CN106774095A - A kind of Industrial Wastewater Treatment control method and system based on intelligent data analysis - Google Patents

A kind of Industrial Wastewater Treatment control method and system based on intelligent data analysis Download PDF

Info

Publication number
CN106774095A
CN106774095A CN201710068233.9A CN201710068233A CN106774095A CN 106774095 A CN106774095 A CN 106774095A CN 201710068233 A CN201710068233 A CN 201710068233A CN 106774095 A CN106774095 A CN 106774095A
Authority
CN
China
Prior art keywords
water
central control
control room
upper computer
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710068233.9A
Other languages
Chinese (zh)
Other versions
CN106774095B (en
Inventor
康伟
方芳
李守东
姜宁
梁猛
孙巍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Easy Voight Technology Co Ltd
Original Assignee
Beijing Easy Voight Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Easy Voight Technology Co Ltd filed Critical Beijing Easy Voight Technology Co Ltd
Priority to CN201710068233.9A priority Critical patent/CN106774095B/en
Publication of CN106774095A publication Critical patent/CN106774095A/en
Application granted granted Critical
Publication of CN106774095B publication Critical patent/CN106774095B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/04Programme control other than numerical control, i.e. in sequence controllers or logic controllers
    • G05B19/048Monitoring; Safety

Abstract

The present invention provides a kind of Industrial Wastewater Treatment control system based on intelligent data analysis and runs on method in the system, it includes central control room upper computer, process control modules, operating cost control module, personnel control module are provided with central control room upper computer, it is respectively used to be controlled technique, operating cost and personnel, information can also be carried out data transmission by the form of wireless network and mobile phone terminal in central control room upper computer, mobile phone terminal performs early warning function, performs the typing of work order operation information and function is presented in, data results;The system integrates technique, cost, personnel's intelligentized control method, by the Industrial Wastewater Treatment control method of service data intellectual analysis, comprehensively timely industrial wastewater treatment system all-around intelligentization control, realize industrial wastewater treatment system stable operation, cost reduction, personnel it is efficient.

Description

A kind of Industrial Wastewater Treatment control method and system based on intelligent data analysis
Technical field
The present invention relates to field of industrial waste water treatment, more particularly to a kind of Industrial Wastewater Treatment based on intelligent data analysis Control method and system.
Background technology
Industrial Wastewater Treatment as wisdom construction of environmental protection important component, be to ensure that wisdom environmental protection policy is conscientiously real Apply, the more efficient key link of Internet of Things.《State Council is on actively pushing forward the instruction that " internet+" takes action》(2015- 2018) issue, shows to accelerate the generation information communication technology and industrial depth integration, from technology path, Industry Model, policy Ensure etc. that comprehensive refinement ecosystem is built, it has also become China's industry development it is leading.In January, 2016《" internet+" green Ecological 3 years action embodiments》Further explicitly point out, to greatly develop wisdom environmental protection, give full play to internet in reverse thing Platform action in stream recovery system, improves facilitation, interactive, transparence that regenerated resources transaction is utilized.According to Industry Waste Water process feature, builds the control system that can be docked with wisdom environmental protection internet platform, realizes that Industrial Wastewater Treatment upgrading turns Type is imperative.
Industrial wastewater is to cause environmental pollution, particularly the major reason of water pollution.Industrial wastewater complicated component, pollution Thing concentration is high and strong toxicity, intractability big, and the pollutant of unprocessed or below standard discharge is easy to migration and variation, to environment The harm that causes is big, effect persistently, it is difficult to recover in the short time.Therefore, control of the Industrial Wastewater Treatment from technique, cost and personnel System all possesses its particularity.Process aspect:Because industrial wastewater pollution thing concentration is high, the fluctuation of strong toxicity, water quality and quantity is notable, useless Water process difficulty is big, causes the technique for treating industrial wastewater system situation that is hit easily to send out, impact that the chain effect for causing is notable, receive System repair time is long after impact.Cost aspect:Industrial wastewater toxic organic pollutant concentration is higher, expends pharmaceutical quantities larger. To ensure meet the requirement of environmental protection, joined using the measure of the multistep treatment such as pretreatment, biochemical treatment, advanced treating and Treatment for Reuse With, it is method that Industrial Wastewater Treatment is generally used, equipment is more, dosage point is more, but each unit Inlet and outlet water water quality, water, sets Standby, dispensing lacks feedback mechanism, and this results in energy consumption, reagent consumption significantly, and operating cost occupies high not low.Personnel's aspect:Existing rank Section is patrolled and examined, repaired, detecting still human beings by scene, but the professional weak, target of Field Force is indefinite, information transfer is poorly efficient, Data analysis capabilities are weak, cause technique management and control to rely on experience, delayed strong;In addition, improving phenols, the cyaniding contained in industrial wastewater The toxicants such as thing, biphenyl, chloride, heavy metal are the principal elements for threatening Field Force's health.
At present, the sewage treatment control system developed is poor in the specific aim of field of industrial waste water treatment, is not suitable for work The intelligentized control method of industry wastewater treatment;Meanwhile, most of sewage treatment control system is only limitted to information, monitor in real time, lacks Weary data analysis, module interaction, cause control system intelligence degree low.
The content of the invention
Industrial Wastewater Treatment control and intelligence are not suitable for it present invention aim to address current sewage treatment control system Change the problem of low degree, propose a kind of Industrial Wastewater Treatment control system based on intelligent data analysis.
Concrete technical scheme is as follows:
A kind of Industrial Wastewater Treatment control system based on intelligent data analysis, including following part:
Central control room upper computer, is internally provided with process control modules, operating cost control module, personnel control module, point Technique, operating cost and personnel Yong Yu be controlled and alarmed;
Mobile phone terminal, for being carried out data transmission by way of wireless network with central control room upper computer;Executable early warning Function, execution work order operation information typing and data results are presented function;Perform prompting, check/safeguard/maintenance work order group Send and complete information feedback function.Operating right is defined with each post concrete power limit detailed rules and regulations in waste water treatment plant;
Technique for treating industrial wastewater system, is inside provided with online monitoring instrument, and central control room upper computer can be set by control command On-line checking instrument parameter is put, and reads online monitoring instrument monitoring result.
Further, the technique for treating industrial wastewater system includes treatment unit for waste water, treatment unit for waste water connection There are inlet channel and outlet conduit, be provided with online monitoring instrument in water inlet, outlet conduit, on-line computing model on inlet channel Table rear end is respectively provided with On-line Control front end valve, rear end valve;Crossing pipeline is set before the valve of On-line Control front end, across pipe Road and accident pool, scratch pool UNICOM;On-line Control is set on crossing pipeline and crosses over valve;Treatment unit for waste water is also associated with dispensing Equipment, steam heater, air blower;The central control room upper computer gathers the data of online monitoring instrument, and according to data control The switch of respective valves and equipment.
Further, the online monitoring instrument includes water flowmeter and measurement COD, NH3The water of-N, pH, temperature etc. Sensor is surveyed in quality supervision.
A kind of method in Industrial Wastewater Treatment control system run on based on intelligent data analysis, the technology controlling and process Module completes following operating procedure:
4.1) influent quality, water rate control:In each treatment unit for waste water inlet channel, crucial water quality (such as COD, NH are set3- N, pH, temperature), water (such as flowmeter) online monitoring instrument, the online monitoring instrument of inlet channel connects with central control room upper computer Connect, according to processing parameter setting online monitoring instrument threshold value, data are transmitted to central control room upper computer by online monitoring instrument, in Control room host computer performs data and calculates and store function to online monitoring instrument real time data.When influent quality, water are in setting In threshold range, inlet channel go forward end valve door, rear end valve be in opening, on crossing pipeline across valve be in close Closed state;When influent quality, water exceed given threshold, central control room upper computer automatic closes inlet channel front end valve work( Can, valve function is crossed over while starting and opening crossing pipeline, realize that superthreshold waste water enters the function of accident pool or scratch pool;When Influent quality, water exceed given threshold, and Central Control Room automatic closes inlet channel rear end valve function, at the same open across More after pipeline aerial crossing valve function, online monitoring instrument continues to show that influent quality, water exceed given threshold, then start immediately Inlet channel front end valve function is closed, realizes that superthreshold waste water enters the function of accident pool or scratch pool, central control room upper computer Prompt message is sent to check instrument, equipment, repair to mobile phone terminal, early warning and prompting;Set on accident pool, scratch pool pipeline Put return valve, and be connected with central control room upper computer, online monitoring instrument numerical value recover threshold range when, perform accident pool, temporarily Pond return valve open function is deposited, superthreshold waste water flows back according to inflow 1-3% in accident pool scratch pool;
4.2) effluent quality, water rate control:The online monitoring instrument of outlet conduit is connected with central control room upper computer, according to work Skill parameter setting online monitoring instrument threshold value;When effluent quality is in threshold range, on-line checking instrument control effluent quality is steady Fixed operation;When effluent quality exceedes threshold range, Central Control Room starting device adjusting function starts administration apparatus, works as effluent quality Return to when in threshold range, regulation and control terminate;When effluent quality exceed threshold range, Central Control Room starting device adjusting function, The continuously display effluent quality of line measuring instrument exceed given threshold duration >=12h, then central control room upper computer send prompt message to Mobile phone terminal, early warning and prompting are checked instrument, equipment, repaired;
4.3) early warning control:Technique real-time early warning, prediction and warning module are additionally provided with the process control modules;Middle control Room host computer performs data storage function to online monitoring instrument real time data, and data storage real-time Transmission is pre- in real time to technique Alert, prediction and warning module;The technique real-time early warning module is used to exceed online when water inlet water quality, water and delivery port water quality During measuring instrument threshold value, early warning is carried out in central control room upper computer and mobile phone terminal, at the same central control room upper computer perform respectively into Water, the water of water outlet, Water-quality control step;The prediction and warning module is used to gather water inlet water quality, water and water outlet saliva Matter, according to process design parameter, by built-in mathematical model prediction effluent quality, water, supervises when predicting the outcome more than online When surveying instrument threshold value, early warning is carried out in central control room upper computer and mobile phone terminal, while central control room upper computer performs the water of water outlet Amount, Water-quality control step.
Further, the operating cost control module completes following operating procedure:
5.1) medicament control:Central control room upper computer performs data to online monitoring instrument real time data and calculates and storage work( Can, by water yield, added amount of chemical, medicament calculation of price and output unit water medicament price;And go out treatment unit for waste water Water, added amount of chemical, medicament price, unit water medicament price are presented according to timing node order;Set according to technological parameter Determine added amount of chemical, unit water medicament price thresholds;When added amount of chemical, unit water medicament valency are in threshold range, in Prompt facility is closed in control room;When added amount of chemical, unit water medicament valency exceed threshold range, Central Control Room starts prompt facility; Medicament price is calculated simultaneously, sends early warning information to mobile phone terminal;
5.2) maintenance maintenance cost control:Central control room upper computer performs maintenance, support price and calculates and store function, calculates And storage content includes:The instrument of central control room upper computer prompting, equipment are checked, mantenance data, instrument, equipment inspection, dimension Field data is repaiied, and key equipment carries out an inspection, safeguards;Data are sorted out according to technological design instrument, unit type;Same model Maintenance of equipment/safeguard frequency accounting less than average 30%, Central Control Room closes prompt facility;Same model maintenance of equipment/safeguard frequency Accounting is higher than average 30%, and Central Control Room starts prompt facility, and calculates maintenance maintenance price, while sending early warning information to mobile phone End:
5.3) energy consumption control:Central control room upper computer performs equipment energy consumption calculation of price and store function;According to technological parameter Plant capacity, unit electricity rates setting power consumption threshold value;When power consumption is in threshold range, Central Control Room closes prompt facility; When medicinal electricity exceedes threshold range, Central Control Room starts prompt facility, and calculates energy consumption price, while sending early warning information to hand Generator terminal;
5.4) human users' control:Central control room upper computer operational staff information, human users' information computing function.By personnel Information, human users' information are presented according to timing node order, and computing staff's expense;Specifying information is sent simultaneously to mobile phone End;
5.5) equipment depreciation control:Central control room upper computer performs technological design instrument, equipment depreciation data computing function;Will Instrument, equipment depreciation are distributed according to timing node, and computing depreciation expense;Specifying information is sent simultaneously to mobile phone terminal;
5.6) totle drilling cost control:Central control room upper computer performs operating cost and calculates and store function, and calculating content includes:Medicine Agent, maintenance maintenance, energy consumption, personnel, depreciable cost data, while sending data to mobile phone terminal.
Further, the personnel control module completes following operating procedure:
6.1) personnel amount control:When personal information, human users' information, the standby number of intermediate node is less than 25% at the same time, Then consider that post is complementary to replace;When personal information, human users' information, the standby number of intermediate node is 25% at the same time, then consider dimension Shield flow of personnel stabilization;When personal information, human users' information, the standby number of intermediate node is higher than 25% at the same time, then consider transfer-position Or reduce the staff:
6.2) personnel's efficiency control:When personal information, human users' information are less than 1: 1 in 8 hours nodes, then consider Post is complementary to replace;When personal information, human users' information are 1: 1 in 8 hours nodes, then consider that attendant's flowing is steady It is fixed;When personal information, human users' information are higher than 1: 1 in 8 hours nodes, then consider transfer-position or reduce the staff;
6.3) personal security control:Safeguard protection note function is set according to personal information, human users' information, according to operation Information is put on record security protection operation information, safety prevention measure information;There is information prompting function in operational staff's security incident, together When send data to mobile phone terminal
6.4) personnel's control of authority:Central control room upper computer is to above-mentioned steps 6.1) -6.3) perform examination & verification, examination & approval function.
The beneficial effects of the present invention are:The application in central control room upper computer by being provided with process control modules, fortune Row cost control module, personnel control module, are respectively used to be controlled technique, operating cost and personnel, and Central Control Room is upper Information can also be carried out data transmission by the form of wireless network and mobile phone terminal in machine, and mobile phone terminal performs early warning function, be performed The typing of work order operation information is presented function in, data results;The system collects technique, cost, personnel's intelligentized control method in one Body, comprehensively timely industrial wastewater treatment system all-around intelligentization control, realize Waste Water Treatment stable operation, into This reduction, personnel are efficient.
Simultaneously for industrial wastewater pollution thing concentration is high, the fluctuation of strong toxicity, water quality and quantity significantly, the big spy of wastewater treatment difficulty Point, by using the system, can improve the resistance to multiple impact of industrial wastewater system, and when significantly improving system after impact and repairing Between;And by the multistage linking treatment measures such as the pretreatment of links, biochemical treatment, advanced treating and Treatment for Reuse, Reducing energy consumption and reagent consumption, reduce cost and pollution on the environment;Patrolled and examined finally by control system raising scene, tieed up Operating efficiency and safe operation are repaiied and detected, the professional of control, information transfer and analysis ability is improve and is significantly improved, and Make one away from the noxious material influence in wastewater treatment process.
Brief description of the drawings
The present invention is described in further detail with reference to accompanying drawing:
Fig. 1 is the application system global structure block diagram;
Fig. 2 is the structured flowchart of process control process in the application;
Fig. 3 is the structured flowchart of operating cost control flow in the application;
Fig. 4 is the structured flowchart of personnel control flow in the application;
Specific embodiment
Below by preferred embodiment shown with reference to the accompanying drawings, the present invention is explained in detail, but the invention is not restricted to The embodiment.
With reference to accompanying drawing 1-4, the technical program is introduced:
The primary focus of the application are that technology controlling and process, the fortune to whole processing procedure are realized by central control room upper computer Row cost control, personnel control, realize being controlled technique, operating cost and personnel respectively, information in central control room upper computer Can also be carried out data transmission by the form of wireless network and mobile phone terminal, mobile phone terminal performs early warning function, perform work order operation Data Enter is presented function in, data results;The system integrates technique, cost, personnel's intelligentized control method, Quan Mianji When industrial wastewater treatment system all-around intelligentization control.
Technology controlling and process:Central control room upper computer setting influent quality, water threshold value, setting each unit inside critical operational parameters Threshold value, performs online monitoring instrument data, account data, the early warning and alert function of model, control each unit influent quality, water Amount, control each unit operation realizes that central control room upper computer realizes control industrial wastewater high concentration, toxic pollutant, water quality and quantity Fluctuation, it is to avoid waste water treatment process system is impacted;Each unit can be separated under realizing impact condition, it is to avoid impact causes chain Effect;Each unit be can be separated under realizing impact condition, shorten system repair time after being hit, and it is comprised the following steps that:
1) influent quality, water rate control:The online monitoring instrument of inlet channel is connected with central control room upper computer, according to technique Parameter setting online monitoring instrument threshold value;When influent quality, water are in the range of given threshold, inlet channel go forward end valve door, Rear end valve is in opening, is closed across valve on crossing pipeline;When influent quality, water exceed setting Threshold value, central control room upper computer automatic closes inlet channel front end valve function, and valve is crossed over while starting and opening crossing pipeline Door function, realizes that superthreshold waste water enters the function of accident pool or scratch pool;When influent quality, water exceed given threshold, and Central Control Room automatic closes inlet channel rear end valve function, while after unlatching crossing pipeline crosses over valve function, online prison Survey instrument to continue to show that influent quality, water exceed given threshold, then start immediately and close inlet channel front end valve function, it is real Existing superthreshold waste water enters the function of accident pool or scratch pool, and central control room upper computer sends prompt message to mobile phone terminal, and early warning is simultaneously Prompting is checked instrument, equipment, repaired;Return valve, and and central control room upper computer are set on accident pool, scratch pool pipeline Connection, when online monitoring instrument numerical value recovers threshold range, performs accident pool, scratch pool return valve open function, accident pool Superthreshold waste water flows back according to inflow 5% in scratch pool;
2) effluent quality, water rate control:The online monitoring instrument of outlet conduit is connected with central control room upper computer, according to technique Parameter setting online monitoring instrument threshold value;When effluent quality is in threshold range, on-line checking instrument control stable effluent quality Operation;When effluent quality exceedes threshold range, Central Control Room starting device adjusting function starts administration apparatus, when effluent quality is extensive When again in threshold range, regulation and control terminate;When effluent quality exceed threshold range, Central Control Room starting device adjusting function, online The continuously display effluent quality of measuring instrument exceedes given threshold duration >=12h, then central control room upper computer sends prompt message to hand Generator terminal, early warning and prompting are checked instrument, equipment, repaired;
3) early warning control:Technique real-time early warning, prediction and warning module are additionally provided with the process control modules;Central Control Room Host computer to online monitoring instrument real time data perform data storage function, data storage real-time Transmission to technique real-time early warning, Prediction and warning module;The technique real-time early warning module is used to exceed online prison when water inlet water quality, water and delivery port water quality Survey instrument threshold value when, carry out early warning in central control room upper computer and mobile phone terminal, at the same central control room upper computer perform respectively water inlet, The water of water outlet, Water-quality control step;The prediction and warning module is used to gather water inlet water quality, water and delivery port water quality, According to process design parameter, by built-in mathematical model prediction effluent quality, water, when predicting the outcome more than on-line computing model During table threshold value, early warning is carried out in central control room upper computer and mobile phone terminal, while central control room upper computer performs water, the water of water outlet Matter rate-determining steps, it is comprised the following steps that:
Operating cost is controlled:Central control room upper computer setting influent quality, water threshold value, the crucial operation in setting each unit inside Parameter threshold, performs influent quality, water, unit inside key parameter control device added amount of chemical function, performs treatment water Amount, added amount of chemical, medicament price, unit water medicament calculation of price function, realize dosage control, realize reagent cost control System.
Central control room upper computer setting influent quality, water threshold value, setting each unit inside critical operational parameters threshold value, perform Key parameter control instrument, equipment inspection, maintenance, repair function inside influent quality, water, unit, perform maintenance, safeguard valency Lattice are calculated and store function, realize maintenance, maintenance cost control.Central control room upper computer setting influent quality, water threshold value, setting Each unit inside critical operational parameters threshold value, performs influent quality, water, unit inside key parameter control device operation work( Can, equipment energy consumption calculation of price and store function are performed, realize energy consumption control.
Central control room upper computer operational staff information, human users' information computing function, by personal information, human users' information Presented according to timing node order, realize that information carries out data biography by the form of wireless network with mobile phone terminal in central control room upper computer It is defeated, perform early warning, check/repair that information feedback function is sent and completed to work order with charge free, human users' control is realized, specifically include Following steps:
1) medicament control:Central control room upper computer performs data and calculates and store function to online monitoring instrument real time data, By water yield, added amount of chemical, medicament calculation of price and output unit water medicament price;And by treatment unit for waste water water outlet Amount, added amount of chemical, medicament price, unit water medicament price are presented according to timing node order;According to processing parameter setting Added amount of chemical, unit water medicament price thresholds;When added amount of chemical, unit water medicament valency are in threshold range, middle control Prompt facility is closed in room;When added amount of chemical, unit water medicament valency exceed threshold range, Central Control Room starts prompt facility;Together When calculate medicament price, send early warning information to mobile phone terminal;
2) maintenance maintenance cost control:Central control room upper computer perform maintenance, support price calculate and store function, calculate and Storage content includes:The instrument of central control room upper computer prompting, equipment are checked, mantenance data, instrument, equipment inspection, maintenance Field data, and key equipment carries out an inspection, safeguards;Data are sorted out according to technological design instrument, unit type;Same model sets Standby to repair/safeguard frequency accounting less than average 30%, Central Control Room closes prompt facility;Same model maintenance of equipment/safeguard that frequency is accounted for Than higher than average 30%, Central Control Room starts prompt facility, and calculates maintenance maintenance price, while sending early warning information to mobile phone End;
3) energy consumption control:Central control room upper computer performs equipment energy consumption calculation of price and store function;Set according to technological parameter Standby power, unit electricity rates setting power consumption threshold value;When power consumption is in threshold range, Central Control Room closes prompt facility;When Medicinal electricity exceedes threshold range, and Central Control Room starts prompt facility, and calculates energy consumption price, while sending early warning information to mobile phone End;
4) human users' control:Central control room upper computer operational staff information, human users' information computing function.Personnel are believed Breath, human users' information are presented according to timing node order, and computing staff's expense;Specifying information is sent simultaneously to mobile phone terminal;
5) equipment depreciation control:Central control room upper computer performs technological design instrument, equipment depreciation data computing function;By instrument Table, equipment depreciation are distributed according to timing node, and computing depreciation expense;Specifying information is sent simultaneously to mobile phone terminal;
6) totle drilling cost control:Central control room upper computer performs operating cost and calculates and store function, and calculating content includes:Medicine Agent, maintenance maintenance, energy consumption, personnel, depreciable cost data, while sending data to mobile phone terminal.
Personnel control:Central control room upper computer operational staff information, human users' information, safety operation information computing function, The complementary replacement in operational staff post, attendant's flowing stabilization, transfer-position or analytic function of reducing the staff, operational staff's security incident occur Information prompting function.Personnel amount, personnel's efficiency, personal security, the control function of personnel's authority are realized, its specific steps is such as Under:
1) personnel amount control:When personal information, human users' information, the standby number of intermediate node is less than 25% at the same time, then Consider that post is complementary to replace;When personal information, human users' information, the standby number of intermediate node is 25% at the same time, then consider to safeguard Flow of personnel stabilization;When personal information, human users' information at the same time the standby number of intermediate node be higher than 25%, then consider transfer-position or Reduce the staff;
2) personnel's efficiency control:When personal information, human users' information are less than 1: 1 in 8 hours nodes, then hilllock is considered Position is complementary to replace;When personal information, human users' information are 1: 1 in 8 hours nodes, then consider that attendant's flowing is steady It is fixed;When personal information, human users' information are higher than 1: 1 in 8 hours nodes, then consider transfer-position or reduce the staff;
3) personal security control:Safeguard protection note function is set according to personal information, human users' information, is believed according to operation Cease put on record security protection operation information, safety prevention measure information;There is information prompting function in operational staff's security incident, while Send data to mobile phone terminal
4) personnel's control of authority:Central control room upper computer is to above-mentioned steps 6.1) -6.3) perform examination & verification, examination & approval function.
To sum up, using invention provide the Industrial Wastewater Treatment control system based on intelligent data analysis, integrated technique, into Originally, in one, the timely all-around intelligentization control of industrial wastewater treatment system, realizes waste water to personnel's intelligentized control method comprehensively The stable operation of processing system, cost reduction, personnel are efficient.

Claims (6)

1. a kind of Industrial Wastewater Treatment control system based on intelligent data analysis, it is characterised in that:
Including following part:
Central control room upper computer, is internally provided with process control modules, operating cost control module, personnel control module, uses respectively In technique, operating cost and personnel are controlled and are alarmed;
Mobile phone terminal, for being carried out data transmission by way of wireless network with central control room upper computer;Executable early warning function, Perform the typing of work order operation information and data results are presented function;Perform prompting, check/safeguard/maintenance work order send with charge free and Complete information feedback function;Operating right is defined by each post authority detailed rules and regulations in waste water treatment plant;
Technique for treating industrial wastewater system, is inside provided with online monitoring instrument, and central control room upper computer can be arranged on by control command Line instrumentation parameter, and read online monitoring instrument monitoring result.
2. the Industrial Wastewater Treatment control system based on intelligent data analysis according to claim 1, it is characterised in that:Institute Stating technique for treating industrial wastewater system includes treatment unit for waste water, and the treatment unit for waste water is connected with inlet channel and outlet pipe Road, online monitoring instrument is provided with water inlet, outlet conduit, and online monitoring instrument rear end is respectively provided with online on inlet channel Control front end valve, rear end valve;Crossing pipeline, crossing pipeline and accident pool, scratch pool are set before the valve of On-line Control front end UNICOM;On-line Control is set on crossing pipeline and crosses over valve;Treatment unit for waste water be also associated with administration apparatus, steam heater, Air blower;The central control room upper computer gathers the data of online monitoring instrument, and controls respective valves and equipment according to data Switch.
3. the Industrial Wastewater Treatment control system based on intelligent data analysis according to claim 2, it is characterised in that:Institute Stating online monitoring instrument includes water flowmeter and measurement COD, NH3-N, pH, the water quality monitoring sensor of temperature.
4. a kind of Industrial Wastewater Treatment control method based on intelligent data analysis, it is by any institutes of such as claim 1-3 Run in the Industrial Wastewater Treatment control system based on intelligent data analysis stated, it is characterised in that:The process control modules Complete following operating procedure:
4.1) influent quality, water rate control:In each treatment unit for waste water inlet channel, water quality monitoring sensor and water stream are set Two kinds of online monitoring instruments of gauge, the online monitoring instrument of inlet channel is connected with central control room upper computer, is set according to technological parameter Determine online monitoring instrument threshold value, data are transmitted to central control room upper computer by online monitoring instrument, and central control room upper computer is to online Measuring instrument real time data performs data and calculates and store function;When influent quality, water are in the range of given threshold, water inlet pipe Road go forward end valve door, rear end valve be in opening, be closed across valve on crossing pipeline;When water inlet water Matter, water exceed given threshold, and central control room upper computer automatic closes inlet channel front end valve function, while start opening Crossing pipeline crosses over valve function, realizes that superthreshold waste water enters the function of accident pool or scratch pool;When influent quality, water surpass Given threshold is crossed, and Central Control Room automatic closes inlet channel rear end valve function, while opening crossing pipeline crosses over valve After function, online monitoring instrument continues to show that influent quality, water exceed given threshold, then start immediately before closing inlet channel End valve function, realizes that superthreshold waste water enters the function of accident pool or scratch pool, central control room upper computer send prompt message to Mobile phone terminal, early warning and prompting are checked instrument, equipment, repaired;Return valve is set on accident pool, scratch pool pipeline, and It is connected with central control room upper computer, when online monitoring instrument numerical value recovers threshold range, performs accident pool, scratch pool return valve and open Function is opened, superthreshold waste water flows back according to inflow 1-3% in accident pool scratch pool;
4.2) effluent quality, water rate control:The online monitoring instrument of outlet conduit is connected with central control room upper computer, is joined according to technique Number setting online monitoring instrument threshold value;When effluent quality is in threshold range, on-line checking instrument control stable effluent quality fortune OK;When effluent quality exceedes threshold range, Central Control Room starting device adjusting function starts administration apparatus, when effluent quality recovers When in threshold range, regulation and control terminate;When effluent quality exceedes threshold range, Central Control Room starting device adjusting function, online prison Survey the continuously display effluent quality of instrument and exceed given threshold duration >=12h, then central control room upper computer sends prompt message to mobile phone End, early warning and prompting are checked instrument, equipment, repaired;
4.3) early warning control:Technique real-time early warning, prediction and warning module are additionally provided with the process control modules;On Central Control Room Position machine performs data storage function to online monitoring instrument real time data, data storage real-time Transmission to technique real-time early warning, pre- Survey warning module;The technique real-time early warning module is used to exceed on-line monitoring when water inlet water quality, water and delivery port water quality During instrument threshold value, early warning is carried out in central control room upper computer and mobile phone terminal, while central control room upper computer performs water inlet, goes out respectively The water of water, Water-quality control step;The prediction and warning module is used to gather water inlet water quality, water and delivery port water quality, root According to process design parameter, by built-in mathematical model prediction effluent quality, water, when predicting the outcome more than online monitoring instrument During threshold value, early warning is carried out in central control room upper computer and mobile phone terminal, while central control room upper computer performs water, the water quality of water outlet Rate-determining steps.
5. a kind of Industrial Wastewater Treatment control method based on intelligent data analysis according to claim 4, its feature exists In:The operating cost control module completes following operating procedure:
5.1) medicament control:Central control room upper computer performs data and calculates and store function to online monitoring instrument real time data, will Water yield, added amount of chemical, medicament calculation of price and output unit water medicament price;And by treatment unit for waste water water yield, Added amount of chemical, medicament price, unit water medicament price are presented according to timing node order;According to processing parameter setting medicament Dosage, unit water medicament price thresholds;When added amount of chemical, unit water medicament valency are in threshold range, Central Control Room is closed Close prompt facility;When added amount of chemical, unit water medicament valency exceed threshold range, Central Control Room starts prompt facility;Count simultaneously Medicament price is calculated, early warning information is sent to mobile phone terminal;
5.2) maintenance maintenance cost control:Central control room upper computer performs maintenance, support price and calculates and store function, calculates and deposits Storage content includes:The instrument of central control room upper computer prompting, equipment are checked, mantenance data, and instrument, equipment inspection, maintenance are existing Field data, and key equipment carries out an inspection, safeguards;Data are sorted out according to technological design instrument, unit type;Same model equipment Frequency accounting is repaired/safeguarded less than average 30%, Central Control Room closes prompt facility;Same model maintenance of equipment/safeguard frequency accounting Higher than average 30%, Central Control Room starts prompt facility, and calculates maintenance maintenance price, while sending early warning information to mobile phone terminal;
5.3) energy consumption control:Central control room upper computer performs equipment energy consumption calculation of price and store function;According to technological parameter equipment Power, unit electricity rates setting power consumption threshold value;When power consumption is in threshold range, Central Control Room closes prompt facility;Work as medicine Power consumption exceedes threshold range, and Central Control Room starts prompt facility, and calculates energy consumption price, while sending early warning information to mobile phone End;
5.4) human users' control:Central control room upper computer operational staff information, human users' information computing function;Personnel are believed Breath, human users' information are presented according to timing node order, and computing staff's expense;Specifying information is sent simultaneously to mobile phone terminal;
5.5) equipment depreciation control:Central control room upper computer performs technological design instrument, equipment depreciation data computing function;By instrument Table, equipment depreciation are distributed according to timing node, and computing depreciation expense;Specifying information is sent simultaneously to mobile phone terminal;
5.6) totle drilling cost control:Central control room upper computer performs operating cost and calculates and store function, and calculating content includes:Medicament, Maintenance maintenance, energy consumption, personnel, depreciable cost data, while sending data to mobile phone terminal.
6. a kind of Industrial Wastewater Treatment control method based on intelligent data analysis according to claim 4, its feature exists In:The personnel control module completes following operating procedure:
6.1) personnel amount control:When personal information, human users' information, the standby number of intermediate node is less than 25% at the same time, then examine Consider the complementary replacement in post;When personal information, human users' information, the standby number of intermediate node is 25% at the same time, then consider to safeguard people Member's flowing stabilization;When personal information, human users' information, the standby number of intermediate node is higher than 25% at the same time, then consider transfer-position or sanction Member;
6.2) personnel's efficiency control:When personal information, human users' information are less than 1: 1 in 8 hours nodes, then post is considered Complementation is replaced;When personal information, human users' information are 1: 1 in 8 hours nodes, then attendant's flowing stabilization is considered; When personal information, human users' information are higher than 1: 1 in 8 hours nodes, then consider transfer-position or reduce the staff;
6.3) personal security control:Safeguard protection note function is set according to personal information, human users' information, according to operation information Put on record security protection operation information, safety prevention measure information;There is information prompting function in operational staff's security incident, while hair Send data to mobile phone terminal
6.4) personnel's control of authority:Central control room upper computer is to step 6.1) -6.3) perform examination & verification, examination & approval function.
CN201710068233.9A 2017-02-07 2017-02-07 A kind of Industrial Wastewater Treatment control method and system based on intelligent data analysis Active CN106774095B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710068233.9A CN106774095B (en) 2017-02-07 2017-02-07 A kind of Industrial Wastewater Treatment control method and system based on intelligent data analysis

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710068233.9A CN106774095B (en) 2017-02-07 2017-02-07 A kind of Industrial Wastewater Treatment control method and system based on intelligent data analysis

Publications (2)

Publication Number Publication Date
CN106774095A true CN106774095A (en) 2017-05-31
CN106774095B CN106774095B (en) 2019-07-30

Family

ID=58955371

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710068233.9A Active CN106774095B (en) 2017-02-07 2017-02-07 A kind of Industrial Wastewater Treatment control method and system based on intelligent data analysis

Country Status (1)

Country Link
CN (1) CN106774095B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110862179A (en) * 2019-12-19 2020-03-06 锦科绿色科技(苏州)有限公司 Water treatment system and control workstation
CN112062325A (en) * 2020-08-04 2020-12-11 湖南大唐先一科技有限公司 Unit operation cost statistical method and device of chemical demineralized water treatment system

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030236649A1 (en) * 2002-06-25 2003-12-25 Kodukula Prasad S. Water treatment monitoring system
KR100609073B1 (en) * 2002-03-19 2006-08-04 영남대학교 산학협력단 Remote monitoring and control system for waste water treatment facility
CN201148388Y (en) * 2008-01-15 2008-11-12 贵州绿色环保设备工程有限责任公司 Methanol production waste water treatment apparatus
US20100332149A1 (en) * 1998-12-17 2010-12-30 Hach Company Method and system for remote monitoring of fluid quality and treatment
CN201825745U (en) * 2010-05-18 2011-05-11 宇星科技发展(深圳)有限公司 On-line automatic control system for sewage treatment medicament
CN102381819A (en) * 2011-11-08 2012-03-21 河南省化工研究所有限责任公司 Industrial wastewater treatment device
CN105278486A (en) * 2014-07-20 2016-01-27 牛玉东 System and method of remote environmental protection sewage discharge monitoring
CN205139659U (en) * 2015-11-06 2016-04-06 武汉新天达美环境科技有限公司 Sewage treatment system based on thing networking

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100332149A1 (en) * 1998-12-17 2010-12-30 Hach Company Method and system for remote monitoring of fluid quality and treatment
KR100609073B1 (en) * 2002-03-19 2006-08-04 영남대학교 산학협력단 Remote monitoring and control system for waste water treatment facility
US20030236649A1 (en) * 2002-06-25 2003-12-25 Kodukula Prasad S. Water treatment monitoring system
CN201148388Y (en) * 2008-01-15 2008-11-12 贵州绿色环保设备工程有限责任公司 Methanol production waste water treatment apparatus
CN201825745U (en) * 2010-05-18 2011-05-11 宇星科技发展(深圳)有限公司 On-line automatic control system for sewage treatment medicament
CN102381819A (en) * 2011-11-08 2012-03-21 河南省化工研究所有限责任公司 Industrial wastewater treatment device
CN105278486A (en) * 2014-07-20 2016-01-27 牛玉东 System and method of remote environmental protection sewage discharge monitoring
CN205139659U (en) * 2015-11-06 2016-04-06 武汉新天达美环境科技有限公司 Sewage treatment system based on thing networking

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘如意: "基于物联网技术的农村污水处理平台构建", 《物流工程与管理》 *
卢亚楠: "水环境智慧监测服务系统设计与实现", 《中国优秀硕士学位论文全文数据库 工程科技Ⅰ辑(月刊)》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110862179A (en) * 2019-12-19 2020-03-06 锦科绿色科技(苏州)有限公司 Water treatment system and control workstation
CN112062325A (en) * 2020-08-04 2020-12-11 湖南大唐先一科技有限公司 Unit operation cost statistical method and device of chemical demineralized water treatment system

Also Published As

Publication number Publication date
CN106774095B (en) 2019-07-30

Similar Documents

Publication Publication Date Title
CN105157756B (en) Control method and device are arranged in a kind of pollution sources anti-theft
Wei et al. Impact of dam construction on water quality and water self-purification capacity of the Lancang River, China
CN105800755A (en) Water quality online monitoring system and method of wastewater coagulation treatment unit
CN103645292B (en) A kind of water quality monitoring pretreatment unit and water quality monitoring system
CN106774095A (en) A kind of Industrial Wastewater Treatment control method and system based on intelligent data analysis
CN107192414A (en) A kind of method of industrial park waste water discharge intelligent monitoring and alarm
CN109928483A (en) It is a kind of based on intelligent algorithm automatically control secondary water-supply add chlorination system
CN105621766B (en) Combined type decontamination waste liquid chlorine residue removes system
CN102354381A (en) Dynamic prediction analysis technology of gas emission quantity in coal mine
CN213750347U (en) Test device for trapping radionuclide in aerosol
CN206610342U (en) Blowdown license management system
CN102507884B (en) Method for determining sampling time and proportion coefficient based on wastewater discharging proportion
CN208780823U (en) A kind of water body radioactivity real time on-line monitoring system
CN109928457B (en) A kind of secondary water-supply ultraviolet catalytic oxidation decontamination system of intelligent control
CN110955962B (en) Method for determining dilution diffusion control requirements for liquid effluent discharge
Herranz Pool scrubbing in unit 1 of fukushima daiichi
Nazarovs et al. Modelling water quality in drinking water distribution networks from real-time direction data
CN206741942U (en) A kind of passive hydrogen recombiner efficiency detection device of nuclear power plant
CN104637178A (en) Card swiping total sewage discharge amount control system and method
CN107390606B (en) Total pollutant emission control system monitored in whole process
CN105044761B (en) A kind of unattended radioactive pollution monitoring equipment
CN203663699U (en) Mounting structure of mass flow meter and wet typedesulfurization system of thermal power plant
CN103121765B (en) Water containing machine set of circulating water system
CN206002467U (en) A kind of sewage heavy metal on-line monitoring equipment based on XRF technology
CN217156497U (en) Miniature sewage detection station

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant