CN106761798B - A kind of large diameter shield tunnel face management system based on BIM - Google Patents

A kind of large diameter shield tunnel face management system based on BIM Download PDF

Info

Publication number
CN106761798B
CN106761798B CN201710025802.1A CN201710025802A CN106761798B CN 106761798 B CN106761798 B CN 106761798B CN 201710025802 A CN201710025802 A CN 201710025802A CN 106761798 B CN106761798 B CN 106761798B
Authority
CN
China
Prior art keywords
face
tunnel
management
pressure
bim
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710025802.1A
Other languages
Chinese (zh)
Other versions
CN106761798A (en
Inventor
张子新
殷彤
李佳宇
张帆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tongji University
Original Assignee
Tongji University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tongji University filed Critical Tongji University
Priority to CN201710025802.1A priority Critical patent/CN106761798B/en
Publication of CN106761798A publication Critical patent/CN106761798A/en
Application granted granted Critical
Publication of CN106761798B publication Critical patent/CN106761798B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The large diameter shield tunnel face management system based on BIM that the present invention relates to a kind of, it include: face management subsystem, according to project profile information, information-based modeling is carried out to large diameter shield tunnel using BIM technology, and area surface pressure is estimated, is arranged and corrected;Monitoring management subsystem carries out real time monitoring and early warning to the construction of large diameter shield tunnel, stores construction data, assess engineering construction, management condition, carries out document management.Compared with prior art, the present invention completes estimating and presetting for area surface pressure, while can be adjusted according to real-time monitoring result to preset pressure by classical face pressure pre-estimating theory in conjunction with BIM technology before excavation;Formation information, face pressure information, tunnel and ambient enviroment deformation information are all integrated into BIM model, realize the visual, controllable of entire work progress.

Description

A kind of large diameter shield tunnel face management system based on BIM
Technical field
The present invention relates to large diameter shield tunnel safe constructions, field of information management, in particular to a kind of based on the big of BIM Diameter shield tunnel face management system.
Background technique
The advantages that shield method is efficient with its, safe and environment-friendly, since the 1970s, is applied more and more widely In the key project constructions such as subway both domestic and external, urban water supply and sewerage, railway, highway, have become city tunnel driving at present One of major way.Although the development of shield method comparative maturity, under poor hydrogeologic condition, major diameter shield Structure face unstability still happens occasionally.In large-diameter shield work progress, establish shield driving parameter Real-time Feedback, adjust It is all particularly significant for risk assessment and construction safety control correctly to recognize construction safety condition for mechanism.
With the universal in-depth of BIM theory, buildings model parametrization, construction information have become a kind of trend.It is based on The remote monitoring system of internet also has been put into practice at present, brings great convenience for engineering management.Building is big The construction of diameter shield tunnel and network management platform are conducive to construction stage shield work on the spot management, Risk-warning, and The monitoring management of operation stage tunnel items health indicator.The architecture information of parametrization, also the face for major diameter tunnel is steady Fixed prediction, analysis and management provides reliable data basis.
Summary of the invention
It is an object of the present invention to overcome the above-mentioned drawbacks of the prior art and provide one kind to advantageously reduce greatly The construction risk of diameter shield tunnel provides the large diameter shield tunnel palm based on BIM of data supporting for related scientific research project Sub- face management system.
The purpose of the present invention can be achieved through the following technical solutions:
A kind of large diameter shield tunnel face management system based on BIM, comprising:
Face management subsystem carries out information to large diameter shield tunnel using BIM technology according to project profile information Change modeling, construction key parameter area surface pressure is estimated, is arranged and corrected, guiding construction, and to live feedback information It is integrated and is exported;
Monitoring management subsystem carries out real time monitoring and early warning to the construction of large diameter shield tunnel, stores construction data, Engineering construction, management condition are assessed, document management is carried out, summarizes construction experience, and can be used for the scientific research project in later period.
The face management subsystem includes:
Informationization model module is opened based on BIM technology to the Parametric three-dimensional modeling of penetrating ground and tunnel structure Digging face macromechanics model can be counted and be managed to the essential informations such as structure size, material utilization amount in project;
Face pressure pre-estimating module calculates in construction stage shield tunneling process according to excavation face macromechanics model The theoretical pressure of face and default supporting pressure;
Face scene feedback management module is analyzed stratum deformation, real-time soil pressure, according to theoretical pressure to shield Structure boring parameter carries out feedback adjustment.
Tunnel is divided into multiple units along tunneling direction by the face pressure pre-estimating module, and the face is existing Field feedback management module judges whether the stratum settlement of each unit meets the requirements, if it is not, then the unit is marked, and adjusts Face presets supporting pressure, and face is preset supporting pressure and supporting pressure feedback adjusted gives monitoring management subsystem System.
The monitoring management subsystem includes:
Tunnel real-time monitoring module, tunnel and ambient enviroment deformation to the constructing tunnel stage carry out real-time synchronization pipe Reason, and by monitoring data Real-Time Sharing to database cloud, it is checked in mobile terminals such as PC, mobile phones using APP for user;
Risk-warning module carries out the risk factors that face during constructing tunnel is likely to occur according to monitoring data Early warning, as far as possible reduction the risk of tunnel construction;
Module for managing files stores the face correlation monitoring data in constructing tunnel stage, forms archives material, convenient for number According to accumulation and scientific research analysis.
Tunnel is divided into multiple units along tunneling direction by the Risk-warning module, if the monitoring data of the unit are super Early warning value out is then marked the unit, and warning information is pushed to mobile terminal.
The system is based on BIM technology, it can be achieved that engineering informationization models, estimates construction parameter, real-time Transmission and storage It deposits construction data, the potential construction risk of forecast, generate the functions such as construction report, to complete to the automatic of entire construction process Change, intelligent monitoring and management, reduction construction risk reduce management cost, improve the efficiency of management;
The system has the clearly network architecture, and organizes rationally, and each module has its specific function, each function Organic assembling realizes the system;Various information is stored in different databases, and is operated in the different interfaces of system, side Just data are managed;By reserved different data interactive interface, it can be achieved that the data between this system and other systems are handed over Mutually, convenient to carry out data sharing with other software.
Compared with prior art, the invention has the following advantages that
1, by classical face pressure pre-estimating theory in conjunction with BIM technology, the pre- of area surface pressure is completed before excavation Estimate and preset, while preset pressure can be adjusted according to real-time monitoring result.
2, it is based on BIM technology, formation information, face pressure information, tunnel and ambient enviroment deformation information are all collected At in BIM model, realizing the visual, controllable of entire work progress.
3, pressure can be set in fact to face and estimates pressure difference carry out emphasis label away from biggish section and save to data Library carries out all-round statistics and assessment to construct after the completion, forms report, accumulate experience.
4, using BIM model as core, by network push, can the multiple terminals such as computer, mobile phone realize the shared of information and Management keeps the communication of entirely construction team more smoothly, it is ensured that safety accident in favor of the real-time management of face safe condition It responds rapidly to.
5, the present invention establishes " setting-feedback-tune by large diameter shield tunnel face pressure pre-estimating and management system The shield driving parameter management mode of solution " formula carries out effective guidance management for large-diameter shield driving safe construction;Information Change the risk management and control that model is also beneficial to later period operation management.
Detailed description of the invention
Fig. 1 is that functional module of the invention forms figure;
Fig. 2 is three-dimensional information modeling and output implementation flow chart of the invention;
Fig. 3 is tunnel management dividing elements schematic diagram of the invention.
Specific embodiment
The present invention is described in detail with specific embodiment below in conjunction with the accompanying drawings.The present embodiment is with technical solution of the present invention Premised on implemented, the detailed implementation method and specific operation process are given, but protection scope of the present invention is not limited to Following embodiments.
Embodiment
As shown in Figure 1, a kind of large diameter shield tunnel face pressure pre-estimating and pipe for being based on BIM (Building Information Model) Reason system includes face management subsystem 1 and monitoring management subsystem 2.The main users of face management subsystem 1 are industry Basic unit administrative staff and construction project department administrative staff, for understanding the information such as project process and construction safety in real time, in time It instructs and manages field personnel's operation;The main users of monitoring management subsystem 2 are owner's unit management personnel and correlation Scientific research personnel for monitoring tunnel traffic-operating period, the monitoring data such as record tunnel deformation in real time, and forms data archival, is used for Later period research work.
Model foundation mode in informationization model module 11 are as follows: the model information for storing BIM related software imports this System, system can carry out intelligent Modeling according to BIM information.It is prompted according to system operatio, selects the tunnel in flat, the vertical face figure in tunnel Road axis, outer profile, the objects such as structural elements elementary contour, are analyzed by procedure identification, carry out tunnel duct piece, knot is gone along with sb. to guard him in inside The modeling of the components such as structure, road foundation road surface, beam column.
In informationization model module 11, user can size, material properties to tunnel structure component carry out browsing check, Parameter information can be carried out to three-dimensional information model to summarize, export the tables such as the basic building block parameter at EXCEL format, material calculation amount Lattice, as shown in Figure 2.
In face pressure pre-estimating module 12, tunnel can be pressed longitudinal tunneling direction point according to Tunnel Design data by system At junior unit, as shown in figure 3, being monitored point to data such as the area surface pressures, stratum settlement of each unit in work progress Analysis.
If sedimentation is met the requirements, without adjustment;It is shade by the segment mark, to the palm if sedimentation is unsatisfactory for requiring The reason of sub- surface pressure is adjusted and places on record, while analysis causes sedimentation to transfinite.Finally by face preset pressure, reality If pressure, pressure adjusted, sedimentation situation, sedimentation are transfinited reason etc. as feature and be recorded in cell attribute, excavates and complete All-round statistics and assessment are carried out afterwards, forms report, are saved to database.
Face scene feedback management module 13 has the characteristics that adaptive dynamic mechanism.For according to theoretical calculation Suggestion supporting pressure, system can feed back according to live real-time monitoring data, be adjusted again to calculated value, make theoretical meter Calculation value is suitable for practice of construction situation, realizes the optimization of shield driving parameter, farthest reduces construction risk, raising is applied The safety and economy of work.
Tunnel real-time monitoring module 21 can according to can by in-situ data Real-Time Sharing to database cloud, user can PC, The terminals such as mobile phone share to cloud data and be checked using APP, and construction personnel is facilitated to obtain corresponding construction in time at the scene Parameter, and software information is combined to make quickly judgement, in time adjustment to the reasonability of construction parameter.Platform provides interaction simultaneously Function, the user for building each unit can be based on the network platform, carry out communication exchange with regard to field measurement data.
Risk-warning module 22 and the principle of face pressure pre-estimating module 12 are almost the same, by tunnel as unit of section of jurisdiction It is divided into junior unit, if the monitoring index in the junior unit exceeds early warning value, is marked and is started early warning, simultaneously will Warning information pushes to the terminal of each relevant person in charge.By analyzing each unit, the wind to each section in tunnel is realized Dangerous Forewarn evaluation and response, and then realize the automation Risk-warning management to entire tunnel operation stage, management cost is reduced, Improve the efficiency of management.
Module for managing files 23 can will construction, operation stage monitoring data information formed database, provide EXCEL, The export function of a variety of data format files such as ACCESS realizes the friendship of this system and mainstream office software and database software Mutually, user can the corresponding construction data of quick obtaining, for entire engineering construction, management condition assessment and construction experience it is total Knot, and can be used for the scientific research project in later period.

Claims (3)

1. a kind of large diameter shield tunnel face management system based on BIM characterized by comprising
Face management subsystem carries out informationization to large diameter shield tunnel using BIM technology and builds according to project profile information Mould, and area surface pressure is estimated, is arranged and corrected, guiding construction;
Monitoring management subsystem carries out real time monitoring and early warning to the construction of large diameter shield tunnel, stores construction data, assessment Engineering construction, management condition carry out document management;
The face management subsystem includes:
Informationization model module obtains excavation face based on BIM technology to the Parametric three-dimensional modeling of penetrating ground and tunnel structure Macromechanics model;
Face pressure pre-estimating module calculates area in construction stage shield tunneling process according to excavation face macromechanics model The theoretical pressure in face and default supporting pressure;
Face scene feedback management module analyzes stratum deformation, real-time soil pressure, is dug according to theoretical pressure to shield Feedback adjustment is carried out into parameter;
Tunnel is divided into multiple units along tunneling direction by the face pressure pre-estimating module, and the face scene is anti- Feedback management module judges whether the stratum settlement of each unit meets the requirements, if it is not, then the unit is marked, and adjusts area Supporting pressure is preset in face, and face is preset supporting pressure and supporting pressure feedback adjusted gives monitoring management subsystem.
2. a kind of large diameter shield tunnel face management system based on BIM according to claim 1, feature exist In the monitoring management subsystem includes:
Tunnel real-time monitoring module, tunnel and ambient enviroment deformation to the constructing tunnel stage carry out real-time synchronization management, And by monitoring data Real-Time Sharing to database cloud, checked for user in mobile terminal;
Risk-warning module carries out the risk factors that face during constructing tunnel is likely to occur according to monitoring data pre- It is alert;
Module for managing files stores the face correlation monitoring data in constructing tunnel stage, forms archives material.
3. a kind of large diameter shield tunnel face management system based on BIM according to claim 2, feature exist In tunnel is divided into multiple units along tunneling direction by the Risk-warning module, if the monitoring data of the unit are beyond pre- Alert value, then be marked the unit, and warning information is pushed to mobile terminal.
CN201710025802.1A 2017-01-13 2017-01-13 A kind of large diameter shield tunnel face management system based on BIM Active CN106761798B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710025802.1A CN106761798B (en) 2017-01-13 2017-01-13 A kind of large diameter shield tunnel face management system based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710025802.1A CN106761798B (en) 2017-01-13 2017-01-13 A kind of large diameter shield tunnel face management system based on BIM

Publications (2)

Publication Number Publication Date
CN106761798A CN106761798A (en) 2017-05-31
CN106761798B true CN106761798B (en) 2019-05-14

Family

ID=58946475

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710025802.1A Active CN106761798B (en) 2017-01-13 2017-01-13 A kind of large diameter shield tunnel face management system based on BIM

Country Status (1)

Country Link
CN (1) CN106761798B (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107608005B (en) * 2017-06-07 2019-04-30 同济大学 A kind of the abnormal geological detection analytic method and system
CN107060726A (en) * 2017-06-19 2017-08-18 广州普华灵动机器人技术有限公司 The system that a kind of use travel engineering robot carries out tunnel boring
CN108227658B (en) * 2018-01-08 2019-11-19 中交第二航务工程局有限公司 The prefabricated information system of steel-shelled concrete immersed tube tube coupling
CN109001038B (en) * 2018-07-03 2020-09-15 上海隧道工程有限公司 Segment loading test device and method
CN109162730B (en) * 2018-07-21 2020-08-11 中铁十八局集团有限公司 Slurry parameter management system of slurry balance shield based on BIM
CN108952815A (en) * 2018-08-24 2018-12-07 中国十九冶集团有限公司 Tunnel safety construction managing and control system
CN109492251A (en) * 2018-09-30 2019-03-19 上海宝冶集团有限公司 The BIM parametric modeling method of sled sled racing track
CN109899076A (en) * 2019-02-22 2019-06-18 中国地质大学(武汉) The intelligent construction and monitoring system of shield undercrossing tunnel based on BIM technology
CN110159290A (en) * 2019-05-29 2019-08-23 南京城市地下空间工程研究院有限公司 Long-distance management system based on shield machine construction
CN111022066B (en) * 2019-11-11 2021-10-01 北京住总集团有限责任公司 Shield machine risk source crossing three-dimensional simulation and monitoring system based on BIM and GIS
TWI792399B (en) * 2021-07-08 2023-02-11 中興工程顧問股份有限公司 Automatic analysis method of shield tunnel engineering and system thereof
CN113763289B (en) * 2021-11-08 2022-01-25 四川省交通勘察设计研究院有限公司 Original terrain correction method and system based on BIM (building information modeling) model and computer terminal

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103400228A (en) * 2013-08-07 2013-11-20 中铁第一勘察设计院集团有限公司 Method for creating post engineering information model for railway and urban railway traffic station
CN103530826A (en) * 2013-09-06 2014-01-22 上海大学 BIM (Building Information Modeling)-based shield method tunnel construction management method
CN104463717A (en) * 2014-12-09 2015-03-25 中国水利水电第十四工程局有限公司 Construction expert information system applicable to extra-large underground cavern group
KR101568958B1 (en) * 2015-03-02 2015-11-13 경희대학교 산학협력단 Method for preliminary regulating checking at architectural design phase using building information modeling

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103400228A (en) * 2013-08-07 2013-11-20 中铁第一勘察设计院集团有限公司 Method for creating post engineering information model for railway and urban railway traffic station
CN103530826A (en) * 2013-09-06 2014-01-22 上海大学 BIM (Building Information Modeling)-based shield method tunnel construction management method
CN104463717A (en) * 2014-12-09 2015-03-25 中国水利水电第十四工程局有限公司 Construction expert information system applicable to extra-large underground cavern group
KR101568958B1 (en) * 2015-03-02 2015-11-13 경희대학교 산학협력단 Method for preliminary regulating checking at architectural design phase using building information modeling

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
BIM技术在大型城市隧道工程——紫之隧道中的应用初探;郑楠 等;《土木建筑工程信息技术》;20161031;第8卷(第5期);第65-70页
软土地层TBM 开挖面支护压力计算模型及可视化;张子新 等;《岩土力学》;20151130;第36卷(第11期);第3193-3200页

Also Published As

Publication number Publication date
CN106761798A (en) 2017-05-31

Similar Documents

Publication Publication Date Title
CN106761798B (en) A kind of large diameter shield tunnel face management system based on BIM
Li et al. Methodologies of safety risk control for China’s metro construction based on BIM
CN104808610B (en) Machinery Control System and method based on BIM BIMs
CN109784746A (en) Urban-rural water supply network waterpower simulation of water quality platform
CN110866161A (en) Urban underground space three-dimensional information visualization system and method
CN104463717A (en) Construction expert information system applicable to extra-large underground cavern group
Montaser et al. Truck+ for earthmoving operations
CN105631154A (en) Method for viewing tunnel monitoring and measurement data on BIM (Building Information Modeling) construction management platform
CN113434565A (en) Water conservancy flood control drought and waterlogging prevention comprehensive disaster reduction platform system based on CIM platform
CN103500371A (en) Change control method based on BIM
CN103106542A (en) Data analyzing and processing system
CN114238543B (en) Drainage pipe network geographic information system
CN112258159B (en) BIM + GIS-based hydraulic structure management system and method
CN114201798A (en) BIM + GIS technology-based long and large tunnel digital twinning system and method
CN113639651A (en) Strip mine slope stability prediction device and prediction method thereof
CN109854960A (en) A kind of long distance water transfer pipe network monitor system and monitoring method
CN106453468B (en) A kind of mine water inrush method for early warning based on GIS technology
Wang et al. A relationship-based and object-oriented software for monitoring management during geotechnical excavation
CN103031862A (en) Three-dimensional digital prewarning method and facility for remote intelligent monitoring of deep foundation pit deformation stability
Deng et al. An integrated urban stormwater model system supporting the whole life cycle of sponge city construction programs in China
CN115456206A (en) BIM + GIS-based tunnel construction visual control method and system
CN115345036A (en) Intelligent research and judgment system and method for numerical comprehensive analysis of karst collapse mechanism
CN102880918A (en) Deep foundation pit risk assessment method based on data fusion analysis
Liu et al. City pipe network intelligent service based on GIS and internet of things
CN113837453A (en) Deep sewage drainage tunnel wisdom operation system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant