizes that the stable operation, cost reduction, personnel of industrial wastewater treatment system are efficient.
Description
Technical field
The present invention relates to field of industrial waste water treatment more particularly to a kind of Industrial Wastewater Treatments based on intelligent data analysis
Control method and system.
Background technique
Important component of the Industrial Wastewater Treatment as wisdom construction of environmental protection is to guarantee that wisdom environmental protection policy is conscientiously real
It applies, the more efficient key link of Internet of Things." State Council is about the instruction for actively pushing forward " internet+" action "
The publication of (2015-2018) shows to accelerate the generation information communication technology and industrial depth integration, from technology path, industry mould
The comprehensive refinement ecosystem construction such as formula, policy guarantee, it has also become China's industry development is dominated.In January, 2016 " " interconnection
3 years action embodiments of net+" green ecological " it further clarifies and points out, wisdom environmental protection is greatly developed, internet is given full play to
Platform action in reverse logistic recovery system improves facilitation, interactive, transparence that regenerated resources transaction utilizes.Root
According to Industrial Wastewater Treatment feature, the control system that can be docked with wisdom environmental protection internet platform is built, is realized at industrial wastewater
It is imperative to manage upgrading and transformation.
Industrial wastewater is to cause environmental pollution, especially the major reason of water pollution.Industrial wastewater complicated component, pollution
Object concentration is high and strong toxicity, processing difficulty are big, and the pollutant of unprocessed or below standard discharge is easy to migration and variation, to environment
Caused by harm is big, effect is lasting, be difficult to restore in the short time.Therefore, Industrial Wastewater Treatment is from technique, cost and the control of personnel
System all has its particularity.Process aspect: since industrial wastewater pollution object concentration height, strong toxicity, water quality and quantity fluctuation are significant, useless
Water process difficulty is big, cause technique for treating industrial wastewater system be hit situation easily send out, impact caused by chain effect it is significant, by
System repair time is long after impact.In terms of cost: industrial wastewater toxic organic pollutant concentration is higher, and it is larger to expend pharmaceutical quantities.
To guarantee meet the requirement of environmental protection, joined using the multistep treatments measure such as pretreatment, biochemical treatment, advanced treating and Treatment for Reuse
With being the method that Industrial Wastewater Treatment generallys use, equipment is more, dosage point is more, but each unit Inlet and outlet water water quality, water, sets
Standby, dispensing lacks feedback mechanism, this is resulted in, and energy consumption, reagent consumption are significant, and operating cost occupies high not low.In terms of personnel: existing rank
The live inspection of section, maintenance, detection still human beings, but Field Force it is professional it is weak, target is indefinite, information transmission is inefficient,
Data analysis capabilities are weak, cause technique control dependence experience, lag strong;In addition, improving the phenols contained in industrial wastewater, cyaniding
The toxicants such as object, biphenyl, chloride, heavy metal are the principal elements for threatening Field Force's health.
Currently, developed sewage treatment control system is poor in the specific aim of field of industrial waste water treatment, it is not suitable for work
The intelligentized control method of industry wastewater treatment;Meanwhile most of sewage treatment control system is only limitted to information and collects, monitors in real time, lacks
Weary data analysis, module interaction, cause control system intelligence degree low.
Summary of the invention
Present invention aim to address current sewage treatment control systems not to be suitable for Industrial Wastewater Treatment control and intelligence
The low problem of change degree proposes a kind of Industrial Wastewater Treatment control system based on intelligent data analysis.
Specific technical solution is as follows:
A kind of Industrial Wastewater Treatment control system based on intelligent data analysis, including following part:
Central control room upper computer is internally provided with process control modules, operating cost control module, personnel control module, point
Technique, operating cost and personnel Yong Yu not controlled and alarmed;
Mobile phone terminal, for being carried out data transmission by way of wireless network with central control room upper computer;Executable early warning
Function executes the typing of work order operation information and data analysis result presentation function;Execute prompt, inspection/maintenance/maintenance work order group
Send and complete information feedback function.Operating right is defined with each post concrete power limit detailed rules and regulations in waste water treatment plant;
Technique for treating industrial wastewater system, interior to be equipped with on-line monitoring instrument, central control room upper computer can be set by control command
On-line checking instrument parameter is set, and reads on-line monitoring instrument monitoring result.
Further, the technique for treating industrial wastewater system includes treatment unit for waste water, treatment unit for waste water connection
There are inlet and outlet pipes, is provided with on-line monitoring instrument, on-line computing model on water inlet line in water inlet, outlet conduit
On-line Control front end valve, rear end valve is respectively set in table rear end;Crossing pipeline is set before the valve of On-line Control front end, across pipe
Road and accident pool, scratch pool connection;On-line Control is set on crossing pipeline and crosses over valve;Treatment unit for waste water is also connected with dispensing
Equipment, steam heater, air blower;The data of the central control room upper computer acquisition on-line monitoring instrument, and controlled according to data
The switch of respective valves and equipment.
Further, the on-line monitoring instrument includes water flowmeter and measurement COD, NH3The water of-N, pH, temperature etc.
Sensor is surveyed in quality supervision.
A method of it runs in the Industrial Wastewater Treatment control system based on intelligent data analysis, the technology controlling and process
Module completes following operating procedure:
4.1) influent quality, water control: each treatment unit for waste water water inlet line be arranged crucial water quality (such as COD,
NH3- N, pH, temperature), water (such as flowmeter) on-line monitoring instrument, the on-line monitoring instrument and Central Control Room of water inlet line be upper
Machine connection, according to processing parameter setting on-line monitoring instrument threshold value, it is upper that data by on-line monitoring instrument are transmitted to Central Control Room
Machine, central control room upper computer execute data calculating and store function to on-line monitoring instrument real time data.When influent quality, water exist
Within the scope of given threshold, go forward end valve door, rear end valve of water inlet line is in open state, across at valve on crossing pipeline
In closed state;When influent quality, water are more than given threshold, central control room upper computer starts end valve before closing water inlet line automatically
Door function, while starting and opening crossing pipeline across valve function, realize that superthreshold waste water enters the function of accident pool or scratch pool
Energy;When influent quality, water be more than given threshold, and Central Control Room start automatically closing water inlet line rear end valve function, simultaneously
After unlatching crossing pipeline crosses over valve function, on-line monitoring instrument continues to show that influent quality, water are more than given threshold, then stands
I.e. water inlet line front end valve function is closed in starting, realizes that superthreshold waste water enters the function of accident pool or scratch pool, Central Control Room
Host computer sends prompt information to mobile phone terminal, and early warning simultaneously prompts check instrument, equipment, repair;Accident pool, scratch pool pipe
Return valve is set on road, and is connect with central control room upper computer, when on-line monitoring instrument numerical value restores threshold range, executes accident
Pond, scratch pool return valve open function, superthreshold waste water flows back according to inflow 1-3% in accident pool scratch pool;
4.2) effluent quality, water control: the on-line monitoring instrument of outlet conduit is connect with central control room upper computer, according to work
Skill parameter setting on-line monitoring instrument threshold value;When effluent quality is in threshold range, it is steady that on-line checking instrument controls effluent quality
Fixed operation;When effluent quality is more than threshold range, Central Control Room starting device adjusting function starts administration apparatus, works as effluent quality
When being restored in threshold range, regulation terminates;When effluent quality be more than threshold range, Central Control Room starting device adjusting function,
The continuously display effluent quality of line measuring instrument is more than given threshold duration >=12h, then central control room upper computer send prompt information to
Mobile phone terminal, early warning simultaneously prompt check instrument, equipment, repair;
4.3) early warning controls: technique real-time early warning, prediction and warning module are additionally provided in the process control modules;Middle control
Room host computer executes data storage function to on-line monitoring instrument real time data, and storing data real-time Transmission is pre- in real time to technique
Alert, prediction and warning module;The technique real-time early warning module is used to when water inlet water quality, water and water outlet water quality be more than online
When measuring instrument threshold value, carry out early warning in central control room upper computer and mobile phone terminal, at the same central control room upper computer execute respectively into
Water, the water of water outlet, Water-quality control step;The prediction and warning module is for acquiring water inlet water quality, water and water outlet saliva
Matter, according to process design parameter, by built-in mathematical model prediction effluent quality, water, when prediction result is more than online prison
When surveying instrument threshold value, early warning is carried out in central control room upper computer and mobile phone terminal, while central control room upper computer executes the water of water outlet
Amount, Water-quality control step.
Further, the operating cost control module completes following operating procedure:
5.1) medicament controls: central control room upper computer executes data to on-line monitoring instrument real time data and calculates and store function
Can, by water yield, added amount of chemical, medicament calculation of price and output unit water medicament price;And treatment unit for waste water is gone out
Water, added amount of chemical, medicament price, unit water medicament price are presented according to timing node sequence;It is set according to technological parameter
Determine added amount of chemical, unit water medicament price thresholds;When added amount of chemical, unit water medicament valence are in threshold range, in
It controls room and closes prompt facility;When added amount of chemical, unit water medicament valence are more than threshold range, Central Control Room starts prompt facility;
Medicament price is calculated simultaneously, sends warning information to mobile phone terminal;
5.2) maintenance maintenance cost control: central control room upper computer executes maintenance, support price calculating and store function, calculates
And storage content include: central control room upper computer prompt instrument, equipment checked, mantenance data, instrument, equipment inspection, dimension
It repairs field data and key equipment carries out an inspection, maintenance;Sort out data according to technological design instrument, device model;Same model
Maintenance of equipment/maintenance frequency accounting is lower than mean value 30%, and Central Control Room closes prompt facility;With model maintenance of equipment/maintenance frequency
Accounting is higher than mean value 30%, and Central Control Room starts prompt facility, and calculates maintenance maintenance price, while sending warning information to mobile phone
End;
5.3) energy consumption controls: central control room upper computer executes equipment energy consumption calculation of price and store function;According to technological parameter
Plant capacity, unit electricity rates set electricity consumption threshold value;When electricity consumption is in threshold range, Central Control Room closes prompt facility;
When electricity consumption is more than threshold range, Central Control Room starts prompt facility, and calculates energy consumption price, while sending warning information to mobile phone
End;
5.4) personnel operate control: central control room upper computer operational staff information, personnel's operation information computing function.By personnel
Information, personnel's operation information are presented according to timing node sequence, and computing staff's expense;Specifying information is sent to mobile phone simultaneously
End;
5.5) equipment depreciation controls: central control room upper computer executes technological design instrument, equipment depreciation data computing function;It will
Instrument, equipment depreciation are distributed according to timing node, and computing depreciation expense;Specifying information is sent to mobile phone terminal simultaneously;
5.6) totle drilling cost controls: central control room upper computer executes operating cost calculating and store function, and calculating content includes: medicine
Agent, maintenance maintenance, energy consumption, personnel, depreciable cost data, while sending data to mobile phone terminal.
Further, the personnel control module completes following operating procedure:
6.1) personnel amount control: when personal information, personnel's operation information at the same time the spare number of intermediate node be lower than 25%,
Then consider that post complementation is replaced;When personal information, personnel's operation information at the same time the spare number of intermediate node be 25%, then consider to tie up
Flow of personnel is protected to stablize;When the spare number of intermediate node then considers transfer-position higher than 25% at the same time for personal information, personnel's operation information
Or it reduces the staff;
6.2) personnel's efficiency controls: when timing node then considers lower than 1:1 when 8 is small for personal information, personnel's operation information
Post complementation replacement;When timing node is 1:1 when 8 is small for personal information, personnel's operation information, then consider that maintenance personnel's flowing is steady
It is fixed;When timing node then considers transfer-position or reduce the staff higher than 1:1 when 8 is small for personal information, personnel's operation information;
6.3) personnel safety controls: safeguard protection note function is set according to personal information, personnel's operation information, according to operation
Information is put on record security protection operation information, safety prevention measure information;Information prompting function occurs for operational staff's safety accident, together
When send data to mobile phone terminal
6.4) personnel's permission controls: central control room upper computer is to above-mentioned steps 6.1) -6.3) execute audit, examination & approval function.
The beneficial effects of the present invention are: the application in central control room upper computer by being provided with process control modules, fortune
Row cost control module, personnel control module are respectively used to control technique, operating cost and personnel, and Central Control Room is upper
Information can also be carried out data transmission by way of wireless network with mobile phone terminal in machine, and mobile phone terminal executes early warning function, be executed
Function is presented in the typing of work order operation information and data analysis result;The system collects technique, cost, personnel's intelligentized control method in one
Body, comprehensively timely industrial wastewater treatment system all-around intelligentization control, realize waste water treatment system stable operation, at
This reduction, personnel are efficient.
Significant, the big spy of wastewater treatment difficulty is fluctuated for industrial wastewater pollution object concentration height, strong toxicity, water quality and quantity simultaneously
The resistance to multiple impact of industrial wastewater system can be improved by using the system in point, and significantly improve impact after system repair when
Between;And by the multistage linkings treatment measures such as the pretreatment of links, biochemical treatment, advanced treating and Treatment for Reuse,
Energy consumption and reagent consumption are reduced, cost and pollution on the environment are reduced;Live inspection, dimension are improved finally by control system
Working efficiency and safe operation are repaired and detected, the professional of control, information transmission and analysis ability is improved and significantly improves, and
It makes one to influence far from the noxious material in wastewater treatment process.
Detailed description of the invention
In conjunction with attached drawing, invention is further described in detail:
Fig. 1 is the application system global structure block diagram;
Fig. 2 is the structural block diagram of process control process in the application;
Fig. 3 is the structural block diagram of operating cost control flow in the application;
Fig. 4 is the structural block diagram of personnel control process in the application;
Specific embodiment
Below will with reference to the accompanying drawings shown in preferred embodiment, the present invention is explained in detail, however the present invention is not limited to
The embodiment.
In conjunction with attached drawing 1-4, the technical program is introduced:
The primary focus of the application is to realize the technology controlling and process to entire treatment process, fortune by central control room upper computer
Row cost control, personnel control realize control technique, operating cost and personnel respectively, information in central control room upper computer
It can also be carried out data transmission by way of wireless network with mobile phone terminal, mobile phone terminal executes early warning function, executes work order operation
Function is presented in data input and data analysis result;The system integrates technique, cost, personnel's intelligentized control method, Quan Mianji
When industrial wastewater treatment system all-around intelligentization control.
Technology controlling and process: central control room upper computer sets influent quality, water threshold value, critical operational parameters inside setting each unit
Threshold value executes on-line monitoring instrument data, account data, the early warning and alert function of model, controls each unit influent quality, water
Amount, control each unit operation realize that central control room upper computer realizes control industrial wastewater high concentration, toxic pollutant, water quality and quantity
Fluctuation, avoids waste water treatment process system from causing to impact;It realizes that each unit is separable under impact condition, avoids impact from causing chain
Effect;Realize that each unit is separable under impact condition, system repair time after shortening is hit, the specific steps of which are as follows:
1) influent quality, water control: the on-line monitoring instrument of water inlet line is connect with central control room upper computer, according to technique
Parameter setting on-line monitoring instrument threshold value;When influent quality, water within the set threshold range, water inlet line go forward end valve door,
Rear end valve is in open state, is in close state on crossing pipeline across valve;When influent quality, water are more than setting
Threshold value, central control room upper computer starts automatically closes water inlet line front end valve function, while starting and opening crossing pipeline across valve
Door function realizes that superthreshold waste water enters the function of accident pool or scratch pool;When influent quality, water be more than given threshold, and
Central Control Room starts automatically closes water inlet line rear end valve function, while opening crossing pipeline across after valve function, online to supervise
It surveys instrument to continue to show that influent quality, water are more than given threshold, then water inlet line front end valve function is closed in starting immediately, real
Existing superthreshold waste water enters the function of accident pool or scratch pool, and central control room upper computer sends prompt information to mobile phone terminal, and early warning is simultaneously
Prompt checks instrument, equipment, is repaired;Return valve, and and central control room upper computer are set on accident pool, scratch pool pipeline
Connection when on-line monitoring instrument numerical value restores threshold range, executes accident pool, scratch pool return valve open function, accident pool
Superthreshold waste water flows back according to inflow 5% in scratch pool;
2) effluent quality, water control: the on-line monitoring instrument of outlet conduit is connect with central control room upper computer, according to technique
Parameter setting on-line monitoring instrument threshold value;When effluent quality is in threshold range, on-line checking instrument controls stable effluent quality
Operation;When effluent quality is more than threshold range, Central Control Room starting device adjusting function starts administration apparatus, when effluent quality is extensive
When again in threshold range, regulation terminates;When effluent quality be more than threshold range, Central Control Room starting device adjusting function, online
The continuously display effluent quality of measuring instrument is more than given threshold duration >=12h, then central control room upper computer sends prompt information to hand
Generator terminal, early warning simultaneously prompt check instrument, equipment, repair;
3) early warning controls: technique real-time early warning, prediction and warning module are additionally provided in the process control modules;Central Control Room
Host computer to on-line monitoring instrument real time data execute data storage function, storing data real-time Transmission to technique real-time early warning,
Prediction and warning module;The technique real-time early warning module is used to when water inlet water quality, water and water outlet water quality be more than online prison
When surveying instrument threshold value, carry out early warning in central control room upper computer and mobile phone terminal, at the same central control room upper computer execute respectively water inlet,
Water, the Water-quality control step of water outlet;The prediction and warning module is used to acquire water inlet water quality, water and water outlet water quality,
According to process design parameter, by built-in mathematical model prediction effluent quality, water, when prediction result is more than on-line computing model
When table threshold value, early warning is carried out in central control room upper computer and mobile phone terminal, while central control room upper computer executes the water of water outlet, water
Matter rate-determining steps.
Operating cost control: central control room upper computer sets influent quality, water threshold value, crucial operation inside setting each unit
Parameter threshold executes influent quality, water, unit inside key parameter and controls equipment added amount of chemical function, executes processing water
Amount, added amount of chemical, medicament price, unit water medicament calculation of price function realize dosage control, realize reagent cost control
System.
Central control room upper computer sets influent quality, water threshold value, and critical operational parameters threshold value inside setting each unit executes
Influent quality, water, unit inside key parameter control instrument, equipment inspection, maintenance, repair function, execute maintenance, maintenance valence
Lattice calculate and store function, realize maintenance, maintenance cost control.Central control room upper computer sets influent quality, water threshold value, setting
Critical operational parameters threshold value inside each unit executes influent quality, water, unit inside key parameter control equipment and runs function
Can, equipment energy consumption calculation of price and store function are executed, realizes energy consumption control.
Central control room upper computer operational staff information, personnel's operation information computing function, by personal information, personnel's operation information
It is presented according to timing node sequence, realizes that information carries out data biography with mobile phone terminal by way of wireless network in central control room upper computer
Defeated, information feedback function is sent and completed to execution early warning, inspection/maintenance work order with charge free, realize that personnel operate control, specifically include
Following steps:
1) medicament controls: central control room upper computer executes data calculating and store function to on-line monitoring instrument real time data,
By water yield, added amount of chemical, medicament calculation of price and output unit water medicament price;And treatment unit for waste water is discharged
Amount, added amount of chemical, medicament price, unit water medicament price are presented according to timing node sequence;According to processing parameter setting
Added amount of chemical, unit water medicament price thresholds;When added amount of chemical, unit water medicament valence are in threshold range, middle control
Prompt facility is closed in room;When added amount of chemical, unit water medicament valence are more than threshold range, Central Control Room starts prompt facility;Together
When calculate medicament price, send warning information to mobile phone terminal;
2) maintenance maintenance cost control: central control room upper computer execute maintenance, support price calculate and store function, calculate and
Storage content include: central control room upper computer prompt instrument, equipment checked, mantenance data, instrument, equipment inspection, maintenance
Field data and key equipment carry out an inspection, maintenance;Sort out data according to technological design instrument, device model;It is set with model
Standby maintenance/maintenance frequency accounting is lower than mean value 30%, and Central Control Room closes prompt facility;It is accounted for model maintenance of equipment/maintenance frequency
Than being higher than mean value 30%, Central Control Room starts prompt facility, and calculates maintenance maintenance price, while sending warning information to mobile phone
End;
3) energy consumption controls: central control room upper computer executes equipment energy consumption calculation of price and store function;It is set according to technological parameter
Standby power, unit electricity rates set electricity consumption threshold value;When electricity consumption is in threshold range, Central Control Room closes prompt facility;When
Electricity consumption is more than threshold range, and Central Control Room starts prompt facility, and calculates energy consumption price, while sending warning information to mobile phone
End;
4) personnel operate control: central control room upper computer operational staff information, personnel's operation information computing function.Personnel are believed
Breath, personnel's operation information are presented according to timing node sequence, and computing staff's expense;Specifying information is sent to mobile phone terminal simultaneously;
5) equipment depreciation controls: central control room upper computer executes technological design instrument, equipment depreciation data computing function;By instrument
Table, equipment depreciation are distributed according to timing node, and computing depreciation expense;Specifying information is sent to mobile phone terminal simultaneously;
6) totle drilling cost controls: central control room upper computer executes operating cost calculating and store function, and calculating content includes: medicine
Agent, maintenance maintenance, energy consumption, personnel, depreciable cost data, while sending data to mobile phone terminal.
Personnel control: central control room upper computer operational staff information, personnel's operation information, safety operation information computing function,
Stable, transfer-position or analytic function of reducing the staff are flowed in the complementation replacement of operational staff post, maintenance personnel, and operational staff's safety accident occurs
Information prompting function.Realize personnel amount, personnel's efficiency, personnel safety, the control function of personnel's permission, specific steps are such as
Under:
1) personnel amount control: when personal information, personnel's operation information at the same time the spare number of intermediate node be lower than 25%, then
Consider post complementation replacement;When personal information, personnel's operation information at the same time the spare number of intermediate node be 25%, then consider to safeguard
Flow of personnel is stablized;When personal information, personnel's operation information at the same time the spare number of intermediate node be higher than 25%, then consider transfer-position or
It reduces the staff;
2) personnel's efficiency controls: when timing node then considers hilllock lower than 1:1 when 8 is small for personal information, personnel's operation information
The complementary replacement in position;When timing node is 1:1 when 8 is small for personal information, personnel's operation information, then consider that maintenance personnel's flowing is steady
It is fixed;When timing node then considers transfer-position or reduce the staff higher than 1:1 when 8 is small for personal information, personnel's operation information;
3) personnel safety controls: setting safeguard protection note function according to personal information, personnel's operation information, believes according to operation
Cease put on record security protection operation information, safety prevention measure information;Information prompting function occurs for operational staff's safety accident, simultaneously
Send data to mobile phone terminal
4) personnel's permission controls: central control room upper computer is to above-mentioned steps 6.1) -6.3) execute audit, examination & approval function.
To sum up, using invention provide the Industrial Wastewater Treatment control system based on intelligent data analysis, integrated technique, at
Originally, personnel's intelligentized control method is in one, and the timely all-around intelligentization control of industrial wastewater treatment system, realizes waste water comprehensively
The stable operation of processing system, cost reduce, personnel are efficient.
Claims (3)
1. a kind of Industrial Wastewater Treatment control method based on intelligent data analysis, by the work based on intelligent data analysis
It is run in industry wastewater treatment control system, the Industrial Wastewater Treatment control system includes following part:
Central control room upper computer is internally provided with process control modules, operating cost control module, personnel control module, uses respectively
In technique, operating cost and personnel are controlled and are alarmed;
Mobile phone terminal, for being carried out data transmission by way of wireless network with central control room upper computer;Executable early warning function,
It executes the typing of work order operation information and function is presented in data analysis result;Execute prompt, inspection/maintenance/maintenance work order is sent with charge free and
Complete information feedback function;Operating right is defined by each post permission detailed rules and regulations in waste water treatment plant;
Technique for treating industrial wastewater system, interior to be equipped with on-line monitoring instrument, central control room upper computer can be arranged by control command
Line detects meter parameter, and reads on-line monitoring instrument monitoring result;
It is characterized by: the process control modules complete following operating procedure:
4.1) water quality monitoring sensor and water stream influent quality, water control: are set in each treatment unit for waste water water inlet line
Two kinds of on-line monitoring instruments of meter, the on-line monitoring instrument of water inlet line connect with central control room upper computer, are set according to technological parameter
Determine on-line monitoring instrument threshold value, data are transmitted to central control room upper computer by on-line monitoring instrument, and central control room upper computer is to online
Measuring instrument real time data executes data calculating and store function;When influent quality, water within the set threshold range, water inlet pipe
Go forward end valve door, rear end valve of road is in open state, is in close state on crossing pipeline across valve;When water inlet water
Matter, water are more than given threshold, and central control room upper computer starts automatically closes water inlet line front end valve function, while starting unlatching
Crossing pipeline crosses over valve function, realizes that superthreshold waste water enters the function of accident pool or scratch pool;When influent quality, water are super
Given threshold is crossed, and Central Control Room starts closing water inlet line rear end valve function automatically, while opening crossing pipeline across valve
After function, on-line monitoring instrument continues to show that influent quality, water are more than given threshold, then before water inlet line is closed in starting immediately
Hold valve function, realize that superthreshold waste water enters the function of accident pool or scratch pool, central control room upper computer send prompt information to
Mobile phone terminal, early warning simultaneously prompt check instrument, equipment, repair;Return valve is set on accident pool, scratch pool pipeline, and
It is connect with central control room upper computer, when on-line monitoring instrument numerical value restores threshold range, executes accident pool, scratch pool return valve is opened
Function is opened, superthreshold waste water flows back according to inflow 1-3% in accident pool scratch pool;
4.2) effluent quality, water control: the on-line monitoring instrument of outlet conduit is connect with central control room upper computer, is joined according to technique
Number setting on-line monitoring instrument threshold value;When effluent quality is in threshold range, on-line checking instrument controls stable effluent quality fortune
Row;When effluent quality is more than threshold range, Central Control Room starting device adjusting function starts administration apparatus, when effluent quality restores
When in threshold range, regulation terminates;When effluent quality is more than threshold range, Central Control Room starting device adjusting function is online to supervise
Surveying the continuously display effluent quality of instrument is more than given threshold duration >=12h, then central control room upper computer sends prompt information to mobile phone
End, early warning simultaneously prompt check instrument, equipment, repair;
4.3) early warning controls: technique real-time early warning, prediction and warning module are additionally provided in the process control modules;On Central Control Room
Position machine executes data storage function to on-line monitoring instrument real time data, storing data real-time Transmission to technique real-time early warning, pre-
Survey warning module;The technique real-time early warning module is used to when water inlet water quality, water and water outlet water quality be more than on-line monitoring
When instrument threshold value, early warning is carried out in central control room upper computer and mobile phone terminal, while central control room upper computer executes water inlet respectively, goes out
Water, the Water-quality control step of water;The prediction and warning module is for acquiring water inlet water quality, water and water outlet water quality, root
According to process design parameter, by built-in mathematical model prediction effluent quality, water, when prediction result is more than on-line monitoring instrument
When threshold value, early warning is carried out in central control room upper computer and mobile phone terminal, while central control room upper computer executes the water of water outlet, water quality
Rate-determining steps.
2. a kind of Industrial Wastewater Treatment control method based on intelligent data analysis according to claim 1, feature exist
In: the operating cost control module completes following operating procedure:
5.1) medicament controls: central control room upper computer executes data calculating and store function to on-line monitoring instrument real time data, will
Water yield, added amount of chemical, medicament calculation of price and output unit water medicament price;And by treatment unit for waste water water yield,
Added amount of chemical, medicament price, unit water medicament price are presented according to timing node sequence;According to processing parameter setting medicament
Dosage, unit water medicament price thresholds;When added amount of chemical, unit water medicament valence are in threshold range, Central Control Room is closed
Close prompt facility;When added amount of chemical, unit water medicament valence are more than threshold range, Central Control Room starts prompt facility;It counts simultaneously
Medicament price is calculated, sends warning information to mobile phone terminal;
5.2) maintenance maintenance cost control: central control room upper computer executes maintenance, support price calculating and store function, calculates and deposits
Storage content include: the instrument of central control room upper computer prompt, equipment checked, mantenance data, instrument, equipment inspection, maintenance are existing
Field data and key equipment carry out an inspection, maintenance;Sort out data according to technological design instrument, device model;Same model device
Maintenance/maintenance frequency accounting is lower than mean value 30%, and Central Control Room closes prompt facility;With model maintenance of equipment/maintenance frequency accounting
Higher than mean value 30%, Central Control Room starts prompt facility, and calculates maintenance maintenance price, while sending warning information to mobile phone terminal;
5.3) energy consumption controls: central control room upper computer executes equipment energy consumption calculation of price and store function;According to technological parameter equipment
Power, unit electricity rates set electricity consumption threshold value;When electricity consumption is in threshold range, Central Control Room closes prompt facility;When with
Electricity is more than threshold range, and Central Control Room starts prompt facility, and calculates energy consumption price, while sending warning information to mobile phone terminal;
5.4) personnel operate control: central control room upper computer operational staff information, personnel's operation information computing function;Personnel are believed
Breath, personnel's operation information are presented according to timing node sequence, and computing staff's expense;Specifying information is sent to mobile phone terminal simultaneously;
5.5) equipment depreciation controls: central control room upper computer executes technological design instrument, equipment depreciation data computing function;By instrument
Table, equipment depreciation are distributed according to timing node, and computing depreciation expense;Specifying information is sent to mobile phone terminal simultaneously;
5.6) totle drilling cost control: central control room upper computer execute operating cost calculate and store function, calculate content include: medicament,
Maintenance maintenance, energy consumption, personnel, depreciable cost data, while sending data to mobile phone terminal.
3. a kind of Industrial Wastewater Treatment control method based on intelligent data analysis according to claim 1, feature exist
In: the personnel control module completes following operating procedure:
6.1) personnel amount controls: when the spare number of intermediate node is then examined lower than 25% at the same time for personal information, personnel's operation information
Consider post complementation replacement;When personal information, personnel's operation information at the same time the spare number of intermediate node be 25%, then consider safeguard people
Member's flowing is stablized;When the spare number of intermediate node then considers transfer-position or sanction higher than 25% at the same time for personal information, personnel's operation information
Member;
6.2) personnel's efficiency controls: when timing node then considers post lower than 1:1 when 8 is small for personal information, personnel's operation information
Complementation replacement;When personal information, personnel's operation information when 8 is small timing node be 1:1, then consider maintenance personnel flow stablize;
When timing node then considers transfer-position or reduce the staff higher than 1:1 when 8 is small for personal information, personnel's operation information;
6.3) personnel safety controls: safeguard protection note function is set according to personal information, personnel's operation information, according to operation information
Put on record security protection operation information, safety prevention measure information;Information prompting function occurs for operational staff's safety accident, sends out simultaneously
Send data to mobile phone terminal
6.4) personnel's permission controls: central control room upper computer is to step 6.1) -6.3) execute audit, examination & approval function.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710068233.9A CN106774095B (en) | 2017-02-07 | 2017-02-07 | A kind of Industrial Wastewater Treatment control method and system based on intelligent data analysis |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710068233.9A CN106774095B (en) | 2017-02-07 | 2017-02-07 | A kind of Industrial Wastewater Treatment control method and system based on intelligent data analysis |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106774095A CN106774095A (en) | 2017-05-31 |
CN106774095B true CN106774095B (en) | 2019-07-30 |
Family
ID=58955371
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710068233.9A Active CN106774095B (en) | 2017-02-07 | 2017-02-07 | A kind of Industrial Wastewater Treatment control method and system based on intelligent data analysis |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106774095B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110862179A (en) * | 2019-12-19 | 2020-03-06 | 锦科绿色科技(苏州)有限公司 | Water treatment system and control workstation |
CN112062325B (en) * | 2020-08-04 | 2023-04-18 | 湖南大唐先一科技有限公司 | Unit operation cost statistical method and device of chemical demineralized water treatment system |
CN114708116A (en) * | 2022-03-11 | 2022-07-05 | 哈尔滨圣昌科技开发有限公司 | Pipe network monitoring intelligent processing system |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100609073B1 (en) * | 2002-03-19 | 2006-08-04 | 영남대학교 산학협력단 | Remote monitoring and control system for waste water treatment facility |
CN102381819A (en) * | 2011-11-08 | 2012-03-21 | 河南省化工研究所有限责任公司 | Industrial wastewater treatment device |
CN105278486A (en) * | 2014-07-20 | 2016-01-27 | 牛玉东 | System and method of remote environmental protection sewage discharge monitoring |
CN205139659U (en) * | 2015-11-06 | 2016-04-06 | 武汉新天达美环境科技有限公司 | Sewage treatment system based on thing networking |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20100332149A1 (en) * | 1998-12-17 | 2010-12-30 | Hach Company | Method and system for remote monitoring of fluid quality and treatment |
US6845336B2 (en) * | 2002-06-25 | 2005-01-18 | Prasad S. Kodukula | Water treatment monitoring system |
CN201148388Y (en) * | 2008-01-15 | 2008-11-12 | 贵州绿色环保设备工程有限责任公司 | Methanol production waste water treatment apparatus |
CN201825745U (en) * | 2010-05-18 | 2011-05-11 | 宇星科技发展(深圳)有限公司 | On-line automatic control system for sewage treatment medicament |
-
2017
- 2017-02-07 CN CN201710068233.9A patent/CN106774095B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100609073B1 (en) * | 2002-03-19 | 2006-08-04 | 영남대학교 산학협력단 | Remote monitoring and control system for waste water treatment facility |
CN102381819A (en) * | 2011-11-08 | 2012-03-21 | 河南省化工研究所有限责任公司 | Industrial wastewater treatment device |
CN105278486A (en) * | 2014-07-20 | 2016-01-27 | 牛玉东 | System and method of remote environmental protection sewage discharge monitoring |
CN205139659U (en) * | 2015-11-06 | 2016-04-06 | 武汉新天达美环境科技有限公司 | Sewage treatment system based on thing networking |
Non-Patent Citations (1)
Title |
---|
水环境智慧监测服务系统设计与实现;卢亚楠;《中国优秀硕士学位论文全文数据库 工程科技Ⅰ辑(月刊)》;20150515(第05期);B027-430:P80 |
Also Published As
Publication number | Publication date |
---|---|
CN106774095A (en) | 2017-05-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106774095B (en) | A kind of Industrial Wastewater Treatment control method and system based on intelligent data analysis | |
CN105800755A (en) | Water quality online monitoring system and method of wastewater coagulation treatment unit | |
CN105974829B (en) | A kind of intelligence adapter sewage control method | |
CN107355688A (en) | A kind of LeakView urban water supplies pipe network model Control management system | |
CN203101366U (en) | Online water quality detecting device and online water quality monitoring system for water supplying network | |
CN109064048A (en) | Quickly check method and system in discharge of wastewater source based on wastewater treatment process analysis | |
Liu et al. | Optimal locations of monitoring stations in water distribution systems under multiple demand patterns: a flaw of demand coverage method and modification | |
Benedetti et al. | Assessment of WWTP design and upgrade options: balancing costs and risks of standards' exceedance | |
CN102230577B (en) | Comprehensive water quality simulation test system for quasi-closed circulation pipe network | |
Liu et al. | Current progress of environmental risk assessment research | |
CN203849606U (en) | Enterprise rainwater discharge outlet monitoring system | |
CN117571947A (en) | River and lake water quality and blue algae early warning method based on Hartee | |
Propato et al. | A sensor location model to detect contaminations in water distribution networks | |
Ostfeld | A review of modeling water quality in distribution systems | |
CN205501009U (en) | Modular wash waste liquid chlorine residue that disappears and get rid of system | |
CN206610342U (en) | Blowdown license management system | |
Grayman | A quarter of a century of water quality modeling in distribution systems | |
CN205563162U (en) | Sewage control system is taken over to intelligence | |
CN208780823U (en) | A kind of water body radioactivity real time on-line monitoring system | |
Nazarovs et al. | Modelling water quality in drinking water distribution networks from real-time direction data | |
CN110955962A (en) | Method for determining dilution diffusion control requirements for liquid effluent discharge | |
Wert et al. | Real-time modeling of trihalomethane formation in a full-scale distribution system | |
KR101365004B1 (en) | Total maintenance system of purifier facility | |
CN109754887A (en) | The method and its system of the processing of nuclear power station radioactive liquid waste are carried out using adsorbent material | |
CN203720618U (en) | A water inlet assessment processing control system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |